CN101309002A - 发动风力发电厂的至少一部分的方法、风力发电厂及其用途 - Google Patents

发动风力发电厂的至少一部分的方法、风力发电厂及其用途 Download PDF

Info

Publication number
CN101309002A
CN101309002A CNA2008100991672A CN200810099167A CN101309002A CN 101309002 A CN101309002 A CN 101309002A CN A2008100991672 A CNA2008100991672 A CN A2008100991672A CN 200810099167 A CN200810099167 A CN 200810099167A CN 101309002 A CN101309002 A CN 101309002A
Authority
CN
China
Prior art keywords
power plant
wind
wind power
wind turbine
electrical network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100991672A
Other languages
English (en)
Inventor
卡耶斯科夫·尼尔森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=39142757&utm_source=***_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN101309002(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Siemens AG filed Critical Siemens AG
Publication of CN101309002A publication Critical patent/CN101309002A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D7/00Controlling wind motors 
    • F03D7/02Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor
    • F03D7/026Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor for starting-up
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D7/00Controlling wind motors 
    • F03D7/02Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor
    • F03D7/028Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor controlling wind motor output power
    • F03D7/0284Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor controlling wind motor output power in relation to the state of the electric grid
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D7/00Controlling wind motors 
    • F03D7/02Controlling wind motors  the wind motors having rotation axis substantially parallel to the air flow entering the rotor
    • F03D7/04Automatic control; Regulation
    • F03D7/042Automatic control; Regulation by means of an electrical or electronic controller
    • F03D7/048Automatic control; Regulation by means of an electrical or electronic controller controlling wind farms
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D9/00Adaptations of wind motors for special use; Combinations of wind motors with apparatus driven thereby; Wind motors specially adapted for installation in particular locations
    • F03D9/20Wind motors characterised by the driven apparatus
    • F03D9/25Wind motors characterised by the driven apparatus the apparatus being an electrical generator
    • F03D9/255Wind motors characterised by the driven apparatus the apparatus being an electrical generator connected to electrical distribution networks; Arrangements therefor
    • F03D9/257Wind motors characterised by the driven apparatus the apparatus being an electrical generator connected to electrical distribution networks; Arrangements therefor the wind motor being part of a wind farm
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Control Of Eletrric Generators (AREA)
  • Wind Motors (AREA)

Abstract

本发明涉及一种风力发电厂和在基本上没有从外部电网输送的用于发动的任何能量的情况下发动可与外部电网组合的风力发电厂的至少一部分的方法和该方法或该风力发电厂的用途,该风力发电厂包括多个风力涡轮机和可与至少一个风力涡轮机组合的至少一个本地电源,其中风力发电厂与外部电网断开连接,风力发电厂的风力涡轮机的一个发动风力涡轮机或者一组发动风力涡轮机与其余风力涡轮机隔离,一个发动风力涡轮机或一组发动风力涡轮机与本地电源连接并且使用从本地电源输送的功率来发动一个发动风力涡轮机或一组发动风力涡轮机,并且其中可从风力发电厂输送的功率被用于外部电网的至少一部分的黑或冷启动,以建立在外部电网上的电压和/或功率。

Description

发动风力发电厂的至少一部分的方法、风力发电厂及其用途
技术领域
本发明涉及特别是在外部电网基本上故障后发动(start up)可与外部电网组合的风力发电厂的至少一部分的方法。本发明还涉及一种风力发电厂和用于恢复在外部电网的至少一部分上的电压和/或功率的风力发电厂的用途。
背景技术
风力发电厂(wind power plant)通常是例如一个地区或国家的电力供应的至少一部分,并因此与电网连接作为电力供应的电压和/或功率的传输和/或配电***。一般而言,所有发电厂都需要电力来发动。在稳定的工作条件下,发电厂然后向电网输送电压和/或功率。在正常环境下,从传输和/或配电***、由此从电力供应的电网提供用于发动发电厂的电力。
但是可能出现这样的情况,例如发生正常停电或电网的至少一部分的故障以至于所有或一些发电厂关闭的灾害。在此情况下,没有来自于电网的可用的电力来发动发电厂。因此包括发电厂和传输和/或配电电网的发电***或电力供应需要意外事故方案(contingency arrangement),以使得在电力供应的全部或一部分关闭的情况下能够重启。一般将恢复电力供应的过程称作黑(black)或冷启动。
在2001年2月,Market Development,National Grid Company plc的“AnIntroduction to Black Start”中描述了单独被启动并逐渐被彼此重新连接以便再次形成互连电力供应或发电***的隔离的所谓黑启动发电站。在紧急情况下,黑启动站从位于现场的小型辅助发电设备分别接收重启和发动所需的电力。这种辅助生成设备可以是小型燃气涡轮机或者柴油机设备,其最小尺寸取决于黑启动发电厂的尺寸。
发明内容
因此,当例如发生与风力发电厂所连接的电网的总电力故障并且风力发电厂关闭时,当在电网上有足够电力可用于发动风力发电厂时可以分别先后重启和发动风力发电厂。这引起风力发电厂的电力生产的损失。
因此,本发明的一个目标是以优选地加速风力发电厂的至少一部分的发动的方式来提供一种用于风力发电厂的方法和一种风力发电厂。本发明的另一目标是提供风力发电厂的一种新的用途。
分别通过发动风力发电厂的至少一部分和通过可与外部电网组合的风力发电厂在基本上没有从外部电网输送的用于发动的任何能量的情况下发明性地实现第一目标,该风力发电厂包括多个风力涡轮机和可与风力发电厂的至少一个风力涡轮机可逆地组合的至少一个本地电源,其中
-风力发电厂与外部电网断开连接,
-风力发电厂的风力涡轮机中的一个发动风力涡轮机或者一组发动风力涡轮机与风力发电厂的其余风力涡轮机隔离,
-该一个发动风力涡轮机或一组发动风力涡轮机与本地电源连接以及
-使用从本地电源输送的电力来发动该一个发动风力涡轮机或一组发动风力涡轮机,并且
其中可从风力发电厂输送的功率被用于外部电网的至少一部分的黑或冷启动,以建立在外部电网上的电压和/或功率。
使用此方法,能够发动或重启风力发电厂的至少一部分,因此例如在整个外部电网基本上故障后,在基本上没有从外部电网输送的用于发动的任何电力和能量的情况下,能够发动或重启发动运转中与外部电网正常连接的风力发电厂的至少一些风力涡轮机。外部电网通常是电力供应的功率传输和/或配电电网。外部电网可以是本地电网或区域电网(regional grid)或在较大区域中的电网。根据本发明,优选地,从基本上与外部电网独立地工作并可以与风力发电厂的至少一个发动风力涡轮机或者一组发动风力涡轮机所连接的小型本地电源来专门提供用于发动的电力。因此,风力发电厂的至少一部分的发动、具体为重启是与外部电网独立的,并因此被简化和加速。这得到风力发电厂的较高可用性和风力发电厂运营商的更好收益(yield),因为例如在掉电后,电力的生产恢复得更快。很清楚,当风力条件足够用于风力发电厂的风力涡轮机的稳定工作时,优选地执行发动风力发电厂的至少一部分的方法。通常,从而发动风力发电厂的所有可工作的风力涡轮机。由于发动,可从风力发电厂输送的电力被用于外部电网的至少一部分的黑或冷启动,以建立在外部电网上的电压和/或功率。
根据本发明的实施例,特别是当实现一个发动风力涡轮机或一组发动风力涡轮机的稳定工作时,使用从一个发动风力涡轮机或一组发动风力涡轮机输送的电力来发动风力发电厂的下一风力涡轮机或下一组风力涡轮机。发动或任何其它风力涡轮机的稳定工作意味着在给定风力条件下的风力涡轮机的功率输出、输出电压和/或输出电压的频率基本上稳定,并因此处于预定范围内。
根据本发明的另一实施例,使用从优选地处于稳定工作中的风力发电厂的一个或多个发动和/或其它风力涡轮机输送的电力,来继续地发动风力发电厂的单一风力涡轮机或多组风力涡轮机。
因此,逐步或逐渐地发动风力发电厂。风力发电厂中可用的电力越多,就可以更快地发动其余风力涡轮机,直到优选地发动风力发电厂的所有风力涡轮机。
根据本发明的变型,风力发电厂包括与风力涡轮机链接的并控制风力发电厂的发动的至少一个中央发电厂控制器。优选地,从而该中央发电厂控制器通过监视风力涡轮机的输出电压和输出电压的频率来控制风力发电厂中的电力的生产和消耗。优选地,中央发电厂控制器可与本地电源可逆地组合。
根据本发明的实施例,风力发电厂包括优选地从中央发电厂控制器工作以接通(close)和断开(open)电连接的多个电路断路器。因此,中央发电厂控制器可以控制哪个发动风力涡轮机或哪组发动风力涡轮机被连接于本地电源用于发动。此外,中央发电厂控制器可以控制哪个风力涡轮机或哪组风力涡轮机连接于一个或多个已经发动的发动风力涡轮机或其它已经发动的风力涡轮机以便进一步发动。
根据本发明的另一实施例,当风力发电厂的预定数量的风力涡轮机处于稳定工作中——这意味着如上所述风力涡轮机在给定风力条件下维持功率输出、输出电压和/或输出电压的频率基本上稳定在预定范围内时,风力发电厂重新连接到外部电网。通过该行动,即使在风力发电厂的所有风力涡轮机都处于工作中或对于风力发电厂的运营商的收益而言是积极的稳定工作中之前,也能够早已将电力输送到外部电网。从而风力涡轮机的预定数量取决于风力发电厂的风力涡轮机的类型,特别是取决于各个类型的风力涡轮机的输出电压和/或功率输出。
根据替换,首先优选地风力发电厂基本上运行在稳定的开路工作(open-circuit operation)中,并且然后重新连接到外部电网。具体地,风力发电厂通过变压器和/或通过频率同步设备可与外部电网组合。因此,当风力发电厂的输出电压的频率与在外部电网上的电压的频率至少彼此基本上相等时,可以变换风力发电厂的输出电压,和/或将风力发电厂连接到外部电网。
根据本发明的变型,可以仅通过从风力发电厂输送的电压和/或功率或通过从风力发电厂输送的电压和/或功率与从至少一个其它电压或电源输送的电压和/或功率相组合地建立外部电网的电压和/或功率。其它电压或电源从而可以是至少另一风力发电厂、热电厂或光伏电厂。
根据本发明的另一变型,中央发电厂控制器通过通信网络与风力涡轮机链接。通信网络从而可以是无线或有线通信网络。
根据本发明的实施例,本地电源是或包括优选为大电池的电池、不间断电源(UPS)或发电机。本地电源可以是或可以包括例如柴油发电机或燃料电池。因此,本地电源的尺寸适应于发动至少一个风力涡轮机或至少一组风力涡轮机所需的电压和/或功率。例如大的3.6MW的风力涡轮机需要大约690V和大约30kW来控制发动机和逆变器,这稍小于风力涡轮机的功率的1%。本地电源的持续时间可以从几分钟到一小时。
本发明的另一目标通过使用如前所述的用于外部电网的至少一部分的黑或冷启动以建立在外部电网上的电压和/或功率的方法或风力发电厂来实现。
附图说明
下面将参考示意图更详细地说明本发明,其中
图1示意性示出根据本发明的风力发电厂,并且
图2示出了通过频率同步设备与外部电网连接的图1的风力发电厂。
具体实施方式
图1示意性示出了根据本发明的风力发电厂1。风力发电厂1通过变压器3可与外部电网2组合。在本实施例的情况下,电网2是由HDVC线路21(高压直流电)连接到主AC电网20的本地或小型AC独立电网(island grid)。HDVC线路21以共同方式包括在电网2侧上的整流器22和在主电网20侧上的逆变器23。在正常工作期间并在给出足够风力条件的情况下,风力发电厂1将电力和/或输出电压输送到电网2。在当例如由于很高的风力条件而导致风力发电厂1关闭时的情况下,可以用从电网2输送的电力来发动或重启风力发电厂。
但是存在像发生正常停电或整个电网基本上故障且与电网连接的几乎所有发电厂都关闭的灾害的情况。那么,分别需要对整个发电***或包括发电厂和传输和/或配电***以及整个电网在内的整个电力供应的黑或冷启动。在这样的情况下,当在电网上有可用的足够电力用于发动时,可以先后发动或重启风力发电厂,即使当风力条件足够用于风力发电厂的工作时,这可能导致风力发电厂的发动的延迟。
