CN100590560C - Molten iron weighing operations management and information transfer device - Google Patents

Molten iron weighing operations management and information transfer device Download PDF

Info

Publication number
CN100590560C
CN100590560C CN200710092401A CN200710092401A CN100590560C CN 100590560 C CN100590560 C CN 100590560C CN 200710092401 A CN200710092401 A CN 200710092401A CN 200710092401 A CN200710092401 A CN 200710092401A CN 100590560 C CN100590560 C CN 100590560C
Authority
CN
China
Prior art keywords
molten iron
weighing
iron
blast furnace
hot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710092401A
Other languages
Chinese (zh)
Other versions
CN101339429A (en
Inventor
胡狄辛
郑晓虎
袁静
裴斌
唐小葳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CISDI Engineering Co Ltd
Original Assignee
CISDI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CISDI Engineering Co Ltd filed Critical CISDI Engineering Co Ltd
Priority to CN200710092401A priority Critical patent/CN100590560C/en
Publication of CN101339429A publication Critical patent/CN101339429A/en
Application granted granted Critical
Publication of CN100590560C publication Critical patent/CN100590560C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • General Factory Administration (AREA)

Abstract

The invention belongs to the technical field of physics department, discloses a device for hot metal weighing management and information transfer, and particularly relates to a vehicle mounted devicefor weighing operation management and information transfer which has nothing to do with transportation path of a hot metal ladle car. The device of the present invention is composed of a hot metal weighing information management server which is specially arranged for a blast furnace, standard weighing site operation boards and a hot metal receiving data packet. A network physical transmission medium is not needed in data transfer between the site operation boards, and reciprocating data packet transfer is performed by taking a unique identification card carried by a driver of a hot metal ladlecar as a carrier. The present invention not only meets the requirement of process flow about one-tank through of hot metal, but also is applied to mutual communication of complex logistics information in common iron works, especially large-scale iron works.

