CN101195460B - Large box girder bottom-mounting hoisting device and method thereof - Google Patents

Large box girder bottom-mounting hoisting device and method thereof Download PDF

Info

Publication number
CN101195460B
CN101195460B CN2007103024987A CN200710302498A CN101195460B CN 101195460 B CN101195460 B CN 101195460B CN 2007103024987 A CN2007103024987 A CN 2007103024987A CN 200710302498 A CN200710302498 A CN 200710302498A CN 101195460 B CN101195460 B CN 101195460B
Authority
CN
China
Prior art keywords
joist
hoist
hoist cable
lifting
suspender
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007103024987A
Other languages
Chinese (zh)
Other versions
CN101195460A (en
Inventor
陈辉
周强
黄新
彭龙超
代华
谢华
高云
王和欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Second Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN2007103024987A priority Critical patent/CN101195460B/en
Publication of CN101195460A publication Critical patent/CN101195460A/en
Application granted granted Critical
Publication of CN101195460B publication Critical patent/CN101195460B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a large box girder pocket bottom hoisting device and a method thereof, wherein the large box girder pocket bottom hoisting device comprises a hoisting tool, a sling and a joist, and is characterized in that: the lifting appliance comprises a double-lifting-point lifting appliance and a single-lifting-point lifting appliance, wherein the double-lifting-point lifting appliance is connected with a lifting cable through a pin shaft, the single-lifting-point lifting appliance is connected with the lifting cable through a balance plate, and the lifting cable is connected with a joist through a slot clamping plate and an anti-skid pin shaft. The invention adopts the bottom-mounted joist and the sling to lift the box girder, and the upper lifting appliance adopts three lifting points to ensure balanced stress of the lifting points, thereby not only ensuring the safety, reliability and stability of the box girder in the process of land transportation, sea shipment and shipment, but also having ingenious concept, safety, reliability and simple operation.

Description

Large-scale girder bottom hoisting device and method thereof
Technical field
Invention relates to a kind of large box girder hanging apparatus, exactly is a kind of large-scale girder bottom hoisting device and method thereof.
Technical background
The non-navigation bridge of bridge 60m prefabricated case beam, its concrete square amount 570m 3, about 1575t conducts oneself with dignity.The treaty contents of place form, construction period and this project that provides according to the owner adopts two 900t/43m tire carrying implements to lift 1575 tons of concrete box girders of a slice jointly and carries out the movement and the shipment of going to sea in the field.The case beam plays the sling general design and makes and need guarantee the land movement process safe of case beam, reliable and stable.Therefore designing which kind of lifting appliance is crucial to the movement and the launching-out operation of the 470 case beams in beam field;
Present domestic case beam lifting method is top board/web/base plate perforation method or the pre-buried suspension rod method of top board/web/base plate, but all needs a large amount of local reinforcements are carried out in case beam lifting position, and the latter more needs pre-buried high strength suspension rod, drops into huge.Be cost-cutting,, adopted the joist of revealing all the details/hoist cable case beam lifting appliance through research and development.This device mainly is divided into three parts, the design of its middle and upper part suspender adopts " three suspension centres " system to guarantee the suspension centre stress equalization, the bottom suspender adopts collet steel case beam to support the 60m prefabricated case beam, and suspender connects by the high strength steel tow that 8 two ends have anchor head up and down.
Summary of the invention
The purpose of invention is at above-mentioned defective, provide a kind of employing joist, hoist cable case beam of slinging of revealing all the details to people, the top suspender adopts " three suspension centres " to guarantee the suspension centre stress equalization simultaneously, not only can guarantee the land movement of the case beam shipment process safe, reliable and stable of going to sea, and be skillfully constructed, large-scale girder bottom hoisting device and method thereof safe and reliable, easy and simple to handle.
Invention comprises suspender, hoist cable and joist, it is characterized in that: suspender comprises two suspension centre suspenders and single suspension centre suspender, and two suspension centre suspenders are connected with hoist cable by bearing pin, and single suspension centre suspender is connected with hoist cable by balance plate, and hoist cable is connected with joist by draw-in groove plate, anti-skidding bearing pin; Single suspension centre suspender comprises top bearing pin and the attaching parts that fuses with it, connects upper and lower crossbeam by the axle of shipping and reselling on another market, and connects hoist cable and cross sill by balance plate, and two suspension centre suspenders are connected and composed by bearing pin and two hoist cables respectively by two secondary suspenders; Hoist cable is made up of high strength steel tow and the anchor head that is loaded on high strength steel tow both ends; Joist comprises the beam body, is loaded on the block of Liang Tishang, places the rubber plinth of Liang Tishang and is loaded on beam body bottom cardan wheel, directional wheel, and beam body both ends have the draw-in groove plate, bow shackle is housed.
A kind of large-scale girder bottom hoisting method, its lifting step is as follows:
(1) before the lifting case beam, will have case beam bracket that rubber plinth and both sides block put down earlier and winch to by the beam making bench again by fork truck with rope traction to the positive center of flank indentation, there with the 50t crane;
(2) lead chain bottom hook and transfer and unload buckle to joist the shackle bolt is fixed by 8t being pulled at the hole for hoist place of back both sides, lead chain top and be fixed on top board hole for hoist side by two secondary holes for hoist, and tension leads chain joist is hung ground, and is closely connected substantially with the case soffit.Last joist both sides block;
(3) two carrying implements run to directly over the bale handle district of revealing all the details, by the top board hole for hoist of case beam, hoist cable lower end anchor head is transferred to the joist both sides, then with manually hoist cable being pushed the draw-in groove plate, spacing with anti-skidding bearing pin to hoist cable, will lead chain at last and be relaxed to state of nature;
(4) carrying implement slowly promotes the top suspender, makes joist rubber plinth and case soffit closely connected;
(5) two carrying implements hoist the case beam synchronously to certain altitude, and are synchronously traversing to carrying implement girder span centre position then;
(6) two the synchronous longitudinal removal case of carrying implement beams are to beam strorage area, and accurately the placing box beam is to depositing on the beam pedestal;
(7) manually once more joist is led the chain tension, its total weight is born by leading chain;
(8) bearing pin of joist location is pulled out, the top suspender is slowly transferred the hoist cable anchor head to the draw-in groove plate, manually hoist cable is released joist, and carrying implement hanging beam dolly breaks away from the case beam with hoist cable fully through hole for hoist then;
(9) manually lead chain joist put to ground, joist is hauled out from case beam bottom transverse by fork truck and 1t winch with joist, again with the handling of 100t carrying implement to specifying deposit position.
The effect of invention
Invention is owing to adopt the joist of revealing all the details, the hoist cable case beam of slinging, the top suspender adopts " three suspension centres " to guarantee the suspension centre stress equalization simultaneously, therefore not only can guarantee the land movement of the case beam shipment process safe, reliable and stable of going to sea, and be skillfully constructed, safe and reliable, easy and simple to handle.
Description of drawings
Fig. 1 is the invention structural representation.
Fig. 2 is the hanger structure scheme drawing.
Fig. 3 is two suspension centre hanger structure scheme drawings.
Fig. 4 is the joist structural representation.
Fig. 5 is the hoist cable structural representation.
Fig. 6 is the connection diagram of draw-in groove plate, anti-skidding bearing pin and joist
The specific embodiment
Embodiment 1:
Referring to Fig. 1~5, the present invention includes suspender 1, hoist cable 2 and joist 3, suspender comprises two suspension centre suspenders and single suspension centre suspender, the attaching parts 5 that single suspension centre suspender comprises top bearing pin 4 and fuses with it, by conversion bearing pin 7 bonded assembly entablatrances 8, cross sill 9, connect hoist cable and cross sill by balance plate 10, two suspension centre suspenders are connected and composed by bearing pin 6 and two hoist cables respectively by two secondary suspenders.Hoist cable is connected with joist 3 by draw-in groove plate 11, anti-skidding bearing pin 12.Hoist cable is made up of high strength steel tow 13 and the anchor head 14 that is loaded on high strength steel tow both ends.Joist comprises beam body 3, is loaded on the block 15 of Liang Tishang, places the rubber plinth 16 of Liang Tishang and is loaded on beam body bottom cardan wheel 17, directional wheel 18, and the design of beam body both ends has draw-in groove plate 11, bow shackle 19 is housed.
When needing lifting case beam, the joist that will have rubber plinth earlier hangs ground, make joist insert in case beam bottom is loaded onto the joist both sides after closely connected substantially with beam case bottom surface block, it is spacing to hoist cable with anti-skidding bearing pin in the joist draw-in groove plate hoist cable lower end anchor head to be packed into again, or else Tong steel rope winding method makes case beam energy " 4 liftings, stressed " in the lifting process at 3.With the case safety beam, reliably and stably carry out the land movement shipment of going to sea.

Claims (2)

1. large-scale girder bottom hoisting device, comprise suspender, hoist cable and joist, it is characterized in that: suspender comprises two suspension centre suspenders and single suspension centre suspender, two suspension centre suspenders are connected with hoist cable by bearing pin, single suspension centre suspender is connected with hoist cable by balance plate, and hoist cable is connected with joist by draw-in groove plate, anti-skidding bearing pin; Single suspension centre suspender comprises top bearing pin and the attaching parts that fuses with it, connects upper and lower crossbeam by the axle of shipping and reselling on another market, and connects hoist cable and cross sill by balance plate, and two suspension centre suspenders are connected and composed by bearing pin and two hoist cables respectively by two secondary suspenders; Hoist cable is made up of high strength steel tow and the anchor head that is loaded on high strength steel tow both ends; Joist comprises the beam body, is loaded on the block of Liang Tishang, places the rubber plinth of Liang Tishang and is loaded on beam body bottom cardan wheel, directional wheel, and the design of beam body both ends has the draw-in groove plate, bow shackle is housed.
2. large-scale girder bottom hoisting method, its lifting step is as follows:
(1) before the lifting case beam, will have case beam bracket that rubber plinth and both sides block put down earlier and winch to by the beam making bench again by fork truck with rope traction to the positive center of flank indentation, there with the 50t crane;
(2) lead chain bottom hook and transfer and unload buckle to joist the shackle bolt is fixed by 8t being pulled at the hole for hoist place of back both sides, lead chain top and be fixed on top board hole for hoist side by two secondary holes for hoist, and tension leads chain joist is hung ground, and is closely connected substantially with the case soffit; Last joist both sides block;
(3) two carrying implements run to directly over the bale handle district of revealing all the details, by the top board hole for hoist of case beam, hoist cable lower end anchor head is transferred to the joist both sides, then with manually hoist cable being pushed the draw-in groove plate, spacing with anti-skidding bearing pin to hoist cable, will lead chain at last and be relaxed to state of nature;
(4) carrying implement slowly promotes the top suspender, makes joist rubber plinth and case soffit closely connected;
(5) two carrying implements hoist the case beam synchronously to certain altitude, and are synchronously traversing to carrying implement girder span centre position then;
(6) two the synchronous longitudinal removal case of carrying implement beams are to beam strorage area, and accurately the placing box beam is to depositing on the beam pedestal;
(7) manually once more joist is led the chain tension, its total weight is born by leading chain;
(8) bearing pin of joist location is pulled out, the top suspender is slowly transferred the hoist cable anchor head to the draw-in groove plate, manually hoist cable is released joist, and carrying implement hanging beam dolly breaks away from the case beam with hoist cable fully through hole for hoist then;
(9) manually lead chain joist put to ground, joist is hauled out from case beam bottom transverse by fork truck and 1t winch with joist, again with the handling of 100t carrying implement to specifying deposit position.
CN2007103024987A 2007-12-25 2007-12-25 Large box girder bottom-mounting hoisting device and method thereof Expired - Fee Related CN101195460B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007103024987A CN101195460B (en) 2007-12-25 2007-12-25 Large box girder bottom-mounting hoisting device and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007103024987A CN101195460B (en) 2007-12-25 2007-12-25 Large box girder bottom-mounting hoisting device and method thereof

Publications (2)

Publication Number Publication Date
CN101195460A CN101195460A (en) 2008-06-11
CN101195460B true CN101195460B (en) 2010-06-16

Family

ID=39546122

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007103024987A Expired - Fee Related CN101195460B (en) 2007-12-25 2007-12-25 Large box girder bottom-mounting hoisting device and method thereof

Country Status (1)

Country Link
CN (1) CN101195460B (en)

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767753B (en) * 2008-12-30 2013-05-15 上海宝冶建设有限公司 Method for hoisting by lifting belt vertically
CN101537971B (en) * 2009-03-18 2012-04-25 太原重工股份有限公司 Welded type crane hanger beam
CN101927962A (en) * 2010-09-27 2010-12-29 中国葛洲坝集团机械船舶有限公司 Method for hoisting large-sized workpiece with double gantry cranes and lifting appliance
CN102774742B (en) * 2012-07-27 2015-03-04 国家电网公司 Current transformer (CT) coil lifting device
CN103287965A (en) * 2013-06-24 2013-09-11 保定天威保变电气股份有限公司 Shunt reactor core column lifting method and special tool
CN103437298B (en) * 2013-09-04 2015-08-05 中国十九冶集团有限公司 Concrete precast box girder hoisting method and hoisting device
CN104961046A (en) * 2015-06-19 2015-10-07 法格霭德兰汽车配件(昆山)有限公司 Crane sling
CN105329768A (en) * 2015-11-30 2016-02-17 四川迅吉科技有限责任公司 Hoisting tool for compartment of high-speed railed motor train unit
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106185596B (en) * 2016-08-24 2018-06-12 中国能源建设集团安徽电力建设第一工程有限公司 A kind of suspender for hoisting large-size flexibility plate
CN108557632B (en) * 2017-12-14 2019-11-19 江苏科技大学 Loader-digger digging arm assembles lifting tooling
CN110342413B (en) * 2018-04-04 2021-01-15 中国二十冶集团有限公司 Simple traction method for prestressed beam
CN109235616B (en) * 2018-11-16 2021-02-19 洛阳栾川钼业集团股份有限公司 Installation method of tailing dam drainage well arch bar
CN109468966A (en) * 2019-01-08 2019-03-15 刘金顶 Steel box-girder suspension bridge dismounts soft rope device
CN110980503A (en) * 2019-11-14 2020-04-10 重庆泰山电缆有限公司 Insulating material loading lifting device and lifting combination for cross-linking production line
CN111824928B (en) * 2020-06-16 2022-01-25 中交第三公路工程局有限公司 Hoisting equipment for steel box girder in complex environment
CN112411381A (en) * 2020-10-26 2021-02-26 中交路桥建设有限公司 Construction method for erecting precast box girder of overbridge in deep cutting area
CN113548581A (en) * 2021-08-04 2021-10-26 中铁十六局集团第一工程有限公司 Suspension lifting appliance for concrete box girder large deflection angle hoisting construction and use method thereof
CN114475926B (en) * 2022-01-17 2023-09-12 益阳中海船舶有限责任公司 Container ship guarantee system based on wind and wave driving safety
CN117699647B (en) * 2024-02-06 2024-04-09 山东汇通建设集团有限公司 Hoisting device and method for construction of curve continuous steel box girder

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1673459A (en) * 2004-03-24 2005-09-28 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
CN200992687Y (en) * 2006-12-30 2007-12-19 中交第二公路工程局有限公司 Slingdevice for suspension bridge steel box beam mounting
CN201151613Y (en) * 2007-12-25 2008-11-19 中铁四局集团有限公司 Hoisting device at bottom of large-scale case roof beam pocket

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1673459A (en) * 2004-03-24 2005-09-28 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
CN200992687Y (en) * 2006-12-30 2007-12-19 中交第二公路工程局有限公司 Slingdevice for suspension bridge steel box beam mounting
CN201151613Y (en) * 2007-12-25 2008-11-19 中铁四局集团有限公司 Hoisting device at bottom of large-scale case roof beam pocket

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
刘吉明.整体式挂孔钢箱梁安装施工技术.中外公路第26卷 第4期.2006,第26卷(第4期),全文.
刘吉明.整体式挂孔钢箱梁安装施工技术.中外公路第26卷 第4期.2006,第26卷(第4期),全文. *
张长荣等.900吨提梁机3吊点起升方案设计.建筑机械化2007年 第3期.2007年(第3期),第3部分"3吊点作业方式".
张长荣等.900吨提梁机3吊点起升方案设计.建筑机械化2007年 第3期.2007年(第3期),第3部分"3吊点作业方式". *
沈枫等.东海大桥预制箱梁海上架设施工.中国市政工程2006年 第5期.2006,2006年(第5期),右栏第2段.
沈枫等.东海大桥预制箱梁海上架设施工.中国市政工程2006年 第5期.2006,2006年(第5期),右栏第2段. *

Also Published As

Publication number Publication date
CN101195460A (en) 2008-06-11

Similar Documents

Publication Publication Date Title
CN101195460B (en) Large box girder bottom-mounting hoisting device and method thereof
CN201151613Y (en) Hoisting device at bottom of large-scale case roof beam pocket
CN201217608Y (en) Integral component suspending beam for hoisting
CN201914868U (en) Tower crane attached mounting-demounting hoisting device
CN204342257U (en) A kind of large-scale component turning device
CN206665952U (en) A kind of novel hanging tool
CN101412488B (en) Air turnover device and method for special-shaped barrel
CN102849613B (en) Special hoisting tool special for high-speed rail motor train unit carriage
CN202390116U (en) High-intensity small-tonnage hoist
CN204752012U (en) Wall -hanging miniature hoist
CN202944976U (en) Hoisting device of light hollow partition board
CN202558444U (en) Steel penstock hoisting balance beam device
CN206985581U (en) A kind of chain block for preventing hoisting-chain from skidding
CN206266077U (en) Sling system
CN205772796U (en) Big bus suspender
CN2910879Y (en) Single hook four points self-balancing sling of lifter
CN101230560B (en) Hydraulic elevator tower cable-stayed straddle bridge hoisting truck
CN201089694Y (en) Vehicle wheel sling
CN201914830U (en) Rope separator of tower hoist
CN207078901U (en) Gravity motion hanging beam
CN201864456U (en) Bracket for loading test of crane
CN202518908U (en) Steel wire rope traction system
CN201212004Y (en) Wheel center spreader
CN201473171U (en) Moving and lifting dual-purpose hanging device of cableway device
CN108059088B (en) Method and device for deflection turning and transposition of carrying pole Liang Kongzhong of slot erecting machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100616

Termination date: 20171225

CF01 Termination of patent right due to non-payment of annual fee