特别是为了克服这种延迟和/或为了帮助电网的至少一部分的黑启动,根据本发明准备风力发电厂1以在基本上没有从电网、具体地从电网2输送的任何能量的情况下发动或重启。
在本实施例的情况下,风力发电厂1因此包括多个风力涡轮机4、中央发电厂控制器5、多个电路断路器CB1-CBX和小型本地电源6。
在本实施例的情况下,分别将三个风力涡轮机4组合成风力涡轮机4的一组GP1-GPX。但是也可以一组包括一个、两个或更多风力涡轮机4。风力涡轮机4的每组GP1-GPX通过电路断路器CB4-CBX可与风力发电厂1的供电线7组合。本地电源6通过电路断路器CB3可与供电线7组合,并且变压器3通过电路断路器CB2可与供电线7组合。中央发电厂控制器5也与供电线7连接,并且工作电路断路器CB1-CBX以断开和接通电连接。风力涡轮机4的组GP1-GPX和中央发电厂控制器5通过电路断路器CB3-CBX可与本地电源6可逆地组合。
风力涡轮机4通过快速通信网络11另外地连接到中央发电厂控制器5。在本实施例的情况下,快速通信网络是例如以太网的有线网络。但是通信网络也可以包括光纤电缆。通信网络还可以是无线网络,例如基于电磁波或提供快速数据传输所需的带宽的任何其它通信网络,如同从中央发电厂控制器5到风力涡轮机4的设置点。因此,中央发电厂控制器5可以与风力发电厂1的所有风力涡轮机通信,特别是与每个风力涡轮机4的没有明确示出的每个涡轮机控制器通信。
中央发电厂控制器5通过监视在正常工作、发动和黑启动序列期间的输出电压和输出电压的频率来控制并平衡风力发电厂1中的电力的生产和消耗。基于在中心点8处的风力发电厂1的输出电压的测量来调节在风力涡轮机4的涡轮机控制器处的输出电压。基于频率控制器所测量的频率来调节在各个风力涡轮机4处的生产电平(production level)。可以将频率控制器本地地置于与中央发电厂控制器5通信的风力涡轮机4的涡轮机控制器处、或者集中地置于中央发电厂控制器5处、或者两者的组合。输出电压和频率的调节可以基于PID控制器(比例加积分加微分)、模糊控制器、神经网络或其组合。
为了说明本发明,假设存在从电网2到主电网20的HVDC线路21的故障。因此,电网2故障,并且风力发电厂1关闭。现在,假定风速正常或者处于用于风力发电厂1的工作的足够工作范围内,风力发电厂1可以被用于恢复或建立在外部电网2上的电力和/或电压。
在第一步骤中,电路断路器CB3接通,这可以例如通过手动将中央发电厂控制器5连接到可以是电池或一般地UPS(不间断电源)或发电机的小型本地电源6来完成。因此,给中央发电厂控制器5供应来自本地电源6的电力,并且中央发电厂控制器5可以控制发动和黑启动顺序,具体地,中央发电厂控制器5可以断开和接通电路断路器。然后,除了电路断路器CB3以外,断开所有还未断开的电路断路器CB1-CBX。因此,风力发电厂1与外部本地传输和配电电网2断开连接。这确保在风力发电厂1处于稳定工作之前,没有电力被反馈给外部电网2的传输和配电线。
在本实施例的情况下,组GP1的风力涡轮机4是发动风力涡轮机4。由于断开了电路断路器CB4-CBX,风力涡轮机4的组GP1-GPX彼此隔离。
为了发动组GP1的发动风力涡轮机4,接通由中央发电厂控制器5工作的电路断路器CB4,并且组GP1的风力涡轮机4连接到供电线7和本地电源6。随后,使用从本地电源6输送的电力,在中央发电厂控制器5的控制下,发动风力发电厂1的组GP1的发动风力涡轮机4。从而,以支持发动功能的方式来调整和工作组GP1的每个风力涡轮机4的每个发电机和每个逆变器。以这种方式,每个风力涡轮机4的每个风力涡轮机控制器能够控制例如风力涡轮机4的各个发电机的磁化电流(magnetising current),以便可以在没有像电网2的外部电网的任何能量或供电的情况下进行风力发电厂1的风力涡轮机4、和因此整个风力发电厂1的发动。
当实现发动风力涡轮机4的组GP1的稳定工作——这意味着在给定风力条件下组GP1的风力涡轮机4的输出电压和输出电压的频率处于预定范围内时,优选地使用从处于稳定工作中的组GP1的发动风力涡轮机4输送的电力来发动风力发电厂1的风力涡轮机4的下一组GP2。在此情况下,电路断路器CB5接通,并且电路断路器CB3断开。但是也可以使得电路断路器CB3接通,并且也可以使用从本地电源6输送的功率来发动组GP2的风力涡轮机4。顺便提及,当电路断路器CB3断开时,从发动风力涡轮机4输送用于工作中央发电厂控制器5的功率。
以这种方式,当电力输送风力涡轮机处于稳定工作时,使用从风力发电厂1的一个或多个发动和/或其它风力涡轮机4输送的电力来相继地发动风力发电厂1的风力涡轮机4的所有组GP2-GPX和因此整个风力发电厂1。
根据本发明的发展,当风力发电厂1的预定数量的风力涡轮机4处于稳定工作时,风力发电厂1被逐渐重新连接到外部电网2。处于稳定工作的预定数量的风力涡轮机4从而取决于风力涡轮机4的类型的额定输出电压和/或取决于外部电网2的容量。为了将风力发电厂1重新连接到外部电网2,通过中央发电厂控制器5接通电路断路器CB2和电路断路器CB1
在本实施例的情况下,从风力发电厂1输送到外部电网2的电力和/或电压被用于在通过HVDC线路21将外部电网2连回到主电网20之前的外部电网2的黑或冷启动、具体地恢复或建立外部电网2上的电压和/或功率。随着负载增加,风力涡轮机4使用其频率控制器来管理输出电压实现可以由可用风力维持的电平。
从本发明的实施例变得很清楚,在基本上没有从作为主电网的部分的外部电网2输送的任何能量的情况下来发动或重启风力发电厂1。在风力发电厂1的发动期间和/或在其之后从风力发电厂1输送的电力可以被用于黑或冷启动至少外部电网2,特别用于恢复和建立电网2上的电压和/或功率。因此,例如在电网停电之后直到风力发电厂1到电网2的功率输送的延迟可以被降低。可以在正常停电或传统过程可能花费较长时间来恢复全部功率生产的灾害情况下使用所述行动。所以,如果风力条件足够,像风力发电厂1一样的作为黑启动站(black start station)的风力发电厂能够比作为在外部电网上的黑启动站的火电厂(thermal plant)更快地恢复电压和/或功率,其中在火电厂中,温度升高是关键因素,并且迅速的温度升高可以潜在地引起对设施的损坏。
风力发电厂1、具体地风力发电厂1的黑或冷启动功能可以被用于独立地或与以另一风力发电厂、小型热电厂(cogeneration plant)、光伏电厂(photovoltaic plant)或任何其它合适的电厂的形式的至少另一电压或电源相组合地建立像本地电网2的外部电网。风力发电厂1还可以被用于重新建立在更大区域内的电网。
在本实施例的情况下,可替换地,风力发电厂1能够在开路工作中运行,并且当在工作中稳定时,特别是当连接了HVDC线路21时,风力发电厂1能够通过电路断路器CB1和CB2重新连接到电网2,以生产功率。
如图2所示,还能够另外使用与风力发电厂控制器5连接的频率同步设备9。然后,当风力发电厂1的输出电压的频率与电网2的电压的频率彼此基本上相等时,能够将风力发电厂1连接到电网2。
注意,本发明的所述例子仅是本发明的实施例。因此,在不脱离本发明的范围的情况下,本发明的其它实施例也是可以的。
通常,调整中央发电厂控制器5用于执行本发明的方法之一、即发动风力发电厂1和/或控制风力发电厂1的黑启动顺序。为此目的,例如以计算机或计算单元的形式的中央发电厂控制器5包括各个计算机程序。但是中央发电厂控制器5不是绝对必需的,特别是当风力涡轮机4的风力涡轮机控制器承担了中央发电厂控制器5的功能,特别是在发动和/或黑启动顺序期间。因此可以调整风力涡轮机控制器之一来发动风力发电厂1和/或控制风力发电厂1的黑启动顺序。
在电池作为风力发电厂1的本地电源6的情况下,可以通过风力发电厂1的风力涡轮机4来装载该电池。优选地,存在电池的监视装载周期,其中电池优选地总是处于用于发动和/或黑启动顺序的情况下。通过接通例如由中央发电厂控制器5工作的电路断路器CB3可以容易地完成装载。
除了已经提到的优点以外,本发明还具有当在功率损失后更快地恢复电网时潜在更好地为与电网连接的本地使用客户服务的优点。
此外,通过本发明,存在电网运营商可用的快得多的功率,为恢复电网提供更大灵活性。
尤其是通过被配电在更大地理区域上的更多风力发电厂,即使任何单独的风力发电厂可能不具有供应该服务所需的风力资源,但是有助于恢复电网上的功率的这些风力发电厂的任意一个的能力增加了。当风力发电达到高级渗透性(high level of penetration)时,将更迫切地需要能够从该资源更快地恢复供应的电网稳定性。

Claims (29)

1.一种在基本上没有从外部电网(2)输送的用于发动的任何能量的情况下发动可与所述外部电网(2)组合的风力发电厂(1)的至少一部分的方法,
所述风力发电厂(1)包括
多个风力涡轮机(4)和
可与至少一个风力涡轮机(4)组合的至少一个本地电源(6),
其中
-所述风力发电厂(1)与所述外部电网(2)断开连接,
-所述风力发电厂(1)的风力涡轮机(4)的一个发动风力涡轮机(4)或者一组(GP1-GPX)发动风力涡轮机(4)与其余风力涡轮机(4)隔离,
-所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)与所述本地电源(6)连接,并且
-使用从所述本地电源(6)输送的功率来发动所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4),并且
其中可从所述风力发电厂(1)输送的功率被用于所述外部电网(2)的至少一部分的黑或冷启动,以建立在所述外部电网(2)上的电压和/或功率。
2.根据权利要求1所述的方法,其中优选地当实现所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)的稳定工作时,使用从所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)输送的功率来发动所述风力发电厂的下一风力涡轮机(4)或下一组(GP1-GPX)风力涡轮机(4)。
3.根据权利要求1或2所述的方法,其中使用从优选地处于稳定工作中的所述风力发电厂(1)的一个或多个发动(4)和/或其它风力涡轮机(4)输送的功率来相继地发动所述风力发电厂(1)的单一风力涡轮机(4)或多组(GP1-GPX)风力涡轮机(4)。
4.根据权利要求1到3的任意一项所述的方法,其中所述风力发电厂(1)包括与所述风力涡轮机(4)链接并控制所述风力发电厂(1)的发动的至少一个中央发电厂控制器(5)。
5.根据权利要求4所述的方法,其中所述中央发电厂控制器(5)与本地电源(6)可逆地连接。
6.根据权利要求4或5所述的方法,其中所述风力发电厂(1)包括优选地从所述中央发电厂控制器(5)工作以接通和断开电连接的多个电路断路器(CB1-CBX)。
7.根据权利要求1到6的任意一项所述的方法,其中当风力发电厂(1)的预定数量的风力涡轮机(4)处于稳定工作中时,所述风力发电厂(1)重新连接到所述外部电网(2)。
8.根据权利要求1到6的任意一项所述的方法,其中所述风力发电厂(1)运行在开路工作中,并且然后被重新连接到所述外部电网(2)。
9.根据权利要求1到8的任意一项所述的方法,其中所述风力发电厂(1)通过变压器(3)可与所述外部电网(2)组合。
10.根据权利要求1到9的任意一项所述的方法,其中所述风力发电厂(1)通过频率同步设备(9)可与所述外部电网(2)组合。
11.根据权利要求1到10的任意一项所述的方法,其中仅通过从所述风力发电厂(1)输送的电压和/或功率或者通过与至少一个其它电压或电源相组合地从所述风力发电厂(1)输送的电压和/或功率来建立所述外部电网(2)的电压和/或功率。
12.根据权利要求11所述的方法,其中所述其它电压或电源是另一风力发电厂、热电厂或光伏电厂。
13.根据权利要求4到12的任意一项所述的方法,其中所述中央发电厂控制器(5)通过通信网络(11)与所述风力涡轮机链接。
14.根据权利要求1到13的任意一项所述的方法,其中所述本地电源(6)是或者包括电池、不间断电源(UPS)或者发电机。
15.一种可与外部电网(2)组合的风力发电厂,包括多个风力涡轮机(4)和可与至少一个风力涡轮机(4)组合的至少一个本地电源(6),
其中为了在基本上没有从所述外部电网(2)输送的用于发动的任何能量的情况下发动所述风力发电厂(1)的至少一部分
-所述风力发电厂(1)可与所述外部电网(2)分离,
-所述风力发电厂(1)的风力涡轮机(4)的一个发动风力涡轮机(4)或者一组(GP1-GPX)发动风力涡轮机(4)可与其余风力涡轮机(4)隔离,
-所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)可与所述本地电源(6)组合,以及
-能够使用从所述本地电源(6)输送的功率来发动所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4),并且
其中可从所述风力发电厂(1)输送的功率能够被用于所述外部电网(2)的至少一部分的黑或冷启动,以建立在所述外部电网(2)上的电压和/或功率。
16.根据权利要求15所述的风力发电厂,其中优选地当实现所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)的稳定工作时,能够使用从所述一个发动风力涡轮机(4)或所述一组(GP1-GPX)发动风力涡轮机(4)输送的功率来发动所述风力发电厂(1)的下一风力涡轮机(4)或下一组(GP1-GPX)风力涡轮机(4)。
17.根据权利要求15或16所述的风力发电厂,其中能够使用从优选地处于稳定工作中的所述风力发电厂(1)的一个或多个发动和/或其它风力涡轮机(4)输送的功率,来相继地发动所述风力发电厂(1)的单一风力涡轮机(4)或多组(GP1-GPX)风力涡轮机(4)。
18.根据权利要求15到17的任意一项所述的风力发电厂,其中所述风力发电厂(1)包括与所述风力涡轮机(4)链接并控制所述风力发电厂(1)的发动的至少一个中央发电厂控制器(5)。
19.根据权利要求18所述的风力发电厂,其中所述中央发电厂控制器(5)与所述本地电源(6)可逆地组合。
20.根据权利要求18或19所述的风力发电厂,其中所述风力发电厂(1)包括优选地从所述中央发电厂控制器(5)工作以接通和断开电连接的多个电路断路器(CB1-CBX)。
21.根据权利要求15到20的任意一项所述的风力发电厂,其中当所述风力发电厂(1)的预定数量的风力涡轮机(4)处于稳定工作中时,所述风力发电厂(1)可与所述外部电网(2)重新组合。
22.根据权利要求15到20的任意一项所述的风力发电厂,其中所述风力发电厂(1)能够运行在开路工作中,并且然后被重新连接到所述外部电网(2)。
23.根据权利要求15到22的任意一项所述的风力发电厂,其中所述风力发电厂(1)通过变压器(3)可与所述外部电网组合。
24.根据权利要求15到23的任意一项所述的风力发电厂,其中所述风力发电厂(1)通过频率同步设备(9)可与所述外部电网(2)组合。
25.根据权利要求15到24的任意一项所述的风力发电厂,其中能够仅通过从所述风力发电厂(1)输送的电压和/或功率或通过与至少一个其它电压或电源相组合地从所述风力发电厂(1)输送的电压和/或功率来建立所述外部电网(2)的电压和/或功率。
26.根据权利要求25所述的风力发电厂,其中所述其它电压或电源是另一风力发电厂、热电厂或光伏电厂。
27.根据权利要求15到26的任意一项所述的风力发电厂,其中所述中央发电厂控制器(5)通过通信网络(11)与所述风力涡轮机链接。
28.根据权利要求15到27的任意一项所述的风力发电厂,其中所述本地电源(6)是或者包括电池、不间断电源(UPS)或者发电机。
29.一种根据权利要求1到28的任意一项的、用于外部电网(2)的至少一部分的黑或冷启动以建立在所述外部电网(2)上的电压和/或功率的方法或风力发电厂(1)的用途。
CNA2008100991672A 2007-05-14 2008-05-14 发动风力发电厂的至少一部分的方法、风力发电厂及其用途 Pending CN101309002A (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP07009644.1 2007-05-14
EP07009644.1A EP1993184B2 (en) 2007-05-14 2007-05-14 Method of start up at least a part of a wind power plant, wind power plant and use of the wind power plant

Publications (1)

Publication Number Publication Date
CN101309002A true CN101309002A (zh) 2008-11-19

Family

ID=39142757

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100991672A Pending CN101309002A (zh) 2007-05-14 2008-05-14 发动风力发电厂的至少一部分的方法、风力发电厂及其用途

Country Status (6)

Country Link
US (1) US8000840B2 (zh)
EP (1) EP1993184B2 (zh)
JP (1) JP5641679B2 (zh)
CN (1) CN101309002A (zh)
CA (1) CA2631153C (zh)
DK (1) DK1993184T3 (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102224671A (zh) * 2008-11-24 2011-10-19 阿克工程及技术股份有限公司 频率转换器
CN102439299A (zh) * 2009-04-03 2012-05-02 湘电达尔文有限责任公司 风力发电场孤岛运行
CN103391038A (zh) * 2012-05-09 2013-11-13 西门子公司 用于衰减轴振荡的方法和布置
CN104393669A (zh) * 2014-11-28 2015-03-04 中国北车集团大连机车车辆有限公司 多台柴油发电机组辅助***供电电路
CN104953616A (zh) * 2015-06-15 2015-09-30 江苏省电力公司 一种用于风力发电场的黑启动***及其供电方法
CN105281375A (zh) * 2015-11-26 2016-01-27 江苏方天电力技术有限公司 一种风电场参与电网黑启动功率匹配的方法
WO2016082070A1 (en) * 2014-11-24 2016-06-02 Abb Technology Ltd Method for black starting wind turbine, wind farm, and restoring wind farm and wind turbine, wind farm using the same
CN105814764A (zh) * 2013-12-20 2016-07-27 西门子公司 用于传输电力的设备
CN107005057A (zh) * 2014-12-23 2017-08-01 Abb瑞士股份有限公司 用于在与公用电网断开期间协调风电场的控制的方法和控制器
CN111742139A (zh) * 2018-02-28 2020-10-02 西门子歌美飒可再生能源公司 启动风电场的方法
CN112952826A (zh) * 2021-04-07 2021-06-11 阳光电源股份有限公司 一种分布式风储电站及其黑启动方法

