CN101550705A - 一种桩基础的加固处理方法 - Google Patents

一种桩基础的加固处理方法 Download PDF

Info

Publication number
CN101550705A
CN101550705A CN 200810300789 CN200810300789A CN101550705A CN 101550705 A CN101550705 A CN 101550705A CN 200810300789 CN200810300789 CN 200810300789 CN 200810300789 A CN200810300789 A CN 200810300789A CN 101550705 A CN101550705 A CN 101550705A
Authority
CN
China
Prior art keywords
pile
castinplace pile
pile foundation
newly
circular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200810300789
Other languages
English (en)
Other versions
CN101550705B (zh
Inventor
杨华
张文清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN 200810300789 priority Critical patent/CN101550705B/zh
Publication of CN101550705A publication Critical patent/CN101550705A/zh
Application granted granted Critical
Publication of CN101550705B publication Critical patent/CN101550705B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明提供了一种桩基础的加固处理方法,紧挨圆形灌注桩(1)的两边挖出新补半圆异形灌注桩(2)的桩孔,将新补半圆异形灌注桩(2)的箍筋(7)和纵筋(5)放入新挖的桩孔内,将箍筋(7)与箍筋(6)连接在一起,再灌入混凝土,最后将圆形灌注桩(1)的纵筋(4)与纵筋(5)一起按构造要求锚入桩基承台(3)内。本发明采用新补半圆异形灌注桩与失去部分承载能力的圆形灌注桩组合成椭圆形桩基础共同受力,来满足桩的承载力设计要求,此桩基础占用的施工面较小、加固简便、施工安全可靠。

Description

一种桩基础的加固处理方法
技术领域
本发明涉及一种桩基础的加固处理方法,属于建筑工程的桩基础领域。
背景技术
建筑工程桩基础的类型很多,但通常采用混凝土灌注桩。由于施工队伍的良莠不齐,混凝土灌注桩的工程事故较多,因此质量检验较其它桩种严格。通过具有相关检测资质的单位对桩基础进行检测,经常会发现桩体断桩、桩身混凝土强度未达到桩的承载力设计要求等等现象。如果因断桩或桩的承载力不够而造成建筑安全隐患甚至拆毁建筑,成本损失严重,则就要采取补救措施来加固桩基础。通常采用的固定方法是:(一)用钻机在基础上成孔至要加固的土层,然后用高压灌浆设备将配制好的水泥化学浆液灌入地层,通过劈裂、挤压作用,使土层与浆液产生物理化学反应而胶结,从而达到改善土体结构和性能的目的,提高土体的强度;(二)利用建筑物的承重柱重力作为反力,通过一套液(油)压设备,把预制桩分节压入土中,上下节桩接驳用预埋角铁焊接。但这两种方法同样都会给工程造成一定的损失,施工复杂。
发明内容
本发明所要解决的技术问题就是桩基础当被检测灌注桩失去部分承载能力的情况下,提供对桩基础加固的简便、安全可靠地处理方法。
为了解决上述问题,本发明提供了一种桩基础的加固处理方法,在紧挨圆形灌注桩1的两边挖出新补半圆异形灌注桩2的桩孔,再将圆形灌注桩1的护壁及保护层混凝土打掉,并露出圆形灌注桩1的箍筋6;然后用新补半圆异形灌注桩2的箍筋7和纵筋5放入新挖的桩孔内,将箍筋7与箍筋6连接在一起,再灌入混凝土,最后将圆形灌注桩1的纵筋4与纵筋5一起按构造要求锚入桩基承台3内。
圆形灌注桩1的中心位置与新补半圆异形灌注桩2的中心位置间的间距为a,新补半圆异形灌注桩2的半径R等于圆形灌注桩1的半径R,新补半圆异形灌注桩2的异形弧与圆形灌注桩1的圆弧相匹配,二者可组成椭圆形桩。
新补半圆异形灌注桩2的箍筋7与其纵筋5先固定成钢筋笼再放入新挖的桩孔内。
与现有技术相比,本发明采用新补半圆异形灌注桩与失去部分承载能力的圆形灌注桩组合成椭圆形桩基础共同受力,来满足桩的承载力设计要求,为被检测灌注桩失去部分承载能力且施工面较为狭窄的情况下,桩基础的加固提供了安全可靠地处理方法。
附图说明
图1:本发明的结构图;
图2:本发明的结构图;
图3:本发明的剖面图。
具体实施方式
实施例:紧挨圆形灌注桩1的两边挖出新补半圆异形灌注桩2的桩孔,其中圆形灌注桩1的中心位置与新补半圆异形灌注桩2的中心位置间的间距为a,新补半圆异形灌注桩2的半径R等于圆形灌注桩1的半径R,新补半圆异形灌注桩2的异形弧与圆形灌注桩1的圆弧相匹配,二者可组成椭圆形桩;再将圆形灌注桩1的护壁及保护层混凝土打掉,并露出圆形灌注桩1的箍筋6;然后将新补半圆异形灌注桩2的箍筋7与其纵筋5先固定成钢筋笼再放入新挖的桩孔内,将箍筋7与箍筋6焊接在一起,再灌入混凝土,最后将圆形灌注桩1的纵筋4与纵筋5一起按构造要求锚入桩基承台3内。

Claims (3)

1.一种桩基础的加固处理方法,其特征在在:紧挨圆形灌注桩(1)的两边挖出新补半圆异形灌注桩(2)的桩孔,将新补半圆异形灌注桩(2)的箍筋(7)和纵筋(5)放入新挖的桩孔内,将箍筋(7)与圆形灌注桩(1)的箍筋(6)连接在一起,再灌入混凝土,最后将圆形灌注桩(1)的纵筋(4)与纵筋(5)一起按构造要求锚入桩基承台(3)内。
2.根据权利要求1所述的桩基础的加固处理方法,其特征在于:圆形灌注桩(1)位于新补半圆异形灌注桩(2)的中心位置,新补半圆异形灌注桩(2)的半径R等于圆形灌注桩(1)的半径R。
3.根据权利要求1所述的桩基础的加固处理方法,其特征在于:新补半圆异形灌注桩(2)的箍筋(7)与其纵筋(5)先固定成钢筋笼再放入新挖的桩孔内。
CN 200810300789 2008-03-31 2008-03-31 一种桩基础的加固处理方法 Expired - Fee Related CN101550705B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810300789 CN101550705B (zh) 2008-03-31 2008-03-31 一种桩基础的加固处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810300789 CN101550705B (zh) 2008-03-31 2008-03-31 一种桩基础的加固处理方法

Publications (2)

Publication Number Publication Date
CN101550705A true CN101550705A (zh) 2009-10-07
CN101550705B CN101550705B (zh) 2012-12-05

Family

ID=41155176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810300789 Expired - Fee Related CN101550705B (zh) 2008-03-31 2008-03-31 一种桩基础的加固处理方法

Country Status (1)

