CN101144320A - Bathroom decoration construction method - Google Patents

Bathroom decoration construction method Download PDF

Info

Publication number
CN101144320A
CN101144320A CNA2006101161326A CN200610116132A CN101144320A CN 101144320 A CN101144320 A CN 101144320A CN A2006101161326 A CNA2006101161326 A CN A2006101161326A CN 200610116132 A CN200610116132 A CN 200610116132A CN 101144320 A CN101144320 A CN 101144320A
Authority
CN
China
Prior art keywords
facing plate
metope
ground
aluminum strip
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2006101161326A
Other languages
Chinese (zh)
Inventor
黎耀华
谭正浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LI YAOHUA TAN ZHENGHAO
Original Assignee
LI YAOHUA TAN ZHENGHAO
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LI YAOHUA TAN ZHENGHAO filed Critical LI YAOHUA TAN ZHENGHAO
Priority to CNA2006101161326A priority Critical patent/CN101144320A/en
Publication of CN101144320A publication Critical patent/CN101144320A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The present invention discloses a bathroom decoration construction method. A stone material plate is pasted on an aluminum honeycomb plate by adhesion agent to be made into an aluminum honeycomb composite board stone material plate as a wall face veneer and a ground veneer; the wall face veneer is installed on the wall body by adopting a hanging way, the ground veneer is installed on the ground by the adhesion agent; an L shape waterproof aluminum strip is installed between the wall body and the wall face veneer at the corner of a wall face, waterproof silica gel is built in the waterproof aluminum strip and the wall face veneer, the L shape waterproof aluminum strip is installed in the boundary of the ground periphery and the wall face, and the waterproof silica gel is built in the waterproof aluminum strip, the wall face veneer, and the ground veneer. The method can greatly shorten the construction period on the site, the construction workload on the site is reduced, simultaneously, the garbage waste generated by the construction on the site is reduced, the quality guarantee of the product is easy to be improved, and the working risk of the construction on the site is reduced.