Families Citing this family (66)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7745948B2 (en) * 2007-11-28 2010-06-29 General Electric Company Emergency pitch drive unit for a wind turbine
US20090160187A1 (en) * 2007-12-19 2009-06-25 Scholte-Wassink Hartmut Control system and method for operating a wind farm in a balanced state
ES2665771T3 (es) * 2008-07-11 2018-04-27 Vestas Wind Systems A/S Sistema para monitorizar un factor de restauración de una población de turbinas eólicas
JP4698718B2 (ja) * 2008-09-30 2011-06-08 株式会社日立製作所 風力発電装置群の制御装置及び制御方法
US20100090463A1 (en) * 2008-10-10 2010-04-15 Jacob Johannes Nies Combined environmental monitoring and power supply device
US20100140937A1 (en) * 2008-12-31 2010-06-10 Andreas Kirchner Wind turbine starting
TWM357517U (en) * 2009-01-14 2009-05-21 Sunyen Co Ltd Wind-powered electric generator
WO2010094814A1 (es) * 2009-02-17 2010-08-26 Gamesa Innovation & Technology, S.L. Metodo y aparato para energizar un aerogenerador
WO2011058170A1 (en) * 2009-11-16 2011-05-19 Vestas Wind Systems A/S Method and device for operation of a wind power plant
US20110144814A1 (en) * 2010-06-29 2011-06-16 Detlef Menke Wind turbine and method for operating a wind turbine
US8120202B2 (en) * 2010-10-25 2012-02-21 General Electric Company Electric power transmission system for wind turbine and wind turbine farm and method for operating same
DE102010060398A1 (de) 2010-11-08 2012-05-10 Adensis Gmbh Verfahren zum Betreiben einer Photovoltaikanlage zur Einspeisung von elektrischer Leistung in ein Mittelspannungsnetz
US9509141B2 (en) * 2011-04-15 2016-11-29 Siemens Aktiengesellschaft Black start of wind turbine devices
GB2490510B (en) * 2011-05-04 2013-10-30 Rolls Royce Plc A turbine array and a method of controlling a turbine array during a loss of grid event
CN103503269B (zh) * 2011-05-30 2016-12-07 Abb研究有限公司 用于向电网分配电功率的***
WO2013005259A2 (en) * 2011-07-06 2013-01-10 Mitsubishi Heavy Industries, Ltd. Energy extraction device, group of energy extraction devices and operating methods
US8519568B2 (en) * 2011-09-16 2013-08-27 General Electric Company Inrush current protection for wind turbines and wind farms
KR101302022B1 (ko) * 2011-10-13 2013-09-02 삼성중공업 주식회사 풍력 발전 시스템 및 그 운전 제어 방법
US9030035B2 (en) * 2011-12-19 2015-05-12 Vestas Wind Systems A/S Quick start-up of wind turbine generators
WO2013091641A1 (en) 2011-12-19 2013-06-27 Vestas Wind Systems A/S Quick start-up of wind turbine generators
CN102522816A (zh) * 2011-12-31 2012-06-27 四川中鼎智能技术有限公司 水电站黑启动中直流逆变的实现方法
EP2817511A4 (en) * 2012-02-20 2016-02-17 Re 10 Ltd DEVICE AND SYSTEMS FOR GENERATING ELECTRICAL ENERGY FROM WIND
EP2679809A1 (en) * 2012-06-28 2014-01-01 Siemens Aktiengesellschaft Method and arrangement for responding to a grid event, such as fast frequency drop, by combining demand response, inertial response and spinning reserve
WO2014082757A1 (de) * 2012-11-27 2014-06-05 Abb Technology Ag Verfahren zum betrieb einer energieanlage und eines energiesystems mit solchen energieanlagen
JP6037803B2 (ja) * 2012-11-30 2016-12-07 三菱重工業株式会社 風車及びその制御方法並びに風力発電システム
JP6257895B2 (ja) * 2012-12-27 2018-01-10 エムエイチアイ ヴェスタス オフショア ウィンド エー/エス 洋上発電施設及びその運転方法
EP3109966B1 (de) * 2013-02-28 2019-08-28 Siemens Aktiengesellschaft Windparkanbindung mit diodengleichrichter
DE102013102603B4 (de) 2013-03-14 2017-02-09 Sma Solar Technology Ag Verfahren für einen Schwarzstart eines Kraftwerks mit mehreren einem Wechselstromnetz zuschaltbaren Wechselrichtern
US9593672B2 (en) 2013-08-07 2017-03-14 Siemens Aktiengesellschaft Isochronous wind turbine generator capable of stand-alone operation
CN104065111B (zh) * 2013-11-30 2017-03-15 国家电网公司 一种用于移动式保电储能的黑启动***及其启动方法
WO2015090375A1 (en) * 2013-12-18 2015-06-25 Abb Technology Ltd Microgrid black-start
IN2013CH06141A (zh) * 2013-12-30 2015-07-03 Gen Electric
US9419439B2 (en) 2014-01-14 2016-08-16 Siemens Aktiengesellschaft Reconnecting a wind power plant to a utility grid
DE102014000784A1 (de) * 2014-01-22 2015-07-23 Senvion Se Windpark mit Vorsteuerung im Leistungsregler
WO2016033769A1 (en) * 2014-09-04 2016-03-10 Abb Technology Ltd Method and system for coordinating control of wind farm during disconnection to utility grid
EP3215735A4 (en) * 2014-11-04 2018-06-27 ABB Schweiz AG Method for coordinating control of wind farm during black start of islanding operation
EP3245400B1 (en) * 2015-01-15 2019-01-09 Vestas Wind Systems A/S Power management system for wind turbine(s) being connected to a power supply with a limited capacity
EP3096004A1 (en) * 2015-05-18 2016-11-23 ABB Technology AG Wind farm inertial response
JP6351557B2 (ja) 2015-09-11 2018-07-04 三菱重工業株式会社 荷重計測装置の較正方法、風車翼の荷重計測システム及び風車
JP6358993B2 (ja) 2015-09-11 2018-07-18 三菱重工業株式会社 風力発電装置および風力発電装置の併入方法
WO2017097308A1 (en) * 2015-12-09 2017-06-15 Vestas Wind Systems A/S A wind power plant
US10968890B2 (en) * 2015-12-10 2021-04-06 Vestas Wind Systems A/S Controlling wind turbine power production within power ramp rate limit for wind power plant
DE102016105662A1 (de) * 2016-03-29 2017-10-05 Wobben Properties Gmbh Verfahren zum Einspeisen elektrischer Leistung in ein elektrisches Versorgungsnetz mit einem Windpark sowie Windpark
JP6674313B2 (ja) * 2016-04-27 2020-04-01 株式会社日立製作所 多端子送電システム
JP6781007B2 (ja) * 2016-10-12 2020-11-04 東京瓦斯株式会社 電力システム
EP3316437A1 (en) * 2016-10-26 2018-05-02 MHI Vestas Offshore Wind A/S Providing auxiliary power when a high-voltage link is nonfunctional
DE102016123384A1 (de) * 2016-12-02 2018-06-07 Wobben Properties Gmbh Verfahren zum Wiederaufbau eines elektrischen Versorgungsnetzes
DE102016124840A1 (de) 2016-12-19 2018-06-21 Wobben Properties Gmbh Verfahren zum Steuern eines Netzwiederaufbaus
KR20180122254A (ko) * 2017-05-02 2018-11-12 한국전자통신연구원 전력 변환 장치 및 방법
DE102017215821A1 (de) 2017-09-07 2019-03-07 Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. Verfahren und system für einen systemwiederaufbau eines onshore-netzes
EP3471231A1 (en) 2017-10-13 2019-04-17 Ørsted Wind Power A/S A method for black-starting an electrical grid
US10819103B2 (en) * 2017-12-07 2020-10-27 General Electric Company Systems and methods for isolating faults in electrical power systems connected to a power grid
US11434871B2 (en) * 2018-01-25 2022-09-06 Vestas Wind Systems A/S Black start restoration
DE102018121022A1 (de) * 2018-08-28 2020-03-05 Hochschule Rheinmain University Of Applied Sciences Wiesbaden Rüsselsheim Verfahren zur Unterdrückung von Stoßkurzschlußströmen sowie Halbleiter-Abschaltvorrichtung dafür
CN109004678B (zh) * 2018-08-30 2024-05-03 中国电力工程顾问集团西北电力设计院有限公司 一种多能组合发电厂黑启动配电***及控制方法
KR102173835B1 (ko) * 2018-10-11 2020-11-05 한국전력공사 신재생에너지용 변전설비의 제어장치 및 그 방법
DE102018130453A1 (de) 2018-11-30 2020-06-04 Sma Solar Technology Ag Verfahren zur elektrischen Versorgung eines Wechselrichters, Anlagenkomponente, Wechselrichter und Energieerzeugungsanlage mit einer derartigen Anlagenkomponente
EP3723229A1 (en) 2019-04-11 2020-10-14 Ørsted Wind Power A/S A method for black-starting an electrical grid
EP3761472A1 (en) * 2019-07-05 2021-01-06 Siemens Gamesa Renewable Energy A/S Black start of a wind farm
US12018655B2 (en) * 2019-08-08 2024-06-25 Vestas Wind Systems A/S Providing auxiliary power using offshore wind turbines
CN110571852B (zh) * 2019-08-30 2022-09-02 昆明理工大学 一种电力***黑启动初期小***形成方法
CN111581856B (zh) * 2020-06-15 2022-06-07 中冶南方都市环保工程技术股份有限公司 一种基于孤立电网的黑启动流程建模与仿真模拟方法
EP4002626A1 (de) 2020-11-19 2022-05-25 Wobben Properties GmbH Definierte schalterstellung bei einem windpark vor ausfall der dc-versorgung
GB2610844A (en) * 2021-09-17 2023-03-22 Aker Offshore Wind Operating Company As Operation of a wind park power system
CN113852141B (zh) * 2021-10-28 2024-06-21 西安热工研究院有限公司 一种联合风光储的具有fcb功能火电厂黑启动***及方法
US11824356B1 (en) * 2022-06-30 2023-11-21 Xi'an Thermal Power Research Institute Co., Ltd. System and method of black start for new power system with energy storage configuration

Family Cites Families (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4193005A (en) * 1978-08-17 1980-03-11 United Technologies Corporation Multi-mode control system for wind turbines
US4357542A (en) * 1979-07-12 1982-11-02 Westinghouse Electric Corp. Wind turbine generator system
US4420692A (en) * 1982-04-02 1983-12-13 United Technologies Corporation Motion responsive wind turbine tower damping
US6980934B1 (en) * 1997-12-12 2005-12-27 Isaac Sadovnik Method and systems for nesting objects
US6870279B2 (en) * 1998-01-05 2005-03-22 Capstone Turbine Corporation Method and system for control of turbogenerator power and temperature
JP3812142B2 (ja) * 1998-05-20 2006-08-23 株式会社日立製作所 可変速発電システムの制御装置
US6462507B2 (en) * 1998-08-07 2002-10-08 Okc Products, Inc. Apparatus and method for initial charging, self-starting, and operation of a power supply with an intermittent and/or variable energy source and a rechargeable energy storage device
US6194793B1 (en) * 1998-08-07 2001-02-27 Okc Products, Inc. Apparatus and method for charging an energy storage source
US20020084655A1 (en) * 2000-12-29 2002-07-04 Abb Research Ltd. System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility
US6670721B2 (en) * 2001-07-10 2003-12-30 Abb Ab System, method, rotating machine and computer program product for enhancing electric power produced by renewable facilities
US6682669B2 (en) * 2001-09-29 2004-01-27 Van Dorn Demag Corporation Model predictive control apparatus and methods for motion and/or pressure control of injection molding machines
US20040044442A1 (en) * 2001-12-28 2004-03-04 Bayoumi Deia Salah-Eldin Optimized dispatch planning of distributed resources in electrical power systems
US7550870B2 (en) * 2002-05-06 2009-06-23 Cyber Switching, Inc. Method and apparatus for remote power management and monitoring
EP1516424A2 (en) 2002-06-18 2005-03-23 Ingersoll-Rand Energy Systems Corporation Microturbine engine system
DE10320087B4 (de) 2003-05-05 2005-04-28 Aloys Wobben Verfahren zum Betreiben eines Windparks
DE102005038558A1 (de) 2005-08-12 2007-02-15 Repower Systems Ag Verfahren zum Betrieb eines Windenergieanlagenparks sowie Windenergieanlagenpark
US7372174B2 (en) * 2005-11-11 2008-05-13 Converteam Ltd Power converters
US7391126B2 (en) * 2006-06-30 2008-06-24 General Electric Company Systems and methods for an integrated electrical sub-system powered by wind energy
US7523001B2 (en) * 2006-09-28 2009-04-21 General Electric Company Method and apparatus for operating wind turbine generators
US7394166B2 (en) 2006-10-04 2008-07-01 General Electric Company Method, apparatus and computer program product for wind turbine start-up and operation without grid power
EP2082132B1 (en) * 2006-11-08 2013-09-25 Vestas Wind Systems A/S Method for controlling a cluster of wind turbines connected to a utility grid and wind turbine cluster.
US9020650B2 (en) * 2007-02-13 2015-04-28 General Electric Company Utility grid, controller, and method for controlling the power generation in a utility grid

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102224671B (zh) * 2008-11-24 2015-07-22 阿克工程及技术股份有限公司 频率转换器
CN102224671A (zh) * 2008-11-24 2011-10-19 阿克工程及技术股份有限公司 频率转换器
CN102439299A (zh) * 2009-04-03 2012-05-02 湘电达尔文有限责任公司 风力发电场孤岛运行
US9217418B2 (en) 2009-04-03 2015-12-22 Xemc Darwind B.V. Wind farm island operation
CN102439299B (zh) * 2009-04-03 2016-07-06 湘电达尔文有限责任公司 风力发电场孤岛运行的方法和相关控制器、涡轮机及发电场***
CN103391038A (zh) * 2012-05-09 2013-11-13 西门子公司 用于衰减轴振荡的方法和布置
CN105814764A (zh) * 2013-12-20 2016-07-27 西门子公司 用于传输电力的设备
US10156225B2 (en) 2014-11-24 2018-12-18 Abb Schweiz Ag Method for black starting wind turbine, wind farm, and restoring wind farm and wind turbine, wind farm using the same
WO2016082070A1 (en) * 2014-11-24 2016-06-02 Abb Technology Ltd Method for black starting wind turbine, wind farm, and restoring wind farm and wind turbine, wind farm using the same
CN104393669A (zh) * 2014-11-28 2015-03-04 中国北车集团大连机车车辆有限公司 多台柴油发电机组辅助***供电电路
US10578082B2 (en) 2014-12-23 2020-03-03 Abb Schweiz Ag Method and controller for coordinating control of wind farm during disconnection to utility grid
CN107005057A (zh) * 2014-12-23 2017-08-01 Abb瑞士股份有限公司 用于在与公用电网断开期间协调风电场的控制的方法和控制器
CN107005057B (zh) * 2014-12-23 2020-04-21 Abb瑞士股份有限公司 用于在与公用电网断开期间协调风电场的控制的方法和控制器
CN104953616B (zh) * 2015-06-15 2017-12-22 江苏省电力公司 一种用于风力发电场的黑启动***及其供电方法
CN104953616A (zh) * 2015-06-15 2015-09-30 江苏省电力公司 一种用于风力发电场的黑启动***及其供电方法
CN105281375B (zh) * 2015-11-26 2016-12-21 江苏方天电力技术有限公司 一种风电场参与电网黑启动功率匹配的方法
CN105281375A (zh) * 2015-11-26 2016-01-27 江苏方天电力技术有限公司 一种风电场参与电网黑启动功率匹配的方法
CN111742139A (zh) * 2018-02-28 2020-10-02 西门子歌美飒可再生能源公司 启动风电场的方法
CN111742139B (zh) * 2018-02-28 2023-07-04 西门子歌美飒可再生能源公司 启动风电场的方法
CN112952826A (zh) * 2021-04-07 2021-06-11 阳光电源股份有限公司 一种分布式风储电站及其黑启动方法

Also Published As

Publication number Publication date
EP1993184A1 (en) 2008-11-19
CA2631153C (en) 2016-06-28
CA2631153A1 (en) 2008-11-14
EP1993184B2 (en) 2024-04-24
JP5641679B2 (ja) 2014-12-17
JP2008283856A (ja) 2008-11-20
DK1993184T3 (en) 2018-05-22
EP1993184B1 (en) 2018-03-14
US8000840B2 (en) 2011-08-16
US20080284172A1 (en) 2008-11-20

Similar Documents

Publication Publication Date Title
CN101309002A (zh) 发动风力发电厂的至少一部分的方法、风力发电厂及其用途
US11462914B2 (en) Method for black-starting an electrical grid
US9509141B2 (en) Black start of wind turbine devices
KR101983427B1 (ko) 고체 산화물 연료 전지를 기초로 한 전력 발생 및 전달 시스템 그리고 이것의 작동 방법
WO2013015256A1 (ja) 電力管理システム及び管理方法
Katiraei et al. Planned islanding on rural feeders—utility perspective
KR20080079596A (ko) 백업 전원시스템
US20080296973A1 (en) Grid interconnection device, grid interconnection system and power control system
US20220209540A1 (en) A method for black-starting an electrical grid
CN113839425A (zh) 一种联合具有fcb功能小型燃机的火电厂黑启动***及方法
Martirano et al. Implementation of SCADA systems for a real microgrid lab testbed
CN104935009B (zh) 含光伏和燃气发电的微电网运行控制方法及***
Mukhopadhyay et al. Black start experiences for 400 kV hydro power plant in western regional grid of India
Lafferte et al. Black start and island operation of distribution grids with significant penetration of renewable resources
CN112615395B (zh) 一种屋顶光储型风电场黑启动方法
Barsali et al. Restoration islands supplied by gas turbines
Wang et al. The existed problems and possible solutions of distributed generation microgrid operation
Wild et al. Spore multifluid microgrid tests and results in the tropics
JP7492296B1 (ja) 系統用蓄電システム
CN208174267U (zh) 基于同期负载控制的大功率智能发电***
Kemsley et al. Making small high-penetration renewable energy systems work-Scottish Island experience
CN105870923A (zh) 大型工厂的供电方法
Vandenbergh et al. Interconnection Management in Microgrids
Vandenbergh et al. Microgrid management with a high share of renewable energy sources
Happ et al. Power System Restoration-A Task Force Report

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20081119