CN100585094C - Construction method of circular deep foundation pit support - Google Patents

Construction method of circular deep foundation pit support Download PDF

Info

Publication number
CN100585094C
CN100585094C CN200810120096A CN200810120096A CN100585094C CN 100585094 C CN100585094 C CN 100585094C CN 200810120096 A CN200810120096 A CN 200810120096A CN 200810120096 A CN200810120096 A CN 200810120096A CN 100585094 C CN100585094 C CN 100585094C
Authority
CN
China
Prior art keywords
pool wall
circular
construction
concrete
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200810120096A
Other languages
Chinese (zh)
Other versions
CN101328713A (en
Inventor
华锦耀
王兼嵘
吴佳雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAFENG CONSTRUCTION CO Ltd
Original Assignee
HUAFENG CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAFENG CONSTRUCTION CO Ltd filed Critical HUAFENG CONSTRUCTION CO Ltd
Priority to CN200810120096A priority Critical patent/CN100585094C/en
Publication of CN101328713A publication Critical patent/CN101328713A/en
Application granted granted Critical
Publication of CN100585094C publication Critical patent/CN100585094C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a method for constructing the circular deep foundation support, comprising the following steps that: firstly, a circular pool wall I (6) is constructed by a segment topdown construction method, wherein, the first segment of the circular pool wall I constructed by the segment topdown construction method is taken as a supporting ring beam, after the digging depth is up to the needed degree, a lower cushion coat (9) and base plate (8) of the pool base plate are cast with concrete, and the pool wall II (7) of the remaining part is constructed by the regular construction method upwards from the base plate (8). Compared with the prior art, the method has the characteristics that the construction degree of advancement is rapid, the cost is low, the deformation is easy to control, the engineering quality is good, the foundation ditch has a high degree of safety, and the method is applicable to circular foundation ditches with any digging depths.

Description

The job practices of circular deep foundation pit support
The method field:
The invention belongs to the realm of building construction, particularly relate to a kind of job practices of circular deep foundation pit support.
Background method:
At present, the method to circular concrete basin deep foundation pit support has combined type soil nailing wall, cement mixing pile to form gravity retaining wall, fender post (tube-sinking cast-in-situ pile, bored pile, prestressed concrete pipe pile) in conjunction with horizontal support, column, ring beam.Adopt combined type soil nailing wall or cement mixing pile to form the method for gravity retaining wall, its construction speed slow (firm time is long), cost is higher, the difficult control of distortion promptly influences the degree of safety that workmanship influences foundation ditch again, so and because the bigger foundation ditch of the difficult control limited inapplicable cutting depth of bearing capacity of distortion; Adopt fender post in conjunction with horizontal support, column, ring beam, its support space enclosing structures such as ring beam and stand column pile the cost height, need layering that the support replacement band is set and after construction, need to remove to support, so construction speed is slow, raw materials consumption is big, cost is high.
Summary of the invention:
The present invention is directed to that above problem provides that a kind of construction speed is fast, cost is low, distortion is easy to control, good engineering quality, the foundation ditch degree of safety is high and the job practices of circular deep foundation pit support that the circular foundation ditch of any cutting depth all is suitable for.
The present invention overcomes the above problems used technical scheme: the job practices that a kind of circular deep foundation pit support is provided, the pool wall I of the circular pool wall of segmentation reverse construction at first, wherein with first section of the circular pool wall I of segmentation reverse construction as the supporting ring beam, after excavating the required degree of depth, fluid concrete pond base plate underlayer and base plate, from base plate begin the to make progress pool wall II of positive practice construction remaining part, the pool wall I of the circular pool wall of described segmentation reverse construction may further comprise the steps again:
1) according to geologic report and the actual cutting depth of foundation ditch, calculate stake type, length, diameter, arrangement of reinforcement and the spacing of the soldier pile determine to go along with sb. to guard him usefulness, and the thickness of definite pool wall;
When 2) the thickness segmentation of calculating pool wall 2/3~4/5 is constructed from top to bottom, bearing capacity during double as circle supporting ring beam and required arrangement of reinforcement; During the pool wall I of the circular concrete-pool-wall of described 2/3~4/5 thickness of section construction from top to bottom, the bar planting that is provided with the straight screw sleeve that is used to connect perpendicular muscle, load-bearing among the pool wall I is in the suspension muscle and the waterstop of soldier pile, and be provided with the fine-stone concrete sand finish in the soldier pile inboard, and be provided with the Screw arbor with nut at both-ends that is used for fixing inner formword, inner formword is provided with the funnel shaped concrete mouth of building, and carries out casting and compacting of concrete in building the concrete mouth;
3), determine stake type, diameter and the length of the water-stop curtain stake in the soldier pile outside according to geologic report and the actual cutting depth of foundation ditch;
4) measure the stake position that unwrapping wire is decided soldier pile and water-stop curtain stake;
5) construction supporting stake and water-stop curtain stake;
6) earthwork in the foundation ditch is excavated in layering, and each layer digs dark 3m~4m;
7) the circular supporting ring beam and the bank protection concrete of construction supporting stake stake roof pressure top double as pool wall;
8) cooperate excavating of the earthwork, the pool wall I of the circular concrete-pool-wall of 2/3~4/5 thickness of section construction from top to bottom simultaneously.
Above technical scheme also can be regarded as: a kind of job practices of circular deep foundation pit support may further comprise the steps:
1) according to geologic report and the actual cutting depth of foundation ditch, calculate stake type, length, diameter, arrangement of reinforcement and the spacing of the soldier pile determine to go along with sb. to guard him usefulness, and the thickness of definite pool wall;
When 2) the thickness segmentation of calculating pool wall 2/3~4/5 is constructed from top to bottom, bearing capacity during double as circle supporting ring beam and required arrangement of reinforcement; During the pool wall I of the circular concrete-pool-wall of described 2/3~4/5 thickness of section construction from top to bottom, the bar planting that is provided with the straight screw sleeve that is used to connect perpendicular muscle, load-bearing among the pool wall I is in the suspension muscle and the waterstop of soldier pile, and be provided with the fine-stone concrete sand finish in the soldier pile inboard, and be provided with the Screw arbor with nut at both-ends that is used for fixing inner formword, inner formword is provided with the funnel shaped concrete mouth of building, and carries out casting and compacting of concrete in building the concrete mouth;
3), determine stake type, diameter and the length of the water-stop curtain stake in the soldier pile outside according to geologic report and the actual cutting depth of foundation ditch;
4) measure the stake position that unwrapping wire is decided soldier pile and water-stop curtain stake;
5) construction supporting stake and water-stop curtain stake;
6) earthwork in the foundation ditch is excavated in layering, and each layer digs dark 3m~4m;
7) the circular supporting ring beam and the bank protection concrete of construction supporting stake stake roof pressure top double as pool wall;
What 8) cooperate cubic metre of earth excavates, the pool wall I of the circular concrete-pool-wall of 2/3~4/5 thickness of section construction from top to bottom simultaneously, wherein with first section of the circular pool wall I of segmentation reverse construction as the supporting ring beam;
9) excavate the required degree of depth after, fluid concrete pond base plate underlayer and base plate;
10) again from base plate begin the to make progress pool wall II of positive practice construction remaining part.
After adopting above method, the present invention compared with prior art owing to adopted reverse construction and the job practices that positive practice construction combines, has following advantage:
1, foundation ditch degree of safety height, the easy to control and good engineering quality of distortion: because behind foundation pit supporting pile and water-stop curtain pile driving construction, adopt the contrary formula section construction pool wall of doing, form the ring beam of annular, under the native water lateral pressure effect of the soldier pile outside, ring beam mainly bears axial compression, help giving full play to the high advantage of concrete material compressive property, after so the foundation ditch layering is cut the earth, pool wall ring beam and soldier pile form whole common stressed work, therefore foundation ditch degree of safety height is out of shape easy to control and good engineering quality.
2, cost is low and the engineering construction progress is fast: since with adopt foundation ditch in horizontal support and ring beam, column (stake) be set tradition go along with sb. to guard him job practices and compare, the present invention can save horizontal support, ring beam, column (stake), only utilize the pool wall of segmentation reverse construction to replace ring beam, thereby saved the cost of foundation pit supporting construction, and accelerated programming to a certain extent.And because circular deep foundation ditch do not have horizontal support, carry out mechanical type and dig haul volume so help foundation ditch, the top earthwork of circular deep foundation ditch is standing puts muck haulage ramp in the hole, and dump truck directly descend foundation ditch to load and transport the earthwork, so cost is low and the engineering construction progress is fast.
Description of drawings:
Fig. 1 is a sectional structure schematic diagram of the present invention.
Fig. 2 is along the sectional structure schematic diagram of A-A line among Fig. 1.
Fig. 3 is the structural representation of segmentation reverse construction pool wall template of the present invention.
Fig. 4 builds the structural representation of concrete figure for the infundibulate of segmentation reverse construction pool wall template of the present invention.
Fig. 5 is the structural representation of the positive practice construction of the present invention pool wall template.
As shown in the figure: 1, soldier pile, 1.2, hang muscle, 2, the water-stop curtain stake, 3, the supporting ring beam, 4, the bank protection concrete, 5, the gutter, 6, pool wall I, 6.1, the fine-stone concrete sand finish, 6.2, Screw arbor with nut at both-ends.6.3, inner formword, 6.4, annular horizontal steel tube clamp bar, 6.5, waterstop, 6.6, build the concrete mouth, 7, pool wall II, 7.1, the treatment of construction joints layer, 7.2, inner formword, 7.3, the tongue and groove constuction joint, 8, base plate, 9, the base plate underlayer, 10, the precipitation well.
Concrete embodiment:
Below in conjunction with accompanying drawing and concrete embodiment, the present invention is described further:
Embodiment 1
Job practices as Fig. 1, Fig. 2, Fig. 3, Fig. 4 and a kind of circular deep foundation pit support shown in Figure 5, the pool wall I6 of the circular pool wall of segmentation reverse construction at first, wherein with first section of the circular pool wall I6 of segmentation reverse construction as supporting ring beam 3, after excavating the required degree of depth, fluid concrete pond base plate underlayer 9 and base plate 8, from base plate 8 begin the to make progress pool wall II7 of positive practice construction remaining part, the circular pool wall of described segmentation reverse construction may further comprise the steps again:
1) according to geologic report and the actual cutting depth of foundation ditch, calculate stake type, length, diameter, arrangement of reinforcement and the spacing of the soldier pile 1 determine to go along with sb. to guard him usefulness, and the thickness of definite pool wall;
2) calculate when the thickness segmentation of pool wall 2/3 is contrary constructs as formula bearing capacity during the circular supporting ring beam 3 of double as and required arrangement of reinforcement from top to bottom; During the pool wall I6 of the circular concrete-pool-wall of described 2/3 thickness of section construction from top to bottom, the bar planting that is provided with the straight screw sleeve that is used to connect perpendicular muscle, load-bearing among the pool wall I6 is in the suspension muscle 1.2 and the waterstop 6.5 of soldier pile 1, and be provided with fine-stone concrete sand finish 6.1 in soldier pile 1 inboard, and be provided with the Screw arbor with nut at both-ends 6.2 that is used for fixing inner formword 6.3, inner formword 6.3 is provided with the funnel shaped concrete mouth 6.6 of building, and carries out casting and compacting of concrete in building concrete mouth 6.6;
3), determine stake type, diameter and the length of the water-stop curtain stake 2 in soldier pile 1 outside according to geologic report and the actual cutting depth of foundation ditch;
4) measure the stake position that unwrapping wire is decided soldier pile 1 and water-stop curtain stake 2;
5) double soldier pile 1 is adopted in construction supporting stake 1 and water-stop curtain stake 2, lays the soldier pile 1 of row's circle distribution again in the outside of water-stop curtain 2;
6) earthwork in the foundation ditch is excavated in layering, and each layer digs dark 3m;
7) the circular supporting ring beam 3 and the bank protection concrete 4 of 1 roof pressure top of construction supporting stake double as pool wall, circular supporting ring beam 3 is embedded with joint bar, bank protection concrete 4 is provided with gutter 5, and in the gutter 5 arranged outside precipitation well 10;
8) cooperate excavating of the earthwork, the pool wall I 6 of the circular concrete-pool-wall of 2/3 thickness of section construction from top to bottom simultaneously, wherein with first section of pool wall I6 as supporting ring beam 3, perpendicular muscle among the pool wall I6 between each section adopts straight screw sleeve to connect, and be provided with the suspension muscle 1.2 that be used for load-bearing and the waterstop 6.5 of bar planting in soldier pile 1, simultaneously during formwork erection earlier with the soldier pile 1 inboard pea gravel concreten that sprays, the back becomes fine-stone concrete sand finish 6.1 with the floating camber face of cement mortar, one end bar planting of split bolt 6.2 is in the soldier pile 1 of going along with sb. to guard him, the other end is welded with the detent rail of inner formword 6.3, and be provided with fixedly inner formword 6.3 of annular horizontal steel tube clamp bar 6.4, split bolt 6.2 answers length in reserve to be used for just doing the pool wall construction, and every section sidewall inner formword 6.3 suitable for reading makes the funnel shaped concrete mouth 6.6 of building, to in building concrete mouth 6.6, carry out during disturbing concrete, after the moulding with the concrete chisel removal of ledge.
Described fluid concrete pond base plate underlayer 9 and base plate 8 are meant lays base plate underlayer 9 earlier, base plate underlayer 9 adopts " five limit methods " (cut the earth in the limit, shop, limit hardcore bed, limit are made the concrete bed course, fetal membrane, limit cutter engineering piles are laid bricks in the limit) assault construction, to stablize foundation pit enclosure structure and preliminary sealing, after carry out colligation base plate reinforcing bar, and setting is erected joint and the waterstop that muscle is connected with contrary sequence method with positive practice pool wall, carry out concreting at last, and form the tongue and groove constuction joint in the position of positive practice pool wall.
The horizontal construction joint of positive practice pool wall II7 and the horizontal construction joint of contrary sequence method pool wall I6 stagger.Vertical constuction joint cutter hair between positive practice pool wall II7 and the contrary sequence method pool wall I6 is cleaned, and brush cementing agent or cement paste becomes treatment of construction joints layer 7.1 on pool wall I6, at Screw arbor with nut at both-ends 6.2 away from the end of the pool wall I6 detent rail of burn-oning, and, carry out casting and compacting of concrete at last with the fixing inner formword 7.2 of annular horizontal steel tube clamp bar 6.4.
Embodiment 2
A kind of job practices of circular deep foundation pit support, the pool wall I6 of the circular pool wall of segmentation reverse construction at first, wherein with first section of the circular pool wall I6 of segmentation reverse construction as supporting ring beam 3, after excavating the required degree of depth, fluid concrete pond base plate underlayer 9 and base plate 8, from base plate 8 begin the to make progress pool wall II7 of positive practice construction remaining part, the circular pool wall of described segmentation reverse construction may further comprise the steps again:
1) according to geologic report and the actual cutting depth of foundation ditch, calculate stake type, length, diameter, arrangement of reinforcement and the spacing of the soldier pile 1 determine to go along with sb. to guard him usefulness, and the thickness of definite pool wall;
When 2) the thickness segmentation of calculating pool wall 4/5 is constructed from top to bottom, bearing capacity during double as circle supporting ring beam 3 and required arrangement of reinforcement; During the pool wall I6 of the circular concrete-pool-wall of described 4/5 thickness of section construction from top to bottom, the bar planting that is provided with the straight screw sleeve that is used to connect perpendicular muscle, load-bearing among the pool wall I6 is in the suspension muscle 1.2 and the waterstop 6.5 of soldier pile 1, and be provided with fine-stone concrete sand finish 6.1 in soldier pile 1 inboard, and be provided with the Screw arbor with nut at both-ends 6.2 that is used for fixing inner formword 6.3, inner formword 6.3 is provided with the funnel shaped concrete mouth 6.6 of building, and carries out casting and compacting of concrete in building concrete mouth 6.6;
3), determine stake type, diameter and the length of the water-stop curtain stake 2 in soldier pile 1 outside according to geologic report and the actual cutting depth of foundation ditch;
4) measure the stake position that unwrapping wire is decided soldier pile 1 and water-stop curtain stake 2;
5) double soldier pile 1 is adopted in construction supporting stake 1 and water-stop curtain stake 2, lays the soldier pile 1 of row's circle distribution again in the outside of water-stop curtain 2;
6) earthwork in the foundation ditch is excavated in layering, and each layer digs dark 4m;
7) the circular supporting ring beam 3 and the bank protection concrete 4 of 1 roof pressure top of construction supporting stake double as pool wall, circular supporting ring beam 3 is embedded with joint bar, bank protection concrete 4 is provided with gutter 5, and in the gutter 5 arranged outside precipitation well 10;
8) cooperate excavating of the earthwork, the pool wall I6 of the circular concrete-pool-wall of 4/5 thickness of section construction from top to bottom simultaneously, wherein with first section of pool wall I6 as supporting ring beam 3, perpendicular muscle among the pool wall I6 between each section adopts straight screw sleeve to connect, and be provided with the suspension muscle 1.2 that be used for load-bearing and the waterstop 6.5 of bar planting in soldier pile 1, simultaneously during formwork erection earlier with the soldier pile 1 inboard pea gravel concreten that sprays, the back becomes fine-stone concrete sand finish 6.1 with the floating camber face of cement mortar, one end bar planting of split bolt 6.2 is in the soldier pile 1 of going along with sb. to guard him, the other end is welded with the detent rail of inner formword 6.3, and be provided with fixedly inner formword 6.3 of annular horizontal steel tube clamp bar 6.4, split bolt 6.2 answers length in reserve to be used for just doing the pool wall construction, and every section sidewall inner formword 6.3 suitable for reading makes the funnel shaped concrete mouth 6.6 of building, to in building concrete mouth 6.6, carry out during disturbing concrete, after the moulding with the concrete chisel removal of ledge.
Described fluid concrete pond base plate underlayer 9 and base plate 8 are meant lays base plate underlayer 9 earlier, base plate underlayer 9 adopts " five limit methods " (cut the earth in the limit, shop, limit hardcore bed, limit are made the concrete bed course, fetal membrane, limit cutter engineering piles are laid bricks in the limit) assault construction, to stablize foundation pit enclosure structure and preliminary sealing, after carry out colligation base plate reinforcing bar, and setting is erected joint and the waterstop that muscle is connected with contrary sequence method with positive practice pool wall, carry out concreting at last, and form the tongue and groove constuction joint in the position of positive practice pool wall.
The horizontal construction joint of positive practice pool wall II7 and the horizontal construction joint of contrary sequence method pool wall I6 stagger.Vertical constuction joint cutter hair between positive practice pool wall II7 and the contrary sequence method pool wall I6 is cleaned, and brush cementing agent or cement paste becomes treatment of construction joints layer 7.1 on pool wall I6, at Screw arbor with nut at both-ends 6.2 away from the end of the pool wall I6 detent rail of burn-oning, and, carry out casting and compacting of concrete at last with the fixing inner formword 7.2 of annular horizontal steel tube clamp bar 6.4.
Above embodiment only is a preferable embodiment of the present invention, and the present invention is not limited to above embodiment, also allow other change as: according to geological conditions the precipitation well can be set, also single soldier pile etc. can be set.

Claims (3)

1, a kind of job practices of circular deep foundation pit support, it is characterized in that: the pool wall I (6) of the circular pool wall of segmentation reverse construction at first, wherein with first section of the circular pool wall I of segmentation reverse construction as supporting ring beam (3), after excavating the required degree of depth, fluid concrete pond base plate underlayer (9) and base plate (8), from base plate (8) begin the to make progress pool wall II (7) of positive practice construction remaining part, the pool wall I (6) of the circular pool wall of described segmentation reverse construction may further comprise the steps again:
1) according to geologic report and the actual cutting depth of foundation ditch, calculate stake type, length, diameter, arrangement of reinforcement and the spacing of the soldier pile (1) of determining to go along with sb. to guard him usefulness, and the thickness of definite pool wall;
When 2) the thickness segmentation of calculating pool wall 2/3~4/5 is constructed from top to bottom, bearing capacity during the circular supporting ring beam of double as (3) and required arrangement of reinforcement; During the pool wall I (6) of the circular concrete-pool-wall of described 2/3~4/5 thickness of section construction from top to bottom, the bar planting that is provided with the straight screw sleeve that is used to connect perpendicular muscle, load-bearing among the pool wall I (6) is in the suspension muscle (1.2) and the waterstop (6.5) of soldier pile (1), and be provided with fine-stone concrete sand finish (6.1) in soldier pile (1) inboard, and be provided with the Screw arbor with nut at both-ends (6.2) that is used for fixing inner formword (6.3), inner formword (6.3) is provided with the funnel shaped concrete mouth (6.6) of building, and carries out casting and compacting of concrete in building concrete mouth (6.6);
3), determine stake type, diameter and the length of the water-stop curtain stake (2) in soldier pile (1) outside according to geologic report and the actual cutting depth of foundation ditch;
4) measure the stake position that unwrapping wire is decided soldier pile (1) and water-stop curtain stake (2);
5) construction supporting stake (1) and water-stop curtain stake (2);
6) earthwork in the foundation ditch is excavated in layering, and each layer digs dark 3m~4m;
The circular supporting ring beam (3) and the bank protection concrete (4) of 7) construction supporting stake (1) stake roof pressure top double as pool wall;
8) cooperate excavating of the earthwork, the pool wall I (6) of the circular concrete-pool-wall of 2/3~4/5 thickness of section construction from top to bottom simultaneously.
2, the job practices of circular deep foundation pit support according to claim 1 is characterized in that: described circular supporting ring beam (3) is embedded with joint bar when construction.
3, the job practices of circular deep foundation pit support according to claim 1, it is characterized in that: described fluid concrete pond base plate underlayer (9) and base plate (8) are meant lays base plate underlayer (9) earlier, back assembling reinforcement, and setting is erected joint and the waterstop that muscle is connected with contrary sequence method with positive practice pool wall, build at last, and form the tongue and groove constuction joint in the position of positive practice pool wall.
CN200810120096A 2008-07-18 2008-07-18 Construction method of circular deep foundation pit support Expired - Fee Related CN100585094C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810120096A CN100585094C (en) 2008-07-18 2008-07-18 Construction method of circular deep foundation pit support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810120096A CN100585094C (en) 2008-07-18 2008-07-18 Construction method of circular deep foundation pit support

Publications (2)

Publication Number Publication Date
CN101328713A CN101328713A (en) 2008-12-24
CN100585094C true CN100585094C (en) 2010-01-27

Family

ID=40204712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810120096A Expired - Fee Related CN100585094C (en) 2008-07-18 2008-07-18 Construction method of circular deep foundation pit support

Country Status (1)

Country Link
CN (1) CN100585094C (en)

Families Citing this family (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892668B (en) * 2010-07-30 2012-07-25 中铁上海工程局第一工程有限公司 Combined support-excavated geological erosion deep foundation pit and construction method thereof
CN102817372A (en) * 2011-06-09 2012-12-12 五冶集团上海有限公司 Construction method of underground deep foundation concrete by reverse formworks
CN102296620B (en) * 2011-06-14 2013-12-04 黄朝阳 Curtain water-stop slope wall and construction method thereof
CN102296616A (en) * 2011-07-05 2011-12-28 中冶天工上海十三冶建设有限公司 Semi-underground retaining and protecting method for constructing cylindrical underground tank
CN103114599B (en) * 2013-03-04 2016-05-18 济南城建集团有限公司 Deep basal pit sealing dewatering device and construction method thereof
CN104060614B (en) * 2013-03-20 2016-03-30 中国二十冶集团有限公司 A kind of soldier pile construction method of first building Guan Liang
CN103243720A (en) * 2013-05-20 2013-08-14 中冶天工集团有限公司 Soft foundation ultra-deep foundation pit supporting method
CN103290849B (en) * 2013-06-20 2015-03-04 江苏城市职业学院 Pit-in-pit supporting structure of half topdown construction method and construction method thereof
CN105089268A (en) * 2014-05-08 2015-11-25 中国二十冶集团有限公司 Construction method of fragmental combined arc steel structure tank wall of large-sized concentration tank
CN103981898B (en) * 2014-05-12 2016-03-16 铁道第三勘察设计院集团有限公司 A kind of inverse underground engineering construction method done of overall open cut node
CN104234056B (en) * 2014-09-15 2016-05-11 上海市政工程设计研究总院(集团)有限公司 For preventing the liquefy construction method of regional underground pipe gallery distortion of high water level
CN104272993B (en) * 2014-10-21 2017-02-08 杭州市园林绿化股份有限公司 Parterre wall waterproof structure
CN105625435B (en) * 2014-10-30 2018-02-16 五冶集团上海有限公司 Sea product island multi-section, multi-level special-shaped equipment deep basal pit quick molding method
CN104314082A (en) * 2014-11-12 2015-01-28 云南建工集团有限公司 Deep function pit supporting structure in karst geology condition and construction method thereof
CN104499495A (en) * 2014-12-23 2015-04-08 中国建筑西南勘察设计研究院有限公司 Waterproof curtain wall for foundation pit
CN106193047B (en) * 2015-04-07 2018-04-03 罗海军 Big width base pit stand construction
CN104846832A (en) * 2015-06-03 2015-08-19 中船第九设计研究院工程有限公司 Construction method of circular deep foundation pit enclosure of discrete pile support
CN106978907B (en) * 2017-04-07 2019-04-09 中建二局第三建筑工程有限公司 A kind of construction method of tall and big curved wall secondary structure
CN107503357A (en) * 2017-08-30 2017-12-22 云南工程建设总承包公司 Annular pile supporting construction
CN109183965A (en) * 2018-09-05 2019-01-11 中铁贵州工程有限公司 A kind of storage pond construction technology
CN109183964A (en) * 2018-09-05 2019-01-11 中铁贵州工程有限公司 A kind of storage pond construction method
CN109594565A (en) * 2018-12-14 2019-04-09 中铁十八局集团第三工程有限公司 Large area circular deep foundation pit support and water-stopping method in weak water rich strata
CN110397039A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of construction method of deep foundation ditch
CN111424675A (en) * 2020-01-14 2020-07-17 中国电建集团西北勘测设计研究院有限公司 Construction method of ultra-large pile spacing deep foundation pit supporting system
CN114657999B (en) * 2022-03-07 2023-04-25 中冶集团武汉勘察研究院有限公司 Combined pile supporting structure for cylindrical foundation pit and construction method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
复合逆作法超深圆形基坑的支护工程施工实例. 朱祥茂等.浙江建筑,第24卷第8期. 2007
复合逆作法超深圆形基坑的支护工程施工实例. 朱祥茂等.浙江建筑,第24卷第8期. 2007 *
超深圆形基坑的半逆筑法施工与监测. 陈越峰等.岩土工程学报,第28卷第增刊期. 2006
超深圆形基坑的半逆筑法施工与监测. 陈越峰等.岩土工程学报,第28卷第增刊期. 2006 *

Also Published As

Publication number Publication date
CN101328713A (en) 2008-12-24

Similar Documents

Publication Publication Date Title
CN100585094C (en) Construction method of circular deep foundation pit support
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN102444142A (en) Pile group column replacement expanded basement and construction method of same
CN104895055A (en) Building grouting pile foundation construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN102817372A (en) Construction method of underground deep foundation concrete by reverse formworks
CN110939303B (en) Semi-reverse construction method of cyclone pool
CN101457526A (en) Circular deep foundation ditch concrete pile arranging support and major structure inversing construction method
CN214530750U (en) Bridge pile foundation structure suitable for rock mass abrupt slope
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN113482011B (en) Large-diameter PHC pipe pile and cast-in-situ bored pile combined foundation pit supporting structure and method
CN212175751U (en) Integrated steel reinforcement cage for combined construction of underground continuous wall and cast-in-situ bored pile
CN218346137U (en) Foundation with strong bearing capacity
CN114622574B (en) Water-rich throwing filling deep foundation pit water interception excavation supporting method and supporting device
CN110924401A (en) Construction foundation pit supporting mode for combined arching and bearing of mixing piles and cast-in-place piles
CN110762286A (en) Drainage pipe network artificial pipe jacking construction process
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN201351279Y (en) Circular deep foundation pit support
CN211421139U (en) Shield constructs well crown beam bearing structure
CN113550764A (en) Method for starting shield concrete sleeve to enter hole and building structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 315700, No. 1, Lake Road, Dandong street, Xiangshan County, Ningbo, Zhejiang

Patentee after: Huafeng Construction Co., Ltd.

Address before: Hangzhou City, Zhejiang province 310014 eight Lane 1, Huadian Zhaohui District 1 Building 6 floor

Patentee before: Huafeng Construction Co., Ltd.

PP01 Preservation of patent right

Effective date of registration: 20130912

Granted publication date: 20100127

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent

Date of cancellation: 20140310

Granted publication date: 20100127

RINS Preservation of patent right or utility model and its discharge
PP01 Preservation of patent right

Effective date of registration: 20150511

Granted publication date: 20100127

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent

Date of cancellation: 20151111

Granted publication date: 20100127

RINS Preservation of patent right or utility model and its discharge
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100127

Termination date: 20150718

EXPY Termination of patent right or utility model