CN101225661A - Pile-anchor foundation ditch supporting construction method - Google Patents

Pile-anchor foundation ditch supporting construction method Download PDF

Info

Publication number
CN101225661A
CN101225661A CNA2008100596828A CN200810059682A CN101225661A CN 101225661 A CN101225661 A CN 101225661A CN A2008100596828 A CNA2008100596828 A CN A2008100596828A CN 200810059682 A CN200810059682 A CN 200810059682A CN 101225661 A CN101225661 A CN 101225661A
Authority
CN
China
Prior art keywords
construction
pile
anchor
row
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100596828A
Other languages
Chinese (zh)
Other versions
CN100465386C (en
Inventor
刘文革
陈绍炳
陶红雨
童宏伟
袁志明
朱其良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG HUANYU CONSTRUCTION GROUP
Original Assignee
ZHEJIANG HUANYU CONSTRUCTION GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG HUANYU CONSTRUCTION GROUP filed Critical ZHEJIANG HUANYU CONSTRUCTION GROUP
Priority to CNB2008100596828A priority Critical patent/CN100465386C/en
Publication of CN101225661A publication Critical patent/CN101225661A/en
Application granted granted Critical
Publication of CN100465386C publication Critical patent/CN100465386C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a foundation pit support method with pile and anchor, belonging to an external staying support technique field of the supporting structural retaining of the foundation pit, comprising that: a. bored piles are constructed to form a retaining wall, after lofting of the pile location according to the planar graph of the pile location; b. the soil is excavated to the bottom elevation of the top beam; c. the bored piles are chiseled to the design elevation; d. the first row of anchors are constructed in the soil layer between the adjacent bored piles; e. the top beams are constructed; f. the soil is excavated to the constructing position of the second row of anchors; g. the second row of anchors are constructed; h. the processes of f and g can be repeated until to the last row of anchors, according to different design conditions; i. the soil is excavated to the bottom of the foundation pit. The foundation pit support method with pile and anchor has the advantages of avoiding a lot of inner supports, providing an open working face for soil excavation, creating a good condition for mechanized construction, increasing the construction progress, needing not to treat the water stop of supporting, bracing substitution, dismantling support during the subsequent construction of the basement, convenient construction, increasing the progress, reducing the construction cost.