Description

Bathroom decoration construction method
Technical field
The present invention relates to a kind of bathroom decoration construction method, specifically, relate to a kind of method of the bathroom of saloon bar being carried out decoration construction.
Background technology
As shown in Figure 1, the decoration construction in traditional saloon bar bathroom comprises 29 site operation programs.For simplifying narration, these programs can be summarized and be divided into 4 stages:
1, waterproof working stage
This stage comprises the pre-buried pipeline of installation that waterproof work is preceding from agent structure and transfer at interval, waterproof work, and waterproof test, the mortar on the waterproofing course whitewashes, and bathtub is installed.The work in this stage can not be left the scene.The work of this stage needs 8-10 consuming time days.
2, wet trade working stage
This stage comprises that from pre-buried shower accessories being installed within the walls the metope mortar whitewashes, and the metope stone material is paved; the ground stone material is paved, stone material edge strip and payment to a porter, stone material joint filling; the wash basin stone panel is installed, and cleaning and protection stone material surface layer avoid being subjected to back work to damage.The work in this stage is labor intensive and time, and produces maximum discarded objects.Moreover most building site all can't provide rational working environment, allows the workman can construct and reach simultaneously the quality requirement of regulation safely.The work of this stage needs 10-12 consuming time days.
3, furred ceiling and paint stage
This stage also often is called dried sessions.Compare with the last stage, construction water is few.But these work also expend many artificial and times, and produce many discarded objects.Work comprises channel and the installation of furred ceiling plaque, and ceiling line is installed, and furred ceiling plaque face is criticized ash and polishing, and oil-base paint is installed dynamo-electric panel and air outlet, and the pasta lacquer is installed doorframe and door leaf, and the paving wallpaper etc.The work of this stage needs 7-9 consuming time days.
4, cleaning and accessory erection stage
The pollutions that the primary working programmes of removing a plurality of wet dried operations of this stage produce, cleaning will divide three roads to finish.Before shower cubicle glass and mirror installation, whole bathroom needs preliminary cleaning, so as not to too dirty, the work that can not play glue in glass edge.Then, after second road cleaning is carried out, begin to install sanitary equipment in the bathroom and various accessories and comprise that towel rail, hook, the fire hose are first-class.At last, when all accessories install, further careful packing cleaning must be finished before transfering work.The work of this stage needs 4-5 consuming time days.
According to above-mentioned whole decoration construction operation as can be known, present traditional bathroom decoration technology, need to decorate at metope, ground, smallpox paving marble or wall floor tile, and these decorations exist site operation, wet trade, labour intensity is big, construction speed is slow, be difficult for guaranteed quality, and operated individual technical level and influence greatly.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of bathroom decoration construction method, with accelerating construction progress, improves construction quality, removes wet trade simultaneously.
In order to achieve the above object, technical scheme of the present invention is as follows:
A kind of bathroom decoration construction method comprises the steps: the stone material plate pasted with adhesive and make aluminium honeycomb compound stone plate on aluminium matter cellular board, as metope facing plate and ground facing plate; Adopt the extension mode of hanging to be installed on the body of wall above-mentioned metope facing plate, ground facing plate is installed on the ground with adhesive; L type waterproof aluminum strip is installed between the body of wall of metope corner and metope facing plate, is inserted water-proof silica-gel in waterproof aluminum strip and the metope facing plate; With the metope intersection, L type waterproof aluminum strip is installed around on ground, inserts water-proof silica-gel in waterproof aluminum strip and metope facing plate, the ground facing plate.
Adopt above-mentioned bathroom decoration construction method, L type waterproof aluminum strip is installed owing to aluminium honeycomb compound stone plate, on aluminium honeycomb compound stone plate all can be prefabricated into standard component, can shorten on-site construction time in a large number, reduce on-the-spot construction working amount, reduce the garbage waste material that site operation produces simultaneously.Prefabricated standard component also be convenient to improve the quality of products assurance, reduce the work danger of site operation.Aluminium honeycomb compound stone plate is keeping the aesthetic feeling of lithotome, but has strengthened flexural strength and impact strength greatly.In addition, weight has only 1/3rd of former stone material, and the workman can install three times of big stone beehive boards.
Description of drawings
Fig. 1 is the decoration construction process flow chart in traditional saloon bar bathroom;
Fig. 2 is the structural representation of aluminium honeycomb compound stone plate of the present invention;
Fig. 3 and Fig. 4 will assemble the schematic diagram of front and back with the prefabricated standard component that has the waterproof connecting parts of metope intersection around will being installed in ground;
Fig. 5 and Fig. 6 are the schematic diagrames that the prefabricated standard component that has the waterproof connecting parts is installed with the metope intersection all around on ground;
Fig. 7 and Fig. 8 are the schematic diagrames that will be installed in the prefabricated standard component assembling front and back that have the waterproof connecting parts of metope corner;
Fig. 9 and Figure 10 are the schematic diagrames that the prefabricated standard component that has the waterproof connecting parts is installed in the metope corner;
Figure 11 and Figure 12 shorten the on-site construction time flow chart;
Figure 13 and Figure 14 reduce on-the-spot construction working amount flow chart;
Figure 15 and Figure 16 reduce the garbage waste material flow chart that site operation produces;
Figure 17 is the three-dimensional exploded view of the floor drain discharge structure of the present invention's use;
Figure 18 is first kind of pattern schematic diagram of the chassis cover of the floor drain discharge structure among Figure 17;
Figure 19 is second kind of pattern schematic diagram of the chassis cover of the floor drain discharge structure among Figure 17;
Figure 20 is the third pattern schematic diagram of the chassis cover of the floor drain discharge structure among Figure 17.
The number in the figure explanation
1-aluminium honeycomb compound stone plate 11-marble thin plate
12-aluminium sheet 13-aluminium honeycomb
14-aluminum honeycomb panel 20-waterproofing course
21-ground facing plate 211-aluminum honeycomb panel
212-side 22-L type waterproof aluminum strip
The 23-first plane 24-second plane
241-nose section 25-metope facing plate
251-aluminum honeycomb panel 252-groove
253-marble thin plate 26-water-proof silica-gel
27-is from levelling mucilage layer 28-bed hedgehopping packed layer
Foam filled dose of 30-waterproofing course of 29-
31-metope facing plate 311-aluminum honeycomb panel
313-hole, 312-side
32-L type waterproof aluminum strip 33-first plane
34-second plane, 331-hole
341-nose section 35-at interval
The 36-aluminium rivet 37-metope facing plate of loosing core
371-marble thin plate 372-aluminum honeycomb panel
38-water-proof silica-gel 41-chassis cover
42-the first half 43-the latter half
The specific embodiment
According to Fig. 2 to Figure 16, provide preferred embodiment of the present invention, and described in detail below, enable to understand better function of the present invention, characteristics.
At first, the present invention has used aluminium honeycomb compound stone plate as prefabricated standard component.As shown in Figure 2, aluminium honeycomb compound stone plate 1 of the present invention comprises the marble thin plate 11 of 5mm and the aluminum honeycomb panel 14 that is made of the aluminium honeycomb 13 of thick aluminium sheet 12 double teams of two-layer 1mm.The mode that marble thin plate 11 adopts vacuum to paste is affixed on the aluminum honeycomb panel 14, as follow-up metope facing plate and ground facing plate.The thickness of aluminium honeycomb 13 is 8mm~12mm.Adopt such material, can keep the aesthetic feeling of lithotome, but strengthened flexural strength and impact strength greatly.In addition, weight has only 1/3rd of former stone material, and equal workman can install three times big aluminium honeycomb compound stone plate.
Metope facing plate is to adopt the extension mode of hanging to be installed on the partition wall of building site with prefabricated chip.Ground facing plate is to be installed on the ground in building site with adhesive.The installation of metope facing plate and ground facing plate allows that the building-site size has an appointment 10mm with interior length variation.
Next, in the body of wall position of metope corner, also have around the ground and the metope intersection, need carry out waterproofing work, on the basis of aluminium honeycomb compound stone plate, pre-install the waterproof connecting parts exactly again, also be prefabricated into standard component.
Fig. 3 and Fig. 4 will assemble the schematic diagram of front and back with the prefabricated standard component that has the waterproof connecting parts of metope intersection around will being installed in ground.As shown in the figure, the ground facing plate 21 that constitutes at aluminium honeycomb compound stone plate is smeared water-proof adhesive with splicing place of L type waterproof aluminum strip 22.L type waterproof aluminum strip 22 has first plane 23 and second plane 24 vertical with first plane, during splicing, first plane 23 of L type waterproof aluminum strip 22 is attached on aluminum honeycomb panel 211 surfaces of ground facing plate 21, and 24 on second plane is the side 212 of facial ornament panel 21 adjacent to each other.Second plane 24 of L type waterproof aluminum strip 22 has a nose section 241, protrudes in outside the height of ground facing plate 21.
On-the-spot installation procedure is consulted Fig. 5 and Fig. 6.Installation procedure is as follows: the aluminum honeycomb panel 251 belows fluting 252 of metope facing plate 25, inject water-proof silica-gel 26 in 25 times square grooves 252 of metope facing plate.Metope facing plate 25 is inserted waterproof aluminum strip 22 downwards, and the nose section 241 of waterproof aluminum strip 22 enters in the groove 252, and the lower surface of the marble thin plate 253 of metope facing plate 25 is resisted against on the marble thin plate of ground facing plate 21.Between body of wall and metope facing plate 25, inject foam filled dose 29 at last.Be provided with bed hedgehopping packed layer 28 successively between ground and the ground facing plate 25 and from levelling mucilage layer 27, between the aluminum honeycomb panel of levelling mucilage layer 27 and ground facing plate 25, be connected by water-proof adhesive.Also be provided with waterproofing course 20 between bed hedgehopping packed layer 28 and the ground.
Fig. 7 and Fig. 8 are the schematic diagrames that will be installed in the prefabricated standard component assembling front and back that have the waterproof connecting parts of metope corner.As shown in the figure, the metope facing plate 31 that constitutes at aluminium honeycomb compound stone plate is smeared water-proof adhesive with splicing place of L type waterproof aluminum strip 32.L type waterproof aluminum strip 32 has first plane 33 and second plane 34 vertical with first plane, during splicing, first plane 33 of L type waterproof aluminum strip 32 is attached on aluminum honeycomb panel 311 surfaces of metope facing plate 31, leaves an interval 35 between the side 312 of 34 on second plane and metope facing plate 31.Second plane 34 of L type waterproof aluminum strip 32 has a nose section 341, protrudes in outside the height of metope facing plate 31.Perforate 313 on the aluminum honeycomb panel 311 of metope facing plate 31, the corresponding position perforate 331 on first plane 33 of L type waterproof aluminum strip 32 is inserted the aluminium rivet 36 of loosing core, the reinforcing of loosing core then in hole 313 and the hole 331.
On-the-spot installation procedure is consulted Fig. 9 and Figure 10.Installation procedure is as follows: inject water-proof silica-gel 38 in the interval of leaving between the side 312 of second plane 34 and metope facing plate 31 35.Metope facing plate 37 is passed in the insertion interval 35.The aluminum honeycomb panel 372 of metope facing plate 37 is attached on second plane 34 of waterproof aluminum strip 32.The marble thin plate 371 of metope facing plate 37 is attached on the side 312 of metope facing plate 31.Also be provided with waterproofing course 30 between body of wall and metope facing plate 31, the metope facing plate 37.
The flow process of above-mentioned job practices is compared with traditional construction process, and advantage is as follows:
At first, shorten on-site construction time and the on-the-spot construction working amount of minimizing
Figure 11 and Figure 12 list respectively, and work progress of the present invention only need just be finished whole bathroom in 13 to 16 days.Adopted metope and ground stone beehive board and other prefabricated accessory, 8 working programmes have been cancelled, and 8 revolutionary reforms of working programme and adjustment are arranged.Usually traditional bathroom takes 29 to 36 days.Topmost change is in the 2nd, 3 and 4 stages; Conventional method needed 21 to 26 days and job practices of the present invention only needs 5 to 8 days.
Figure 13 and Figure 14 list respectively, and work progress of the present invention has significantly reduced site operation work day, and from 29 to 38 required work days of tradition, reducing to only needs just finish 11 to 16 day work day whole bathroom.Same topmost change is in the 2nd, 3 and 4 stages; Conventional method needed 26-33 days and job practices of the present invention only needs 8-11 days.
Secondly, reduce the garbage waste material that site operation produces
Figure 15 and Figure 16 list respectively, and work progress of the present invention has significantly reduced the garbage waste material that site operation produces, because of most of discarded object has been handled in factory.In fact, the discarded object that produces in factory also more effectively reduces the discarded object that produces more than the construction site.From 29 to 38 day required work day of tradition, reducing to only needs just finish 11 to 16 day work day whole bathroom, because of wet trade complained most produce the most maximum.Job practices of the present invention has reduced by 67% discarded object, reduces to 2 to 3.5 cubic metres for from 6 to 9.5 cubic metres.A large amount of minimizing rubbish and discarded object help field supervision, and help better environment control.
Once more, the assurance of improving the quality of products
Leading notion of the present invention is at the plant produced decorative finish, because of factory more effectively carries out the implementation quality management system.I) job site can not provide rational construction environment and equipment to allow the workman that high-quality product is provided effectively; Ii) the quality managemant problem that exists in the job site that the hotel is decorated is that the workman is dispersed in the countless rooms, is difficult to effectively monitor.Yet, in factory, all kinds of machineries can be set and production line is effectively monitored product; Iii) in the national ubiquity construction worker's of development shortage, especially very the person is the skilled worker, comprises craftsman such as stone material workman, carpenter.Erector in the work progress of the present invention only needs the unskilled worker to add that the training of a couple of days just can install, and the effect of installing is the high-quality product on the plant produced.
At last, reduce the work danger of site operation
One of the most dangerous work of job site is that the stone material worker needs to use electric tools in wet trade, and fatal accident takes place when the workman is careless.The working programme of eliminating this class fully at the construction field (site) is to reduce the most effectual way that this tragedy takes place.
In addition, job practices of the present invention also is included in the step that the floor drain discharge structure is set between gutter and the ground facing plate.As shown in figure 17, the floor drain discharge structure comprises a stainless cylindrical chassis cover 41, and the first half 42 external diameters of this chassis cover 41 are greater than the external diameter of the latter half 43.Usually the position of the gutter in building site just need be carried out before waterproof work, and also must carry out in factory in the drain hole position on ground stone material plate or shower chassis, makes the displacement problem.The present invention makes three kinds to the floor drain discharge structure, and respectively shown in Figure 18 to 20, the latter half 43 of the chassis cover 41 among Figure 18 is set to and the first half 42 coaxial inner conductors, be applied to gutter just with drain structure position coordination.The axial line of the latter half 43 of the chassis cover 41 of Figure 19 is set to depart from slightly the first half 42 axial lines, is applied to the situation that there is less error gutter and drain structure position.The axial line of the latter half 43 of Figure 20 dish cover 41 is set to depart from the big distance of the first half 42 axial lines, and being applied to gutter and drain structure position has situation than mistake.Like this, just utilize different chassis covers to solve the draining displacement problem.
The present invention construct " the premade bath room system " that form be a construction system of innovation, its changes the construction process of a large amount of use stone materials in traditional decoration saloon bar bathroom.Adopt novel stone honeycombed plate technique and be prefabricated in the factory, add the design and the member of many innovations, and production method, it provides a total solution; With Fast Installation, the discarded object that reduces the artificial of a large amount of scenes and produce.On the other hand, its batch production production provides high-quality product, and a large amount of construction crisis that reduces the building site.Especially the building site skilled worker's of developed country and area appearance shortage problem satisfies the quality requirement that owner and designer constantly strengthen.
Above-described, be preferred embodiment of the present invention only, be not in order to limiting scope of the present invention, the above embodiment of the present invention can also be made various variations.Be that every simple, equivalence of doing according to the claims and the description of the present patent application changes and modification, all fall into the claim protection domain of patent of the present invention.

Claims (10)

1. a bathroom decoration construction method comprises the steps:
1-1 pastes the stone material plate and make aluminium honeycomb compound stone plate on aluminium matter cellular board with adhesive, as metope facing plate and ground facing plate;
1-2 adopts the extension mode of hanging to be installed on the body of wall above-mentioned metope facing plate, and ground facing plate is installed on the ground with adhesive;
1-3 installs L type waterproof aluminum strip between the body of wall of metope corner and metope facing plate, insert water-proof silica-gel in waterproof aluminum strip and the metope facing plate;
1-4 on ground around with the metope intersection, L type waterproof aluminum strip is installed, insert water-proof silica-gel in waterproof aluminum strip and metope facing plate, the ground facing plate.
2. bathroom decoration construction method as claimed in claim 1 is characterized in that, described aluminium honeycomb compound stone plate comprises the marble thin plate of 4mm~6mm and the aluminum honeycomb panel that is made of the aluminium honeycomb of the thick aluminium sheet double team of two-layer 0.5 mm~2mm; The mode that the marble thin plate adopts vacuum to paste is affixed on the aluminum honeycomb panel.
3. bathroom decoration construction method as claimed in claim 2 is characterized in that, the thickness of described aluminium honeycomb is 8mm~12mm.
4. bathroom decoration construction method as claimed in claim 1 is characterized in that, the step that L type waterproof aluminum strip is installed between the body of wall of metope corner and metope facing plate is:
4-1 splices with L type waterproof aluminum strip after being coated with water-proof adhesive on the aluminum honeycomb panel of the first metope facing plate;
The reinforcing of loosing core behind the aluminium rivet of loosing core is inserted in perforate on 4-2 first metope facing plate and the waterproof aluminum strip in the hole;
The interstitial site of 4-3 between the first metope facing plate and waterproof aluminum strip filled water-proof silica-gel;
4-4 passes the gap location that inserts between the first metope facing plate and the waterproof aluminum strip with the second metope facing plate, and the second metope facing plate is perpendicular to the first metope facing plate, and the aluminum honeycomb panel of the second metope facing plate is attached on the waterproof aluminum strip.
5. bathroom decoration construction method as claimed in claim 4 is characterized in that, scribbles waterproofing course on the body of wall of described metope corner.
6. as the described bathroom decoration construction method of arbitrary claim in the claim 1 to 4, it is characterized in that the step of L type waterproof aluminum strip being installed with the metope intersection around on ground is:
6-1 splices with L type waterproof aluminum strip after being coated with water-proof adhesive on the aluminum honeycomb panel of ground facing plate;
6-2 injects water-proof silica-gel in the notch below metope facing plate;
6-3 inserts the waterproof aluminum strip downwards with metope facing plate, and metope facing plate lower surface is resisted against on the marble thin plate of ground facing plate;
Inject foam filled dose between 6-4 body of wall and the metope facing plate.
7. bathroom decoration construction method as claimed in claim 6, it is characterized in that, be provided with the bed hedgehopping packed layer successively between described ground and the ground facing plate and from the levelling mucilage layer, between the aluminum honeycomb panel of levelling mucilage layer and ground facing plate, be connected by water-proof adhesive.
8. bathroom decoration construction method as claimed in claim 1 is characterized in that, this method also is included in the step that the floor drain discharge structure is set between gutter and the ground facing plate.
9. bathroom decoration construction method as claimed in claim 8, it is characterized in that, described floor drain discharge structure comprises a stainless cylindrical chassis cover, and first part external diameter is overlapped greater than the latter half external diameter in this chassis, and the latter half is set to and the first half coaxial inner conductor.
10. bathroom decoration construction method as claimed in claim 8, it is characterized in that, described floor drain discharge structure comprises a stainless cylindrical chassis cover, and first part external diameter is overlapped greater than the latter half external diameter in this chassis, and the latter half axial line departs from the axial line of the first half.
CNA2006101161326A 2006-09-15 2006-09-15 Bathroom decoration construction method Pending CN101144320A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006101161326A CN101144320A (en) 2006-09-15 2006-09-15 Bathroom decoration construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006101161326A CN101144320A (en) 2006-09-15 2006-09-15 Bathroom decoration construction method

