CN100532971C - Outdoor unit of multi-split air conditioner - Google Patents

Outdoor unit of multi-split air conditioner Download PDF

Info

Publication number
CN100532971C
CN100532971C CNB2004100936465A CN200410093646A CN100532971C CN 100532971 C CN100532971 C CN 100532971C CN B2004100936465 A CNB2004100936465 A CN B2004100936465A CN 200410093646 A CN200410093646 A CN 200410093646A CN 100532971 C CN100532971 C CN 100532971C
Authority
CN
China
Prior art keywords
air
compressor
refrigerant
control box
air conditioner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2004100936465A
Other languages
Chinese (zh)
Other versions
CN1782557A (en
Inventor
林银淑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LG Electronics Tianjin Appliances Co Ltd
Original Assignee
LG Electronics Tianjin Appliances Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LG Electronics Tianjin Appliances Co Ltd filed Critical LG Electronics Tianjin Appliances Co Ltd
Priority to CNB2004100936465A priority Critical patent/CN100532971C/en
Publication of CN1782557A publication Critical patent/CN1782557A/en
Application granted granted Critical
Publication of CN100532971C publication Critical patent/CN100532971C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

The present invention relates to outdoor unit of multi-split air conditioner. The outdoor unit of multi-split air conditioner includes a partition board to separate the inside of the outdoor unit into an upper space and a lower space, a control box assembled below the partition board, a heat radiating part set on one side of the control box to dissipate the heat of the heat releasing element board in the control box, and a heat dissipating fan on one side of the control box to blow. One air guide hole is formed on the partition board for the heat dissipating fan guided air to flow through, and one air guide cover with back opening is set over the air guide hole to guide the backward excellent of air. The outdoor unit of multi-split air conditioner has the advantage of avoiding malfunction and performance degradation of air conditioner.

Description

The off-premises station of one one dragging more air conditioner
Technical field
The invention belongs to a kind of air conditioning apparatus, be specifically related to a kind of off-premises station that control box distributes an one dragging more air conditioner of hot gas of emitting effectively.
Background technology
In general, air regulator is according to after the refrigerant heat exchange of the hot-air in the suction chamber with low temperature these effects repeatedly to indoor discharge being made indoor refrigeration, perhaps make the cooling/heating system of indoor heating, and constitute the machine of a freeze cycle by compressor-condenser-expansion valve-evaporimeter shape with adverse effect.Recently, air regulator except refrigeration and heat-production functions, after also having both suction chamber internal contamination air and being converted to peace and quiet air after filtering and being converted to dried humid air to indoor air-cleaning function of discharging again, many humid air to the indoor multiple additional functions such as dehumidification function of discharge again.As everyone knows, air regulator is broadly divided into split air conditioning system and off-premises station and the integrally formed unitary air conditionary of indoor set that off-premises station and indoor set are installed separately.Occurred recently the air regulator situation more than 2 is installed or is having in each office the situation of air regulator will be installed in the building of a plurality of offices the time, more effectively be suitable for an one dragging more air conditioner of these situations in family.An one dragging more air conditioner like this is to connect a plurality of indoor sets, the effect that can obtain installing many split air conditioning systems on an off-premises station.
As shown in Figure 1, 2, off-premises station 1 includes compressor 10, fluid reservoir 20 and outdoor heat converter 30 etc., and indoor set 50 includes indoor heat converter 60 and expansion valve 70.In such one dragging more air conditioner, be connected with a plurality of indoor sets 50 on the off-premises station 1, connect high-voltage tube 80 with high pressure and low-voltage tube 90 between off-premises station 1 and the indoor set 50 separately with relative low pressure.When air regulator freezed, the outdoor heat converter 30 of off-premises station 1 played the condenser effect of condensation from the gaseous state refrigerant of the high temp/high pressure of compressor 10 conveyings.Such condensation refrigerant is expanded to after the gaseous state of low temperature/low pressure by expansion valve 70, is transported to 60 li of indoor heat converters.Inflow refrigerants in the indoor heat converter 60 are owing to carry out heat exchange with room air, so be transformed to low temperature/low pressure refrigerant that 2 kinds of states that gaseous state and liquid condition mix mutually mix.Such refrigerant is transported in the compressor 10 again by after the fluid reservoir 20, constitutes the 1st circulation of refrigerant.When air regulator heated, the flow direction of refrigerant and the effect of heat exchanger were just in time opposite.That is, in compressor 10 refrigerant of compression with fluid reservoir 20-indoor heat converter 60-expansion valve 70-the order of outdoor heat converter 30 flows.At this moment, indoor heat converter 60 plays to make through its inner HTHP refrigerant follows room air to carry out the condenser effect of heat exchange, and outdoor heat converter 30 plays the evaporimeter effect that makes inner low-temp low-pressure refrigerant and outdoor air carry out heat exchange.
To shown in Figure 5, the bottom of off-premises station 1 is formed with the chassis 2 that a plurality of parts are installed as Fig. 3, and the front end on chassis 2 is equipped with the front panel 4 that forms the front outward appearance.Front panel 4 is by front upper panel 4 ' that is installed in upside and the front lower panel 4 that is installed in downside " constitute.Front lower panel 4 " the last catheter carriage 4 that is equipped with " a.That is, front lower panel 4 " the lower end cut a part, such cut-away portions is with catheter carriage 4 " a sealing, but catheter carriage 4 " a direct high pressure pipe 80 and low-voltage tube 90 be communicated with and install on the indoor sets 50.Front upper panel 4 ' and front lower panel 4 " between central bracket 6 guiding also be installed install.And the upper end of front upper panel 4 ' is equipped with upper bracket 6 ' again, the motor base 48 ' leading section that will illustrate below being combined with on such upper bracket 6 '.The left and right sides side of front panel 4 promptly is equipped with the place ahead support 8 on the front end left and right sides edge on chassis 2.The place ahead support 8 is that direction forms more longways up and down, supports front panel 4 and side grid 34.Compressor 10 is installed on the chassis 2, and compressor 10 compression refrigerants make it become the HTHP refrigerant, and are installed in the left and right sides separately, and the constant speed compressor 10 ' of constant speed drive is installed on the promptly relative right side, and frequency-changeable compressor 10 is installed in the left side ".
One side of compressor 10 is equipped with oil eliminator 12 separately.Oil eliminator 12 filters the oil that mixes and reclaims to compressor 10 from the refrigerant that compressor 10 is discharged.With certain altitude valve support 14 is installed on the left side rearward end on chassis 2, auxiliary valve 16 is installed and supported in the upper end of valve support 14 separately.The central portion on chassis 2, i.e. constant speed compressor 10 ' and frequency-changeable compressor 10 " between fluid reservoir 20 is installed.Fluid reservoir 20 filter liquide refrigerants only allow gaseous coolant flow into compressor 10 inside.The upside of compressor 10 is equipped with control box 22, and (not shown) control assembly and printed circuit board (PCB)s such as voltage transformer, capacitor are installed on the control box 22.Control box 22 is four jiaos of box-like shapes of front openings, by the front control lid 22 ' come closed interiors is installed.Installation room outer heat-exchanger 30 on the side end on chassis 2 and the rearward end, outdoor heat converter 30 are to make inner mobile refrigerant carry out heat exchange with extraneous air, and in left and right sides mounted in pairs.Promptly install in the left side "
Figure C200410093646D0004113658QIETU
" the left side outdoor heat converter 30 ' of shape (from the top), install on the right side "
Figure C200410093646D0004113702QIETU
" the right side outdoor heat converter 30 of shape (from the top) ".Also be equipped with the conduit tube component 32 that guiding refrigerant flows on the inlet of outdoor heat converter 30, be equipped with air accumulator 33 in the outlet.
Side grid 34 is installed on the left-hand end on chassis 2 and the right-hand end, and on the rear end back grid 36 is installed.Grid 36 mounted in pairs in back are also corresponding with outdoor heat converter 30.Be back, the left side grid installed on the rear of back grid 36 by left side outdoor heat converter 30 ' 36 ' and right side outdoor heat converter 30 " back, the right side grid 36 installed on the rear " constitute.Left side back grid 36 ' and back, right side grid 36 " between the back support 38 of the promising fixedly back of installation grid 36, on the left and right sides edge part of the rear end on chassis 2, be formed with rear support 38 ' separately.The top outward appearance of off-premises station 1 is formed by top panel 40, and top panel 40 is and chassis 2 corresponding four jiaos of flat boards that the central left and right sides is formed with a pair of passage 40 '.The top installing ring cover 42 of passage 40 ', ring cover 42 is outstanding upward drum shapes, the air that guiding blowing fan 46 is discharged to the outside.The upper end of ring cover 42 is installed and is discharged grid 44, and ring cover 42 installed inside have blowing fan 46.Blowing fan 46 is to be rotated by the fan electromotor 48 that is installed in the bottom, plays a part to discharge inner air to the outside.In addition, fan electromotor 48 is installed on the motor base 48 '.
But following shortcoming is arranged in the aforesaid prior art: the inside of control box 22 is equipped with a plurality of parts, and these parts generate heat owing to the air regulator operational temperature rises gradually, causes these control assemblies can not bring into play self function.Be not to be equipped with radiator structure in the prior art constructions, so can not cool off the parts of control box 22 inside effectively.
Summary of the invention
The present invention proposes for the shortcoming that solves prior art, and the one dragging more air conditioner that provides a kind of control box and outdoor heat converter to be installed separately is provided its purpose.Another object of the present invention is to emit effectively for the hot gas that makes control box.An one dragging more air conditioner of the present invention, comprise the chassis that forms the bottom surface, front end on the chassis is provided with front panel, top panel is set above the chassis, left-hand end and right-hand end are equipped with side panel on the chassis, surface rear end is equipped with rear board on the chassis, carry out the outdoor heat converter of heat exchange, also be included in the chassis and be provided with constant speed compressor and frequency-changeable compressor, between constant speed compressor and frequency-changeable compressor, oil equalizing pipe is set, constant speed compressor and frequency-changeable compressor are communicated with outdoor heat converter by oil eliminator and cross valve, described outdoor heat converter is made up of front heat exchanger and back heat exchanger, and constant speed compressor and frequency-changeable compressor are communicated with each indoor set by fluid reservoir and cross valve; Also comprise the dividing plate that off-premises station inside is divided into upside space and lower side space, form control box, be provided in the heat unit that the one side of control box is emitted the heater element plate hot gas of control box easily at the lower partition.Heat unit forms in a side that is built in the heater element plate in the control box.One side of control box be equipped with to the heat unit forced air supply anti-Hot-air fan, be formed with the air guide holes that becomes by the air flow passage of radiator fan guiding on the dividing plate.Be provided with the air pilot cap of rear opening at the upside of air guide holes, rearward guide the air of discharging upward by air guide holes.The present invention's one one dragging more air conditioner off-premises station has the advantage that prevents that running of air regulator mistake and performance from descending.
Description of drawings
Fig. 1 is the installment state figure of an one dragging more air conditioner of prior art;
Fig. 2 is the structure and the mobile schematic diagram of refrigerant of an one dragging more air conditioner of prior art;
Fig. 3 is the off-premises station outward appearance oblique view of an one dragging more air conditioner of prior art;
Fig. 4 is the off-premises station STRUCTURE DECOMPOSITION oblique view of an one dragging more air conditioner of prior art;
Fig. 5 is that prior art one one dragging more air conditioner off-premises station is pulled down the inner front elevation of front panel;
Fig. 6 is the installment state figure of an one dragging more air conditioner of the present invention;
Fig. 7 is the structure of an one dragging more air conditioner of the present invention and the schematic diagram that refrigerant flows;
Fig. 8 is the detailed pie graph of an one dragging more air conditioner off-premises station of the present invention;
Fig. 9 is an one dragging more air conditioner off-premises station outward appearance oblique view of the present invention;
Figure 10 is the inner formation of an an one dragging more air conditioner off-premises station of the present invention exploded perspective view;
Figure 11 is the inside front elevation that the off-premises station front panel of an one dragging more air conditioner of the present invention is pulled down;
Figure 12 is the left side control box inside front elevation of rotary state forwards of an one dragging more air conditioner off-premises station of the present invention;
Figure 13 is the outdoor unit of air conditioner sectional side view of the air flow condition of embodiment of the invention inside.
Wherein:
100: off-premises station 102: outdoor magnetic valve
110: chassis 112: front panel
114: front grid 116: the front upper bracket
120: constant speed compressor 120 ': frequency-changeable compressor
120a: coolant injection device 121: oil equalizing pipe
121 ': oil equalizing pipe temperature sensor 122: oil eliminator
123: oil return pipe 124: cross valve
126: valve support 128: auxiliary valve
130: supercooling machine 130 ': contrary transfer tube
130 ' a: supercooling expansion valve 132: fluid reservoir
134,134 ': the place ahead support 136: central bracket
140: left side control box 140 ': the right side control box
142: voltage transformer 144: capacitor
146: heater element plate 146 ': radiating part
148: radiator fan 150: dividing plate
152: air guide holes 154: the air pilot cap
160: top panel 162: passage
164: ring cover 166: discharge grid
170: blowing fan 172: fan electromotor
174: motor base 180: outdoor heat converter
182: front heat exchanger 184: the back heat exchanger
186: drip tray 188: side panel
190: back grid 192: rear board
194: back upper bracket 196: the rear support
200: indoor set 202: indoor heat converter
204: expansion valve 210: the general pipe of liquid
210 ': liquid branch pipe 210 ": outdoor liquid line
212: the general pipe 212 ' of gas: gas branch pipe
212 ": outdoor flue 214: the general pipe of high-low pressure
The specific embodiment
The present invention is described in detail below in conjunction with drawings and Examples:
Shown in Fig. 6,7, off-premises station 100 comprises constant speed compressor 120, frequency-changeable compressor 120 ', fluid reservoir 132, outdoor heat converter 180, outdoor magnetic valve 102 etc.Indoor set 200 comprises indoor heat converter 202, expansion valve 204 etc.In an one dragging more air conditioner, connect a plurality of indoor sets 200 on the off-premises station 100 more than one or two, it is that the unitary catheter that general pipe 210 of liquid and gas coolant flow is the general pipe 212 of gas that the unitary catheter that liquid coolant flows is arranged between off-premises station 100 and the indoor set 200, and general pipe 210 of liquid and the general pipe 212 of gas are interconnected.The promising balanced and general pipe 214 of high-low pressure of UNICOM mutually of refrigerant of keeping between the plural off-premises station 100.The general pipe 214 of high-low pressure is to install for outdoor heat converter 180 entrance sides on a plurality of off-premises stations 100 that are interconnected, and what make off-premises station 100 keeps the refrigerant equilibrium each other.And, make refrigerant also flow in a plurality of off-premises stations 100 180 li of untapped off-premises station 100 outdoor heat converters, so the effect that has the overall thermal exchange efficiency to improve.In addition, according to freezing or heating running, 214 li mobile high pressure refrigerants of the general pipe of high-low pressure or low pressure refrigerant.
Be formed with the gas branch pipe 212 ' that liquid coolant flowing liquid branched pipe 210 ' and gas coolant flow on the indoor set 200 separately.Such liquid branch pipe 210 ' and gas branched pipe 212 ' are communicated with general pipe 210 of liquid and the general pipe 212 of gas.Liquid branch pipe 210 ' and gas branched pipe 212 ' according to be connected with it different its diameters of indoor set 200 capacity different separately.Be formed with the outdoor liquid line 210 that liquid coolant flows on the off-premises station 100 separately " and the mobile outdoor flue 212 of gas coolant ".Outdoor liquid line 210 like this " and outdoor flue 212 " be communicated with general pipe 210 of liquid and the general pipe 212 of gas.
Shown in Fig. 8-12, an one dragging more air conditioner off-premises station of the present invention comprises: form the chassis 110 of bottom surface, be installed in chassis 110 and be equipped with a plurality of parts bottom.The front end on chassis 110 is equipped with the front panel 112 that forms the front lower outward appearance, and the upside of front panel 112 is equipped with front grid 114.Extraneous air flows into by front grid 114, and through outdoor heat converter 180.The upside of front grid 114 also is equipped with front upper carriage 116, and the front end of motor base 174 is fastened on the front upper carriage 116.Compressor 120,120 ' is installed on chassis 110.Compressor 120,120 ' is a compression refrigerant, makes refrigerant become the HTHP refrigerant, and is installed in the left and right sides on chassis 110 separately.The constant speed compressor 120 of constant speed drive promptly is installed on the right side, variable-ratio heat pump, i.e. frequency-changeable compressor 120 ' are installed on the left side.Compressor 120,120 ' entrance side are equipped with coolant injection device 120a, and coolant injection device 120a supplies with refrigerant according to working order when compressor 120,120 ' is overheated, prevent the damage of compressor.The refrigerant here preferably uses the discharge refrigerant of outdoor heat converter 180.Oil equalizing pipe 121 is set between constant speed compressor 120 and the frequency-changeable compressor 120 ', constant speed compressor 120 and frequency-changeable compressor 120 ' are interconnected.When the phenomenon of fuel feeding deficiency appears in the compressor of any side,, prevent that thus the compressor 120,120 ' that causes because of low on fuel from decreasing the phenomenon in bosom from another compressor make-up oil.
Compressor 120,120 ' uses the screw compressor that noise is little and efficient is high, and especially frequency-changeable compressor 120 ' is the frequency-changing cyclone formula compressor according to the adjustable turn over number of load capacity.Have only minority indoor set 200 running and under the little situation of load capacity, at first start frequency-changeable compressor 120 ', and, start constant speed compressor 120 and start because of load capacity increases when only using frequency-changeable compressor 120 ' not bear load gradually.Outlet side at constant speed compressor 120 and frequency-changeable compressor 120 ' is equipped with compressor discharge temperature sensor 120b, 120 ' b and the oil eliminator 122 that detects compressor 120,120 ' discharge refrigerant temperature separately.Oil eliminator 122 filters the oil that mixes from compressor 120, the 120 ' refrigerant of discharging, lubricating oil is recovered in the compressor 120,120 '.Oil is discharged from compressor 120,120 ' outlet together with refrigerant, so the oil that mixes in the refrigerant after oil eliminator 122 is separated, is got back to compressor 120,120 ' by oil return pipe 123.Use the reason of lubricating oil to be: in order to reduce the frictional heat that produces when compressor 120,120 ' turns round.The outlet side of oil eliminator 122 has check valve 122 ', prevents the adverse current of refrigerant.When promptly having only in constant speed compressor 120 or the frequency-changeable compressor 120 ' any one running, prevent compressor 120,120 ' the inner adverse current of compression refrigerant in stopping.Oil eliminator 122 is to utilize conduit to follow cross valve 124 to be communicated with, cross valve 124 is according to refrigeration or heats the flow direction that running comes the conversion refrigerant, so port separately and compressor 120,120 ' outlet (perhaps oil eliminator), compressor 120,120 ' inlet (perhaps fluid reservoir), outdoor heat converter 180 and indoor set 200 are connected.The refrigerant of discharging from constant speed compressor 120 and frequency-changeable compressor 120 ' flows into cross valve 124 after local a gathering.
Such cross valve 124 inlets are provided with and detect the high pressure sensor 124 ' that compressor 120,120 ' is discharged refrigerant pressure.Traverse cross valve 124 heating pipe 125 is installed.The effect of heating pipe 125 is to make from oil eliminator 122 can flow directly into 132 li of fluid reservoirs to the refrigerant part that cross valve 124 flows.The effect of heating pipe 125 is: be necessary to improve in the low pressure refrigerant pressure that flows into fluid reservoir 132 in the running of air regulator, make compressor 120,120 ' the high pressure refrigerant of discharging oral-lateral flow directly into compressor 120,120 ' entrance side.On such heating pipe 125 by-passing valve is installed, promptly hot-blast valve 125 ' opens and closes conduit.
Valve support 126 is installed by the top first half central authorities on chassis 110, and valve support 126 plays a part to support and guide outdoor liquid line 210 ", outdoor flue 212 ", the general pipe 214 of high-low pressure, and auxiliary valve 128 also is installed in here.And, drawn and be connected on the off-premises station 100 by the conduit gateway 188 ' of side panel 188 by the conduit 210,212,214 that valve support 126 supports.Be formed with supercooling machine 130 on the last left side of face rearward end on chassis 110, refrigerant after the further cooling chamber outer heat-exchanger 180 interior heats exchange of supercooling machine 130, and with the outdoor liquid line 210 of junction chamber outer heat-exchanger 180 outlet sides " the optional position on form.Supercooling machine 130 is to be formed by dual pipe.Outdoor liquid pipe 210 promptly is set in the inboard ", and form contrary transfer tube 130 ' in the outside.Therefore, contrary transfer tube 130 ' comes out from the outlet branch of supercooling machine 130, and the supercooling expansion valve 130 ' a by expansion process cooling refrigerant is installed on so contrary transfer tube 130 '.A part of refrigerant of discharging from supercooling machine 130 flows into contrary transfer tube 130 ', and is cooled through supercooling expansion valve 130 ' a the time, and the cooling refrigerant is in supercooling machine 130 adverse currents, and Nei Ce refrigerant further is cooled thus.The adverse current refrigerant of discharging from supercooling machine 130 supplies to 132 li in oil storage tank again, circulates once more.
The outlet of supercooling machine 130 is provided with and detects the liquid line temperature sensor 130a that off-premises station 100 is discharged refrigerant temperature.In the outlet of supercooling expansion valve 130 ' a supercooling inlet sensor 130 ' b is installed, detects the adverse current refrigerant temperature that flows into supercooling machine 130.Supercooling machine 130 is discharged the adverse current refrigerant and be provided with supercooling outlet sensor 130 ' c on the contrary transfer tube 130 ' of internal flow.Through the refrigerant of outdoor heat converter 180 in the central portion flow and be inflated valve (not shown) the low temperature refrigerant that expands is externally flowed round about, further reduce the temperature of refrigerant thus.In a side of supercooling machine 130, promptly discharge the outdoor liquid pipe 210 of refrigerants to indoor set 200 guiding outdoor heat converters 180 " a side be provided with drying machine 131.Drying machine 131 plays a part to remove outdoor liquid pipe 210 " in the moisture in the refrigerant that flows.
110 the central portion on the chassis is installed fluid reservoir 132 between constant speed compressor 120 and the frequency-changeable compressor 120 '.Fluid reservoir 132 filter liquide refrigerants only guide the refrigerant of gaseous state to compressor 120,120 '.From the refrigerant that indoor set 200 flows into, be fed directly in the compressor 120,120 ' with the refrigerant that liquid condition stays if can not evaporate, the compressor 120,120 ' that refrigerant is converted to high temperature, gases at high pressure state refrigerant is gone up and is increased load, brings compressor 120,120 ' damage thus.In the inflow refrigerant of fluid reservoir 132 inside, the liquid refrigerant that does not have enough time to evaporate and stay with liquid condition is heavier than gasiform refrigerant, so assemble in the bottom of fluid reservoir 132, and have only the gaseous state refrigerant on top to flow in the compressor 120,120 '.
In addition, the entrance side of fluid reservoir 132 is provided with detection separately and sucks the suction lead temperature sensor 132 ' of refrigerant temperature and the low pressure sensor 132 of perception refrigerant pressure ".The front end both sides on chassis 110 are formed with the place ahead support 134,134 ' separately.The place ahead support 134,134 ' on the chassis 110 front end up and down direction form more longways, and be divided into left forward side support 134 that is installed in left-hand end and the right forward side support 134 ' that is installed in right-hand end.The place ahead support 134,134 ' plays a part to support front upper carriage 116, front grid 114 and control box 140,140 '.And the mediad left and right directions of left forward side support 134 and right forward side support 134 ' is equipped with central bracket 136.In the bottom of central bracket 136 control box 140,140 ' is installed.Control box 140,140 ' forms in pairs in the left and right sides, bottom of central bracket 136.Control box 140,140 ' is made up of left side control box 140 that is installed in the left side and the right side control box 140 ' that is installed in the right side.Left side control box 140 utilizes hinge 140a to be connected on the left forward side support 134, and right side control box 140 ' utilizes hinge 140 ' a to be fastened on right forward side support 134 '.
Four jiaos of box-like shapes of control box 140,140 ' each self-forming front openings, its place ahead is by front panel 112 sealings.140 li of the control boxes in left side are equipped with control assembly such as voltage transformer 142, capacitor 144 and possess the heater element plate 146 of a plurality of heating terminals.The back of heater element plate 146 is formed with the radiating part 146 ' that is made of fin.The upper end, back of left side control box 140 is equipped with the radiator fan 148 to radiating part 146 ' forced air supply, and radiator fan 148 is cross flow fans.If radiator fan 148 sucks air and discharges upward, then promote the heat exchange on radiating part 146 ', heater element plate 146 is cooled.Control box 140,140 ' side utilize hinge 140a, 140 ' a to be installed on the place ahead support 134,134 ' separately, serve as that axle can forwards rotate with hinge 140a, 140 ' a.Therefore, when needing repairing internal part,, just can carry out operation as long as control box 140,140 ' is forwards rotated.
Dividing plate 150 is installed on the central bracket 136, and dividing plate 150 is divided into upside space and lower side space to off-premises station 100 inside.Promptly be divided into compressor 120,120 ' and control box 140,140 ' etc. downside and the upside of installation room outer heat-exchanger 180 is installed.Dividing plate 150 is and control box 140,140 ' the same left and right sides that is installed in central bracket 136 separately.Dividing plate 150 rake 150 that certain angle forms that tilts downwards by the horizontal part 150 ' that rearward forms from central bracket 136 with from the rear end of horizontal part 150 ' " constitute.In dividing plate 150, on the horizontal part 150 ' of left side dividing plate 150, be formed with air guide holes 152.The upside of air guide holes 152 is equipped with air pilot cap 154, and air pilot cap 154 constitutes sealing the place ahead and top and opens the structure at rear, rearward guides from the air of radiator fan 148 forced air supplies that are installed in its underpart.
The top outward appearance of off-premises station 100 is formed by top panel 160, and top panel 160 has four jiaos of writing board shapes and in its left and right sides mounted in pairs.Be formed with passage 162 on the top panel 160, the edge of passage 162 prolongs downwards and forms drum type ring cover 164, ring cover 164 and top panel 160 whole formation, and preferably make of plastic material.Ring cover 164 is with drum formation type, to the air of exterior guiding by blowing fan 170 forced air supplies.At ring cover 164 upsides, be equipped with on the passage 162 with the corresponding mutually circular row of passage 162 and go out grid 166.The installed inside of ring cover 164 has blowing fan 170, and blowing fan 170 is driven by the fan electromotor 172 of bottom and rotates, and discharges inner air upward.Promptly basis is from outside turn-on power, and fan electromotor 172 produces revolving forces, and blowing fan 170 fixing on rotating shaft one end of the fan motor 172 that follows the wind thus rotates, and air is discharged upward.Fan electromotor 172 is fixed on the motor base 174, and motor base 174 is by the fixed head 174 ' of four jiaos of flat boards and the bracing frame 174 of support fixation plate 174 ' " constitute.Bracing frame 174 " about it, form in pairs, and in such pair of supporting 174 " mounting plate 174 ' on the central portion.Bracing frame 174 " front-end and back-end crooked upward and be fixed on separately on front upper carriage 116 and the back upper bracket 194.
The bottom installation room outer heat-exchanger 180 of plate 160 in the above, outdoor heat converter 180 be both sides mounted in pairs before and after the bottom of plate 160 in the above, makes inner mobile refrigerant carry out heat exchange with extraneous air.Be that outdoor heat converter 180 is made of front heat exchanger 182 that is installed in top panel 160 front end downsides and the back heat exchanger 184 that is installed in top panel 160 rear end downsides.The Lower Half of front heat exchanger 182 is rearward crooked, promptly the Lower Half of front heat exchanger 182 prolong the vertical component effect 182 ' of certain-length downwards by front end from front panel 112 and from the rake 182 of vertical component effect 182 ' lower end tilted rearward certain angle " constitute.Rake 182 " the lower end and the lower end of back heat exchanger 184 adjoin each other, the lower end of outdoor heat converter 180 with between the chassis 110 at intervals.The side of outdoor heat converter 180 also is formed with to each position distributes the conduit tube component 180 ' of supplying with refrigerant from compressor 120,120 '.The inside of outdoor heat converter 180 is provided with the heat-exchanger temperature sensor 180a that detects heat exchanger temperature, and the outside also is provided with the outdoor temperature sensor 180b that detects external temperature.The lower end downside of outdoor heat converter 180 is equipped with drip tray 186, and drip tray 186 direction to the left and right forms more longways and assembles the condensed water that generates from outdoor heat converter 180, discharges condensed water to the side then.
Left-hand end and right-hand end are equipped with side panel 188 on chassis 110, and side panel 188 forms the side outward appearance of off-premises station 100, each self-forming conduit access hole 188 ' in the both sides, front and back of bottom.Back grid 190 is installed in the rear end on chassis 110, and the size of back grid 190 and back heat exchanger 184 forms accordingly, and the downside of back grid 190 is equipped with rear board 192.The upper end of grid 190 in the back, back upper bracket 194 direction to the left and right forms more longways.Back upper bracket 194 is installed in the bracing frame 174 of the upper end anterior support motor base 174 of back grid 190 " rear end.Rear support 196 is installed on the angle, rear end on chassis 110.Rear support 196 direction up and down forms more longways, supports back grid 190 and rear board 192 and top panel 160.
Below, the course of work and the effect of an one dragging more air conditioner of the present invention are described with reference to Fig. 7-13:
As mentioned above, air regulator of the present invention is to connect a plurality of indoor sets 200 on an off-premises station 100, moves a part or all indoor sets 200 according to user's selection.If air regulator turns round under refrigeration mode, outdoor magnetic valve 102 is opened, and refrigerant flows between off-premises station 100 and indoor set 200.At first, the refrigerant that 100 li of off-premises stations are described flows: the gas that flows into from indoor set 200 flows into 132 li of fluid reservoirs through cross valve 124.The gas coolant that comes out from fluid reservoir 132 flows in the compressor 120,120 '.When supplying with compressor 120,120 ' cold medium shortage or compressor 120,120 ' overheated the time, supply with refrigerant from coolant injection device 120a.Compressor 120,120 ' compression refrigerant are discharged from outlet, and by oil eliminator 122.And refrigerant is fuel-displaced in 122 li separation of oil eliminator, and lubricating oil is recovered in the compressor 120,120 ' by oil return pipe 123.Oil is blended in the refrigerant in compressor 120,120 ' compression refrigerant process, but such oil is liquid condition and refrigerant is a gaseous state, so be 122 li each self-separations of oil eliminator at gas-liquid separator.
Compressor 120,120 ' inner lubricating oil in both sides is kept equilibrium by the oil equalizing pipe 121 that connects constant speed compressor 120 and frequency-changeable compressor 120 '.Refrigerant by oil eliminator 122 passes through 180 li of cross valve 124 inflow outdoor heat exchangers.Outdoor heat converter 180 plays condenser (during refrigeration mode) effect, so refrigerant is by carrying out heat exchange with extraneous air, be cooled into being liquid coolant.Refrigerant by outdoor heat converter 180 further cools off through supercooling machine 130 time.After the drying machine 131 through moisture in the refrigerant removal refrigerant of supercooling machine 130, flow into 200 li of indoor sets by the general pipe 210 of liquid.In compressor 120,120 ' the refrigerant, a part flows into 100 li of another off-premises stations by the general pipe 214 of high-low pressure.
180 li of off-premises station 100 outdoor heat converters that the refrigerant inflow of supplying with to another off-premises station 100 by the general pipe 214 of high-low pressure shuts down, make refrigerant pressure reach balanced on the whole, the outdoor heat converter 180 by the off-premises station 100 that shuts down also can carry out certain heat exchange simultaneously.Supply with refrigerant by the general pipe 210 of liquid to indoor set 200, refrigerant flows into 200 li of each central indoor sets of running by the liquid branch pipe 210 ' that comes out from the general pipe of liquid 210 branches.Such refrigerant carries out heat exchange for 202 li in expansion valve 204 decompressions and at indoor heat converter.At this moment, indoor heat converter 202 plays a part evaporimeter, so refrigerant is converted to low-pressure gas by heat exchange.Assemble at the general pipe 212 of gas through gas branch pipe 212 ' from the refrigerant that indoor heat converter 202 is discharged, flow into 100 li of off-premises stations then.By general pipe 212 of gas and outdoor flue 212 " refrigerant that flows into off-premises station 100 enters into 132 li of fluid reservoirs through cross valve 124.Filter at the be not able to do in time refrigerant of evaporated liquid state of 132 li of fluid reservoirs, have only the refrigerant of gaseous state to separate and supply to compressor 120,120 '.Thus, the course of work is finished a circulation.In the time of the running of air regulator heating mode, refrigerant flows to foregoing opposite direction, regulates coolant quantity in outdoor magnetic valve 102.
13 illustrate that the air of 100 li of off-premises stations flows with reference to the accompanying drawings.Power turn-on, fan electromotor 172 drives rotation blowing fan 170.If blowing fan 170 rotations, air outside flows into inner by front grid 114 and back grid 190.The inflow air of off-premises station 100 inside carries out heat exchange when passing through outdoor heat converter 180.At this moment, if the air regulator cooling operation, air outside is accepted heat from outdoor heat converter 180 and is become high temperature air, if opposite air regulator heats running, air outside is transmitted heat to outdoor heat converter 180 and become Cryogenic air.Air by outdoor heat converter 180 is by blowing fan 170 forced air supply upward.At this moment, ring cover 164 guiding air are discharged air upward.After radiator fan 148 sucks air, discharge upward, promote radiating part 146 ' heat exchange, heater element plate 146 is cooled.After the air of forced air supply passes through the air guide holes 152 of dividing plate 150 upward from radiator fan 148,, forwards discharge by 154 guiding of air pilot cap.The air of forwards discharging by air pilot cap 154 carries out heat exchange through front heat exchanger 182 time, discharges upward by ring cover 164.The scope of the invention does not limit in the above-described embodiment, and those of ordinary skill in the art can produce the various deformation based on the present invention within the scope of the claims.
As mentioned above, in the off-premises station of an one dragging more air conditioner of the present invention, be the center with the demarcation strip, at upside installation room outer heat-exchanger and at downside control box is installed.The various parts of control box inside can not be subjected to the influence of outdoor heat converter, can prevent the running of air regulator mistake thus.Be provided with radiating part and radiator fan in the back of control box, more effectively cooling is built in parts in the control box, can prevent the parts Yin Gaowen of control box inside thus and wrong running.Because each control assembly is normally brought into play the function of self, so the effect that can prevent in advance that the air regulator performance from descending is arranged.

Claims (5)

1, a kind of off-premises station of an one dragging more air conditioner, comprise the chassis (110) that forms the bottom surface, the front end of (110) is provided with front panel (112) on the chassis, the top of (110) is provided with top panel (160) on the chassis, left-hand end and right-hand end are equipped with side panel (188) on chassis (110), the last surface rear end of (110) is equipped with rear board (192) on the chassis, carry out the outdoor heat converter (180) of heat exchange, it is characterized in that: also be included in chassis (110) and be provided with constant speed compressor (120) and frequency-changeable compressor (120 '), between constant speed compressor (120) and frequency-changeable compressor (120 '), oil equalizing pipe (121) is set, constant speed compressor (120) and frequency-changeable compressor (120 ') are communicated with outdoor heat converter (180) by oil eliminator (122) and cross valve (124), described outdoor heat converter (180) is made up of front heat exchanger (182) and back heat exchanger (184), and constant speed compressor (120) and frequency-changeable compressor (120 ') are communicated with each indoor set by fluid reservoir (132) and cross valve (124); Also comprise off-premises station (100) inside is divided into the demarcation strip (150) of upside space and lower side space and the control box (140,140 ') that forms in dividing plate (150) bottom, and be arranged on a side of control box (140,140 '), the heat unit (146 ') that the hot gas of the heater element plate (146) of control box (140,140 ') is emitted easily.
2, the off-premises station of an one dragging more air conditioner according to claim 1 is characterized in that: heat unit (146 ') forms in heater element plate (146) one side that is built in described control box (140,140 ') lining.
3, the off-premises station of an one dragging more air conditioner according to claim 1 and 2 is characterized in that: a side of control box (140,140 ') be equipped with to heat unit (146 ') forced air supply radiator fan (148).
4, the off-premises station of an one dragging more air conditioner according to claim 3 is characterized in that: be formed with the air guide holes (152) that becomes by the air flow passage of radiator fan (148) guiding on the dividing plate (150).
5, the off-premises station of an one dragging more air conditioner according to claim 4, it is characterized in that: be provided with the air pilot cap (154) of rear opening at the upside of air guide holes (152), guiding is rearward discharged air upward by air guide holes (152).
CNB2004100936465A 2004-11-29 2004-11-29 Outdoor unit of multi-split air conditioner Expired - Fee Related CN100532971C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100936465A CN100532971C (en) 2004-11-29 2004-11-29 Outdoor unit of multi-split air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100936465A CN100532971C (en) 2004-11-29 2004-11-29 Outdoor unit of multi-split air conditioner

Publications (2)

Publication Number Publication Date
CN1782557A CN1782557A (en) 2006-06-07
CN100532971C true CN100532971C (en) 2009-08-26

Family

ID=36773031

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100936465A Expired - Fee Related CN100532971C (en) 2004-11-29 2004-11-29 Outdoor unit of multi-split air conditioner

Country Status (1)

Country Link
CN (1) CN100532971C (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105299841B (en) * 2015-11-12 2018-04-06 广东美的暖通设备有限公司 The fault detection method of the heat exchange valve body of multiple on-line system and its outdoor heat exchanger

Also Published As

Publication number Publication date
CN1782557A (en) 2006-06-07

Similar Documents

Publication Publication Date Title
CN107438527B (en) Vehicle air conditioning system
US20090126293A1 (en) Telecommunications shelter with emergency cooling and air distribution assembly
CN101086362B (en) Outdoor machine control box of air conditioner
CN216868675U (en) Air conditioner
KR101096412B1 (en) Roof-Top Type Air-Conditioning System for Bus
JP2006297964A (en) Air-conditioner for railroad vehicle
CN103743014A (en) Evaporative cooling air conditioning system
CN103712302B (en) Wet curtain cooling air conditioning system
CN102455023A (en) Integrated window type air conditioner
CN100532971C (en) Outdoor unit of multi-split air conditioner
CN215570832U (en) Indoor air conditioner
KR102054306B1 (en) Hybrid air conditioning system
KR100621243B1 (en) Multi-airconditioner
CN100455922C (en) Outdoor unit of one dragging more ceiling air conditioner
CN100513900C (en) Top panel connection structure of outdoor unit of air conditioner
CN218805092U (en) Air conditioning equipment and vehicle
CN220041977U (en) Air conditioner
CN220065844U (en) Air conditioner
CN1782558A (en) Outdoor unit of one dragging more air conditioner
CN220065786U (en) Air conditioner
KR20190084588A (en) Movable air conditioner
CN219435970U (en) Air conditioner
CN220209067U (en) Air conditioner
CN114013248B (en) Vehicle-mounted air conditioner and automobile
CN219350380U (en) Air conditioner

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090826

Termination date: 20111129