Description

Pile-anchor foundation ditch supporting construction method
Technical field
The invention discloses a kind of pile-anchor foundation ditch supporting construction method, belong to building foundation pit supporting engineering construction technical field.
Background technology
The existing building foundation pit supporting system has a variety of, and their each have their own advantages, the scope of application separately are also different.Wherein, it is more commonly used that stake adds supporting system, but it contains a large amount of interior supports, is not easy to cut the earth, structure construction, has influenced construction speed, has brought inconvenience also for simultaneously follow-up construction, influences construction speed.
Summary of the invention
In order to overcome above-mentioned shortcoming, but the invention provides a kind of reduction of erection time, accelerating construction progress, and can reduce the pile-anchor foundation ditch supporting construction method of cost.
To achieve these goals, the technical solution adopted in the present invention is: a kind of pile-anchor foundation ditch supporting construction method comprises: a. is according to the stake bit plan, carry out stake position setting-out after, carry out Bored Pile Construction again, form barricade; B. the absolute altitude at the bottom of the capping beam of cutting the earth; C. cut a hole bored pile to design elevation; D. carry out first row's anchor bolt construction in the soil layer between each adjacent bored pile; E. capping beam construction; F. cut the earth to second row's anchor bolt construction position; G. carry out second row's anchor bolt construction; H. according to different design conditions, can repeat the operation of f and g and arrange anchor pole to last; I. cut the earth to the foundation ditch bottom.
According to conditions such as foundation ditch engineering geology of living in, hydrogeology, clay distribution and physico-mechanical propertieses thereof, when requirement is made water-stop curtain with cement mixing pile, just should before described bored pile construction, carry out the construction of cement mixing pile earlier, form water-stop curtain.
Described first row's anchor pole, second row's anchor pole are prestressed anchor.
Pile-anchor foundation ditch supporting construction method of the present invention effectively combines bored pile construction and anchor bolt construction in deep excavation project, a large amount of interior supports have been removed from, provide open work plane to shoveling, create good condition to mechanized construction, accelerated construction speed, and in follow-up basement construction, need not handle and support sealing, support replacement, tear open the support processing, make things convenient for construction, accelerated progress, reduced cost.
Specifically, the present invention has following characteristics:
(1) stressed reasonable.Can make full use of the pulling force of the shear strength of the soil body with the balanced structure thing.Do not add the gravity and the drag that rely on self support structure and come the balance pulling force and do not resemble traditional stake.
Thereby can save construction investment in a large number, reduce construction costs.
(2) initiatively contend with.Prestressed anchor can provide enough drags once enforcement, limits the displacement of the soil body effectively.And a traditional mark structure stake propping is passive force structure, just can play one's part to the full after the soil body is subjected to displacement.
(3) improve the stress state of the soil body.Make the interior soil body of anchoring scope be in the compressive stress district, increased the stability of the soil body, and can improve the shear strength on weak structural plane or the slide surface.
(4) stake adds anchor, and the application point of anchor-holding force of anchor bolt and action direction can be chosen as required, thereby obtains best stablizing effect.
(5) in the work progress when the stratum condition changes, can in time adjust design parameters, the construction operating mode more gears to actual circumstances.
(6) can construct as usual under the narrow and small or geographical environment complicated situation at action space, need not to use big machinery.
(7) in deep foundation ditch soil excavation process, replace support with anchor pole, open shoveling work plane can be provided, created good condition to mechanized construction, accelerated speed of application.
(8) after stake added anchor and construct, basement structure construction can be constructed routinely, need not to do support place waterproofing work, and support replacement is torn support open and the post-processed of constructing such as handled, and has both made things convenient for construction, has guaranteed quality again, and has accelerated speed of application.
Description of drawings
The present invention is further detailed explanation below in conjunction with the drawings and specific embodiments.
Fig. 1 is the plane structure schematic diagram of the specific embodiment of the invention;
Fig. 2 is that A among Fig. 1 is to elevation;
Fig. 3 is that B-B among Fig. 1 is to sectional view;
Fig. 4 is cement mixing pile construction schematic diagram;
Fig. 5 is the bored pile construction schematic diagram;
Fig. 6 is the schematic diagram of at the bottom of capping beam absolute altitude of cutting the earth;
Fig. 7 is the schematic diagram of cutter bored pile to design elevation;
Fig. 8 is the schematic diagram of first row's anchor bolt construction;
Fig. 9 is the schematic diagram of capping beam construction;
Figure 10 is for cutting the earth to the schematic diagram of second row's anchor bolt construction position;
Figure 11 is the schematic diagram of second row's anchor bolt construction;
Figure 12 is the schematic diagram to foundation ditch bottom of cutting the earth.
The specific embodiment
The invention will be further described below by specific embodiment, but the present invention is not limited by following examples.
The concrete construction sequence of pile-anchor foundation ditch supporting construction method embodiment 1 of the present invention is as follows:
1. according to the stake bit plan, carry out stake position setting-out after, carry out the construction of cement mixing pile 1 earlier, as shown in Figure 4, form water-stop curtain, carry out the construction of bored pile 2 again, as shown in Figure 5, form the barricade of bank protection retaining soil.
2. 3 absolute altitudes at the bottom of the capping beam of cutting the earth, as shown in Figure 6.
3. cutter bored pile 2 is to design elevation, as shown in Figure 7.
4. carry out first row's anchor pole 4a construction in the soil layer between each adjacent bored pile 2, and be prestressed anchor, as Fig. 1, Fig. 2, shown in Figure 8.
5. carry out capping beam 5 constructions, as shown in Figure 9.After capping beam 5 constructions, the end of first row's anchor pole 4a encloses purlin 6a by channel-section steel and locks mutually with capping beam 5, and the other end is anchored in the soil layer, as Fig. 2, shown in Figure 3.The first row anchor pole 4a, has further safeguarded the stable of the soil body and bored pile 2, thereby has reached the stable purpose of foundation ditch so can better bear the structure pulling force that is produced by soil pressure, water pressure etc. owing to adopt prestressed anchor.
6. cut the earth to second row's anchor pole 4b construction location, as shown in figure 10.
7. carry out second row's anchor pole 4b construction, and be prestressed anchor, as shown in figure 11.The end of second row's anchor pole 4b encloses purlin 6b by channel-section steel and locks mutually with bored pile 2, and the other end is anchored in the soil layer, as Fig. 2, shown in Figure 3.
8. cut the earth to the foundation ditch bottom, as shown in figure 12.
The concrete construction sequence of pile-anchor foundation ditch supporting construction method embodiment 2 of the present invention is identical with embodiment's 1, just because designed foundation depth is darker than embodiment 1, therefore need after second row's anchor pole 4b has constructed, append row's anchor bolt construction again, cut the earth at last to the foundation ditch bottom.
The construction principle of pile-anchor foundation ditch supporting construction method of the present invention is to utilize single bored pile 2 and anchor pole 4a, 4b to form retaining soil series system.According to bored pile 2 stability checking computations and the safe and reliable requirements of foundation ditch strengthening; reach under the prerequisite of designing requirement in bored pile 2 quality own; adopt anchor pole 4a, 4b to reinforce bored pile 2, form barricade and anchor pole 4a, 4b combined supporting system, to guarantee the safety of excavation of foundation pit.The end of anchor pole 4a, 4b locks mutually with capping beam 5, bored pile 2 respectively, the other end all is anchored in the upper strata, the load (power of toppling that the soil pressure of side direction, water pressure, buoyance in water and wind-force bring) that supporting and protection structure and other structures are born passes to anchoring body by the pull bar of anchor pole 4a, 4b, and anchoring body will pass to the firm stratum of ground by frictional resistance resistance or supporting resistance from the power of pull bar again.
Pile-anchor foundation ditch supporting construction method of the present invention is applicable to deep-foundation pit engineering and space enclosing structures such as station, underground power house, underground garage, underground substation, basement in high rise building, is particularly useful for that the foundation ditch area is big, the deep foundation pit construction of absolute altitude complexity in the foundation ditch plane irregularity, same foundation ditch.
The quality specifications of cement mixing pile 1 of the present invention, bored pile 2 constructions is according to " building pile foundation tecnical regulations " (JGJ94-99) and national standard " Standard for quality inspection and assessment of buiding construction " pertinent regulations execution such as (GBJ301-88).The quality specifications of anchor pole 4a, 4b construction be according to " Technical code for shotcrete rock bolts shore " (GBJ86-85) and " soil bolt design and construction standard " (CECS22:90) pertinent regulations carry out.Foundation ditch displacement deformation value is controlled at and is not more than 30mm.(existing national regulation is 30~50mm.)

