CN101559863A - Silo inertia protection device - Google Patents

Silo inertia protection device Download PDF

Info

Publication number
CN101559863A
CN101559863A CNA2008102253841A CN200810225384A CN101559863A CN 101559863 A CN101559863 A CN 101559863A CN A2008102253841 A CNA2008102253841 A CN A2008102253841A CN 200810225384 A CN200810225384 A CN 200810225384A CN 101559863 A CN101559863 A CN 101559863A
Authority
CN
China
Prior art keywords
silo
gas
inflation
coal
pipe network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008102253841A
Other languages
Chinese (zh)
Other versions
CN101559863B (en
Inventor
朱耀平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhu Yaoping
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2008102253841A priority Critical patent/CN101559863B/en
Publication of CN101559863A publication Critical patent/CN101559863A/en
Application granted granted Critical
Publication of CN101559863B publication Critical patent/CN101559863B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

The invention relates to an explosion-proof inertia protection process for a pulverized coal and raw coal silo system of a thermoelectric power station and a device thereof. The device comprises an air supply, a gas tank, a decompressor, and embedded pipes arranged on silo walls and bottom plate of the silo and a gas locking pipe network, a gas filling pipe network and a breather pipe network which are arranged inside and outside the silo and combined to realize integration of locking, filling and breathing, thus preventing and inhibiting self combustion and explosion of raw coal in the silo deeply. The inertia protection method of the invention can be used for safety prevention of inflammable and explosive locations such as powder magazines, granaries, oil houses, coal mines, chemical workshops and the like.

Description

Silo inertia protection device
Technical field
The invention belongs to the silo fender guard, be specifically related to a kind of inerting gas replacement protection technology and device that is used for heat power plant boiler coal pulverized coal preparation system.
Background technology
Now, in order to solve the coal air storage of loosing, contaminated environment reduces the weathering ature of coal.Taked the silo storing mode.Facts have proved that raw coal silo housing coal storage has takes up an area of little, no dust pollution, is applicable to advantage such as various climatic conditions.But because raw coal silo vome of shell reaches tens thousand of cubic meters, belong to the container of relative closure, also brought the new problem of safety anti-explosive, as because the coal self-characteristic, i.e. oxidation heat liberation spontaneous combustion tendency is added " the air duct effect " of silo.In limited relative sealed space, be unfavorable for heat radiation, raw coal spontaneous combustion is certain a bit at first generation that possesses autoignition conditions in the part in addition, finally causes large tracts of land spontaneous combustion and detonation.During local spontaneous combustion, because scope is little, heat is low, ambient interference is big.Silo routine monitoring facility as: sensors such as temperature, combustable gas concentration, tolerance can not in time be made accurate forecast.If by the time the spontaneous combustion scope is big, the heat height, combustable gas concentration is big again forecast can affect improvement opportunity again adversely.The fire extinguishing of silo ignition retard is very difficult, can only consider prevention and control, promptly non-fire-fighting fire extinguishing problem.This class problem is for running into overhaul of the equipments, and when needing to store raw coal for a long time, the coal that especially the spontaneous combustion tendency is high, magnitude of explosion belongs to the I class is just more urgent.
At present power plant mainly usefulness be the aqueous vapor inerting system, the source is wide, price is low, but after spraying into water vapour, can't keep very high system temperature, can be condensed into aqueous water very soon and lose the effect of inerting gas, and the coal of burning can generate inflammable and explosive water gas with water vapor acting, all the other are the standby host state because each use has only 8~12 minutes simultaneously, also the phenomenon that the time spent can't afford to drive often appears in a large amount of hydrophobic hold modes of need, and is not only uneconomical but also dangerous.
Summary of the invention
At the characteristic of silo blast mechanism and coal, carried out long-term analytic demonstration, finally designed the silo inertia protection system.Inertia protection device adopts locks, fills, changes three-in-one automatic inactive protect technology.Explosion-proof technology is risen to the prevention and control stage, is comprehensive, profound datonation-inhibition, anti-explosion safety up-to-date technology.It can prevent effectively that silo from blasting, and causes unnecessary economic loss, thereby reaches the purpose of further protection silo.
The silo inertia protection device cardinal principle is: lock: with inerting gas lock coal outlet, isolated extraneous oxygen; Fill: permeate highly purified inerting gas to the coal seam, to coal seam cooling, protective mulch; Change: cement out with the fire gases of inerting gas with top, coal seam; It is minimum that the interior combustion source of silo is dropped to, and combustion-supporting source reaches minimum, thereby actv. has been protected the safety of silo, and detailed process realizes around locking, fill, change three grades exactly.
The present invention proposes the coal powder process that is used for thermal powerplant of arch, the explosion-proof inertia protection device of run coal bin system includes: one or more sources of the gas, pressure purger, one or more storage tank also include:
The pre-pipe laying of a plurality of lock gas is arranged on the circumference of silo body inner wall protection eaves, and a plurality of being arranged on equally in the silo body, is positioned at the coal spout place of activation feeder below, and is arranged on coal spout place, center convolution reclaimer below.Finish connection with steel pipe from source of the gas to each lock gas pre-pipe laying, constitute lock tracheae net, guarantee when system monitoring produces primary signal to silo, system begins to fill highly purified inerting gas automatically in the silo that produces elementary warning, pin coal outlet, stop air from the coal outlet coal storage layer infiltration that make progress.
A grommet type seals; the one end is installed on the protection eaves in the silo body by angle steel, bolt; one end is fixedly connected on the shelves material ring of silo bottom; fuse with the rotary vane of spiral discharging machine,, do gyroscopic movement around center shaft together by driver drives; make silo bottom relative closure; protection profile of tooth rotary track is not buried by material, stops and has filled the into inerting gas leak of silo, and reduce involving in of oxygen.The implementation of grommet type seals can be flexible also can be rigidity or other array configuration.
Inflation ring of the present invention has two kinds of inflation modes:
1. hoop multi-point inflation
Inerting gas has the hole of certain intervals to charge into highly purified inerting gas as inflation inlet to silo so that inner multi-point inflation ring is upward a plurality of.Poroid can be round, the side etc. multiple shape.
2. hoop continous way inflation
Inerting gas can only charge into highly purified inerting gas to each absolute altitude place of silo continuously equably with fixed position place embedded steel tube as inflation inlet.
The required pre-pipe laying of one-level inflation ring, be arranged on silo a plurality of activation feeders in bottom and center convolution reclaimer entrance, and a plurality of silo bottoms that are arranged on equally, being positioned at encircling bottom bottom and the outer shroud of center convolution reclaimer, its effect is to silo base plate place infiltration high purity inerting gas.
Wherein, an inflation ring is respectively arranged in 6 of silo bottoms or a plurality of activation feeder, center convolution reclaimer entrance, and the inflation mode is the hoop continous way.Be positioned at the inflation ring of the ring bottom and the outer shroud bottom of center convolution reclaimer, mode is the inflation of hoop multi-point.
The pre-pipe laying of secondary inflation ring is arranged on silo endogenous protective eaves with absolute altitude place and protection eaves and silo wall intersection.The secondary inflation ring inflation mode that wherein is on the silo protection eaves is the hoop continous way.The pre-pipe laying of evenly arranging with absolute altitude place circumference by the protection eaves of secondary charges into highly purified inerting gas to silo.The secondary inflation ring inflation mode of protection eaves and silo wall intersection is the hoop multi-point; be arranged on silo inside; being characterized in inflating ring can be installed in the square groove that silo reserves; installation accessories also can be set will inflate ring and be fixed on the silo inwall, inerting gas has the hole of certain intervals to charge into highly purified inerting gas to silo by a plurality of on the inflation ring.
Three grades of inflation rings can be 2 layers or multilayer, and its pre-pipe laying evenly is arranged on the silo wall circumference that pushes up near silo.
The present invention also the layer in three grades of inflation rings with layer between be provided with automatic charge valve, implementation can be multiple modes such as spring loaded, gravity type boat davit.Automatically charge valve all is by flange and inflates the standpipe that encircles and fix in two ends up and down; move according to automatic charge valve pressure at two ends is different; its effect is that the automatic tracking coal seam guarantees to fill highly purified inerting gas between coal seam, different level place; to the coal seam cooling, and above the coal seam, form protective cover.
According to the system monitoring signal, air inflator system is according to the rank of the highly automated selection inflation ring in coal seam, automatically begin in producing the silo of reporting to the police, to fill highly purified inerting gas,, reach the purpose that comb. gas concentration is reduced to coal seam infiltration high purity inerting gas.
Fender guard of the present invention also comprises a plurality of embedded boards, is arranged on the silo outer wall, and the assurance dish is climbed at the steel pipe on the silo and is fixed on the silo outer wall.
A plurality of ventilation posts are arranged on the silo inwall circumference, form the ventilation groove.
The pre-pipe laying of a plurality of ventilations is arranged on the silo external wall of upper portion, is in the top of ventilation post, guarantees to charge into from the top down the ventilation post from the inerting gas that source of the gas comes out.
A plurality of scavenge valves, its implementation can be electromagnetic type, weight valve or motorized valve.Be arranged on each ventilation post, press the homodisperse layout of absolute altitude, inerting gas is come out by source of the gas, pressure purger, the pre-pipe laying of taking a breath through silo top, be stored in from top to bottom in the ventilation post, can exchange a plurality of scavenge valves generation actions of gas column automatically with the absolute altitude place according to monitor signal.Reach the highly purified inerting gas to this layer injection, gas increases from low to high gradually, and displaces the fire gases on top, coal seam.For the silo of top complete closed, be at the explosion door of silo top mounting strap electric pushrod, the explosion door that original hazardous gas is opened from the silo top in the silo is discharged, and reaches the purpose with hazardous gas in the former silo of inerting gas replacement.
Lock gas, inflation, the pre-pipe laying of ventilation, the trend of decision pipe network, multiple trend can be arranged, in the mode of saving pipe network most is best implementation, the position that pre-pipe laying is provided with can be any suitable position of silo, can be along evenly arranging on the silo circumference, can be in silo inside, also can be at the silo outer wall.
The mode of operation of locking, filling, changing many grades inertia protection device can be when elementary alerting signal is arranged, the gas of unblanking; When senior alerting signal was arranged, inflation was carried out simultaneously with lock gas, also multiple mode such as inflation work only; When senior alerting signal was arranged, ventilation was carried out simultaneously with inflation, lock gas, also several working ways such as ventilation work only.
The number of plies of the pipe network of lock gas, inflation, ventilation is to decide according to the actual conditions at scene and the kind of silo, can be one or more layers.
Pressure purger in the silo inertia protection system of the present invention, its effect are that the gas of the band pressure that comes out from source of the gas is reduced pressure, and make its force value reach requirement, and its implementation can be various valves.
The present invention has adopted " lock, fill, change " three-in-one complex technique, solved silo explosion-proof, control a quick-fried difficult problem.Silo inertia protection device of the present invention is simple in structure; easy to use; maintaining is simple and easy; the unattended operation that can realize ideal; used inerting gas source is wide; inerting is effective, safely and fast, burn into multi-stage protection not, safety factor is big, is applicable to the material storage that various silos, run coal bin, powder storehouse, silo and spontaneous combustion tendency thereof are high.
Description of drawings
Fig. 1 silo inertia protection process schematic representation.
The structural representation of Fig. 2 silo inertia protection device.
Fig. 3 locks tracheae web frame scheme drawing.
The structural representation of Fig. 4 grommet type seals.
Fig. 5 appendix web frame scheme drawing.
The automatic charge valve structural representation of Fig. 6.
Fig. 7 scavenge trunk web frame scheme drawing.
Fig. 8 scavenge valve structural representation.
The specific embodiment:
As Fig. 2 is the structural representation of silo inertia protection device.The present invention by 1 source of the gas 1, storage tank 2,2 sources of the gas 3, pressure purger 4, ventilation pipe network 5, lock tracheae net 6, one-level inflation pipe network 7, secondary inflation pipe network 8, three grades of inflation pipe networks 9, annular seal 13, automatically charge valve 18, scavenge valve 21, silo are formed automatically.Detailed process realizes that around locking, fill, change three grades technological process as shown in Figure 1 exactly.Inflammable, explosive gas in the displacement silo make the combustion source cooling in the silo, thereby actv. has been protected the safety of silo.The entry condition of " locking, fill, changing " is to decide according to the characteristic that stores coal in the storehouse, and carries out by the signal that the silo monitoring is transmitted.
Lock gas: as Fig. 3; utilize steel pipe being arranged on the circumference of silo body inner wall protection eaves, reach a plurality of being arranged on equally in the silo body, be positioned at the coal spout place of activation feeder below; and the pre-pipe laying that is arranged on coal spout place, center convolution reclaimer below couples together formation lock tracheae net.Lock tracheae net move towards according to pre-pipe laying decision, when system monitoring when silo produces elementary alerting signal, use inerting gas blockade coal outlet, avoid the inerting gas leak, improved explosion-proof, datonation-inhibition efficient.
As Fig. 4 is the annular seal structural representation, is made up of angle steel 26, steel ball 27, closing plate 28, bolt 29, steel plate 30 etc.One end is installed on the protection eaves 15 in the silo body by angle steel 26, bolt 29; one end is fixedly connected on the shelves material ring 31 of silo base plate 45; fuse with the rotary vane of spiral discharging machine; by driver drives; do gyroscopic movement around center shaft together, make silo bottom relative closure, protection profile of tooth rotary track 12 is not buried by material; stop and filled the into inerting gas leak of silo, and reduce involving in of oxygen.
Inflation: as Fig. 5, the one-level inflation is arranged in silo a plurality of activation feeders 34 in bottom and center convolution reclaimer 32 entrance, and a plurality of silo bottom that is arranged on equally, is positioned at the ring bottom 33 and the outer shroud bottom 35 of center convolution reclaimer.Wherein, an inflation ring is respectively arranged in 6 of silo bottoms or a plurality of activation feeder 34, center convolution reclaimer 32 entrance, and the inflation mode is the hoop continous way.Be positioned at the inflation ring of the ring bottom 33 and the outer shroud bottom 35 of center convolution reclaimer, mode is the inflation of hoop multi-point;
On silo endogenous protective eaves 15, evenly arrange the gas filed pre-pipe laying 16 of secondary with silo wall intersection circumference with absolute altitude place and protection eaves 15; wherein be in the secondary inflation ring on the silo protection eaves 15, the pre-pipe laying of evenly arranging with absolute altitude place circumference by the protection eaves 16 of secondary charges into highly purified inerting gas to silo.The inflation ring of protection eaves and silo wall intersection can be installed in the square groove that silo is reserved herein, installation accessories also can be set will inflate ring and be fixed on the silo inwall, inerting gas has the hole of certain intervals to charge into highly purified inerting gas to silo by a plurality of on the inflation ring;
The pre-pipe laying 17 of three grades of inflation rings is arranged on the circumference of silo outer wall different level uniformly, and three grades of inflation pipe networks are coupling together to a plurality of pre-pipe layings from source of the gas; According to the system monitoring signal, the rank that air inflator system selects inflation to encircle according to the height in coal seam begins to fill highly purified inerting gas automatically in producing the silo of reporting to the police, and to coal seam infiltration high purity inerting gas, reaches the purpose that comb. gas concentration is reduced.
Also comprising 2 or a plurality of automatic charge valve in three grades of inflation rings, is automatic charge valve structural representation as Fig. 6, is made up of valve companion flange 36, bonnet, 37, spool 38, bottom flange 39, socket bolt 40 etc.Two ends are fixed by the valve companion flange 36 and the standpipe of inflation ring, move according to automatic charge valve 18 pressure at two ends are different, and the big bottom flange 39 of the pressure of lower end is opened.The coal seam that is higher than automatic charge valve 18 is put on the air protective mulch.Inerting gas is filled in real having reached between coal, the automatic tracking coal seam forms protective cover above the coal seam.Reach comb. gas concentration is reduced, and reduce the purpose of coal seam temperature.At this moment inflation is carried out simultaneously with lock gas.
Ventilation: be ventilation unit construction scheme drawing as Fig. 7, form by 2 sources of the gas 3, ventilation pipe network 5, silo wall 19, automatic scavenge valve 21, the pre-pipe laying 22 of ventilation, ventilation post 20.On silo inner and upper circumference, evenly arrange 20,2 on the ventilation post of enough height or a plurality of, with the absolute altitude place the automatic scavenge valve 21 of one deck is set in the vertical direction of silo wall.When system monitoring arrives senior alerting signal, electromagnet 41 in a plurality of automatic scavenge valve at nearest same absolute altitude place, coal seam moves simultaneously, there is the inerting gas of pressure to open as the plate washer among Fig. 8 42, highly purified inerting gas is injected in this top, coal seam, along with increasing gradually of inerting gas, the hazardous gas of coal seam upper space is progressively discharged from the silo top vent in the silo.For the silo of top complete closed, be at silo top mounting strap Electric Explosion-proof door, the explosion door that original hazardous gas is opened from the silo top in the silo is discharged, and reaches the purpose of replacing hazardous gas in the former silo with the noble gas body.
The above, it only is preferred embodiment of the present invention, be not that the present invention is done any pro forma restriction, any those skilled in the art, every technical solution of the present invention that do not break away from,, all still belong in the scope of technical solution of the present invention any simple modification, variation and modification that above embodiment did according to technical spirit of the present invention.

Claims (11)

1, the present invention carries and has encircleed a kind of inerting safety guard-safeguard technology that is used for powder process of thermal powerplant coal and run coal bin system, comprises source of the gas, pressure purger, inertia protection device pipe network, it is characterized in that:
The pre-pipe laying 14,11 of lock gas is reserved in the silo bottom, is arranged on the circumference of silo body inner wall protection eaves 15, and a plurality of being arranged on equally in the silo body, be positioned at the coal spout place 23 of activation feeder below, and be arranged on coal spout place, center convolution reclaimer below 24.Between the shelves material ring of protection eaves in the silo body and silo bottom grommet type seals 13 is installed.The one end is installed on the protection eaves 15 in the silo body, and an end is fixedly connected on the shelves material ring 31 of silo bottom, fuses with the rotary vane of spiral discharging machine, by driver drives, does gyroscopic movement around center shaft together.
Silo base plate 45 places reserve one-level and inflate pre-pipe laying 10, are arranged on silo a plurality of activation feeders 34 in bottom and center convolution reclaimer 33 entrance, and a plurality of silo bottom that is arranged on equally, are positioned at the ring bottom 33 and the outer shroud bottom 35 of center convolution reclaimer; Evenly arrange the gas filed pre-pipe laying 16 of secondary with absolute altitude place and protection eaves 15 with silo wall intersection circumference on silo endogenous protective eaves 15, protection eaves 15 is inner multi-point inflation ring with the secondary inflation ring of silo wall intersection; The pre-pipe laying 17 of a plurality of three grades of inflation rings is arranged on the circumference of silo outer wall different level uniformly.By valve companion flange 36 the automatic charge valve 18 and the standpipe of inflation ring are fixed between the multilayer inflation ring.
The pre-pipe laying 22 of ventilation is reserved in the silo middle and upper part, and ventilation pipe network 5 is installed.Be provided with ventilation post 20 at the silo inwall, on each ventilation post, press a plurality of scavenge valves 21 of the homodisperse layout of absolute altitude, can start the ventilation pipe network of different layers automatically according to the height of different coals position.
2, silo inertia protection device according to claim 1; it is characterized in that being provided with lock, fill, change datonation-inhibition, the explosion-proof pipe network of many grades; reach lock, fill, change three-in-one, be applicable to the material storage that various types of silos, powder storehouse, silo and spontaneous combustion thereof tendency is high.
3, silo inertia protection device according to claim 1, it is characterized in that inertia protection device lock, fill, the trend of replace tubes net can have different implementations, is best implementation in the mode of saving pipe network most.
4, lock according to claim 1, fill, change many grades inactive protect, it is characterized in that mode of operation can be batch (-type), continous way, can also one work or a plurality ofly work simultaneously.
5, lock gas according to claim 1, inflation, the pre-pipe laying of ventilation is characterized in that being arranged on any suitable position of silo, can be along evenly arranging on the silo circumference, can be in silo inside, and also can be at the silo outer wall, quantity is a plurality of.
6, silo inertia protection device pipe network according to claim 1 is characterized in that and can decide the number of plies of lock gas, inflation, ventilation pipe network according to the actual conditions and the silo kind at scene, can be one or more layers.
7, the inside multiple spot of silo inwall according to claim 1 inflation ring, it is characterized in that the point of multiple spot shape can be justified, side etc. multiple shape.
8, source of the gas according to claim 1 is characterized in that the kind of gas can be a kind of of multiple inerting gases such as flue gas, carbon dioxide, nitrogen, and quantity is one or more.
9, annular seal according to claim 1, its feature can have multiple implementation, can be flexible also can be rigidity or other array configuration.
10, automatic charge valve according to claim 1; the height of automatic tracking coal position; realize the inflation of different level place; form protective cover on the surface, coal seam; fill inerting gas in the middle of the coal seam, its feature can be according to the size of silo, and the number of plies of inflation pipe network decides; can be for one or more, multiple mode such as implementation can spring loaded, gravity type boat davit.
11, scavenge valve according to claim 1, evenly arrange along the silo circumference with the absolute altitude place at silo inwall ventilation post, its feature can decide according to the size of silo or the height of ventilation post, can be for a plurality of, implementation can be electromagnetic type, weight valve or motorized valve, also can lever etc. various ways occur.
CN2008102253841A 2008-10-31 2008-10-31 Silo inertia protection device Expired - Fee Related CN101559863B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008102253841A CN101559863B (en) 2008-10-31 2008-10-31 Silo inertia protection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008102253841A CN101559863B (en) 2008-10-31 2008-10-31 Silo inertia protection device

Publications (2)

Publication Number Publication Date
CN101559863A true CN101559863A (en) 2009-10-21
CN101559863B CN101559863B (en) 2011-11-23

Family

ID=41218879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008102253841A Expired - Fee Related CN101559863B (en) 2008-10-31 2008-10-31 Silo inertia protection device

Country Status (1)

Country Link
CN (1) CN101559863B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102303758A (en) * 2010-11-26 2012-01-04 徐州中矿奥特麦科技有限公司 Coal storage silo safety protection process and protection system
CN102323798A (en) * 2011-05-16 2012-01-18 上海发电设备成套设计研究院 Automatic control system of coal bed loads of thermal power generating unit
CN102338795A (en) * 2010-07-15 2012-02-01 通用电气公司 System and method of monitoring combustible gases in a coal supply
CN103625803A (en) * 2013-12-13 2014-03-12 徐州中矿奥特麦科技有限公司 Full inerting protection device of shared wall cylindrical silo and protection method
CN103662490A (en) * 2013-04-25 2014-03-26 陕西祥瑞电气工程自动化有限公司 Coal storage silo feeding device
CN103920260A (en) * 2014-04-16 2014-07-16 西安西热锅炉环保工程有限公司 System and method for preventing spontaneous combustion by oxidization of raw coal in spherical bunker by drawing low-temperature flue gas into bunker for inerting
CN104771852A (en) * 2015-04-03 2015-07-15 煤炭科学技术研究院有限公司 Pulverized coal tank inert gas protective device and application method thereof
CN105314298A (en) * 2014-07-29 2016-02-10 盛美半导体设备(上海)有限公司 Liquid storage tank adopting inert gas protection
CN107082205A (en) * 2017-05-18 2017-08-22 北京工业大学 A kind of ball storehouse inertia protection device
CN108455103A (en) * 2018-03-15 2018-08-28 樊建华 A kind of thermal storage tank's floating insulation cover having wind resistance, rain-proof, dehumidification function
CN113697308A (en) * 2021-08-28 2021-11-26 徐州国晟智能科技有限公司 Silo safety inerting protection device convenient for quick inflation
CN115282543A (en) * 2022-08-03 2022-11-04 新疆天池能源有限责任公司 Intelligent fire prevention and extinguishing system and method for coal storage silo

