CN100525953C - Technique for preventing surface crack of continuous casting steel billet for petroleum casing - Google Patents

Technique for preventing surface crack of continuous casting steel billet for petroleum casing Download PDF

Info

Publication number
CN100525953C
CN100525953C CNB2005101336307A CN200510133630A CN100525953C CN 100525953 C CN100525953 C CN 100525953C CN B2005101336307 A CNB2005101336307 A CN B2005101336307A CN 200510133630 A CN200510133630 A CN 200510133630A CN 100525953 C CN100525953 C CN 100525953C
Authority
CN
China
Prior art keywords
steel
continuous casting
furnace
temperature
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2005101336307A
Other languages
Chinese (zh)
Other versions
CN1990137A (en
Inventor
于泳
张露
王振祥
朱立国
张志忠
史志生
李志园
及占林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Steel Tube Manufacturing Co., Ltd.
Original Assignee
Tianjin Pipe Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Pipe Group Corp filed Critical Tianjin Pipe Group Corp
Priority to CNB2005101336307A priority Critical patent/CN100525953C/en
Publication of CN1990137A publication Critical patent/CN1990137A/en
Application granted granted Critical
Publication of CN100525953C publication Critical patent/CN100525953C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling

Landscapes

  • Treatment Of Steel In Its Molten State (AREA)
  • Continuous Casting (AREA)

Abstract

The invention provides a art method for prevent oil annular tube continuous casting billet surface crack, said billet is used for oil annular tube, its steps include : (1) electric arc furnace (EAF) smelt station, (2) ladle refining furnace (LF) process station, (3) vacuum refining furnace (VD) process station, (4) continuous casting (CCM) process station. The effect of the invention is: using said technology, changing and improving constantly under the condition of using 150t super high-capacity arc furnace, 150t ladle refining furnace, 150t vacuum refining furnace, and round billet continuous casting machine with 6 flows in one machine, it prevents the oil annular tube continuous casting billet surface crack through the production of two steel types of 39Mn2V and 39Mn2V/l, improves the quality of the steel species and reduces waste by 60%.