Claims (3)

1. pile-anchor foundation ditch supporting construction method is characterized in that:
A. according to the stake bit plan, carry out stake position setting-out after, carry out the construction of bored pile (2) again, form barricade;
B. (3) absolute altitude at the bottom of the capping beam of cutting the earth;
C. cut a hole bored pile (2) to design elevation;
D. carry out first row's anchor pole (4a) construction in the soil layer between each adjacent bored pile (2);
E. capping beam (5) construction;
F. cut the earth to second row's anchor pole (4b) construction location;
G. carry out second row's anchor pole (4b) construction;
H. according to different design conditions, can repeat the operation of f and g and arrange anchor pole to last;
I. cut the earth to the foundation ditch bottom.
2. according to the described pile-anchor foundation ditch supporting construction method of claim 1, it is characterized in that: before described bored pile (2) construction, carry out the construction of cement mixing pile (1) earlier, form water-stop curtain.
3. according to the described pile-anchor foundation ditch supporting construction method of claim 1, it is characterized in that: described first row's anchor pole (4a), second row's anchor pole (4b) are prestressed anchor.
CNB2008100596828A 2008-02-02 2008-02-02 Pile-anchor foundation ditch supporting construction method Active CN100465386C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008100596828A CN100465386C (en) 2008-02-02 2008-02-02 Pile-anchor foundation ditch supporting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008100596828A CN100465386C (en) 2008-02-02 2008-02-02 Pile-anchor foundation ditch supporting construction method

Publications (2)

Publication Number Publication Date
CN101225661A true CN101225661A (en) 2008-07-23
CN100465386C CN100465386C (en) 2009-03-04

Family

ID=39857841

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008100596828A Active CN100465386C (en) 2008-02-02 2008-02-02 Pile-anchor foundation ditch supporting construction method

Country Status (1)

Country Link
CN (1) CN100465386C (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793032A (en) * 2010-04-21 2010-08-04 邵辉 Construction method of deep foundation ditch on small place
CN101886393A (en) * 2010-07-03 2010-11-17 朱奎 Construction method of combined foundation ditch support
CN101906780A (en) * 2010-07-12 2010-12-08 中铁四局集团第五工程有限公司 Method for protecting and reinforcing anchor rope of steel pipe pile
CN102031784A (en) * 2011-01-12 2011-04-27 陕西建工集团第六建筑工程有限公司 Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN102108708A (en) * 2010-12-16 2011-06-29 张继红 Compound anchor rod foundation pit building envelope, construction method thereof and adopted cement soil notcher
CN102235007A (en) * 2010-04-27 2011-11-09 中国华冶科工集团有限公司 Method for supporting deep foundation with upper nail-lower pile combination
CN102493465A (en) * 2011-12-12 2012-06-13 中国建筑西南勘察设计研究院有限公司 Anchorage type anchor pile retaining structure for soil filling field
CN102505698A (en) * 2011-10-12 2012-06-20 李宪奎 Soil mass supporting structure and construction method thereof
CN102518135A (en) * 2011-12-29 2012-06-27 标力建设集团有限公司 Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN102817364A (en) * 2012-08-22 2012-12-12 中国建筑第六工程局有限公司 Construction method for deep foundation pit steel sheet pile and anchor rope timbering system
CN103015436A (en) * 2013-01-01 2013-04-03 中国建筑西南勘察设计研究院有限公司 Cemented-type water-blocking curtain and anchor pulling pile compounded supporting structure
CN103132531A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit supporting system construction method
CN103215958A (en) * 2013-04-22 2013-07-24 中国建筑第七工程局有限公司 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN103290847A (en) * 2013-06-18 2013-09-11 福建省九龙建设集团有限公司 Inner oblique beam supporting structure for oversized-area deep foundation pit and construction method
CN103603357A (en) * 2013-10-12 2014-02-26 姚攀峰 Multi-platform inner-support-free self-waterproof foundation pit retaining structure and construction method thereof
CN103898916A (en) * 2014-04-09 2014-07-02 浙江理工大学 Mini-pile combined support structure and construction method thereof
CN104612160A (en) * 2014-11-18 2015-05-13 中大建设有限公司 Maintenance structure for foundation pit next to existing building and construction method
CN106677192A (en) * 2017-03-03 2017-05-17 周同和 Row pile anchoring cement soil pile continuous wall supporting structure and construction process thereof
CN106759405A (en) * 2017-03-06 2017-05-31 中国电建集团中南勘测设计研究院有限公司 A kind of soil-slope supporting construction and construction method
CN106988344A (en) * 2017-03-23 2017-07-28 中铁十六局集团地铁工程有限公司 A kind of construction method of the assembled chassis of assembled station Cast-in-Situ Segment
CN109371985A (en) * 2018-05-28 2019-02-22 中南大学 A kind of foundation pit supporting method for recent fill
CN110029673A (en) * 2019-04-16 2019-07-19 潮峰钢构集团有限公司 Anchor cable drilling pilework and its enclosing method suitable for Extra-Deep Foundation Pit
CN110424450A (en) * 2019-07-31 2019-11-08 中国十七冶集团有限公司 A kind of construction method for the retaining wall also serving as brick fetal membrane
CN111648370A (en) * 2020-05-15 2020-09-11 宁波市北仑精诚设备安装有限公司 Earth excavation construction process with deep foundation pit support
CN112709231A (en) * 2020-12-23 2021-04-27 广东省地质工程公司 Basement foundation pit supporting structure and construction method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3840331B2 (en) * 1998-04-16 2006-11-01 近畿日本鉄道株式会社 Retaining wall using corrosion-resistant structural anchor
JP4123058B2 (en) * 2003-02-05 2008-07-23 株式会社大林組 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction
CN1563605A (en) * 2004-03-23 2005-01-12 孙学毅 Constructing method for controlling deformation on ground excavated