Publications (1)

Publication Number Publication Date
CN101144320A true CN101144320A (en) 2008-03-19

Family

ID=39207032

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006101161326A Pending CN101144320A (en) 2006-09-15 2006-09-15 Bathroom decoration construction method

Country Status (1)

Country Link
CN (1) CN101144320A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103526833A (en) * 2013-10-23 2014-01-22 华煜建设集团有限公司 Waterproof structure of bathroom
CN104452981A (en) * 2014-12-26 2015-03-25 苏州金螳螂住宅集成装饰有限公司 Restroom water-seepage-preventing construction structure and construction method thereof
CN107296740A (en) * 2017-06-16 2017-10-27 北京松盛元环境科技有限公司 A kind of installation method of micro- mist saunas health care bathing system
CN109606571A (en) * 2019-02-11 2019-04-12 企力(大连)海事科技有限公司 Ship cold storage ontology with the welding totally-enclosed spill pallet of aluminum honeycomb

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103526833A (en) * 2013-10-23 2014-01-22 华煜建设集团有限公司 Waterproof structure of bathroom
CN104452981A (en) * 2014-12-26 2015-03-25 苏州金螳螂住宅集成装饰有限公司 Restroom water-seepage-preventing construction structure and construction method thereof
CN107296740A (en) * 2017-06-16 2017-10-27 北京松盛元环境科技有限公司 A kind of installation method of micro- mist saunas health care bathing system
CN109606571A (en) * 2019-02-11 2019-04-12 企力(大连)海事科技有限公司 Ship cold storage ontology with the welding totally-enclosed spill pallet of aluminum honeycomb

Similar Documents

Publication Publication Date Title
CN204163299U (en) For the indoor integrated finishing assembly of integration
CN110173081B (en) Assembled dry process smart dress system
CN104047406A (en) Construction process for ultra-thin stone-facing heat-preserving decorative plate
CN105464309A (en) Integral indoor decorating method and integral indoor decorating component
KR100274218B1 (en) Color rock insulating board for inter or exterior of building and method for fabricating and constructing the same
EP3358096A1 (en) Method for producing a wall or roof panel having installations included, walls or roofs pre-fabricated using said method and joints between the wall and roof panels
CN102535846A (en) One-step forming construction process for integrally pouring housing construction
CN201144494Y (en) Assembly type indoor stepless decorative wall
RU2451141C2 (en) Method to make decorative ornament on building in place of location
CN206428924U (en) A kind of assembled Decorative hanging board
CN101131002A (en) Mould-locking assembled water-proof heat-insulating slab and construction method thereof
CN101144320A (en) Bathroom decoration construction method
CN103556804A (en) Wall and floor decoration module and mounting method thereof
CN203334476U (en) Unit-assembled framework partition wall system
CN105256964A (en) Heat preservation graphene decorative sheet in building outer wall and production flow thereof
CN210395921U (en) Assembled dry-process fine-assembling system
CN203569842U (en) Wall and floor decoration module
CN203684567U (en) Waterproof wall floor decoration structure
CN215341676U (en) Fitment is with technology worker method teaching display device that visits
CN205046814U (en) Compound top hangs wiring strip
CN205035969U (en) Integral wall plates
CN103982042A (en) Split mounting technique of quick home-decoration split mounting engineering
CN211058237U (en) Easily adorn type gypsum lines structure
CN1325733C (en) Tecnique for fabricating facing before pouring building facilities made from reinforced concrete
US20220325530A1 (en) Shower tray and wall panels

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20080319