Description

A kind of molten iron weighing operations management and information transfer device
Technical field
The invention belongs to the physical department technical field, disclose a kind of molten iron weighing management and information transfer device, particularly a kind of vehicular weighing information transfer device that has nothing to do with the hot-metal ladle and carriage transportation route.
Background technology
Molten iron tank switching station has been cancelled in the newly-built steel plant of part steel-making zone at present, take " one jar on earth " flow process mode, promptly use hot-metal bottle after blast furnace receives molten iron, directly to deliver to steelmaking converter, cause hot-metal bottle when blast furnace receives molten iron, will specify the reception weight of molten iron by the strictness of steelmaking converter volume, can not reach specified wt and must receive molten iron by secondary, can't effectively discern a molten iron storage that has received when the strange land secondary receives molten iron between blast furnace, make the molten iron weighing slack tank, half jar of identification is complicated, be prone to misoperation initiation molten iron and overflow accident, the reliability of the reception of molten iron and the control of weighing process operation becomes matter of utmost importance.
Need in the blast furnace production process information such as the process of tapping a blast furnace such as every blast furnace, each iron mouth 1 year, a day, the amount of tapping a blast furnace once, the time of tapping a blast furnace, hot-metal bottle access times are carried out general management, so that analyze blast furnace production load, infer maintenance time, rational allocation raw material etc., how collecting these information also is a difficult problem that perplexs the blast furnace safety in production for a long time.
Hot-metal bottle receives molten iron and implement (being a plurality of generation points) between different blast furnaces and iron mouth in addition, need be sent to different steelworkss iron foundry (shop) (being a plurality of consuming points) not even together after finishing receiving at every turn, the conveying destination of hot-metal car is subjected to factor affecting such as molten iron demand relation and transportation dispatching, also carries the destination because of the incident Iterim Change of burst; The molten iron that produces point from molten iron receives data packet delivery to the molten iron consuming point, and the molten iron that the molten iron consuming point is produced uses data packet delivery to return molten iron and produces point again, and the information bang path is difficult to control.
Summary of the invention
The present invention has not only satisfied molten iron " a jar on earth " technological process requirement, also is applicable to the especially large-scale steel plant in ordinary steel ironworks complicated logistics transmission ﹠ distribution information mutual communication.
The technical scheme that technical solution problem of the present invention is adopted is: by functional requirement the standard weighing execute-in-place dish of different outfit band intelligent controllers, the on-the-spot Word message prompting operation steps of molten iron weighing overall process are set in ironmaking, steel-making, iron foundry (shop) respectively.Every blast furnace disposes proprietary molten iron weighing information management server, except that to molten iron weighing is monitored in the blast furnace casting process, blast furnace casting amount, each iron mouth duty etc. is carried out the comprehensive information collection, make historical storage and provide complete production data for blast furnace production.Molten iron receives packet and molten iron uses packet, adopts short word joint data splitting form respectively; The irrelevant vehicular hot-metal bottle of brand-new exploitation and the transportation route information transmission technique of weighing satisfies complicated logistics transmission ﹠ distribution information mutual communication.
Description of drawings
Fig. 1 molten iron weighing weighing operations management of the present invention and information transfer device pie graph
The on-the-spot Word message prompting figure of Fig. 2 molten iron weighing operations management of the present invention and information transfer device
Among the figure, part 1 is the other molten iron weighing execute-in-place of a track scale A dish, part 2 is a cast house platform molten iron weighing execute-in-place B dish, the regional molten iron weighing execute-in-place C dish of part 3 steel-making, part 4 is for being cast iron unit room molten iron weighing execute-in-place D dish, part 5 is molten iron weighing information management server (band industrial data storehouse), and part 6 is a hot-metal bottle.
Embodiment
Below in conjunction with accompanying drawing specific embodiments of the invention are described further:
1, molten iron weighing operations management and information transfer device: molten iron weighing operations management of the present invention and information transfer device are the standard weighing execute-in-place dishes that four types of band intelligent controllers are set by different function requirements in ironmaking, steel-making, iron foundry (shop) respectively: the other molten iron weighing execute-in-place of track scale A dish 1, one in each iron mouth; Cast house platform molten iron weighing execute-in-place B dish 2, one in each iron mouth; The regional molten iron weighing execute-in-place C that makes steel coils 3, one of each steelshop; Cast iron unit room molten iron weighing execute-in-place D dish 4, one of each cast iron unit room.Each coils quantity type and disposes as required.And on the other molten iron weighing execute-in-place of track scale A dish 1 and cast house platform molten iron weighing execute-in-place B dish 2, alarm lamp, action button etc. both be set, the giant-screen alphabetic character also is set to be shown, make text prompt directly perceived by signals collecting and logic determines to the molten iron weighing process, pilot operationp person step by step, reasonable operation, even the operator is not in time by prompting operation, non-key step also can change next step over to automatically, reduce the misoperation rate, the reliability that improves the molten iron weighing device is had great improvement.
Molten iron weighing information management server (band industrial data storehouse) 5 is collected all iron mouths of this blast furnace overall process information of tapping a blast furnace, to monitoring in real time such as blast furnace casting amount, each iron mouth duty; The server data database data receives packet+molten iron by molten iron and uses packet to merge as the subject term bar with hot-metal bottle number to form, carry out record to the blast furnace casting process and to hot-metal bottle 6 behaviours in service, add up hot-metal bottle 6 access times, time, slag residual quantity etc. at any time; In addition when existing a plurality of converters and volume inequality, corresponding hot-metal bottle 6 receives iron water amount and difference must occur, and server is discerned automatically according to hot-metal bottle search call setup parameter, promoted blast furnace holistic management level, for blast furnace production provides partial data.
Data transfer between the execute-in-place dish does not need the network physical transmission medium, and the unique identification card that relies on hot-metal car transportation driver to carry is that carrier carries out blast furnace and makes steel transmission regional, pig machine number of chambers certificate, but the mode difference that different zones reads and writes data.Insertion identification snapped into the other molten iron weighing execute-in-place of track scale A dish 1 after hot-metal car sailed into and stops accurate position under the blast furnace iron notch, at first input is about to receive the hot-metal bottle 6 codings numbering of molten iron as unique identification, need not increase equipment finishing hot-metal bottle number reads, after hot-metal bottle 6 reception molten iron reach the quantitative setting value of molten iron, automatically form molten iron reception packet and write to identification card, short word joint data splitting bag only sends the key message that needs.After hot-metal ladle and carriage sails steelshop into, insert identification and snap into the regional molten iron weighing execute-in-place C dish 3 of steel-making, read all hot-metal bottle molten iron reception information on this hot-metal ladle and carriage, under the normal condition, the converter computer system sends confirmation signal after receiving information, interpolation is simultaneously taken out identification card after writing molten iron use packet.Under the improper situation, the transmission part did not receive hot-metal bottle 6 signals after information was received by the converter computer system, a while interpolation writes the molten iron reception packet that the molten iron that will receive uses the packet reservation not receive, and hot-metal car can remove other steelshop or cast iron unit room, consumes up to molten iron to finish.Cast iron unit room molten iron weighing execute-in-place D coils 4 principle of work and steelshop and makes steel regional molten iron weighing execute-in-place C and coil 3 similarly, just must receive hot-metal bottle 6.Hot-metal ladle and carriage is got back under the blast furnace iron notch again after reapposing slack tank, read hot-metal bottle molten iron use last time packet information by track scale side molten iron weighing execute-in-place A dish 1 and be directly passed to molten iron weighing information management server (band industrial data storehouse) 5, cast house platform molten iron weighing execute-in-place B dish 2 is finished molten iron reception weighing process operation control on the cast house platform.