Country Link
CN (1) CN101550705B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410182A (zh) * 2013-08-22 2013-11-27 天津大学 桩基单侧卸荷水平顶拉纠偏及断桩补强加固施工方法
CN103726503A (zh) * 2014-01-08 2014-04-16 中铁十一局集团有限公司 用于加固变形桥桩的锚杆桩加固承台结构及施工方法
CN103741963A (zh) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN104420487A (zh) * 2013-08-21 2015-03-18 贵阳铝镁设计研究院有限公司 一种基础短柱的加固方法及结构
CN105275024A (zh) * 2015-09-29 2016-01-27 华蓝设计(集团)有限公司 有缺陷大直径嵌岩桩竖向承载力检测及加固的方法
CN106087984A (zh) * 2016-07-27 2016-11-09 江苏东合南岩土科技股份有限公司 一种异形钢筋笼以及一种异形抗拔桩的施工方法
CN107023030A (zh) * 2017-03-30 2017-08-08 河海大学 用于潮流能工程的椭圆桩基础及其性能试验装置和方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3689840B2 (ja) * 1999-03-24 2005-08-31 東洋建設株式会社 既設構造物基礎の耐震補強工法
JP2001164561A (ja) * 1999-12-06 2001-06-19 Tone Geo Tech Co Ltd 地中構造物の構築工法
CN100513704C (zh) * 2007-09-05 2009-07-15 哈尔滨工业大学 工程改造用叠合桩的成桩方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104420487A (zh) * 2013-08-21 2015-03-18 贵阳铝镁设计研究院有限公司 一种基础短柱的加固方法及结构
CN103410182A (zh) * 2013-08-22 2013-11-27 天津大学 桩基单侧卸荷水平顶拉纠偏及断桩补强加固施工方法
CN103410182B (zh) * 2013-08-22 2015-07-22 天津大学 桩基单侧卸荷水平顶拉纠偏及断桩补强加固施工方法
CN103741963A (zh) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN103741963B (zh) * 2014-01-06 2015-09-09 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN103726503A (zh) * 2014-01-08 2014-04-16 中铁十一局集团有限公司 用于加固变形桥桩的锚杆桩加固承台结构及施工方法
CN103726503B (zh) * 2014-01-08 2015-07-08 中铁十一局集团有限公司 用于加固变形桥桩的锚杆桩加固承台结构及施工方法
CN105275024A (zh) * 2015-09-29 2016-01-27 华蓝设计(集团)有限公司 有缺陷大直径嵌岩桩竖向承载力检测及加固的方法
CN106087984A (zh) * 2016-07-27 2016-11-09 江苏东合南岩土科技股份有限公司 一种异形钢筋笼以及一种异形抗拔桩的施工方法
CN106087984B (zh) * 2016-07-27 2018-01-19 江苏东合南岩土科技股份有限公司 一种异形钢筋笼以及一种异形抗拔桩的施工方法
CN107023030A (zh) * 2017-03-30 2017-08-08 河海大学 用于潮流能工程的椭圆桩基础及其性能试验装置和方法

Also Published As

Publication number Publication date
CN101550705B (zh) 2012-12-05

Similar Documents

Publication Publication Date Title
CN101550705B (zh) 一种桩基础的加固处理方法
KR101410471B1 (ko) 기존건물 흙막이용 h파일을 이용한 상향식 지하옹벽 제거공법
CN202530367U (zh) 深水复杂地质基础施工***
CN203034464U (zh) 一种桁架式基坑支护结构
CN104018490B (zh) 一种z字型矩形截面抗滑桩及其施工方法
CN103882869A (zh) 一种用于基坑围护的斜向支撑桩结构及其施工方法
CN101967983A (zh) 超挖锚注回填控制深井岩巷底臌的方法
CN205024712U (zh) 一种组合式塔吊基础
CN101532296A (zh) 一种桩基础的加固处理方法
CN203768914U (zh) 一种用于基坑围护的斜向支撑桩结构
CN211571692U (zh) 一种灌注阻尼基桩及基桩结构
CN205576957U (zh) 桩底桩结构
CN209211459U (zh) 一种深埋pba地铁车站围护边桩
CN104018496B (zh) 一种桩身设置水平加腋梁的圆形截面抗滑桩及其施工方法
CN110512667A (zh) 一种处理因水害导致桩基沉降的新方法
WO2011021985A1 (en) Structure supporting system
CN214460568U (zh) 一种顺层岩面上桥梁钢管支架基础
CN112832252B (zh) 一种两侧高差较大的深基坑支护施工方法
CN214219732U (zh) 一种机械旋挖抗滑桩与挡土板的连接结构
CN105003088B (zh) 一种钢结构施工中漏埋埋件的施工方法
CN104018495B (zh) 一种双侧加腋梁圆截面抗滑桩及其施工方法
JP5984286B2 (ja) 地盤内補強工法及びそれにより構築される補強構造体
KR20180062669A (ko) 내진 및 지반강화용 마이크로파일 성형방법 및 상기 방법에 의하여 시공된 내진 및 지반강화용 마이크로파일
CN207499006U (zh) 既有受荷工程基桩检测再恢复结构
JP2006177097A (ja) 地下水位以深における既存杭の鉛直載荷試験方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20150331

EXPY Termination of patent right or utility model