Description

A kind of process that prevents surface crack of continuous casting steel billet for petroleum casing
Technical field
The present invention relates to be used in a kind of API standard produce the production technology of N80-1 class petroleum casing pipe with continuous casting billet, particularly a kind of process that prevents surface crack of continuous casting steel billet for petroleum casing.
Background technology
In STEELMAKING PRODUCTION, rolling 39Mn2V, 39Mn2V/1 are two steel grades that are applicable to N80-1 class petroleum casing pipe in the production " sleeve pipe and oil pipe standard " (API SPEC 5CT standard), have been widely used in Shengli Oil Field at present, told the main oil plays in the whole nation such as breathing out oil field, Qinghai Oil Field, Liaohe Oil Field.The main production technology of this kind of current domestic production is electric arc furnaces (EAF), ladle refining furnace (LF), vacuum refining furnace (VD), continuous casting (CCM), but aborning, these two steel grades quality stability in the operation of rolling is relatively poor, occur in a large number rolling over outside the body after rolling through being everlasting, defective such as crackle, and then cause a large amount of waste products to produce.Cause the main cause of this type of defective to exceed standard with non-metallic inclusion and the strand cooling procedure in internal stress excessive, strand low temperature aligning when producing is relevant, this and production technology have very big relation, main cause is:
At first, in the steelmaking process, because general production technology mostly uses aluminium, silicomanganese, Antaciron to carry out deoxidation, therefore if, the silicate that easy hard, indeformable tiny solid alumina inclusion of generation and silicate and metal oxide chemical combination form in molten steel is mingled with, adequate time come-up that the two do not have, can accumulate in the steel, destroy the basic continuity of steel, cause the tissue odds of steel even, influence the various performances of steel.
In addition, when continuous casting, because the manganese content of these two steel grades is all in 1.0~2.0% scopes, and in general carbon steel, manganese content is only below 0.70%, and is little to the performance impact of steel, because manganese content is increased at 1.0%~2.0% o'clock, intensity raising, plasticity are reduced, easily make grain coarsening, internal stress is bigger.And steel has a brittleness temperature scope in the time of 700~900 ℃, in this temperature range, easily cracks as the effect that is subjected to stress when aligning.Therefore,, must adopt adjust the distribution of secondary cooling water, make the surface temperature of continuous casting billet when aligning avoid the pressure of this temperature range and suitable adjustment straightening machine for fear of this phenomenon.
Summary of the invention
At above-mentioned situation, the objective of the invention is under the prerequisite that does not change conventional process flow, improving the molten steel cleanliness factor by conventional method, when reducing non-metallic inclusion, provide a kind of process that prevents surface crack of continuous casting steel billet for petroleum casing.
For achieving the above object, the technical solution used in the present invention provides a kind of process that prevents surface crack of continuous casting steel billet for petroleum casing, and its concrete steps are as follows:
(1) electric arc furnaces (EAF) is smelted station
During electric furnace smelting, for remedying the deficiency of carbon content in the steel scrap, the mixed carbon comtent by reasonably ensureing furnace charge with addition of molten iron and the pig iron guarantees to have made as early as possible Pao Droplets slag in 1.0 ~ 1.5% scopes, finished the dephosphorization decarburization in 25~35 minutes; For avoiding five-harmful elements in the operation of rolling (Pb, Sn, As, Sb, Bi) poly-partially at the crystal boundary place, avoid the higher steel scrap of disposable a large amount of use five-harmful elements (Pb, Sn, As, Sb, Bi) content during batching, when smelting, pass through to add molten iron and sponge iron simultaneously in order to the five-harmful elements in the dilution molten steel; Adopt eccentric furnace bottom slag free tapping, prevent that oxidizing slag from entering in the ladle, utilize and stay the method for steel in stove, to stay part molten steel (near 20t), guarantee certain electric furnace steel tapping temperature; Steel coolant-temperature gage ≧ 1520 ℃ in half an hour after tapping, guarantee molten steel in vacuum refining furnace, have the enough high vacuum time for ≧ 8Min and calm time;
(2) ladle refining furnace (LF) is handled station
Stir a little less than refining finishes afterwards by argon gas and guarantee that molten steel temperature in casting process is even and the suitable degree of superheat is arranged, last casting temperature is controlled at following scope:
Open and water furnace temperature: T L+ 80+ (0 ~ 5) ℃
Connect and water furnace temperature: T L+ 55+ (0 ~ 5) ℃
In the formula: T L--the liquidus temperature of-----steel grade
The field trash of having given birth to is fully floated, will avoid new field trash to generate simultaneously;
(3) vacuum refining furnace (VD) is handled station
Vacuum refining furnace promotes inclusion floating by the vacuum BOTTOM ARGON BLOWING, improves the molten steel degree of purity; Prolong high vacuum time Wei ≧ 8Min and calm time then, utilization Ca treatment technology makes string bunch shape Al 2O 3Become the spherical low melting point CaO-Al that is easy to discharge 2O 3Be field trash, and guarantee that hello Al silk and CaSi silk time are Jian Ge ≧ 10Min; The control vacuum refining furnace concluding time, when the big Baogang of continuous casting water remained 40~50t, next Baogang's water will possess last continuous-casting conditions; When remaining 30~40t, next Baogang's water rises and hangs on continuous casting;
(4) continuous casting (CCM) station
The long nozzle of the big bag of continuous casting adopts sealing ring, to the omnidistance Argon of big canning tube, middle bag liquid level 〉=30t, use corresponding water meter, assurance secondary cooling water spraying, and shower waters selection tandem in 1,2 districts when producing, 3 district's shower waters are controlled at 30L/Min, 4 district's shower waters are closed, and 3 districts, 4 district's shower water control modes are become manual mode by the tandem mode; First the hot base pressure of straightening machine is set to zero, has avoided 700~900 ℃ in fragility sensitive temperature zone; After cast big bag of later stage waters steel and finishes, pulling rate is progressively reduced to the starting pulling rate, residue molten steel height 〉=200mm in the tundish is involved in the strand to reduce field trash.
Effect of the present invention is by adopting above technology, continuous modification under appointed conditions such as use 150t ultra high electric arc furnace, 150t ladle refining furnace, 150t vacuum refining furnace, 1 machine, 6 stream curved circular billet continuous casting machines and perfect, finally determined the new production technology of 39Mn2V, 39,Mn2,V/1 two steel grades, prevented the appearance of surface crack of continuous casting steel billet for petroleum casing, improved the quality of steel grade, and rejection number has been reduced by 60%.
The specific embodiment
Be that φ 270mm, φ 310mm strand are embodiment with 39Mn2V, 39Mn2V/1 section below, a kind of process of surface crack of continuous casting steel billet for petroleum casing that prevents of the present invention is illustrated.
Because internal stress is very big in 39Mn2V, the 39Mn2V/1 strand cooling procedure, strand is low excessively as if temperature before entering the straightening machine, will behind aligning, produce the aligning crackle, therefore, we adjust the intensity of secondary cooling when producing these two steel grades, weakened the water yield in He Si districts, three districts, two cold-zones, the cooling water inflow in Jiang San district is reduced to 30L/min, and Jiang Si district water is closed, in order to improve the strand straightening temperature, avoid 700~900 ℃ brittleness temperature scope.Also adjust simultaneously the pressure of first straightening machine, the hot base pressure of first straightening machine has been reduced to 0MPa, reduced the possibility that causes the core crackle because of when the strand internal stress is excessive, aligning.
A kind of process that prevents surface crack of continuous casting steel billet for petroleum casing of the present invention mainly is under the prerequisite that is not changing existing total production procedure, and is as follows to the process procedure concrete operations of each flow process:
1, electric arc furnaces (EAF) is smelted station
During electric furnace smelting, for remedying the deficiency of carbon content in the steel scrap, by reasonably ensureing that with addition of the molten iron and the pig iron mixed carbon comtent of furnace charge is in 1.0~1.5% scopes, guarantee to have made as early as possible Pao Droplets slag, in 25~35 minutes, finish the task of dephosphorization decarburization, prevent the phenomenon of long Molten Steel over-oxidation that causes of smelting cycle and then increase oxide inclusions.For avoiding five-harmful elements (Pb, Sn, As, Sb, Bi) poly-partially at the crystal boundary place, reduce the elevated temperature strength and the plasticity of steel, folding or crackle outside in the operation of rolling, producing, by rational proportion scheme, the higher steel scrap of disposable a large amount of use five-harmful elements content when avoiding preparing burden passes through to add molten iron and sponge iron simultaneously in order to the five-harmful elements in the dilution molten steel when smelting.Adopt eccentric furnace bottom slag free tapping, prevent that oxidizing slag from entering in the ladle, utilize and stay the method for steel in stove, to stay part molten steel (about 20t).Guarantee suitable electric furnace steel tapping temperature, this is not only the key that guarantees the molten steel quality, and is to guarantee to produce the key of carrying out smoothly, and its computing formula is:
Add the temperature drop that alloy and slag making material cause during the liquidus temperature of tapping temperature=steel (1530 ℃)+(40~50 ℃)+tapping
Calculate back interior steel coolant-temperature gage half an hour of guaranteeing to tap ≧ 1520 ℃ in strict accordance with above-mentioned formula.To reduce refining station heat time heating time, guarantee that molten steel has enough high vacuum time (≧ 8Min) and calm time at vacuum refining furnace.
2, ladle refining furnace (LF) is handled station
Refining treatment is a control field trash important link, not only will allow the field trash of having given birth to fully float, but also will avoid new field trash to generate.Therefore require it in deployed each composition, refining finish the back stir a little less than by argon gas guarantee molten steel in casting process temperature evenly and the suitable degree of superheat is arranged, last casting temperature is controlled at following scope:
Open and water furnace temperature: T L+ 80+ (0~5) ℃
Connect and water furnace temperature: T L+ 55+ (0~5) ℃
In the formula: T L--the liquidus temperature of-----steel grade
Prevent because of casting strand inner inclusion and the aligning crackle that the higher secondary oxidation that causes of temperature causes.
3, vacuum refining furnace (VD) is handled station
The VD stove reaches the purpose to molten steel dehydrogenation, denitrogenation, deoxidation and desulfurization by the vacuum BOTTOM ARGON BLOWING, promotes inclusion floating, improves the molten steel degree of purity.When accomplishing these, prolong high vacuum time (≧ 8Min) and calm time, control well feed Al silk and CaSi silk time to improve the calcium treatment effect, require to feed Al silk and CaSi silk Shi Jian Jian Ge ≧ 10Min, handle by Ca, can be fully with the residual Al in the steel 2O 3Be converted into low-melting combination product, discharge molten steel easily, the category-B that is beneficial to fully remove in the molten steel is mingled with (Al 2O 3).Reach inclusion modification and cleaning molten steel effect, control the VD concluding time well, when the surplus 40~50t of the big Baogang of continuous casting water, next Baogang's water will possess last continuous-casting conditions; When remaining 30~40t, next Baogang's water rises and hangs on continuous casting.So just guaranteed that molten steel has the enough calm time before cast, fully float field trash.
4, continuous casting (CCM) station
The big bag long nozzle of continuous casting adopts sealing ring, guarantees that the omnidistance Argon of big canning tube guarantees that middle bag liquid level 〉=30t, two steel grades still use each self-corresponding water meter in the operation card, guarantees that the secondary cooling water spraying is good.As shown in the table, 1,2 district's shower waters are selected tandem during production, and 3 district's shower waters are controlled at 30L/Min, and 4 district's shower waters are closed, and control mode becomes manual mode by original tandem mode; First the hot base pressure of straightening machine is set to zero, has avoided fragility sensitive temperature zone.After cast big bag of later stage waters steel and finishes, pulling rate progressively must be reduced to the starting pulling rate, residue molten steel height 〉=200mm is above in the tundish is involved in the strand to reduce field trash.
1. the adjustment of secondary cooling water intensity
Φ 270mm specification 1 district water yield L/min Control mode 2 district water yield L/min Control mode 3 district water yield L/min Control mode 4 district water yield L/min Control mode Amount to L/min
Before the adjustment 29.7 Tandem 56.5 Tandem 33.0 Tandem 33.0 Tandem 152.3
After the adjustment 29.7 Tandem 56.5 Tandem 30 Manually 0 Manually 116.2
Φ 310mm specification 1 district water yield L/min Control mode 2 district water yield L/min Control mode 3 district water yield L/min Control mode 4 district water yield L/min Control mode Amount to L/min
Before the adjustment 49.9 Tandem 60.2 Tandem 31.0 Tandem 31.0 Tandem 172.1
After the adjustment 49.9 Tandem 60.2 Tandem 30 Manually 0 Manually 140.1
2. to the adjustment of the pressure of first straightening machine
Figure C200510133630D00091

Claims (1)

1, a kind of process that prevents surface crack of continuous casting steel billet for petroleum casing, its concrete steps are as follows:
(1) electric arc furnaces (EAF) is smelted station
During electric furnace smelting, for remedying the deficiency of carbon content in the steel scrap, the mixed carbon comtent by reasonably ensureing furnace charge with addition of molten iron and the pig iron guarantees to have made as early as possible foamed slag in 1.0~1.5% scopes, finished the dephosphorization decarburization in 25~35 minutes; For avoiding five-harmful elements in the operation of rolling, its five-harmful elements is Pb, Sn, As, Sb, Bi, poly-partially at the crystal boundary place, avoid the higher steel scrap of the above-mentioned five-harmful elements content of disposable a large amount of use during batching, when smelting, pass through to add molten iron and sponge iron simultaneously in order to the five-harmful elements in the dilution molten steel; Adopt eccentric furnace bottom slag free tapping, prevent that oxidizing slag from entering in the ladle, utilize and stay the method for steel to stay the part molten steel in stove, molten steel guarantees certain electric furnace steel tapping temperature near 20t; Steel coolant-temperature gage ≧ 1520 ℃ in half an hour after tapping, guarantee molten steel in vacuum refining furnace, have the enough high vacuum time for ≧ 8Min and calm time;
(2) ladle refining furnace (LF) is handled station
Stir a little less than refining finishes afterwards by argon gas and guarantee that molten steel temperature in casting process is even and the suitable degree of superheat is arranged, last casting temperature is controlled at following scope:
Open and water furnace temperature: T L+ 80+ (0~5) ℃
Connect and water furnace temperature: T L+ 55+ (0~5) ℃
In the formula: T L--the liquidus temperature of-----steel grade
The field trash of having given birth to is fully floated, will avoid new field trash to generate simultaneously;
(3) vacuum refining furnace (VD) is handled station
Vacuum refining furnace promotes inclusion floating by the vacuum BOTTOM ARGON BLOWING, improves the molten steel degree of purity; Prolong high vacuum time Wei ≧ 8Min and calm time then, utilization Ca treatment technology makes string bunch shape Al 2O 3Become the spherical low melting point CaO-Al that is easy to discharge 2O 3Be field trash, and guarantee that hello Al silk and CaSi silk time are Jian Ge ≧ 10Min; The control vacuum refining furnace concluding time, when the big Baogang of continuous casting water remained 40~50t, next Baogang's water will possess last continuous-casting conditions; When remaining 30~40t, next Baogang's water rises and hangs on continuous casting;
(4) continuous casting (CCM) station
The long nozzle of the big bag of continuous casting adopts sealing ring, to the omnidistance Argon of big canning tube, middle bag liquid level 〉=30t, use corresponding water meter, assurance secondary cooling water spraying, and shower waters selection tandem in 1,2 districts when producing, 3 district's shower waters are controlled at 30L/Min, 4 district's shower waters are closed, and 3 districts, 4 district's shower water control modes are become manual mode by the tandem mode; First the hot base pressure of straightening machine is set to 0MPa, has avoided 700~900 ℃ in fragility sensitive temperature zone; After cast big bag of later stage waters steel and finishes, pulling rate is progressively reduced to the starting pulling rate, residue molten steel height 〉=200mm in the tundish is involved in the strand to reduce field trash.
CNB2005101336307A 2005-12-26 2005-12-26 Technique for preventing surface crack of continuous casting steel billet for petroleum casing Active CN100525953C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005101336307A CN100525953C (en) 2005-12-26 2005-12-26 Technique for preventing surface crack of continuous casting steel billet for petroleum casing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005101336307A CN100525953C (en) 2005-12-26 2005-12-26 Technique for preventing surface crack of continuous casting steel billet for petroleum casing

Publications (2)

Publication Number Publication Date
CN1990137A CN1990137A (en) 2007-07-04
CN100525953C true CN100525953C (en) 2009-08-12

Family

ID=38212802

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005101336307A Active CN100525953C (en) 2005-12-26 2005-12-26 Technique for preventing surface crack of continuous casting steel billet for petroleum casing

Country Status (1)

Country Link
CN (1) CN100525953C (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100542715C (en) * 2007-10-19 2009-09-23 攀钢集团攀枝花钢铁研究院 Continuous casting method of 450mm 360mm medium carbon manganese steel bloom
CN101565771B (en) * 2009-04-29 2011-01-19 天津钢管集团股份有限公司 Calcium treatment method for molten steel in steel making
CN101792843B (en) * 2010-01-19 2011-09-21 南京钢铁股份有限公司 Production process of Nb-containing mill coil for automobile
CN101850409B (en) * 2010-06-08 2012-02-29 攀钢集团钢铁钒钛股份有限公司 Continuous casting method
CN102059331A (en) * 2010-11-26 2011-05-18 首钢总公司 Continuous casting blank hot charging and hot conveying process for preventing surface crack of steel plate
CN105458205B (en) * 2015-12-03 2017-12-19 攀钢集团成都钢钒有限公司 The production method of high nickel steel Gr.8 continuous cast round billets
CN115627409A (en) * 2022-10-24 2023-01-20 石钢京诚装备技术有限公司 Production method for reducing surface crack rate of medium-carbon boron-containing round steel

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4494999A (en) * 1982-07-09 1985-01-22 Mannesmann Aktiengesellschaft Process for making fine-grain weldable steel sheet for large-diameter pipes

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4494999A (en) * 1982-07-09 1985-01-22 Mannesmann Aktiengesellschaft Process for making fine-grain weldable steel sheet for large-diameter pipes

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
P110石油管坯水平连铸工艺改进和质量控制. 钟春生,彭自胜.特殊钢,第24卷第1期. 2003
P110石油管坯水平连铸工艺改进和质量控制. 钟春生,彭自胜.特殊钢,第24卷第1期. 2003 *
电炉钢连铸坯表面裂纹攻关. 谭俊敏,周国平,姚家华,于平.特殊钢,第21卷第2期. 2000
电炉钢连铸坯表面裂纹攻关. 谭俊敏,周国平,姚家华,于平.特殊钢,第21卷第2期. 2000 *

Also Published As

Publication number Publication date
CN1990137A (en) 2007-07-04

Similar Documents

Publication Publication Date Title
CN105839015B (en) A kind of production method of Mn-Cr series high-performances pinion steel
CN100525953C (en) Technique for preventing surface crack of continuous casting steel billet for petroleum casing
CN109023059A (en) The production technology of automotive suspension spring steel 60Si2Mn gren rod
CN102021488B (en) Steel for nuclear-island seamless steel tube and production method thereof
CN104946972B (en) Steel disc strip for diode lead and production technology of steel disc strip
CN105063474B (en) Electric furnace smelting method of steel for welding wire
CN106811577A (en) A kind of bearing steel smelting process for being conducive to controlling field trash
CN105018669B (en) A kind of production method of nuclear power ingot iron
CN102758144A (en) Production method for steel ingot of large-sized high-nitrogen retaining ring steel
CN103572165A (en) Steel for petroleum sleeve connecting piece and production method of steel
CN109252013A (en) A kind of bearing steel slagging process control method of full plastic occluded foreignsubstance
CN104043797B (en) The continuous cast method of a kind of super-low sulfur high chrome and the bloom of preparation thereof
CN108950129A (en) A kind of production method controlling Medium Carbon Steel Containing Manganese continuous cast round billets Large Inclusions
CN105154623A (en) Efficient alloying method for smelting 38CrMoAl steel
CN116904863B (en) High-cleanliness high-carbon steel and low-carbon-emission production method thereof
CN107058905A (en) A kind of super austenitic stainless steel and preparation method thereof
CN107245637A (en) A kind of AOD smelts the method and a kind of AOD furnace of high manganese stainless steel
CN109082588A (en) A kind of CrMo pole quenched and tempered steel and preparation method thereof
CN101381787B (en) Smelting method of high-alloy steel
CN104152632B (en) The method of extra furnace dephosphorization smelted by a kind of intermediate frequency furnace
CN102703809A (en) Hot-rolled steel and manufacturing method thereof
CN105648301A (en) 42CrMo melting process
CN107619899B (en) A kind of production method and Steel material of low remaining chromium content molten steel
CN109022670A (en) A kind of converter steel making method producing ultra-low phosphoretic steel
CN104946845A (en) Method for producing high-carbon-chrome bearing steel from vanadium-titanium-containing molten iron

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190624

Address after: No. 396 Jintang Highway, Dongli District, Tianjin 300301

Patentee after: Tianjin Steel Tube Manufacturing Co., Ltd.

Address before: 300301 Jintang Road, Dongli District, Tianjin

Patentee before: Tianjin Steel Pipe Group Co., Ltd.