It is to finish receiving the back at molten iron to form that molten iron receives packet, it is to form when molten iron is really consumed that molten iron uses packet, packet contains these contents respectively, is equivalent to point-to-point intelligence " manifest " formula information transmission mode and has thoroughly avoided the information transmission difficult problem that complicated logistics transmission ﹠ distribution process is brought.Using this information writes, reads mode and realized that also the molten iron between accessible many blast furnaces receives again.The present invention has not only satisfied molten iron " a jar on earth " technological process requirement, also is applicable to the especially large-scale steel plant in ordinary steel ironworks complicated logistics transmission ﹠ distribution information mutual communication.
2, the mode of operation of molten iron weighing management devices: the mode of operation of molten iron weighing management devices is by the on-the-spot Word message prompting of molten iron weighing management devices, sail state into according to the detected weight signal animation display of weighing track scale hot-metal car, the coding numbering on the hot-metal ladle and carriage is imported in the back prompting of stopping, this hot-metal ladle and carriage of storage gross weight sends hot-metal ladle and carriage and is ready to signal after the automatic average processing.Molten iron dynamically shows hot-metal bottle general assembly (TW) and molten iron nt wt net weight after flowing into hot-metal bottle; Trigger molten iron simultaneously and receive timer, record taps a blast furnace process constantly, adds up to tap a blast furnace process time.By to weight of molten iron differential calculation molten iron inbound pacing, according to the quantitative setting value of molten iron, extrapolate this hot-metal bottle and finish receiving Estimated Time Remaining again.
Automatically the preceding quantitative setting value of molten iron of this hot-metal bottle of search call behind the input hot-metal bottle number, and by roughly 90% calculate generate molten iron quantitatively before setting value.The quantitative setting value of molten iron, the quantitatively preceding setting value of molten iron also can changes once more on picture.Reach molten iron quantitatively before setting value, the quantitative setting value of molten iron scene send sound and light alarm, when another line hot-metal ladle and carriage is ready to, the mouth commutation is slipped in the prompting swing.
Swing slide mouth commutation position signal arrives, and this hot-metal bottle molten iron receiving course is finished.The hot-metal bottle gross weight stops computing, and the molten iron inbound pacing stops to calculate.Central Control Room sends the off-line confirmation signal, and hot-metal car weight decline pace of change thinks that hot-metal car begins off-line greater than setting value with to hang down gross weight outer 50%, hangs down 95% and thinks that off-line finishes.After waiting for that next empty hot-metal ladle and carriage sails into, above-mentioned weighing master routine turns round again.
After the shutoff of iron mouth was finished, trough noresidue molten iron was pressed the conclusion button that taps a blast furnace, and stopped molten iron and received timing, stopped to write down the process time that taps a blast furnace.The time of tapping a blast furnace that does not reach the quantitative setting value of molten iron and calculate by the molten iron inbound pacing, whether needed secondary receive molten iron signal, judged by Central Control Room if sending in short-term; Operating personnel think to send in the quantitative setting value error range of molten iron does not need secondary to receive the molten iron confirmation signal; Operating personnel think to send outside the quantitative setting value error range of molten iron needs secondary to receive the molten iron confirmation signal.Secondary receives molten iron inquiry picture and jumps out, and by retrieving for examination other iron message breath, tentatively judge the back: first telephone contact is consulted, and selected again secondary receives the molten iron position; Or Web broadcast mode request between blast furnace, wait for that other blast furnace replys, determine that again secondary receives the molten iron position; A molten iron receives information and calls between blast furnace, directly is transferred to secondary and receives the molten iron position, finishes the secondary molten iron and receives.If need to confirm secondary to receive molten iron, but do not have secondary to receive the molten iron record, be considered as defective molten iron, should be by the production scheduling special processing.
Receive in the molten iron process,, judge whether weighing sensor has damage by the hot-metal bottle wheel being divided into the weighing A that puts and the weight operational analysis of B section; General assembly (TW) equals A+B under the normal condition.As A+B>2A, B>A, A section pressure head damages damage; A+B>2B, A>B, B section pressure head damage, and general assembly (TW) equals 2A or the 2B big value after relatively under the improper situation.Automatic zero set (AZS) when no hot-metal ladle and carriage is parked.
Omnidistance by the sequencing that occurs to operating process, alarm on picture has only and just can send this hot-metal bottle molten iron receiving course finish signal after basic step is finished.If the secondary molten iron receives, just can send this hot-metal bottle molten iron receiving course after also must finishing and finish signal by secondary molten iron reception basic step.
3 information packet constitute form and transmission condition: hot-metal bottle receives molten iron end signal to Central Control Room and judges that also Central Control Room sends confirmation signal, treats that the weighing process finishes the back and sends " molten iron reception packet ".Molten iron receives data packet format: hot-metal bottle number+high heat (batch) number+iron slogan and weighing line code+hot-metal bottle gross weight+molten iron net weight+reception molten iron the start time+reception molten iron concluding time+secondary sign indicating number+effect sign indicating number that taps a blast furnace.Data are by writing the card device identification card that writes direct.
When receiving molten iron as the need secondary, do not form " molten iron reception packet ", a molten iron receives data and can call between blast furnace.After secondary reception molten iron is finished, send packet in a manner described.
After hot-metal bottle is made steel or pig machine receives allocation and transportation and finish, send " molten iron use packet ".Molten iron uses data packet format: hot-metal bottle number+steelshop or iron foundry (shop) numbering+hot-metal bottle gross weight+molten iron net weight+hot-metal bottle send to time+the effect sign indicating number.Data are added on molten iron and receive after the packet by writing the card device identification card that writes direct.
Hot-metal ladle and carriage is got back to the blast furnace ironmaking zone before receiving molten iron again, use in the packet information to read in molten iron, be directly passed to the molten iron weighing information management server, and wipe " molten iron reception packet " and " molten iron use packet ", receive information so that store new molten iron, beginning next round molten iron receives, uses writing of data.
Identification card is divided into upper half and bottom half, and each dualization of packet record (promptly upper half and bottom half each once) prevents the Card read/write mistake; According to maximum hot-metal bottle transportation quantity, will divide erasable information record segment, byte number is not less than " molten iron reception packet " and " molten iron use packet " total volume; Identification card has also been opened up the fix information storage area in addition.
It is to finish receiving the back at molten iron to form that molten iron receives packet, it is to form when molten iron is really consumed that molten iron uses packet, packet contains these contents respectively, is equivalent to point-to-point intelligence " manifest " formula information transmission mode and has thoroughly avoided the information transmission difficult problem that complicated logistics transmission ﹠ distribution process is brought.Using this information writes, reads mode and realized that also the molten iron between accessible many blast furnaces receives again.The present invention has not only satisfied molten iron " a jar on earth " technological process requirement, also is applicable to the especially large-scale steel plant in ordinary steel ironworks complicated logistics transmission ﹠ distribution information mutual communication.

