CN101492921B - Arch bar base and construction method - Google Patents

Arch bar base and construction method Download PDF

Info

Publication number
CN101492921B
CN101492921B CN200910037529XA CN200910037529A CN101492921B CN 101492921 B CN101492921 B CN 101492921B CN 200910037529X A CN200910037529X A CN 200910037529XA CN 200910037529 A CN200910037529 A CN 200910037529A CN 101492921 B CN101492921 B CN 101492921B
Authority
CN
China
Prior art keywords
arch bar
arch
bar
foundation
grade beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910037529XA
Other languages
Chinese (zh)
Other versions
CN101492921A (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SINO RISING-SUN CONSTRUCTION GROUP Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200910037529XA priority Critical patent/CN101492921B/en
Publication of CN101492921A publication Critical patent/CN101492921A/en
Application granted granted Critical
Publication of CN101492921B publication Critical patent/CN101492921B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention discloses an arch bar foundation the foundation plate of which comprises a plurality of arch bars with arch sections. As the arch bar shape of the arch bar foundation of the invention has better structural stiffness and better stability than the plate shape of the traditional foundation, capabilities of horizontal force resistance, slippage resistance, differential settlement reduction and the like of the foundation are improved. The invention also provides a construction method of the arch bar foundation, comprising the following steps: 1) leveling the land; 2) producing arch groves; 3) casting and pounding a cushion coat; 4) arranging an arch bar moulding board; 5) arranging a foundation beam moulding board; 6) binding the arch bar and foundation beam steel; 7) casting and pounding arch bar concrete; and 8) casting and pounding foundation beam concrete.

Description

A kind of arch bar base job practices
Technical field
The present invention relates to a kind of arch bar base.The job practices that also relates to this arch bar base.
Background technology
Arch Bar Structure is the simple space thin walled construction of form, bears the space force system effect, and the transfer route of power is short, and Arch Bar Structure is mainly used in superstructure at present.Foundation structure commonly used adopts slabbed construction, and the slabbed construction structural shape is simple, but poor with Arch Bar Structure structure compared rigidity.Arch bar base stability is stronger than slabbed construction in addition, can increase basic horizontal force resistant, antiskid moves and reduce abilities such as relative settlement.
Summary of the invention
Technical problem to be solved by this invention provides a kind of arch bar base job practices, and the rigidity of the arch bar base that this method is made is better.
For this reason, the invention provides a kind of job practices of arch bar base, construction sequence comprises:
1) levelling of the land;
2) carry out the arch groove;
3) water and smash bed course;
4) install the arch bar template;
5) install the grade beam template;
6) colligation arch bar and grade beam reinforcing bar;
7) water and smash the arch bar concrete;
8) water and smash the grade beam concrete.
It is characterized in that: the arch bar radius is identical with post distance or load bearing wall spacing.
The arch bar base of the job practices manufacturing of arch bar base provided by the invention has the better rigidity of structure, and stability is better, and horizontal force resistant, the antiskid that therefore can strengthen this kind basis moves and reduce ability such as relative settlement.
Description of drawings
Fig. 1 arch bar base plan view
Fig. 2 arch bar base sectional drawing
Accompanying drawing sign: 1, arch bar, 2, foundation soil, 3, grade beam.
The specific embodiment
As shown in Figure 1 and Figure 2, arch bar base foundation slab provided by the invention is arch arch bar 1 by a plurality of cross sections and constitutes, and the junction of arch bar 1 is provided with arch bar base reinforcing bar extension 2, is cast with grade beam between the adjacent arch bar 1.
The design procedure of arch bar base provided by the invention comprises:
1) determines the arch bar radius.
Determine the arch bar radius according to post distance or load bearing wall spacing.
2) determine that arch bar chooses length.
According to the total load of building and the bearing capacity of foundation soil, try to achieve required foundation ' s bottom area, so that the preliminary outer length of choosing of determining each limit, basis, externally choose part and carry out rigidity checking, adjust according to checking computation results.It is as follows to choose the length computation formula outside minimum:
a=3K bR/2E cλ 2h 3
A is that length is chosen on the basis in the formula; K bBe the ground coefficient of subgrade reaction; R is the arch bar radius; E cBe modulus of elasticity of concrete; λ is the rigidity characteristic coefficient of foded plate foundation, gets 0.6~0.7; H is an arch bar thickness.
3) determine the arch bar thickness of slab.
Bending resistance, shear strength according to arch bar require to select suitable thickness of slab.Thickness of slab is got the number of plies and be multiply by 3cm generally speaking, and is not less than 10cm.For the end gable, consider that counter-force is concentrated and influence such as overhanging arch bar loading characteristic, its average counter-pressure be multiply by enhancement coefficient 1.15, guarantee the trouble free service of arch bar.
4) grade beam is set.
In order to bear the uneven horizontal force that adjacent arch junction exists, reduce the relative displacement of the adjacent arch seam in stressed back, under cross wall, be provided with and connect horizontal grade beam.Elongated end socket beam should be established in the arch bar base end, strengthens basic longitudinal rigidity, bears the integrally bending effect of building on the weak soil, and bears the uneven horizontal force of handing over the ridge place, restriction arch bar crease place lateral deflection.For grade beam under vertical wall, should look the length of building and the uniformity of ground and get 35~70cm, the grade beam depth of section must satisfy the restrictive condition of section edges maximum tension stress.
5) determine basic arrangement of reinforcement.
The arch bar longitudinal reinforcement is by support moment minimum value control in the moment of flexure and first of the part of encorbelmenting.The grade beam arrangement of reinforcement need be considered the arch bar counter-force.To strengthen the arch bar arrangement of reinforcement at bigger place, aperture of door hole.
Its job practices comprises:
Embodiment 1:
1) levelling of the land.
Levelling of the land rolls with road roller when place soil is smooth back and forth to design elevation, is pressed onto till the no vestige.To carry out yard drain after the levelling of the land.
2) carry out the arch groove.
Do the arch groove on foundation soil 2, check size behind the arch Slot shaping, departure is in 10mm.Arch should reduce open-assembly time after groove finishes as far as possible, is strictly on guard against to expose to the sun and rain and steeped by water logging, avoids encircleing the groove distortion.
3) water and smash bed course.
Bed course adopts the C20 fine-stone concrete, and the fine-stone concrete cushion thickness is 50cm, and native tire scale error is eliminated as far as possible in this bed course.
4) install arch bar 1 template.
Arch bar 1 radius is identical with post distance or load bearing wall spacing.Bending resistance, shear strength according to arch bar 1 require to select suitable thickness of slab.Arch bar 1 thickness is got the number of plies and be multiply by 3cm, and is not less than 10cm.
According to the total load of building and the bearing capacity of foundation soil, try to achieve required foundation ' s bottom area, so that the preliminary outer length of choosing of determining each limit, basis, externally choose part and carry out rigidity checking, adjust according to checking computation results.
It is as follows that arch bar 1 is chosen the length computation formula:
a=3K bR/2E cλ 2h 3
A is that length is chosen on the basis in the formula; K bBe the ground coefficient of subgrade reaction; R is the arch bar radius; E cBe modulus of elasticity of concrete; λ is the rigidity characteristic coefficient of arch bar base, gets 0.6~0.7; H is an arch bar thickness.
For end gable arch bar 1, consider that counter-force is concentrated and influence such as overhanging arch bar 1 loading characteristic, its average counter-pressure be multiply by enhancement coefficient 1.15, guarantee the trouble free service of arch bar 1.
The strict control of arch bar 1 template axis, deviation must not surpass 1mm.
5) install grade beam 3 templates.
Hand over the ridge place that grade beam 3 is set at two arch bars.The friendship ridge place of arch bar 1 must be provided with grade beam 3, and grade beam 3 width are greater than wall thickness, and thickness is 30cm, and grade beam 3 is 50~70cm highly, plays the effect of distribution loading and the brick house of reinforcement globality.
Elongated end socket beam should be established in the arch bar base end, strengthens basic longitudinal rigidity, bears the integrally bending effect of building on the weak soil, and bears the uneven horizontal force of handing over the ridge place, restriction arch bar 1 crease place lateral deflection.
Grade beam 3 template deviations must not surpass 2mm.
6) colligation arch bar base reinforcing bar.
Arch bar 1 longitudinal reinforcement is by support moment minimum value control in the moment of flexure and first of the part of encorbelmenting.Arch bar 1 arrangement of reinforcement sectional area will strengthen 15% at place, aperture of door hole.
7) water and smash arch bar 1 concrete.
Water arch bar 1 concrete earlier to grade beam 3 soffits, constuction joint has been stayed the bottom of grade beam 3.At the arch bar concrete L shaped Φ 6 reinforcing bars are set, L shaped reinforcing bar Φ 6 length are 30cm, and spacing is 400cm.
8) water and smash grade beam 3 concrete.
Treat that arch bar 1 solidifies more than the 12h formwork again and builds grade beam 3 concrete.
Embodiment 2:
1) levelling of the land.
Levelling of the land rolls with road roller when place soil is smooth back and forth to design elevation, is pressed onto till the no vestige.To carry out yard drain after the levelling of the land.
2) carry out the arch groove.
Do the arch groove on foundation soil 2, check size behind the arch Slot shaping, departure is in 10mm.Arch should reduce open-assembly time after groove finishes as far as possible, is strictly on guard against to expose to the sun and rain and steeped by water logging, avoids encircleing the groove distortion.
3) water and smash bed course.
Bed course adopts the C20 fine-stone concrete, and the fine-stone concrete cushion thickness is 50cm, and native tire scale error is eliminated as far as possible in this bed course.
4) place prefabricated arch bar 1.
Prefabricated arch bar 1 radius is identical with post distance or load bearing wall spacing.Prefabricated arch bar 1 thickness is got the number of plies and be multiply by 3cm, and is not less than 10cm.
According to the total load of building and the bearing capacity of foundation soil, try to achieve required foundation ' s bottom area, so that the preliminary outer length of choosing of determining each limit, basis, externally choose part and carry out rigidity checking, adjust according to checking computation results.
It is as follows that prefabricated arch bar 1 is chosen the length computation formula:
a=3K bR/2E cλ 2h 3
A is that length is chosen on the basis in the formula; K bBe the ground coefficient of subgrade reaction; R is the arch bar radius; E cBe modulus of elasticity of concrete; λ is the rigidity characteristic coefficient of arch bar base, gets 0.6~0.7; H is an arch bar thickness.
For the prefabricated arch bar 11 of end gable, consider that counter-force is concentrated and influence such as overhanging prefabricated arch bar 11 loading characteristics, its average counter-pressure be multiply by enhancement coefficient 1.15, guarantee the trouble free service of prefabricated arch bar 1.
Prefabricated arch bar 1 termination is provided with U-shaped Φ 8 reinforcing bars, and U-shaped reinforcing bar Φ 8 length are 50cm, and the contiguous prefabricated arch bar of U-shaped reinforcing bar effectively connects by the welding of U-shaped reinforcing bar.
5) install grade beam 3 templates.
Hand over the ridge place that grade beam 3 is set at two arch bars.The friendship ridge place of arch bar 1 must be provided with grade beam 3, and grade beam 3 width are greater than wall thickness, and thickness is 30cm, and grade beam 3 is 50~70cm highly, plays the effect of distribution loading and the brick house of reinforcement globality.
Elongated end socket beam should be established in the arch bar base end, strengthens basic longitudinal rigidity, bears the integrally bending effect of building on the weak soil, and bears the uneven horizontal force of handing over the ridge place, restriction arch bar 1 crease place lateral deflection.
Grade beam 3 template deviations must not surpass 2mm.
6) water and smash grade beam 3 concrete.

Claims (4)

1. the job practices of an arch bar base, construction sequence comprises:
1) levelling of the land;
2) carry out the arch groove;
3) water and smash bed course;
4) install the arch bar template;
5) install the grade beam template;
6) colligation arch bar and grade beam reinforcing bar;
7) water and smash the arch bar concrete;
8) water and smash the grade beam concrete.
It is characterized in that: the arch bar radius is identical with post distance or load bearing wall spacing.
2. arch bar base job practices according to claim 1 is characterized in that: the grade beam height is 50~70cm, and thickness is 30cm.
3. arch bar base job practices according to claim 1 is characterized in that: at the arch bar concrete L shaped Φ 6 reinforcing bars are set, L shaped reinforcing bar Φ 6 length are 30cm, and spacing is 400cm.
4. arch bar base job practices according to claim 1 is characterized in that: prefabricated arch bar termination is provided with U-shaped Φ 8 reinforcing bars, and U-shaped reinforcing bar Φ 8 length are 50cm, and the contiguous prefabricated arch bar of U-shaped reinforcing bar effectively connects by the welding of U-shaped reinforcing bar.
CN200910037529XA 2009-02-25 2009-02-25 Arch bar base and construction method Expired - Fee Related CN101492921B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910037529XA CN101492921B (en) 2009-02-25 2009-02-25 Arch bar base and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910037529XA CN101492921B (en) 2009-02-25 2009-02-25 Arch bar base and construction method

Publications (2)

Publication Number Publication Date
CN101492921A CN101492921A (en) 2009-07-29
CN101492921B true CN101492921B (en) 2011-06-08

Family

ID=40923706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910037529XA Expired - Fee Related CN101492921B (en) 2009-02-25 2009-02-25 Arch bar base and construction method

Country Status (1)

Country Link
CN (1) CN101492921B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499497B (en) * 2014-11-21 2017-01-18 朱奎 Concrete brick-sandwiched folded plate foundation
CN106087944B (en) * 2016-08-23 2018-08-28 福州市第三建筑工程公司 A kind of construction method of ground structure applied to soft soil foundation

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张庆辉,李继业.薄壳反拱基础在工程上的应用.中外建筑 2000年第2期.2000,(2000年第2期),第76-77页.
张庆辉,李继业.薄壳反拱基础在工程上的应用.中外建筑 2000年第2期.2000,(2000年第2期),第76-77页. *
贺炳庆.在软弱地基上采用筏式倒圆筒壳基础.《建筑结构学报》.1983,78-79. *

Also Published As

Publication number Publication date
CN101492921A (en) 2009-07-29

Similar Documents

Publication Publication Date Title
CN101570960B (en) Fastening method of T-shaped beam bridge
CN105369729A (en) External prestressing corrugated steel web T-shaped beam and construction method
CN101994325B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN104233942A (en) Method for enhancing overall stress on assembled type heterotropic pre-stress hollow slab beam bridge
KR20180014793A (en) Double wall structure construction method using connection steel beam and wall structure construction method therewith
CN102864854A (en) L-shaped precast concrete wall connection
CN104674658A (en) Single layer FRP concrete composite bridge slab construction method
CN103046463A (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN110042770A (en) A method of using the original bridge of external prestressing steel Shu Tuokuan in length and breadth
CN101492921B (en) Arch bar base and construction method
CN106012806A (en) Hollow slab hinge joint shear connection structure and construction process
CN210262769U (en) Hollow slab bridge reinforcing and widening structure
CN107916625B (en) Widening structure and method for wide cantilever box girder
CN205954971U (en) Two -way coincide floor of honeycomb holes profiled sheet
CN202450441U (en) Stiffness matching system for broadening and transforming hollow slab bridges
CN202466913U (en) Concrete overlapping plate connected by 180 DEG bent reinforcing steel anchor within span
CN205917862U (en) Connected node on basis
CN213142814U (en) Utilize UHPC's T-shaped roof beam web reinforced structure
CN209760323U (en) Pile foundation off normal cushion cap roof beam reinforced structure
CN113653508A (en) Bridge-lining combined structure with tunnel inner crossing function and construction method thereof
KR102133079B1 (en) Structure of column and flat plate slab
CN203080397U (en) Assembly-type saddle-shell-shaped bottom plate continuous box girder bridge
KR100962677B1 (en) Assembled bridge for constructing an assembled bridge
CN110777658A (en) Construction method of inverted splayed cast-in-place arc-shaped wing web formwork system
CN211571766U (en) Assembled light steel structure base that stability is good

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Free format text: FORMER OWNER: ZHU KUI

Effective date: 20141211

Owner name: ZHANG XUDONG

Free format text: FORMER OWNER: YE CHANGQING

Effective date: 20141211

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Xudong

Inventor before: Zhu Kui

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHU KUI TO: ZHANG XUDONG

Free format text: CORRECT: ADDRESS; FROM: 325000 WENZHOU, ZHEJIANG PROVINCE TO: 239000 CHUZHOU, ANHUI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20141211

Address after: Langya District of Anhui city in Chuzhou province to support 239000 West Road No. 121 building 6 room 105

Patentee after: Zhang Xudong

Address before: 325000 No. 4, Jinchuan Road, Longwan District, Zhejiang, Wenzhou

Patentee before: Ye Changqing

Patentee before: Zhu Kui

ASS Succession or assignment of patent right

Owner name: SINO RISING-SUN CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: ZHANG XUDONG

Effective date: 20141224

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 239000 CHUZHOU, ANHUI PROVINCE TO: 239001 CHUZHOU, ANHUI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20141224

Address after: 239001 Anhui province Chuzhou Nanqiao Road North Street Management Office

Patentee after: SINO RISING-SUN CONSTRUCTION GROUP CO., LTD.

Address before: Langya District of Anhui city in Chuzhou province to support 239000 West Road No. 121 building 6 room 105

Patentee before: Zhang Xudong

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110608

Termination date: 20150225

EXPY Termination of patent right or utility model