CN101429763A - Bamboo spar grillage ultra-soft soil base surface treatment structure - Google Patents

Bamboo spar grillage ultra-soft soil base surface treatment structure Download PDF

Info

Publication number
CN101429763A
CN101429763A CNA2008101541822A CN200810154182A CN101429763A CN 101429763 A CN101429763 A CN 101429763A CN A2008101541822 A CNA2008101541822 A CN A2008101541822A CN 200810154182 A CN200810154182 A CN 200810154182A CN 101429763 A CN101429763 A CN 101429763A
Authority
CN
China
Prior art keywords
bamboo
layer
spar
ultra
soft soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008101541822A
Other languages
Chinese (zh)
Inventor
唐元松
尹广田
***
蔡波
刘宏伟
潘秉忠
李学艳
刘雷
周宝江
朱子平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbour Consultants Co Ltd
Original Assignee
CCCC First Harbour Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbour Consultants Co Ltd filed Critical CCCC First Harbour Consultants Co Ltd
Priority to CNA2008101541822A priority Critical patent/CN101429763A/en
Publication of CN101429763A publication Critical patent/CN101429763A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention provides a bamboo spar grillwork structure for treating the surface layer of an ultra-soft soil foundation. The structure is arranged on the surface layer of the ultra-soft soil foundation and provided with a bottom layer, a bamboo spar layer and a surface layer in turn, wherein the bottom layer is a geotechnological cloth layer or a grille layer; the bamboo spar layer is a bamboo spar layer which takes the shape of a grid beam and is formed by bundling vertical bamboo spars and the horizontal bamboo spars; and the surface layer is a bedding surface or geotechnological cloth which is made of wattle sheathings, bamboo sheathings or geotechnological grilles, has certain strength and hardness and takes the shape of a grid beam. The bamboo spar grillwork structure has the advantages that the structure can form a working surface on which an artificial machine or a light machine can be operated on the ultra-soft soil foundation, perform further operation on the ultra-soft soil foundation, and make staff and equipment directly enter the ultra-soft soil foundation. The bamboo spar grillwork structure lays bamboo spar grillwork at the bottom or in the middle of the wattle sheathings on the basis of the prior principle of laying the wattle sheathings, so as to increase the rigidity of the wattle sheathings and the stress area of the ultra-soft soil foundation, and reduce the amount of the wattle sheathings and the bamboo sheathings, thereby saving expense and achieving the aim that the artificial machine or the light machine can be operated.