Claims (4)

1. molten iron weighing operations management and information transfer device, it is characterized in that: every blast furnace disposes proprietary molten iron weighing information management server, standard weighing execute-in-place dish and molten iron and receives packet, data transfer between the execute-in-place dish does not need the network physical transmission medium, and the unique identification card that relies on hot-metal car transportation driver to carry is that carrier carries out reciprocal data packet delivery between blast furnace and steel-making zone and cast iron unit room.
2. according to described molten iron weighing operations management of claim 1 and information transfer device, it is characterized in that: the standard weighing execute-in-place dish that four types of band intelligent controllers are set by functional requirement in ironmaking, steel-making, iron foundry (shop) respectively, the other molten iron weighing execute-in-place of track scale A dish, one in each iron mouth; Cast house platform molten iron weighing execute-in-place B dish, one in each iron mouth; The regional molten iron weighing execute-in-place C that makes steel coils one of each steelshop; Cast iron unit room molten iron weighing execute-in-place D dish, one of each cast iron unit room, the molten iron weighing overall process is by on-the-spot Word message prompting operation steps.
3. according to described molten iron weighing operations management of claim 1 and information transfer device, it is characterized in that: the proprietary molten iron weighing information management server of blast furnace configuration, collect all iron mouths of this blast furnace overall process information of tapping a blast furnace, to monitoring in real time such as blast furnace casting amount, each iron mouth duty; The server data database data receives packet and molten iron by molten iron and uses packet number to form as the merging of subject term bar with hot-metal bottle, carries out record to the blast furnace casting process with to the hot-metal bottle behaviour in service.
4. according to described molten iron weighing operations management of claim 1 and information transfer device, it is characterized in that: it is to finish receiving the back at molten iron to form that molten iron receives packet, it is to form when molten iron is really consumed that molten iron uses packet, realize producing, consuming point-to-point intelligence " manifest " formula information delivery form, packet adopts short word joint data splitting form respectively.
CN200710092401A 2007-07-06 2007-07-06 Molten iron weighing operations management and information transfer device Active CN100590560C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710092401A CN100590560C (en) 2007-07-06 2007-07-06 Molten iron weighing operations management and information transfer device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710092401A CN100590560C (en) 2007-07-06 2007-07-06 Molten iron weighing operations management and information transfer device

Publications (2)

Publication Number Publication Date
CN101339429A CN101339429A (en) 2009-01-07
CN100590560C true CN100590560C (en) 2010-02-17

Family

ID=40213510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710092401A Active CN100590560C (en) 2007-07-06 2007-07-06 Molten iron weighing operations management and information transfer device

Country Status (1)

Country Link
CN (1) CN100590560C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110702193A (en) * 2019-11-05 2020-01-17 山东钢铁集团日照有限公司 Intelligent metering method for molten iron transported by overhead travelling crane

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103627831A (en) * 2013-10-26 2014-03-12 芜湖新兴铸管有限责任公司 On-line weighing system for molten iron
CN103978167A (en) * 2014-05-24 2014-08-13 北京首钢国际工程技术有限公司 Multifunctional pig casting machine system for molten iron transportation one-jar-to-bottom process
CN107300890A (en) * 2017-08-10 2017-10-27 中冶赛迪工程技术股份有限公司 A kind of continuous casting information confirmation method and system again
CN107677347B (en) * 2017-09-19 2019-06-25 余姚太平洋称重工程有限公司 Static state railroad track scale vehicle parking position detection method
CN110175716A (en) * 2019-05-27 2019-08-27 中冶赛迪重庆信息技术有限公司 State change and gravimetric analysis sensing method, equipment and medium towards blast furnace casting
CN112916846A (en) * 2021-03-02 2021-06-08 首钢京唐钢铁联合有限责任公司 Method and device for controlling iron ladle
CN113988234B (en) * 2021-10-28 2022-06-03 宁波银河自控设备有限公司 Automatic identification and acquisition method and system for molten iron car, intelligent terminal and storage medium

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110702193A (en) * 2019-11-05 2020-01-17 山东钢铁集团日照有限公司 Intelligent metering method for molten iron transported by overhead travelling crane

Also Published As

Publication number Publication date
CN101339429A (en) 2009-01-07

Similar Documents

Publication Publication Date Title
CN100590560C (en) Molten iron weighing operations management and information transfer device
CN111815230B (en) Transportation management and control system for hot-metal bottle of iron and steel enterprise
CN105353733B (en) A kind of steelmaking process intelligent dispatching method
CN101152668A (en) Method for centralized monitoring of continuous casting production working procedure of steel-smelting
CN109919271B (en) Molten iron car scheduling system and scheduling method
CN101898569A (en) Method and system for controlling train route
CN201489347U (en) Ladle tracking management system
CN106647674A (en) Knowledge representation-based steel production scheduling model matching method
CN107164592A (en) Blast furnace casting information centralized-moni- tor system
CN2869027Y (en) Blast furnace molten iron weighing apparatus
CN100552726C (en) A kind of ticket-checking equipment cluster control system and method
CN113723768A (en) Steel production management and control system and method
CN209728814U (en) A kind of molten iron information tracking system
CN107284475A (en) Metallurgic railway haulage vehicle virtual positioning method based on RFID
CN109531799A (en) A kind of Full automatic servo brick machine production line
CN108109005A (en) Consider the public bicycles double mode charge system and charging method of parking demand
CN115818157A (en) Intelligent stock bin management system and method for blast furnace
CN112224243B (en) Real-time monitoring method for dynamic information of position of torpedo hot metal mixer car
CN114559027A (en) Molten iron scheduling method and system based on quality requirement of steelmaking molten iron
CN117313963A (en) Automatic long-way system and method for railway transportation in iron and steel plant area
CN105118275B (en) A kind of blast furnace hot-metal bottle tractor remote control system and remote control thereof
JP2003082407A (en) Method and device for verifying balance in hot metal storage between blast furnace and steel-making shop
CN106406146A (en) Intelligent control system and method for slow cooling process of slag
CN205038785U (en) Blast furnace hot metal jar tractor remote control system
CN116027745B (en) Platform control method based on hot metal ladle running time flow control

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant