CN101435269B - Prestress pipe anti-blocking method - Google Patents

Prestress pipe anti-blocking method Download PDF

Info

Publication number
CN101435269B
CN101435269B CN2008101479357A CN200810147935A CN101435269B CN 101435269 B CN101435269 B CN 101435269B CN 2008101479357 A CN2008101479357 A CN 2008101479357A CN 200810147935 A CN200810147935 A CN 200810147935A CN 101435269 B CN101435269 B CN 101435269B
Authority
CN
China
Prior art keywords
water bag
water
prestress pipe
pipeline
blocking method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008101479357A
Other languages
Chinese (zh)
Other versions
CN101435269A (en
Inventor
马斌
万宗江
卿三惠
谢卜均
张明书
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 5th Engineering Co Ltd
Original Assignee
China Railway Erju Co Ltd
China Railway Erju 5th Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd, China Railway Erju 5th Engineering Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN2008101479357A priority Critical patent/CN101435269B/en
Publication of CN101435269A publication Critical patent/CN101435269A/en
Application granted granted Critical
Publication of CN101435269B publication Critical patent/CN101435269B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pipe Accessories (AREA)

Abstract

The invention discloses a prestressed pipeline anti-blocking method, which comprises the following steps: the first step, a single steel twisted wire is adopted as a lead wire to penetrate the pipeline after the prestressed pipeline is mounted; the second step, the lead wire leads a water bas to a water bag penetrating prestressed pipeline; the third step, the two ends of the water bag are mounted with valves, and the water bag is filled with high pressure water; the fourth step, the valves at the two ends of the water bag are closed after the high pressure water is full; and the fifth step, concrete is poured, and the water in the water bag is pumped out after the concrete is poured and solidified, then the water bag is pulled out, and the prestressed pipeline is cleared to guarantee the pipeline unblocked. The method has good anti-blocking function and effect to long distance prestressed pipeline, low cost, and convenient construction.