Description

Bamboo spar grillage ultra-soft soil base surface is handled structure
Technical field
The present invention relates to the foundation treatment technology in civil engineering work field, particularly a kind of bamboo spar grillage ultra-soft soil base surface is handled structure, be applicable to that stream mud, mud and the mucky soil of hydraulic reclamation adopt construction fields such as consolidation recently, particularly great to the resourceful regional application value of bamboo punt-pole.
Background technology
When handled on traditional soft foundation top layer, the method for treating surface layer on the soft foundation was generally to lay as to lay geotextiles, chaste tree basketry, bamboo basketry, geo-grid etc.But on super soft ground, because the pliability of chaste tree basketry, bamboo basketry, if lay the chaste tree basketry merely, the bamboo basketry needs wide variety of materials, laying flexible primer, but on the top layer based on the zone of stream mud, the above flexible bottom layer material of simple laying, can cause a large amount of of material to sink, thereby cause the waste of material, the support strength of a spot of flexible bottom layer material can not reach the purpose of bearing manual work or light-duty machinery operation.
Summary of the invention
For solving the problem in the above-mentioned technology, the purpose of this invention is to provide a kind of bamboo spar grillage ultra-soft soil base surface and handle structure, be beneficial to reduce demand to the flexible bottom layer quantity of material, shorten the cost of duration of a project and reduction engineering.
For achieving the above object, the technical solution used in the present invention provides a kind of bamboo spar grillage ultra-soft soil base surface and handles structure, and this structure places the super soft ground top layer, and wherein: this structure is provided with bottom, bamboo punt-pole layer and surface layer successively; Described bottom is geotechnological layer of cloth or grid layer, described bamboo punt-pole layer is that horizontal vertical bamboo punt-pole is tied up and compiled the bamboo punt-pole layer be linked as the grid beam shape, a kind of for the aspect of the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making or geotextiles of described surface layer.
Directly be equipped with bamboo punt-pole layer on described super soft ground surface.
In described super soft ground surface laying chaste tree basketry, geotextiles is bottom, repaves on this bottom and is provided with bamboo punt-pole layer.
Described grid layer is the aspect that adopts the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making.
On described bamboo punt-pole layer, be equipped with grid layer, geotechnological layer of cloth or wherein a kind of successively.
Effect of the present invention be this structure can super soft ground form can carry out work that artificial or light-duty machinery can operation and, can on super soft ground, carry out next step operation, thereby solve the problem that personnel, equipment can not enter super soft ground.Thereby cause cost too high.Bamboo punt-pole frame structure is on the principle of traditional laying chaste tree basketry, laid bamboo punt-pole screen work at chaste tree basketry bottom or centre, thereby strengthened the rigidity of chaste tree basketry, strengthened the lifting surface area that surpasses soft foundation, reduced the consumption of chaste tree basketry, bamboo basketry, thereby saved expense and reached the purpose that artificial or light-duty machinery can operation.
Description of drawings
Fig. 1 is a bamboo punt-pole frame structure sectional schematic diagram of the present invention.
1, geotechnological layer of cloth 2, grid layer 3, bamboo punt-pole layer
The specific embodiment
Below in conjunction with accompanying drawing bamboo punt-pole frame structure super soft ground of the present invention top layer processing structure and utilization are further specified.
The dominant ideas that structure is handled on bamboo punt-pole frame structure super soft ground of the present invention top layer are this structure engineering characteristics in conjunction with ultra-soft soil district, adopt bamboo punt-pole frame structure, need manually lay.
At first, determine whether to lay primer, lay horizontal vertical bamboo punt-pole then, horizontal vertical bamboo punt-pole is banded together form bamboo punt-pole screen work, to carry the overall performance of bamboo punt-pole according to soft clay area soil property situation.Determine whether surface materials such as needs laying bamboo basketry, chaste tree basketry, geo-grid again according to the soil property situation.These materials form the construction surface layer of the artificial or light-duty machinery operation of the confession on a super soft ground top layer with certain intensity together.By this processing, reduced the flexible bottom layer material, as the demand of quantity of material such as chaste tree basketry, bamboo basketry, geo-grid, obtain the purpose that shortens the duration of a project and reduce construction costs.
Structure is handled on bamboo punt-pole frame structure super soft ground of the present invention top layer: this structure places the super soft ground top layer, and this structure is provided with bottom, bamboo punt-pole layer and surface layer successively; Described bottom is geotechnological layer of cloth 1 or grid layer 2, described bamboo punt-pole layer 3 is that horizontal vertical bamboo punt-pole is tied up and compiled the bamboo punt-pole layer be linked as the grid beam shape, a kind of for the aspect of the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making or geotextiles of described surface layer.
Directly be equipped with bamboo punt-pole layer 3 on described super soft ground surface, also can lay the chaste tree basketry, geotextiles is a bottom, repave on this bottom to be provided with bamboo punt-pole layer 3.
Described grid layer 2 is the aspects that adopt the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making.
On described bamboo punt-pole layer 3, also can be equipped with grid layer 2, geotechnological layer of cloth 1 or wherein a kind of successively.
Bamboo punt-pole frame structure super soft ground of the present invention top layer is handled structure and is achieved in that
1. laying primer
So-called primer comprises materials such as geotextiles, woven cloth, chaste tree basketry, bamboo basketry, geo-grid.Structure is handled on bamboo punt-pole frame structure super soft ground top layer, at first to determine whether needs laying primer according to the soft or hard degree on soft foundation surface, the purpose of laying primer is to solve artificial construction operation face problem of laying bamboo punt-pole screen work, if do not need primer just can carry out manual work, then this step just can be cancelled, and directly carries out the second step operation.
2. lay bamboo punt-pole layer
Lay horizontal vertical bamboo punt-pole with manual method, spacing is determined according to the soft or hard of soil material and the soft or hard of bamboo punt-pole, after laying is finished, with the colligation of horizontal vertical bamboo punt-pole together, forms bamboo punt-pole screen work.
3. paved surface layer material
After laying bamboo punt-pole layer 3, paved surface layer material, surface material comprise chaste tree basketry, bamboo basketry, geo-grid, geotextiles etc.
The integral body of being made up of primer, bamboo punt-pole screen work, surface material has formed super soft ground top layer processing surface layer structure.A place adopts the limit to lay primer usually, and bamboo punt-pole screen work is laid on the limit, the construction of limit paved surface layer material flowing water.The work plane of Xing Chenging is as the scope of operation of construction in later period in advance.
The top layer scope of operation of this super soft ground that is formed by bamboo punt-pole frame structure has certain intensity and toughness, after the scope of operation forms, can carry out next step ground and handle or other work.
Described bamboo punt-pole layer 3 can directly be laid on the super soft ground surface, also can re-lay bamboo punt-pole layer 3 behind soft foundation surface laying chaste tree basketry, geotextiles or other materials---bamboo punt-pole screen work.Can re-lay reinforcement materials such as bamboo basketry, chaste tree basketry, geotextiles grid after laying bamboo punt-pole screen work.Described bamboo punt-pole layer 3 can be that other natural or artificial materials with certain intensity and hardness are replaced, also can be with the material substitution that has the analog material performance with the bamboo punt-pole.
It is that the bamboo punt-pole is laid on the soft foundation surface at a certain distance that structure is handled on bamboo punt-pole frame structure super soft ground of the present invention top layer, transverse and longitudinal is formed bamboo punt-pole screen work, at an upper portion thereof or the bottom spread chaste tree basketry or geo-grid, thereby formed a work plane that can carry out artificial or light-duty machinery can operation at super soft ground.By this processing, can on super soft ground, carry out next step operation, on super soft ground, carry out ground processing operation or other operations thereby solved, personnel's equipment can not enter the problem of super soft ground.
Traditional method for treating surface layer is generally laying chaste tree basketry, bamboo basketry, geotextiles on the soft foundation, but on super soft ground, because the pliability of chaste tree basketry, bamboo basketry, if lay the chaste tree basketry merely, the bamboo basketry needs wide variety of materials, thereby causes cost too high.Bamboo punt-pole frame structure is on the principle of traditional laying chaste tree basketry, laid bamboo punt-pole screen work at chaste tree basketry bottom or centre, thereby strengthened the rigidity of chaste tree basketry, strengthened the lifting surface area that surpasses soft foundation, reduced the consumption of chaste tree basketry, bamboo basketry, thereby saved expense and reached the purpose that artificial or light-duty machinery can operation.

Claims (5)

1. a bamboo spar grillage ultra-soft soil base surface is handled structure, and this structure places the super soft ground top layer, it is characterized in that: this structure is provided with bottom, bamboo punt-pole layer and surface layer successively; Described bottom is geotechnological layer of cloth (1) or grid layer (2), described bamboo punt-pole layer (3) is that horizontal vertical bamboo punt-pole is tied up and compiled the bamboo punt-pole layer be linked as the grid beam shape, a kind of for the aspect of the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making or geotextiles of described surface layer.
2, bamboo spar grillage ultra-soft soil base surface according to claim 1 is handled structure, it is characterized in that: directly be equipped with bamboo punt-pole layer (3) on described super soft ground surface.
3, bamboo spar grillage ultra-soft soil base surface according to claim 1 is handled structure, it is characterized in that: in described super soft ground surface laying chaste tree basketry, geotextiles is bottom, repaves on this bottom and is provided with bamboo punt-pole layer (3).
4, bamboo spar grillage ultra-soft soil base surface according to claim 1 is handled structure, it is characterized in that: described grid layer (2) is the aspect that adopts the grid beam shape with certain intensity and hardness of chaste tree basketry, bamboo basketry or geo-grid making.
5, bamboo spar grillage ultra-soft soil base surface according to claim 1 is handled structure, it is characterized in that: be equipped with grid layer (2), geotechnological layer of cloth (1) or wherein a kind of successively on described bamboo punt-pole layer (3).
CNA2008101541822A 2008-12-17 2008-12-17 Bamboo spar grillage ultra-soft soil base surface treatment structure Pending CN101429763A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008101541822A CN101429763A (en) 2008-12-17 2008-12-17 Bamboo spar grillage ultra-soft soil base surface treatment structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008101541822A CN101429763A (en) 2008-12-17 2008-12-17 Bamboo spar grillage ultra-soft soil base surface treatment structure

Publications (1)

Publication Number Publication Date
CN101429763A true CN101429763A (en) 2009-05-13

Family

ID=40645382

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008101541822A Pending CN101429763A (en) 2008-12-17 2008-12-17 Bamboo spar grillage ultra-soft soil base surface treatment structure

Country Status (1)

Country Link
CN (1) CN101429763A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101942827A (en) * 2010-10-14 2011-01-12 中交一航局第四工程有限公司 Construction method of ultrasoft foundation raft working cushion layer
CN101684649B (en) * 2009-08-21 2012-04-18 中山大学 Method for performing construction operation on large-area ultra-soft soil site and steel frame system used by same
CN108978681A (en) * 2018-08-10 2018-12-11 吴慧明 A kind of method of large area mud place backfill

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101684649B (en) * 2009-08-21 2012-04-18 中山大学 Method for performing construction operation on large-area ultra-soft soil site and steel frame system used by same
CN101942827A (en) * 2010-10-14 2011-01-12 中交一航局第四工程有限公司 Construction method of ultrasoft foundation raft working cushion layer
CN101942827B (en) * 2010-10-14 2012-05-30 中交一航局第四工程有限公司 Construction method of ultrasoft foundation raft working cushion layer
CN108978681A (en) * 2018-08-10 2018-12-11 吴慧明 A kind of method of large area mud place backfill

Similar Documents

Publication Publication Date Title
CN201321593Y (en) Surface layer treatment structure for bamboo spar latticework ultra-soft soil foundation
CN205116185U (en) A supporting construction for weak soil foundation ditch
CN101718089A (en) Combined vacuum preloading method foundation treatment construction method
CN105649005B (en) GSZ joint grouting ultra-soft soil electric osmose construction method
CN201343730Y (en) Ecological protection structure for high rock slope
CN202117068U (en) Micropile plate-type composite foundation
CN110374054A (en) A kind of ecological slope protection consolidates soil structure and method
CN205804078U (en) A kind of pervious concrete pavement structure of band reinforcement
CN101429763A (en) Bamboo spar grillage ultra-soft soil base surface treatment structure
CN109853513A (en) A kind of preparation method of geotechnical grid and the geotechnical grid
CN207092080U (en) A kind of MC stiff composite piles using high-pressure rotary jet grouting pile
CN212896172U (en) River course slope protection and canal bottom structure for ecological reconstruction of black and odorous river course
CN202124863U (en) Screw anchor excavated composite foundation
CN204151767U (en) CFG stake and PHC pile tube combine composite foundation
CN103696435A (en) Water conservancy project retaining wall
CN204081064U (en) Basement sandwich structure
CN202899176U (en) Existing bridge pile foundation cross section increasing reinforced structure
CN201891114U (en) Dual radial mesh cage sandstone pile
CN202099795U (en) Crushed stone pile for reinforcing extremely soft soil foundation
CN205188936U (en) Novel manual work of combination formula is dug hole rectangle friction pile and is protected concrete wall
CN205662896U (en) Check guest web frame that contains skeleton
CN201786360U (en) Supporting structure improving load-carrying property of loess tunnel arch springing
CN212772459U (en) Steel mould structure of lining of check net
CN209649043U (en) A kind of prefabricated components applied to macrovoid concrete for plant growth
CN202954381U (en) Equipment for repairing roadbed slope

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090513