Construction method of high-performance cement soil pile Download PDFInfo
- Publication number
- CN100376750C CN100376750C CNB2004100611980A CN200410061198A CN100376750C CN 100376750 C CN100376750 C CN 100376750C CN B2004100611980 A CNB2004100611980 A CN B2004100611980A CN 200410061198 A CN200410061198 A CN 200410061198A CN 100376750 C CN100376750 C CN 100376750C
- Authority
- CN
- China
- Prior art keywords
- hole
- performance cement
- soil
- cement soil
- cement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000004568 cement Substances 0.000 title claims abstract description 37
- 239000002689 soil Substances 0.000 title claims abstract description 34
- 238000010276 construction Methods 0.000 title abstract description 7
- 238000003756 stirring Methods 0.000 claims abstract description 12
- 238000000034 method Methods 0.000 claims abstract description 9
- 150000001875 compounds Chemical class 0.000 claims description 6
- 239000000654 additive Substances 0.000 claims description 3
- 230000000996 additive effect Effects 0.000 claims description 3
- 239000002002 slurry Substances 0.000 abstract description 10
- 239000003795 chemical substances by application Substances 0.000 abstract 2
- 238000011065 in-situ storage Methods 0.000 abstract 1
- 238000002347 injection Methods 0.000 abstract 1
- 239000007924 injection Substances 0.000 abstract 1
- 239000007921 spray Substances 0.000 description 6
- 229940098458 powder spray Drugs 0.000 description 4
- 230000007547 defect Effects 0.000 description 3
- 238000000465 moulding Methods 0.000 description 3
- 230000003487 anti-permeability effect Effects 0.000 description 2
- 235000008429 bread Nutrition 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The invention relates to a construction method of a high-performance cement soil pile, which is characterized by comprising the following steps: 1) adopting a hole forming device to form a hole or a groove; 2) stirring the slurry, the curing agent and the admixture outside the hole to form high-performance cement-soil slurry; 3) and injecting or pressing the high-performance cement soil slurry into the hole or the groove by using an injection pump. The invention thoroughly changes the traditional cement soil forming process, namely, the in-situ stirring of cement soil in the underground hole to form the pile is changed into the stirring of mud and a curing agent outside the hole. The high-performance cement-soil pile constructed by the method has higher strength than the traditional cement-soil pile, good impermeability and low cost, and is suitable for underground engineering in the fields of civil engineering and construction.
Description
Technical field
The present invention relates to the underground construction of building and building field, specifically a kind of job practices of high-performance cement soil stake.
Background technology
In building and building engineering field, cement earth pile has powder spray piling, slurry spray stake and high-pressure rotary jet grouting pile at present, and there is the following problem in these cement earth piles:
1, powder spray piling, slurry spray stake all are cement mixing methods, and its moulding process is that original position stirs in underground stake hole, and limit spraying cement or cement paste limit promote drilling rod, and jet velocity and hoisting velocity are difficult to coupling, thereby easily cause the common quality defect of " multi-layer steamed bread ".
2, since when powder spray piling and slurry spray pile driving construction the cement amount of the cement-soil in the drill pipe diameter seldom also be difficult to stir, promptly pile body is outer soft in hard, is commonly called as in the industry to be " egg core ", this common quality defect also is masty.
3, owing to above reason, quality problems often appear in a lot of powder spray pilings and a slurry spray stake engineering, some area even forbidden adopting this two kinds of stake types.
4, high-pressure rotary-spray cement earth pile, be by water under high pressure, gas, slurry, can pass through single tube, dual pipe, triple pipe, rely on the high-pressure rotary-spray jet in underground hole, to carry out the original position pile, the pile body diameter can differ bigger according to soil property situation difference, and also occurs dried layer cake phenomenon and the expanded diameter quality problems less than intended diameter easily.
Summary of the invention
The present invention seeks to propose a kind of job practices of high-performance cement soil stake, make it can solve " egg core " and the common quality defect of " multi-layer steamed bread " that the conventional soil cement stake produces in order to solve the problem that the above-mentioned background technology exists.
For achieving the above object, the present invention adopts following technical scheme:
1. the job practices of a high-performance cement soil stake is characterized in that this method adopts following steps:
1) adopts pore-forming equipment pore-forming or grooving;
2) outside the hole, utilize mud and curing compound and additive to stir into the high-performance cement soil paste;
3) with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove.
The present invention has thoroughly changed the moulding process of conventional soil cement, is promptly changed into by original position stirring concrete earth pile in the underground hole and utilizes mud and curing compound to stir outside the hole, and it has following advantage:
1, the moulding process of cement-soil is stirred to change into outside the hole by original position in the underground hole and stirs, and soil cement slurry stirs, and can make the high-performance cement soil that satisfies different resistance to compressions, anti-permeability performance according to different needs.
2, can utilize discarded slurry, turn waste into wealth, reduce pollution environment.
3, good with the high-performance cement soil stake strength ratio of this method construction traditional cement earth pile height, anti-permeability performance, cost is low, and it is applicable to the underground construction of building and building field.
Description of drawings
Fig. 1 is the schematic diagram of high-performance cement soil stake.
In the drawings, 1-hole, the stake of 2-high-performance cement soil, 3-core, 4-soil layer.
The specific embodiment
The present invention adopts following steps:
1, adopts rig or long spiral equipment or revolve and dig equipment pore-forming or grooving;
2, utilizing mud and cement outside the hole is that curing compound and additive stir into the high-performance cement soil paste;
3, with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove;
4, in above-mentioned high-performance cement soil stake, insert steel work or concrete structure core.
Claims (3)
1. the job practices of a high-performance cement soil stake is characterized in that this method is made up of following steps:
1) adopts long spiral equipment or revolve and dig equipment pore-forming or grooving;
2) outside the hole, utilize mud and curing compound and additive to stir into the high-performance cement soil paste;
3) with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove.
2. according to the job practices of the described high-performance cement soil stake of claim 1, it is characterized in that described curing compound is that cement is curing compound.
3. according to the job practices of claim 1 or 2 described high-performance cement soil stakes, it is characterized in that in above-mentioned steps 3) then in the high-performance cement soil stake, insert core.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100611980A CN100376750C (en) | 2004-11-26 | 2004-11-26 | Construction method of high-performance cement soil pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100611980A CN100376750C (en) | 2004-11-26 | 2004-11-26 | Construction method of high-performance cement soil pile |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1641111A CN1641111A (en) | 2005-07-20 |
CN100376750C true CN100376750C (en) | 2008-03-26 |
Family
ID=34868794
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004100611980A Expired - Fee Related CN100376750C (en) | 2004-11-26 | 2004-11-26 | Construction method of high-performance cement soil pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100376750C (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831907A (en) * | 2010-05-05 | 2010-09-15 | 山东省机械施工有限公司 | Construction method of cement mixing pile |
CN109137899A (en) * | 2018-08-29 | 2019-01-04 | 衡水京坤岩土工程有限公司 | A kind of compound tube pile construction engineering method of soil cement |
CN112030940B (en) * | 2020-06-23 | 2022-04-19 | 武汉谦诚桩工科技股份有限公司 | Construction process of in-situ premixed cement soil cast-in-place pile of marine soft soil |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423636A (en) * | 1992-12-10 | 1995-06-13 | Kencho Kobe Co., Ltd. | Cement soil apparatus of underground borer |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
JP2001146739A (en) * | 1999-11-24 | 2001-05-29 | Sato Kogyo Co Ltd | Construction method for impervious wall |
CN2587933Y (en) * | 2002-12-25 | 2003-11-26 | 曾毅学 | Reinforced cement composite pile |
CN1482307A (en) * | 2002-09-10 | 2004-03-17 | 周同和 | Sand concrete free small pile foundation consolidation process by stone throwing and squeezing |
-
2004
- 2004-11-26 CN CNB2004100611980A patent/CN100376750C/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423636A (en) * | 1992-12-10 | 1995-06-13 | Kencho Kobe Co., Ltd. | Cement soil apparatus of underground borer |
JP2001146739A (en) * | 1999-11-24 | 2001-05-29 | Sato Kogyo Co Ltd | Construction method for impervious wall |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
CN1482307A (en) * | 2002-09-10 | 2004-03-17 | 周同和 | Sand concrete free small pile foundation consolidation process by stone throwing and squeezing |
CN2587933Y (en) * | 2002-12-25 | 2003-11-26 | 曾毅学 | Reinforced cement composite pile |
Also Published As
Publication number | Publication date |
---|---|
CN1641111A (en) | 2005-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929114A (en) | High pressure jet grouting pile waterproof curtain construction device and method | |
CN1193141C (en) | Combined grouting construction process of reinforcing foundation | |
CN101581093B (en) | Composite high performance soil cement mortar pile construction method | |
CN101694096B (en) | Treatment method for grouting sand-layer foundation on the condition of flowing water | |
CN106759297A (en) | A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits | |
CN103806479A (en) | Pile foundation combined grouting reinforcement construction method combining waterproof curtain | |
CN204753574U (en) | High pressure jet grouting pile stagnant water curtain construction equipment | |
CN201395793Y (en) | Long spiral high-pressure spraying mud injecting stirring pile-forming device | |
CN102900079A (en) | High-frequency hydraulic vibratory construction method for cement-soil core-inserted combined pile | |
CN105239561A (en) | Long spiral mix spray pre-grouting press concrete post-inserted steel reinforcement cage cast-in-place pile construction process | |
CN102011399A (en) | PHC pile-based multiple high jet pedestal pile construction method | |
CN106284295A (en) | Multichannel high-pressure vibro-grouting jet groutinl construction method | |
CN100386483C (en) | High-performance cement soil continuous wall construction method | |
CN104988914A (en) | Cast-in-situ bored pile breakage processing method under water area environment | |
CN102817361B (en) | Double bushing top cover for broken rock curtain grouting and construction method of double bushing top cover | |
CN110468828A (en) | A kind of construction method of pattern foundation pit supporting structure water-stop continuous wall | |
CN204491591U (en) | A kind of triaxial cement mixing pile pile-forming equipment | |
CN105672329B (en) | The large size prefabricated building enclosure of deep basal pit and construction method | |
CN101649614A (en) | Variable-diameter multi-direction anchor pile | |
CN105178858A (en) | Drilling rig for double-tube high pressure jet grouting technology | |
CN100376750C (en) | Construction method of high-performance cement soil pile | |
CN211816208U (en) | Stirring rock-entering precast pile | |
CN101793024B (en) | Construction method for multi-head small-diameter deep mixing and high-pressure jet combined anti-seepage wall of foundation pit | |
CN100374657C (en) | Construction method employing threaded stirring shaft to decrease ambient foundation deformation | |
CN103603345B (en) | Cement mixing grouting pile foundations and forming method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |