CN101672026A - 合理利用砂砾石料的面板堆石坝结构及其施工方法 - Google Patents

合理利用砂砾石料的面板堆石坝结构及其施工方法 Download PDF

Info

Publication number
CN101672026A
CN101672026A CN 200910152861 CN200910152861A CN101672026A CN 101672026 A CN101672026 A CN 101672026A CN 200910152861 CN200910152861 CN 200910152861 CN 200910152861 A CN200910152861 A CN 200910152861A CN 101672026 A CN101672026 A CN 101672026A
Authority
CN
China
Prior art keywords
dam
rock
sand gravel
shop
less
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200910152861
Other languages
English (en)
Inventor
陈振文
彭育
汤旸
李健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN 200910152861 priority Critical patent/CN101672026A/zh
Publication of CN101672026A publication Critical patent/CN101672026A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

本发明涉及一种合理利用砂砾石料的面板堆石坝结构及其施工方法。本发明要解决的技术问题是提供一种合理利用砂砾石料的面板堆石坝结构及其施工方法,将坝址附近的砂砾石料置于坝体中部干燥区,避免另行开辟堆石料场,保护生态环境。解决该问题的技术方案是:合理利用砂砾石料的面板堆石坝结构,具有坝主体,其上游侧由内到外依次铺设过渡层、垫层和面板,垫层下方设特殊垫层,主体上游侧坝基处设石渣回填区和粉土回填区,下游侧设干砌石护坡,下游坝基设超径石压坡区,主体包括主堆石区和次堆石区,两者围成的空腔内设位于浸润线之上的砂砾石区,砂砾石区底部及下游面低高程部位设置反滤保护层。本发明用于坝址附近存在天然砂砾石料的面板坝工程。

Description

合理利用砂砾石料的面板堆石坝结构及其施工方法
技术领域
本发明涉及一种合理利用砂砾石料的面板堆石坝结构及其施工方法。主要适用于坝址附近存在天然砂砾石料源的混凝土面板坝、沥青混凝土面板坝工程。
背景技术
面板堆石坝是当前水利水电工程中的一种主流坝型之一,在满足水力过渡等基本原则的前提下,坝体材料分区形式灵活多样。实际工程中,将砂砾石料放置在坝体上游、中部、下游均有应用,但由于砂砾石料渗透稳定性较差,往往需要设置单独的排水区,这样对施工进度、难度等均会造成一定的影响;同时由于砂砾石料在低围压条件下的抗剪强度较低,放置在上游和下游均需要放缓坝坡,增加坝体填筑量及工程投资。
发明内容
本发明要解决的技术问题是:提供一种合理利用砂砾石料的面板堆石坝结构及其施工方法,充分利用坝址附近的天然砂砾石料,将砂砾石料放置在坝体中部的干燥区,不仅能够减少坝体沉降,避免垫层开裂、面板脱空、减小坝体堆石料填筑方量,而且能够协调土石方挖填平衡,避免另行开辟堆石料场,有效保护生态环境,节省工程投资。
本发明所采用的技术方案是:合理利用砂砾石料的面板堆石坝结构,具有堆石坝主体,其上游侧由内到外依次铺设过渡层、垫层和面板,其中垫层下方设置特殊垫层,主体上游侧坝基处设置石渣回填区和粉土回填区,主体下游侧设干砌石护坡,下游坝基设置超径石压坡区,其特征在于:所述主体包括主堆石区和设在下游侧的次堆石区,两者围成的空腔内设置位于坝体浸润线之上的砂砾石区,砂砾石区底部及下游面低高程部位设置反滤保护层。
一种合理利用砂砾石料的面板堆石坝结构的施工方法,其特征在于按照以上分区自下而上进行铺设:
过渡层,主要利用枢纽建筑物的洞碴料和其它建筑物通过控制***参数的开挖料,岩质要求新鲜或微风化,最大粒径300mm,小于5mm颗粒的含量不超过19%的连续级配料;铺层厚35-45cm,碾压6-10遍,加水量为所铺土方体积的10%~20%;
垫层,由枢纽建筑物开挖的新鲜洞碴料和河床砂砾石超径骨料轧碎并掺配河砂而成,最大粒径80mm,小于5mm颗粒含量为35%~55%,小于0.075mm颗粒含量不大于8%的连续级配料;铺层厚35-45cm,并剔除与过渡层界面上粒径大于20cm的颗粒,与过渡层同层碾压6-10遍,加水量为所铺土方体积的8~12%;
特殊垫层,采用最大粒径为40mm的垫层用料,铺层厚35-45cm,碾压6-10遍;
石渣回填区,采用枢纽建筑物的开挖料填充,无压实要求;
粉土回填区,其填充料从料场开采,最大粒径小于1mm,水溶盐含量不大于3%,有机质含量不大于5%,塑性指数不大于10;
干砌石护坡,在下游坝面采用干砌块石筑砌,厚度为70-90cm;
超径石压坡区,坝体下游河床部位采用直径大于800mm的超径石压坡;
主堆石区,采用枢纽建筑物开挖料,要求是新鲜、微风化及少量分散弱风化岩石,最大粒径800mm,小于5mm的细粒含量小于20%,含泥量小于5%;铺层厚70-90cm,碾压6-10遍,加水量为所铺土方体积的15%~20%;
次堆石区,采用枢纽建筑物的开挖料,允许部分弱风化石料分散填筑,使下游次堆石区也保持良好的排水性,施工铺层厚110-130cm,碾压6-10遍,加水量为所铺土方体积的10%~20%;
砂砾石区,填充料从坝址附近的料场采挖后直接上坝,粒径小于600mm,含泥量小于5%;施工铺层厚70-90mm,碾压6-10遍;
反滤层,填充料为最大粒径小于300mm的砂砾石料或洞渣料。
本发明的有益效果是:本发明将砂砾石料放置在坝体中部的干燥区,以协调土石方挖填平衡,从而避免了另行开辟堆石料场,有效保护了生态环境,节省了工程投资;另一方面由于砂砾石料本身具有低压缩性的特点,将其设置在坝体中部大大减少了坝体沉降,避免了垫层开裂、面板脱空,减小了坝体堆石料填筑方量;此外,由于将砂砾石料置于坝体浸润线之上的干燥区,从而有效防止了砂砾石料渗透破坏,确保了工程安全。
附图说明
图1是本发明截面图。
具体实施方式
如图1所示,本实施例具有堆石坝主体,其上游侧由内到外依次铺设过渡层、垫层和面板4,其中垫层3下方设置特殊垫层5,主体上游侧坝基处设置石渣回填区6和粉土回填区7,主体下游侧设干砌石护坡8,下游坝基设置超径石压坡区9,所述主体包括主堆石区10和设在下游侧的次堆石区11,两者围成的空腔内设置位于坝体浸润线之上的砂砾石区12,以协调土石方挖填平衡,从而避免了另行开辟堆石料场,有效保护了生态环境,节省了工程投资。同时考虑到施工期间垫层3临时挡水度汛的情况,在砂砾石区12底部及下游面低高程部位设置反滤保护层13。
本实施例在实际操作过程中的施工方法是,按照以上分区从中间到两侧、自下而上进行分层铺设:
过渡层2,其材料主要利用枢纽建筑物的洞碴料和其它建筑物通过控制***参数的开挖料,岩质要求是新鲜或微风化,最大粒径300mm,小于5mm颗粒的含量不超过19%的连续级配料;施工时,铺层厚40cm,用22t拖式振动碾碾压8遍,加水量为所铺土方体积的15%,使得过渡层2的孔隙率不大于19%,干密度为2.163g/cm3,渗透系数的数量级为10-2cm/s;
垫层3,其填充材料由枢纽建筑物开挖的新鲜洞碴料和河床砂砾石超径骨料轧碎并掺配河砂而成,要求该料具有半透水性及渗透稳定性,同时要求对面板4上游的粉土起反滤作用。最大粒径80mm,小于5mm颗粒含量为35%~55%,小于0.075mm颗粒含量不大于8%的连续级配料;施工时,铺层厚40cm,并剔除与过渡层2界面上粒径大于20cm的颗粒,采用22t拖式振动碾与过渡层2同层碾压8遍,加水量为所铺土方体积的10%,使得垫层3的孔隙率不大于17%,干密度为2.216g/cm3
特殊垫层5,填充料与垫层3用料相同,区别在于其最大粒径为40mm,以对面板4上游的粉土起到良好的反滤效果;施工时,铺层厚40cm,采用一种安装在液压挖掘机上平板振动器碾压8遍,其渗透系数的数量级为10-4cm/s;
石渣回填区6,采用枢纽建筑物的开挖料回填,无压实要求;
粉土回填区7,其填充料从料场开采,最大粒径小于1mm,水溶盐含量不大于3%,有机质含量不大于5%,塑性指数不大于10,渗透系数比小区料的渗透系数小一个数量级,即10-5cm/s;由于粉土粒径比较小,当面板4表面产生裂缝发生渗漏时,粉土在水压下自动回填进入面板4上的裂缝内补漏;
干砌石护坡8,在下游坝面采用干砌块石筑砌,厚度为80cm;
超径石压坡区9,坝体下游河床部位采用直径大于800mm的超径石压坡,无需碾压;
主堆石区10,为坝体主要组成部分,采用枢纽建筑物开挖料,要求是新鲜、微风化及少量分散弱风化岩石,最大粒径800mm,小于5mm的细粒含量小于20%,含泥量小于5%;施工时,铺层厚80cm,采用22t拖式振动碾碾压8遍,加水量为所铺土方体积的17.5%,使得主堆石区的孔隙率不大于20%,干密度为2.12g/cm3
次堆石区11,采用枢纽建筑物的开挖料,允许部分弱风化石料分散填筑,使下游次堆石区也保持良好的排水性,施工铺层厚120cm,采用22t拖式振动碾碾压8遍,加水量为所铺土方体积的15%;
砂砾石区12,填充料从坝址附近的料场采挖后直接上坝,粒径小于600mm,含泥量小于5%;施工时,铺层厚80cm,采用22t拖式振动碾碾压8遍,使得砂砾石区的孔隙率不大于18%,干密度为2.12g/cm3;由于砂砾石本身具有低压缩性的特点,将砂砾石区12布置在主堆石区10和次堆石区11围成的空腔内,不仅减小了坝体的堆石料填筑方量,而且可以减少坝体沉降,确保坝体安全。
反滤层13,反滤料为满足对坝体砂砾石料反滤要求的洞渣料,最大粒径小于300mm。

Claims (2)

1、一种合理利用砂砾石料的面板堆石坝结构,具有堆石坝主体,其上游侧由内到外依次铺设过渡层(2)、垫层(3)和面板(4),其中垫层(3)下方设置特殊垫层(5),主体上游侧坝基处设置石渣回填区(6)和粉土回填区(7),主体下游侧设干砌石护坡(8),下游坝基设置超径石压坡区(9),其特征在于:所述主体包括主堆石区(10)和设在下游侧的次堆石区(11),两者围成的空腔内设置位于坝体浸润线之上的砂砾石区(12),砂砾石区(12)底部及下游面低高程部位设置反滤保护层(13)。
2、一种合理利用砂砾石料的面板堆石坝结构的施工方法,其特征在于按照以上分区从中间到两侧、自下而上进行铺设:
过渡层(2),主要利用枢纽建筑物的洞碴料和其它建筑物通过控制***参数的开挖料,岩质要求新鲜或微风化,最大粒径300mm,小于5mm颗粒的含量不超过19%的连续级配料;铺层厚35-45cm,碾压6-10遍,加水量为所铺土方体积的10%~20%;
垫层(3),由枢纽建筑物开挖的新鲜洞碴料和河床砂砾石超径骨料轧碎并掺配河砂而成,最大粒径80mm,小于5mm颗粒含量为35%~55%,小于0.075mm颗粒含量不大于8%的连续级配料;铺层厚35-45cm,并剔除与过渡层(2)界面上粒径大于20cm的颗粒,与过渡层(2)同层碾压6-10遍,加水量为所铺土方体积的8~12%;
特殊垫层(5),采用最大粒径为40mm的垫层(3)用料,铺层厚35-45cm,碾压6-10遍;
石渣回填区(6),采用枢纽建筑物的开挖料回填;
粉土回填区(7),其填充料从料场开采,最大粒径小于1mm,水溶盐含量不大于3%,有机质含量不大于5%,塑性指数不大于10;
干砌石护坡(8),在下游坝面采用干砌块石筑砌,厚度为70-90cm;
超径石压坡区(9),坝体下游河床部位采用直径大于800mm的超径石压坡;
主堆石区(10),采用枢纽建筑物开挖料,要求是新鲜、微风化及少量分散弱风化岩石,最大粒径800mm,小于5mm的细粒含量小于20%,含泥量小于5%;铺层厚70-90cm,碾压6-10遍,加水量为所铺土方体积的15%~20%;
次堆石区(11),采用枢纽建筑物的开挖料,施工铺层厚110-130cm,碾压6-10遍,加水量为所铺土方体积的10%~20%;
砂砾石区(12),填充料从坝址附近的料场采挖后直接上坝,粒径小于600mm,含泥量小于5%;施工铺层厚70-90mm,碾压6-10遍;
反滤层(13),填充料为最大粒径小于300mm的砂砾石料或洞渣料。
CN 200910152861 2009-09-18 2009-09-18 合理利用砂砾石料的面板堆石坝结构及其施工方法 Pending CN101672026A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910152861 CN101672026A (zh) 2009-09-18 2009-09-18 合理利用砂砾石料的面板堆石坝结构及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910152861 CN101672026A (zh) 2009-09-18 2009-09-18 合理利用砂砾石料的面板堆石坝结构及其施工方法

Publications (1)

Publication Number Publication Date
CN101672026A true CN101672026A (zh) 2010-03-17

Family

ID=42019417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910152861 Pending CN101672026A (zh) 2009-09-18 2009-09-18 合理利用砂砾石料的面板堆石坝结构及其施工方法

Country Status (1)

Country Link
CN (1) CN101672026A (zh)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936007A (zh) * 2010-08-19 2011-01-05 中国水利水电第五工程局有限公司 面板坝碾压固坡施工方法
CN102277859A (zh) * 2011-05-16 2011-12-14 河海大学 基于分形理论的***堆石料颗粒级配的优化方法
CN102635091A (zh) * 2012-04-28 2012-08-15 中国水电顾问集团成都勘测设计研究院 土石坝防渗体及其建造方法
CN102644259A (zh) * 2012-03-05 2012-08-22 西安理工大学 锚固混凝土挡墙堆石坝及其构筑方法
CN102864760A (zh) * 2012-10-22 2013-01-09 安蓉建设总公司 一种寒冷地区砂砾石坝料填筑施工方法
CN102995608A (zh) * 2012-12-14 2013-03-27 中国水电顾问集团成都勘测设计研究院 一种土质心墙堆石坝及其施工方法
CN104120686A (zh) * 2014-07-28 2014-10-29 中国电建集团西北勘测设计研究院有限公司 一种高弹模垫座式复合坝
CN104372770A (zh) * 2014-11-05 2015-02-25 华北水利水电大学 橡胶面板堆石坝及其施工方法
CN105350552A (zh) * 2015-09-25 2016-02-24 中国二十冶集团有限公司 回填夹渣土层的地下水控制方法
CN105442499A (zh) * 2015-12-29 2016-03-30 云南华电金沙江中游水电开发有限公司 300m级面板堆石坝自承式面板结构体系及安装方法
CN106120662A (zh) * 2016-08-17 2016-11-16 中国电建集团西北勘测设计研究院有限公司 一种局部高模量堆石面板坝
CN106400743A (zh) * 2016-09-22 2017-02-15 南昌大学 一种堤坝反滤结构
CN106651845A (zh) * 2016-12-16 2017-05-10 天津大学 一种土石坝填筑施工过程中料界污染实时监控方法
CN107142902A (zh) * 2017-06-24 2017-09-08 浙江华东工程咨询有限公司 高水头大流量全断面筑坝方法
CN108060655A (zh) * 2017-12-15 2018-05-22 国家电网公司 一种三面环山一面冲沟抽水蓄能电站上水库的构造及其施工方法
CN110616681A (zh) * 2019-08-27 2019-12-27 国家电网有限公司 一种岩溶发育地区面板堆石坝的构建方法
CN115613522A (zh) * 2022-10-26 2023-01-17 中国海洋大学 一种坚实防渗透的堆石拦海坝

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936007A (zh) * 2010-08-19 2011-01-05 中国水利水电第五工程局有限公司 面板坝碾压固坡施工方法
CN102277859A (zh) * 2011-05-16 2011-12-14 河海大学 基于分形理论的***堆石料颗粒级配的优化方法
CN102277859B (zh) * 2011-05-16 2013-03-06 河海大学 基于分形理论的***堆石料颗粒级配的优化方法
CN102644259B (zh) * 2012-03-05 2014-11-26 西安理工大学 锚固混凝土挡墙堆石坝及其构筑方法
CN102644259A (zh) * 2012-03-05 2012-08-22 西安理工大学 锚固混凝土挡墙堆石坝及其构筑方法
CN102635091A (zh) * 2012-04-28 2012-08-15 中国水电顾问集团成都勘测设计研究院 土石坝防渗体及其建造方法
CN102864760A (zh) * 2012-10-22 2013-01-09 安蓉建设总公司 一种寒冷地区砂砾石坝料填筑施工方法
CN102995608A (zh) * 2012-12-14 2013-03-27 中国水电顾问集团成都勘测设计研究院 一种土质心墙堆石坝及其施工方法
CN102995608B (zh) * 2012-12-14 2015-09-30 中国电建集团成都勘测设计研究院有限公司 一种土质心墙堆石坝及其施工方法
CN104120686A (zh) * 2014-07-28 2014-10-29 中国电建集团西北勘测设计研究院有限公司 一种高弹模垫座式复合坝
CN104120686B (zh) * 2014-07-28 2016-04-13 中国电建集团西北勘测设计研究院有限公司 一种高弹模垫座式复合坝
CN104372770A (zh) * 2014-11-05 2015-02-25 华北水利水电大学 橡胶面板堆石坝及其施工方法
CN105350552A (zh) * 2015-09-25 2016-02-24 中国二十冶集团有限公司 回填夹渣土层的地下水控制方法
CN105442499A (zh) * 2015-12-29 2016-03-30 云南华电金沙江中游水电开发有限公司 300m级面板堆石坝自承式面板结构体系及安装方法
CN105442499B (zh) * 2015-12-29 2017-07-18 云南华电金沙江中游水电开发有限公司 300m级面板堆石坝自承式面板结构体系及安装方法
CN106120662A (zh) * 2016-08-17 2016-11-16 中国电建集团西北勘测设计研究院有限公司 一种局部高模量堆石面板坝
CN106400743A (zh) * 2016-09-22 2017-02-15 南昌大学 一种堤坝反滤结构
CN106651845A (zh) * 2016-12-16 2017-05-10 天津大学 一种土石坝填筑施工过程中料界污染实时监控方法
CN106651845B (zh) * 2016-12-16 2019-10-11 天津大学 一种土石坝填筑施工过程中料界污染实时监控方法
CN107142902A (zh) * 2017-06-24 2017-09-08 浙江华东工程咨询有限公司 高水头大流量全断面筑坝方法
CN107142902B (zh) * 2017-06-24 2018-12-21 浙江华东工程咨询有限公司 高水头大流量全断面筑坝方法
CN108060655A (zh) * 2017-12-15 2018-05-22 国家电网公司 一种三面环山一面冲沟抽水蓄能电站上水库的构造及其施工方法
CN110616681A (zh) * 2019-08-27 2019-12-27 国家电网有限公司 一种岩溶发育地区面板堆石坝的构建方法
CN115613522A (zh) * 2022-10-26 2023-01-17 中国海洋大学 一种坚实防渗透的堆石拦海坝
CN115613522B (zh) * 2022-10-26 2024-06-11 中国海洋大学 一种坚实防渗透的堆石拦海坝

Similar Documents

Publication Publication Date Title
CN101672026A (zh) 合理利用砂砾石料的面板堆石坝结构及其施工方法
CN102146679B (zh) 复杂地质地段土压平衡盾构通过中间风井施工方法
CN204059124U (zh) 一种砂桩排水强夯后注浆地基加固结构
CN102383413B (zh) 一种加固饱和流塑淤泥软土地基的施工方法
CN201598610U (zh) 合理利用砂砾石料的面板堆石坝结构
CN101486555A (zh) 一种现浇反滤型透水生态混凝土及其护坡的建造方法
CN107419630A (zh) 一种有效控制工后沉降的软土地基高填方路堤及施工方法
CN111851505A (zh) 一种灌注式防渗心墙土石坝的构筑方法及其结构
WO2019214701A1 (zh) 一种模块式土体施压成型装置及软土地基的处理方法
CN109537603A (zh) 一种新型回填土加固方法
CN106542769A (zh) 一种铺设透水路面的复合材料
CN108892527A (zh) 用于坝后护坡的透水混凝土反滤层、制备方法及护坡结构
CN105951672A (zh) 一种新型堤岸与护坡的施工工艺
CN106087880B (zh) 一种300米级高的大坝及其施工工艺
CN102839683B (zh) 散体桩-透水性混凝土桩二元复合地基及处理方法
CN107032660B (zh) 一种铺设透水路面的复合材料的制备方法
CN106702845B (zh) 一种防盐碱透水路面结构
CN106012971A (zh) 一种植被混凝土护坡及其施工方法
CN102677704A (zh) 多泥沙河流利用天然铺盖的坝基防渗方法
CN107129208A (zh) 一种生物活性多孔隙粗骨料生态护岸基质工程材料
CN104695455B (zh) 大流量高水头防冲刷、防渗过水围堰结构及其施工方法
CN112813756A (zh) 一种基于市政软土路基及施工方法
CN105839653A (zh) 一种沉管隧道重建围堰防渗体系的施工方法
CN109440756A (zh) 回填放置加筋模块承压桩体联合固化夹层复合地基结构处理方法
CN107299620A (zh) 水闸主体结构施工方案

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100317