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102338795A (en) * 2010-07-15 2012-02-01 通用电气公司 System and method of monitoring combustible gases in a coal supply
CN102303758A (en) * 2010-11-26 2012-01-04 徐州中矿奥特麦科技有限公司 Coal storage silo safety protection process and protection system
CN102323798A (en) * 2011-05-16 2012-01-18 上海发电设备成套设计研究院 Automatic control system of coal bed loads of thermal power generating unit
CN102323798B (en) * 2011-05-16 2013-05-15 上海发电设备成套设计研究院 Automatic control system of coal bed loads of thermal power generating unit
CN103662490A (en) * 2013-04-25 2014-03-26 陕西祥瑞电气工程自动化有限公司 Coal storage silo feeding device
CN103625803B (en) * 2013-12-13 2016-03-23 徐州中矿奥特麦科技有限公司 The full inertia protection device of wall silo altogether
CN103625803A (en) * 2013-12-13 2014-03-12 徐州中矿奥特麦科技有限公司 Full inerting protection device of shared wall cylindrical silo and protection method
CN103920260A (en) * 2014-04-16 2014-07-16 西安西热锅炉环保工程有限公司 System and method for preventing spontaneous combustion by oxidization of raw coal in spherical bunker by drawing low-temperature flue gas into bunker for inerting
CN103920260B (en) * 2014-04-16 2016-04-27 西安西热锅炉环保工程有限公司 Low-temperature furnace smoke sucking inerting ball-type coal bunker anti-raw coal oxidation and spontaneous combustion system and method
CN105314298A (en) * 2014-07-29 2016-02-10 盛美半导体设备(上海)有限公司 Liquid storage tank adopting inert gas protection
CN105314298B (en) * 2014-07-29 2019-05-17 盛美半导体设备(上海)有限公司 Inert gas shielding reservoir
CN104771852A (en) * 2015-04-03 2015-07-15 煤炭科学技术研究院有限公司 Pulverized coal tank inert gas protective device and application method thereof
CN104771852B (en) * 2015-04-03 2018-07-24 煤科院节能技术有限公司 A kind of coal dust pot inert gas protection device and its application method
CN107082205A (en) * 2017-05-18 2017-08-22 北京工业大学 A kind of ball storehouse inertia protection device
CN108455103A (en) * 2018-03-15 2018-08-28 樊建华 A kind of thermal storage tank's floating insulation cover having wind resistance, rain-proof, dehumidification function
CN108455103B (en) * 2018-03-15 2023-11-24 樊建华 Heat-storage pool floating heat-insulating cover with wind resistance, rain resistance and dehumidification functions
CN113697308A (en) * 2021-08-28 2021-11-26 徐州国晟智能科技有限公司 Silo safety inerting protection device convenient for quick inflation
CN113697308B (en) * 2021-08-28 2022-08-12 徐州国晟智能科技有限公司 Silo safety inerting protection device convenient for quick inflation
CN115282543A (en) * 2022-08-03 2022-11-04 新疆天池能源有限责任公司 Intelligent fire prevention and extinguishing system and method for coal storage silo

Also Published As

Publication number Publication date
CN101559863B (en) 2011-11-23

Similar Documents

Publication Publication Date Title
CN101559863B (en) Silo inertia protection device
CN103625803B (en) The full inertia protection device of wall silo altogether
CN101575057B (en) Combined coal powder storage and supply system
CN102303758A (en) Coal storage silo safety protection process and protection system
CN202464544U (en) Inerting safety protection device for coal storage silo
CN201458374U (en) Combined coal powder storage and supply system
CN201458098U (en) Pulverized coal warehouse
CN100443132C (en) Inerting protection method and protection device in use for silo of storing raw coal
CN206108066U (en) Explosion -proof flame -retardant safety monitoring system of large -scale former coal bunker
US6644165B1 (en) Explosion containment vessel
US10272276B2 (en) Cooling device for spontaneous combustion prevention
CN202152181U (en) Oil tank and oil tank truck nitrogen gasbag separation explosion-proof apparatus
US10905908B2 (en) Dome-based cyclic inert sealing system for external floating roof tank and QHSE storage and transport method thereof
CN103995503A (en) A control system for the conversion of a carbonaceous feedstock into gas
CN205574743U (en) A let out and explode device that is used for buggy storehouse to let out seam broken
CN101298901A (en) Separating explosion-proof skid-mounted type vehicle gasification device
WO2015181617A1 (en) Automatic fire extinguishing system and method for at least one large storage tank containing a flammable liquid
CN210762356U (en) Inerting protection device for coal storage silo
CN104370122A (en) Treatment system and method for coal bunker gas
JP6329323B2 (en) Natural gas hydrate tank container loading system capable of automating the connection of power lines and evaporative gas pipes
CN203413352U (en) Gas chamber cover for LNG (liquefied natural gas) storage tank
CN211226322U (en) Explosion-proof sled dress formula filling station of separation
KR101310448B1 (en) Emergency steam drain cooling system of nuclear power plant containment vessel
CN202687208U (en) Cylinder cabin comprising inerting protection system
RU2635303C2 (en) Reservoir for process operations with oil or oil products with self-extinguishing in reservoir

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: QINGDA NEW ENERGY TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: ZHU YAOPING

Effective date: 20130326

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 030032 TAIYUAN, SHAANXI PROVINCE TO: 100040 SHIJINGSHAN, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20130326

Address after: 100040 Beijing Shijingshan District Galaxy South Street No. 2 hospital purple imperial international 4-1808

Patentee after: QINGDA XINNENG TECHNOLOGY CO., LTD.

Address before: 030032 133 District, Taiyuan economic and Technological Development Zone, Taiyuan, Shanxi

Patentee before: Zhu Yaoping

DD01 Delivery of document by public notice

Addressee: Guo Fengli

Document name: Notification of Passing Examination on Formalities

ASS Succession or assignment of patent right

Owner name: RONGQING ENERGY EQUIPMENT CO., LTD.

Free format text: FORMER OWNER: QINGDA NEW ENERGY TECHNOLOGY CO., LTD.

Effective date: 20140603

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100040 SHIJINGSHAN, BEIJING TO: 100010 DONGCHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20140603

Address after: 100010, room 50738, Galaxy sohoD, Chaoyangmen inner Avenue, Dongcheng District, Beijing

Patentee after: RONGQING ENERGY EQUIPMENT CO., LTD.

Address before: 100040 Beijing Shijingshan District Galaxy South Street No. 2 hospital purple imperial international 4-1808

Patentee before: QINGDA XINNENG TECHNOLOGY CO., LTD.

DD01 Delivery of document by public notice

Addressee: Yue Hengbi

Document name: Notification of Passing Examination on Formalities

ASS Succession or assignment of patent right

Owner name: ZHU YAOPING

Free format text: FORMER OWNER: RONGQING ENERGY EQUIPMENT CO., LTD.

Effective date: 20150215

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100010 DONGCHENG, BEIJING TO: 102206 CHANGPING, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20150215

Address after: 102206, room 2, building 2, block 1, North Zone, North Zone, Shahe higher education zone, Changping District, Beijing,

Patentee after: Zhu Yaoping

Address before: 100010, room 50738, Galaxy sohoD, Chaoyangmen inner Avenue, Dongcheng District, Beijing

Patentee before: RONGQING ENERGY EQUIPMENT CO., LTD.

DD01 Delivery of document by public notice

Addressee: Yue Xueming

Document name: Notification of Passing Examination on Formalities

DD01 Delivery of document by public notice

Addressee: Zhu Yaoping

Document name: Notification of Passing Examination on Formalities

DD01 Delivery of document by public notice

Addressee: Zhu Yaoping

Document name: Notification of Termination of Patent Right

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111123

Termination date: 20151031

EXPY Termination of patent right or utility model