Description

Prestress pipe anti-blocking method
Technical field
The present invention relates to the realm of building construction, especially a kind of prestress pipe anti-blocking method.
Background technology
In Post-tension Prestress Construction, the anti-blocking main employing polyethylene pipe of bellows (mainly refer to here when concreting not the bellows of steel strand bundle) is as stay tube in it, polyethylene pipe self strength ratio is higher, can play good inner support effect to bellows, prevent that bellows from stopping up because of pipeline is damaged the infiltration concrete in concreting process, but polyethylene pipe costs an arm and a leg, while is because himself intensity is higher, not flexible, the operation easier that runs through polyethylene pipe for long bellows pipeline is bigger.Big when bellows quantity, when pipeline is longer, in pre-stress construction, adopt polyethylene pipe low as interior stay tube practicality, can not play good effect to the anti-blocking of bellows.
Summary of the invention
The purpose of this invention is to provide a prestress pipe anti-blocking method, these method concrete steps are as follows:
The first step after the prestress pipe installation, runs through pipeline with single steel strand as lead-in wire;
In second step, connect prestress pipe with lead-in wire traction water bag to water bag, as shown in Figure 1;
In the 3rd step, water bag two ends mounted valve dashes to water bag and to increase setting-out;
The 4th one, after filling it up with, water under high pressure closes water bag two ends valve, guarantee that enough water pressures are arranged in the water bag (in order to allow the water pressure in the water bag lasting, the port valve at water bag two ends improves as far as possible, with the prestressed pipe road junction the bigger discrepancy in elevation is arranged), the water bag installation is shown in figure two;
The 5th step, concreting, concreting finish and initial set after extract water in the water bag out, extract water bag, the cleaning prestress pipe guarantees that pipeline is unimpeded.
Adopt the rubber water bag to carry out the advantage that prestress pipe anti-blocking has three aspects:
1, after the rubber water bag is full of water under high pressure, can bear concrete pressure, play good effect preventing that prestress pipe from stopping up;
2, since rubber water bag price than polyethylene pipe at the bottom of, saved construction cost;
3, adopt the anti-blocking equipment of rubber water bag as prestress pipe, simple to operate, easy construction is than adopting the easier operation of polyethylene pipe.
Description of drawings
The present invention will illustrate by example and with reference to the mode of accompanying drawing, wherein:
Fig. 1 is a water bag installation process schematic diagram.
Fig. 2 is a water bag installation schematic diagram.
The specific embodiment
The present invention adopts the anti-blocking material of common rubber water bag as prestress pipe, is used to protect prestress pipe.The rubber water bag arranges at prestress pipe and finishes that install before the concreting, its concrete anti-blocking method process is as follows:
1, after the prestress pipe installation, runs through pipeline as lead-in wire with single steel strand;
2, connect prestress pipe with lead-in wire traction water bag to water bag, as shown in Figure 1;
3, water bag two ends mounted valve dashes to water bag and to increase setting-out;
4, close water bag two ends valve after water under high pressure is filled it up with, guaranteeing has enough water pressures in the water bag, generally at 0.06~0.08MPa; In order to allow the water pressure in the water bag lasting, the port valve at water bag two ends improves as far as possible, with the prestressed pipe road junction the bigger discrepancy in elevation is arranged, and generally can be controlled in the scope of 1.5~3.0m according to the concrete height of building, and the water bag installation is shown in figure two;
5, concreting, concreting finish and initial set after extract water in the water bag out, extract water bag, the cleaning prestress pipe guarantees that pipeline is unimpeded.
Its diameter generally got final product than the little 1.0~1.5cm of prestressing force inside diameter of bel when the rubber water bag adopted.Learn that by test the rubber water bag can bear the pressure of 0.1MPa at least, can bear fully that concrete plays the effect of inner support to the pressure of pipeline to pipeline in the concreting process.
Adopt the rubber water bag as interior stay tube can solve long apart from prestress pipe with polyethylene pipe the unconspicuous problem of effect when anti-blocking, its price is than polyethylene pipe cheap 3/4 simultaneously, and self softness, can curl, fitting operation is very convenient, can customize corresponding rubber water bag according to prestress pipe different length and specification.In view of the advantage more than the rubber water bag, in the prestress pipe anti-blocking construction, adopt the rubber water bag can satisfy construction requirement as stay tube in the pipeline, can reduce construction cost again, be suitable for extensively promoting in the Post-tension Prestress Construction afterwards.
Disclosed all features in this manual, or the step in disclosed all methods or the process except mutually exclusive feature and/or step, all can make up by any way.
Disclosed arbitrary feature in this manual (comprising any accessory claim, summary and accompanying drawing) is unless special narration all can be replaced by other equivalences or the alternative features with similar purpose.That is, unless special narration, each feature is an example in a series of equivalences or the similar characteristics.
The present invention is not limited to the aforesaid specific embodiment.The present invention expands to any new feature or any new combination that discloses in this manual, and the arbitrary new method that discloses or step or any new combination of process.

Claims (4)

1. prestress pipe anti-blocking method is characterized in that these method concrete steps are as follows:
The first step after the prestress pipe installation, runs through pipeline with single steel strand as lead-in wire;
In second step, connect prestress pipe with lead-in wire traction water bag to water bag;
In the 3rd step, water bag two ends mounted valve dashes to water bag and to increase setting-out;
In the 4th step, after filling it up with, water under high pressure closes water bag two ends valve;
The 5th step, concreting, concreting finish and initial set after extract water in the water bag out, extract water bag, the cleaning prestress pipe guarantees that pipeline is unimpeded;
Wherein said water bag is the rubber water bag.
2. prestress pipe anti-blocking method as claimed in claim 1 is characterized in that: the diameter of described rubber water bag is than the little 1.0~1.5cm of prestress pipe internal diameter.
3. prestress pipe anti-blocking method as claimed in claim 1 is characterized in that: described the 4th step water under high pressure is filled it up with back pressure at 0.06~0.08MPa.
4. prestress pipe anti-blocking method as claimed in claim 1 is characterized in that: the port valve at described water bag two ends improves as far as possible, with the prestressed pipe road junction discrepancy in elevation of 1.5~3.0m is arranged.
CN2008101479357A 2008-12-22 2008-12-22 Prestress pipe anti-blocking method Active CN101435269B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101479357A CN101435269B (en) 2008-12-22 2008-12-22 Prestress pipe anti-blocking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101479357A CN101435269B (en) 2008-12-22 2008-12-22 Prestress pipe anti-blocking method

Publications (2)

Publication Number Publication Date
CN101435269A CN101435269A (en) 2009-05-20
CN101435269B true CN101435269B (en) 2010-09-01

Family

ID=40709889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101479357A Active CN101435269B (en) 2008-12-22 2008-12-22 Prestress pipe anti-blocking method

Country Status (1)

Country Link
CN (1) CN101435269B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107143752A (en) * 2017-07-11 2017-09-08 中铁二十四局集团福建铁路建设有限公司 A kind of prestress pipe deformation and spillage detector and its application method

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101985819B (en) * 2010-09-14 2012-02-01 安徽万邦高森造纸有限公司 Process for producing low-basis-weight waxed base paper
CN103726664B (en) * 2013-12-25 2015-12-09 中铁十三局集团有限公司 Reeve method in reeve device and clear hole, a kind of clear hole, post-tensioned prestressing duct
CN104179354B (en) * 2014-08-29 2016-05-18 上海建工七建集团有限公司 Prestressing force bellows dredge and using method thereof
CN105443864B (en) * 2015-08-27 2017-12-05 中国十七冶集团有限公司 A kind of method for preventing bellows to be destroyed in packing course
CN107338729A (en) * 2017-07-11 2017-11-10 中铁四局集团第二工程有限公司 A kind of prestress pipe anti-blocking device and construction method
CN112832537B (en) * 2021-01-11 2022-05-13 中国十七冶集团有限公司 Construction method for preventing blockage and pipe blockage caused by slurry leakage of prestressed pre-buried pipeline
CN113832955A (en) * 2021-09-02 2021-12-24 上海隧道工程有限公司 Filling structure of profile steel underground continuous wall lock catch joint and using method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107143752A (en) * 2017-07-11 2017-09-08 中铁二十四局集团福建铁路建设有限公司 A kind of prestress pipe deformation and spillage detector and its application method
CN107143752B (en) * 2017-07-11 2019-06-21 中铁二十四局集团福建铁路建设有限公司 A kind of deformation of prestress pipe and spillage detector and its application method

Also Published As

Publication number Publication date
CN101435269A (en) 2009-05-20

Similar Documents

Publication Publication Date Title
CN101435269B (en) Prestress pipe anti-blocking method
CN201722685U (en) No-adhesive prestress and pile side rear grouting punching pile structure
CN104389314B (en) A kind of shallow clay grouting and reinforcing device and method
CN102425311B (en) Concrete structure reinforcing method based on near surface mounted prestressed FRP (Fiber Reinforced Polymer)
CN103850441B (en) A kind of stretch-draw construction method of prestressed reinforced concrete construction and tensioning equipment
CN201801861U (en) Repeated self-adaptive grouting system
CN203307803U (en) Pre-stress pressure type anti-floating anchor rod with spiral stirrup
CN204551461U (en) A kind of pressure dispersing type electric hoist enlarged footing anchor cable
CN102704971A (en) Grouting and Grouting-stopping anchor cable inside hole
KR101748432B1 (en) Method for flexible grouting using flexible grout composite of sheath pipe in psc bridge
CN102345292B (en) A kind of composite prestressed uplift pile with enlarged footing
CN100532727C (en) Water-stopping treatment method for steel reinforced concrete pipe culvert
CN105649074A (en) Tubular pile expansion concrete stiffened composite pile and construction method thereof
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN103603337A (en) Grouting precast pile and grouting method
CN204385727U (en) Spiral grouting preformed pile
CN103898839A (en) Bridge supplementary pile preloading consolidation method
CN105332716A (en) Adaptive lining structure capable of bearing simultaneous actions of high internal and external water
CN108360510A (en) A kind of grouting behind shaft or drift lining system and method increasing perfusion shaft resistance
CN104818861A (en) Pre-stress floor reinforcement method
CN103790180B (en) The building pile body construction method of the underground space and underground space building structure
CN110424635A (en) Grouting sleeve and construction method thereof
CN206581264U (en) A kind of reducing multinode churning anti-float anchor rod
CN207727614U (en) Spliced piping lane sealing structure
CN107387883A (en) A kind of structure sheaf pipeline waterproof technique

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160107

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

Address before: 610041 high building, No. nine Hing Road, Chengdu hi tech Development Zone, Sichuan, 6

Patentee before: CHINA RAILWAY ERJU Co.,Ltd.

Patentee before: CHINA RAILWAY ERJU 5TH ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190109

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: CHINA RAILWAY ERJU 5TH ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

TR01 Transfer of patent right