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793032A (en) * 2010-04-21 2010-08-04 邵辉 Construction method of deep foundation ditch on small place
CN102235007B (en) * 2010-04-27 2013-08-07 中国华冶科工集团有限公司 Method for supporting deep foundation with upper nail-lower pile combination
CN102235007A (en) * 2010-04-27 2011-11-09 中国华冶科工集团有限公司 Method for supporting deep foundation with upper nail-lower pile combination
CN101886393A (en) * 2010-07-03 2010-11-17 朱奎 Construction method of combined foundation ditch support
CN101906780A (en) * 2010-07-12 2010-12-08 中铁四局集团第五工程有限公司 Method for protecting and reinforcing anchor rope of steel pipe pile
CN102108708A (en) * 2010-12-16 2011-06-29 张继红 Compound anchor rod foundation pit building envelope, construction method thereof and adopted cement soil notcher
CN102031784A (en) * 2011-01-12 2011-04-27 陕西建工集团第六建筑工程有限公司 Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN102505698A (en) * 2011-10-12 2012-06-20 李宪奎 Soil mass supporting structure and construction method thereof
CN102493465A (en) * 2011-12-12 2012-06-13 中国建筑西南勘察设计研究院有限公司 Anchorage type anchor pile retaining structure for soil filling field
CN102518135A (en) * 2011-12-29 2012-06-27 标力建设集团有限公司 Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN102518135B (en) * 2011-12-29 2015-08-05 标力建设集团有限公司 Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN102817364A (en) * 2012-08-22 2012-12-12 中国建筑第六工程局有限公司 Construction method for deep foundation pit steel sheet pile and anchor rope timbering system
CN103015436A (en) * 2013-01-01 2013-04-03 中国建筑西南勘察设计研究院有限公司 Cemented-type water-blocking curtain and anchor pulling pile compounded supporting structure
CN103015436B (en) * 2013-01-01 2015-07-08 中国建筑西南勘察设计研究院有限公司 Cemented-type water-blocking curtain and anchor pulling pile compounded supporting structure
CN103132531A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit supporting system construction method
CN103215958A (en) * 2013-04-22 2013-07-24 中国建筑第七工程局有限公司 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN103290847A (en) * 2013-06-18 2013-09-11 福建省九龙建设集团有限公司 Inner oblique beam supporting structure for oversized-area deep foundation pit and construction method
CN103603357A (en) * 2013-10-12 2014-02-26 姚攀峰 Multi-platform inner-support-free self-waterproof foundation pit retaining structure and construction method thereof
CN103898916A (en) * 2014-04-09 2014-07-02 浙江理工大学 Mini-pile combined support structure and construction method thereof
CN104612160A (en) * 2014-11-18 2015-05-13 中大建设有限公司 Maintenance structure for foundation pit next to existing building and construction method
CN106677192A (en) * 2017-03-03 2017-05-17 周同和 Row pile anchoring cement soil pile continuous wall supporting structure and construction process thereof
CN106759405A (en) * 2017-03-06 2017-05-31 中国电建集团中南勘测设计研究院有限公司 A kind of soil-slope supporting construction and construction method
CN106988344B (en) * 2017-03-23 2019-12-17 中铁十六局集团地铁工程有限公司 Construction method of assembled trolley for cast-in-place section of fabricated station
CN106988344A (en) * 2017-03-23 2017-07-28 中铁十六局集团地铁工程有限公司 A kind of construction method of the assembled chassis of assembled station Cast-in-Situ Segment
CN109371985A (en) * 2018-05-28 2019-02-22 中南大学 A kind of foundation pit supporting method for recent fill
CN110029673A (en) * 2019-04-16 2019-07-19 潮峰钢构集团有限公司 Anchor cable drilling pilework and its enclosing method suitable for Extra-Deep Foundation Pit
CN110029673B (en) * 2019-04-16 2023-10-13 潮峰钢构集团有限公司 Anchor cable bored pile structure suitable for deep foundation pit support and support method thereof
CN110424450A (en) * 2019-07-31 2019-11-08 中国十七冶集团有限公司 A kind of construction method for the retaining wall also serving as brick fetal membrane
CN111648370A (en) * 2020-05-15 2020-09-11 宁波市北仑精诚设备安装有限公司 Earth excavation construction process with deep foundation pit support
CN112709231A (en) * 2020-12-23 2021-04-27 广东省地质工程公司 Basement foundation pit supporting structure and construction method thereof

Also Published As

Publication number Publication date
CN100465386C (en) 2009-03-04

Similar Documents

Publication Publication Date Title
CN100465386C (en) Pile-anchor foundation ditch supporting construction method
CN204418187U (en) Subway protection region soil nail wall is in conjunction with double-row pile deep foundation ditch composite supporting construction
CN104532868B (en) High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method
CN103306289A (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN211006756U (en) Interface structure of open cut station and large-span duplex arch buried tunnel
CN102116030A (en) Combined bracing structure for foundation pit and construction method thereof
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN102660955A (en) Quick construction method for foundation pit slope support
CN110886507B (en) Method for increasing storey and expanding under existing building
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN211447877U (en) Structure of floor extension is increased to existing building below
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
CN202273233U (en) Deep foundation pit of three-dimensional garage
CN106988337A (en) Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house
CN203625911U (en) Soil discharging construction structure with pit-in-pit door opening arranged in deep foundation pit
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN209780906U (en) Tunnel hole-entering structure
CN205012347U (en) Step supporting construction that three campsheds and single pile cluster closed
CN204435389U (en) A kind of assembled lattice unit for pattern foundation pit supporting structure
CN112942377A (en) Novel support shear-resistant structure and construction method thereof
CN100593052C (en) Open cut foundation pit supporting and protecting method
CN201943076U (en) Combined foundation pit supporting structure
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
CN109680695A (en) Bore forming technique is perfused in anhydrous thickness sand cobble stratum long auger
CN214328899U (en) Combined support-replacing force transmission device for deep foundation pit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant