CH711365A2 - Failure safety of power networks. - Google Patents

Failure safety of power networks. Download PDF

Info

Publication number
CH711365A2
CH711365A2 CH01109/15A CH11092015A CH711365A2 CH 711365 A2 CH711365 A2 CH 711365A2 CH 01109/15 A CH01109/15 A CH 01109/15A CH 11092015 A CH11092015 A CH 11092015A CH 711365 A2 CH711365 A2 CH 711365A2
Authority
CH
Switzerland
Prior art keywords
load
value
power grid
determining
failure
Prior art date
Application number
CH01109/15A
Other languages
German (de)
Other versions
CH711365B1 (en
Inventor
Stefanidou Ifigeneia
Moor Daniel
Original Assignee
Axpo Power AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Axpo Power AG filed Critical Axpo Power AG
Priority to CH01109/15A priority Critical patent/CH711365B1/en
Priority to DE102016211275.9A priority patent/DE102016211275A1/en
Publication of CH711365A2 publication Critical patent/CH711365A2/en
Publication of CH711365B1 publication Critical patent/CH711365B1/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/04Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

Ein erfindungsgemässes Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes weist die folgenden Schritte auf: Erfassen von Lastgrössen (P) für das betreffende Stromnetz; Ermitteln eines Wertes (X) für die Ausfallsicherheit in Abhängigkeit von zumindest den erfassten Lastgrössen (P) und einer Netztopologie des Stromnetzes; und Ausgeben des Ausfallsicherheitswertes (X). Die Erfindung betrifft auch ein System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes.An inventive method for computer-aided determination of the reliability of a power grid comprises the following steps: detecting load variables (P) for the relevant power grid; Determining a value (X) for the failure safety as a function of at least the recorded load variables (P) and a network topology of the power grid; and outputting the fail-safe value (X). The invention also relates to a system for computer-aided determination of the reliability of a power grid.

Description

Gebiet der ErfindungField of the invention

[0001] Die Erfindung betrifft ein Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes, ein zugehöriges Computerprogrammelement, sowie ein System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes. The invention relates to a method for computer-aided determination of the reliability of a power grid, an associated computer program element, and a system for computer-aided determination of the reliability of a power grid.

Hintergrundbackground

[0002] Der Überwachung, Gestaltung und Planung von Stromnetzen kommt grosse Bedeutung zu, insbesondere hinsichtlich der potentiellen Konsequenzen bei Ausfällen der Stromversorgung. The monitoring, design and planning of power grids is of great importance, especially with regard to the potential consequences of power outages.

[0003] Ziel ist es, ein Stromnetz hinsichtlich seiner Ausfallsicherheit einschätzen zu können. The aim is to be able to estimate a power grid in terms of its reliability.

Darstellung der ErfindungPresentation of the invention

[0004] Diese Aufgabe wird durch das Verfahren gemäss Anspruch 1 und das System gemäss Anspruch 10 gelöst. This object is achieved by the method according to claim 1 and the system according to claim 10.

[0005] Das Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes weist die folgenden Schritte auf: Erfassen von Lastgrössen für das betreffende Stromnetz; Ermitteln eines Wertes für die Ausfallsicherheit in Abhängigkeit von zumindest den erfassten Lastgrössen und einer Netztopologie des Stromnetzes; und Ausgeben des Ausfallsicherheitswertes. Das System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes enthält Mittel zum Erfassen von Lastgrössen für das betreffende Stromnetz, eine Recheneinheit zum Ermitteln eines Wertes für die Ausfallsicherheit des Stromnetzes in Abhängigkeit von zumindest den erfassten Lastgrössen und einer Netztopologie des Stromnetzes, sowie eine Einrichtung zum Ausgeben des Ausfallsicherheitswertes. The method for computer-aided determination of the reliability of a power grid comprises the following steps: detecting load variables for the relevant power grid; Determining a value for the failure safety as a function of at least the recorded load sizes and a network topology of the power grid; and outputting the fail-safe value. The system for computer-aided determination of the reliability of a power grid includes means for detecting load sizes for the relevant power grid, a computing unit for determining a value for the reliability of the power grid as a function of at least the recorded load sizes and a network topology of the power grid, and means for outputting the reliability value.

[0006] Ein Stromnetz ist insbesondere als elektrisches Energieversorgungsnetz im energietechnischen Sinne zu verstehen, zur Übertragung von elektrischer Energie hin zu Verbrauchern zu deren Energieversorgung, wobei die elektrische Energie erzeugt wird beispielsweise von in das Stromnetz einspeisenden Energieerzeugern, wie etwa Kraftwerke. Ein Stromnetz kann im Sinne der Erfindung nur ein Teil eines grösseren Stromnetzes sein, wenn nur dieser Teil Gegenstand von Ausfallbetrachtungen sein soll, oder aber ein beispielsweise durch einen gemeinsamen Netzbetreiber definiertes Stromnetz, oder ein Verbundnetz, oder ein Inselnetz. Das Stromnetz dient der Übertragung von elektrischer Energie von den Energieerzeugern zu den Energieverbrauchern, wobei als Energieverbraucher wiederum Verbundverbraucher wie etwa Gemeinden oder Städte, oder aber Einzelverbraucher wie Haushalte oder Betriebe angesehen werden können. A power grid is to be understood in particular as an electrical energy supply network in energy terms, for the transmission of electrical energy to consumers to their energy supply, the electrical energy is generated, for example, from feeding into the grid power generators, such as power plants. For the purposes of the invention, a power network can only be part of a larger power network, if only this part is to be the subject of failure considerations, or a power grid defined by a common grid operator, for example, or an interconnected grid or island grid. The power grid is used to transfer electrical energy from the energy producers to the energy consumers, whereby energy consumers can in turn be regarded as composite consumers such as municipalities or cities, or individual consumers such as households or businesses.

[0007] Vorzugsweise enthält ein Stromnetz ein oder mehrere elektrische Stromleitungen wie etwa Freileitungen oder Erdleitungen, und / oder Transformatoren – kurz Trafos genannt, beispielsweise in Umspannwerken oder Transformatorstationen, in denen die Spannungen zwischen Teilnetzen umgespannt werden. Leitungen und Transformatoren werden im Folgenden kollektiv auch als Elemente des Stromnetzes bezeichnet. Bevorzugt enthalten Stromnetze auch ein oder mehrere Schaltanlagen, im Folgenden auch Netzknoten genannt, an die Leitungen, Verbraucher, Energieerzeuger oder Transformatoren angeschlossen sind. In einer Weiterbildung der Erfindung zählen auch Schaltanlagen zu den Elementen des Stromnetzes. Ein Stromnetz im Sinne der Erfindung kann unterschiedliche Spannungsebenen – etwa Kombinationen aus Höchstspannung, Hochspannung oder Mittelspannung – umfassen, oder aber auch nur eine einzige Spannungsebene. Preferably, a power grid includes one or more electrical power lines such as overhead lines or ground lines, and / or transformers - short called transformers, for example, in substations or transformer stations, in which the voltages between subnets are spanned. Cables and transformers are collectively referred to below as elements of the power grid. Power grids preferably also include one or more switchgear, also referred to below as network nodes, to which lines, consumers, energy generators or transformers are connected. In a further development of the invention, switchgear also belongs to the elements of the power grid. A power network according to the invention may comprise different voltage levels - such as combinations of maximum voltage, high voltage or medium voltage - or even only a single voltage level.

[0008] Für die einzelnen Elemente oder ein Set aus Elementen des Stromnetzes, bevorzugt für jede Leitung und jeden Trafo des Stromnetzes wird zumindest je eine Lastgrösse erfasst. Unter Lastgrössen werden im Allgemeinen Grössen verstanden, die eine elektrische Belastung des Elements mit einer elektrischen Leistung abbilden. Hierzu zählen beispielsweise Wirk- und/oder Blind- und/oder Scheinleistung. Diese Lastgrössen, vorzugsweise erfasst in der Dimension Megawatt MW, werden bevorzugt in einem Normalbetrieb des Stromnetzes erfasst, d.h. in einem Betrieb ohne Ausfall eines oder mehrere Elemente. Insbesondere wird beispielsweise je Leitung und je Trafo ein Leistungswert erfasst, mit dem das betreffende Element als Lastfluss beaufschlagt ist. Die Lastgrössen sind also bevorzugt elektrische Leistungsgrössen, die die elektrische Belastung des betreffenden Elements zum jeweiligen Zeitpunkt angibt. Eine Lastgrösse kann vorzugsweise im Stromnetz direkt gemessen werden, was auch das Ableiten der Lastgrösse aus anderen im Stromnetz gemessenen elektrischen Grössen wie etwa Strom und Spannung umfasst. Eine Lastgrösse kann auch durch eine Lastflussberechnung erfasst werden, bei der aufgrund einer gegebenen Topologie des Stromnetzes und eines angenommenen Verbrauchs von elektrischer Energie durch Verbraucher und einer angenommenen Erzeugung und Einspeisung von elektrischer Energie in das Stromnetz und eines gegebenen Betriebsmittelzustands Lastgrössen je Leitung und Trafo berechnet werden. Auch können Lastgrössen des Stromnetzes abgeleitet werden aus Messwerten im Stromnetz in der Vergangenheit. Die zugehörigen Mittel zur Lastgrössenerfassung können also Messeinrichtungen oder auch Berechnungseinrichtungen umfassen. For each element or a set of elements of the power grid, preferably for each line and each transformer of the power network at least one load size is detected. Under load sizes are generally understood sizes that reflect an electrical load on the element with an electric power. These include, for example, active and / or reactive and / or apparent power. These load quantities, preferably detected in the dimension megawatt MW, are preferably detected in a normal operation of the power grid, i. in one operation without failure of one or more elements. In particular, for example, per line and per transformer a power value is detected, with which the element concerned is acted upon as a load flow. The load variables are therefore preferably electrical power quantities which indicates the electrical load of the relevant element at the respective time. A load variable can preferably be measured directly in the power grid, which also includes deriving the load variable from other electrical quantities measured in the power grid, such as current and voltage. A load size may also be detected by a load flow calculation which calculates load sizes per line and transformer based on a given topology of the power grid and an assumed consumption of electrical energy by consumers and an assumed generation and supply of electrical energy to the grid and a given resource state , Also, load variables of the power network can be derived from measured values in the power grid in the past. The associated means for load size detection can therefore comprise measuring devices or also calculating devices.

[0009] Abhängig von den erfassten Lastgrössen und abhängig von einer Netztopologie des Stromnetzes wird nun ein Wert für die Ausfallsicherheit des Stromnetzes ermittelt. Die Ausfallsicherheit gibt an, wie sicher ein Stromnetz mit der angegebenen Topologie, bevorzugt dem angegebenen Zustand der Netzanlagen und unter den erfassen Lastgrössen gegen Ausfälle ist. Der Wertebereich der zulässigen Ausfallsicherheitswerte mag definiert sein durch ein Minimum, das einen hochwahrscheinlichen, grossflächigen Ausfall kennzeichnet, und ein Maximum, das einen sicheren Betrieb mit hoher Redundanz kennzeichnet. Ein Netzbetreiber mag basierend hierauf innerhalb des zulässigen Wertebereichs spezifische Wertebereiche definieren, innerhalb derer der Netzbetrieb tolerabel, gewünscht, und nicht tolerabel ist. Depending on the detected load sizes and depending on a network topology of the power grid, a value for the reliability of the power grid is now determined. Fail-safety indicates how safe a power grid is with the specified topology, preferably the stated state of the grid systems and the detection of load variables against failures. The range of acceptable fail-safe values may be defined by a minimum indicating a high-probability, large-scale failure, and a maximum indicating safe operation with high redundancy. Based on this, a network operator may define specific value ranges within the permissible value range within which the network operation is tolerable, desired, and intolerable.

[0010] Bevorzugt wird der Wert für die Ausfallsicherheit ausgegeben, beispielsweise auf einer Ausgabeeinrichtung wie einem Display. Dabei mag die Ausgabeeinrichtung räumlich getrennt von der Recheneinheit angeordnet sein, beispielsweise als Display in einem Kontrollraum des Netzbetreibers. Alternativ mag die Ausgabeeinrichtung ein zur Recheneinheit zugehöriges Display sein. Preferably, the value for the reliability is output, for example on an output device such as a display. In this case, the output device may be arranged spatially separated from the arithmetic unit, for example as a display in a control room of the network operator. Alternatively, the output device may be a display associated with the computing unit.

[0011] Bevorzugt stellt beispielsweise ein Ausfallsicherheitswert, der für den Netzbetreiber den Beginn eines nicht tolerablen Betriebsbereichs kennzeichnet, einen Schwellwert dar, mit dem der aktuell ermittelte Ausfallsicherheitswert verglichen wird. Überschreitet der Ausfallsicherheitswert diesen Schwellwert, so wird vorzugsweise eine Warnung auf einer optischen oder akustischen Einheit ausgegeben. Diese Warnung mag beispielsweise in einem Kontrollraum des Netzbetreibers ausgegeben werden, sodass Bedienpersonal sich auf einen drohenden Ausfall vorbereiten kann. In einer bevorzugten Weiterbildung der Erfindung kann beispielsweise auch bei Überschreiten des Schwellwerts automatisch eine Aktion getriggert werden, beispielsweise das Zuschalten weiterer Energieerzeuger, das Umschalten von Verbrauchern auf andere (Teil-)Netze, oder ähnliches. Preferably, for example, a fail-safe value, which marks the beginning of a non-tolerable operating range for the network operator, represents a threshold value with which the currently determined fail-safe value is compared. If the fail-safe value exceeds this threshold value, a warning is preferably output on an optical or acoustic unit. This warning may for example be issued in a control room of the network operator, so that operating personnel can prepare for an impending failure. In a preferred embodiment of the invention, for example, an action can be automatically triggered even when the threshold value is exceeded, for example, the connection of other energy producers, the switching of consumers to other (sub) networks, or the like.

[0012] Insofern eignet sich das erfindungsgemässe Verfahren und das erfindungsgemässe System zur Bewertung des Ausfallsicherheit von Stromnetzen, entweder in Echtzeit unter Berücksichtigung von aktuellen gemessenen Lastgrössen, oder offline basierend auf gemessenen Lastgrössen der Vergangenheit, berechneten oder antizipierten Lastgrössen, und kann damit zur Überwachung eines Stromnetzes eingesetzt werden, aber auch zur Planung von Stromnetzen, oder zur Bewertung von Netzzuständen aus der Vergangenheit. Insbesondere, können mit dem erfindungsgemässen Verfahren bzw. System Entscheidungen getroffen werden zu Varianten und zur Priorisierung von (n-1)-sicheren Varianten und einer Bewertung verschiedener Netzregionen. Beispielhaft kann auch eine jährliche Performance des Netzbetriebs durch Mittelung der über das Jahr ermittelten Ausfallsicherheitswerte erzielt werden. In this respect, the inventive method and the inventive system for evaluating the reliability of power networks, either in real time taking into account current measured load sizes, or offline based on measured load variables of the past, calculated or anticipated load sizes, and thus is suitable for monitoring a Power network, but also for the planning of power grids, or for the evaluation of network conditions from the past. In particular, decisions can be made with the method or system according to the invention for variants and for the prioritization of (n-1) -safe variants and an evaluation of different network regions. By way of example, an annual performance of the grid operation can be achieved by averaging the fail-safe values determined over the year.

[0013] Bevorzugt umfasst das Ermitteln des Wertes für die Ausfallsicherheit das Bilden eines Durchschnittslastwertes über die für die Leitungen erfassten Lastgrössen. Der Leitungs-Durchschnittslastwert wird im Folgenden bevorzugt normiert auf eine Leitungslastnorm. Generell dient die Normierung in diesem Fall wie auch in den weiteren Ausführungsbeispielen dem Herstellen der Vergleichbarkeit von unterschiedlichen in die Berechnung eingehenden Grössen. In einer bevorzugten Weiterbildung wird für jede Norm ein Idealwert verwendet, der beispielsweise einem gewünschten Wert – hier beispielsweise einer gewünschten Leitungslast – oder aber einem Durchschnittswert der Vergangenheit, also einem «normalen» zugrundeliegenden Netzbetrieb entspricht. Preferably, determining the value for the failsafe comprises forming an average load value over the load sizes detected for the lines. The line average load value is preferably standardized in the following to a line load standard. In general, in this case as well as in the other exemplary embodiments, the normalization serves to establish the comparability of different variables which enter into the calculation. In a preferred refinement, an ideal value is used for each standard which, for example, corresponds to a desired value-here, for example, to a desired line load-or to an average value of the past, that is to say a "normal" underlying network operation.

[0014] In gleicher Weise wird vorteilhaft – sofern zumindest ein Trafo in dem betrachteten Stromnetz vorhanden ist – ein Durchschnittswert über die für die Trafos erfassten Lastgrössen gebildet und dieser auf eine Trafolastnorm normiert. In the same way is advantageous - if at least one transformer in the considered power grid is present - an average value formed on the load variables recorded for the transformers and normalized to a Traffastnorm.

[0015] In den Ausfallsicherheitswert gehen also die auf Leitungen und Trafos einwirkenden Lastgrössen ein. Je höher diese Lastgrössen sind, desto geringer ist die Ausfallsicherheit. Je geringer diese Lastgrössen sind, desto höher ist die Ausfallsicherheit. In the fail-safe value so the loads acting on lines and transformers enter a. The higher these load sizes, the lower the reliability. The smaller these load sizes, the higher the reliability.

[0016] Bevorzugt geht auch die über alle Leitungen und Trafos erfasste maximale Lastgrösse als maximaler Lastwert in die Ausfallsicherheit ein, bevorzug wiederum in normierter Form, d.h. bezogen auf eine Maximallastnorm. Es wurde erkannt, dass Spitzenlasten die Ausfallsicherheit beträchtlich beeinflussen, und nicht nur die obigen erwähnten Durchschnittslasten. Ferner geht bevorzugt zusätzlich eine durchschnittliche Abweichung von für das Stromnetz erfassten Spannungsgrössen von zugeordneten Spannungsgrenzwerten in die Ermittlung der Ausfallsicherheit ein, ebenfalls wieder bevorzugt in normierter Form, also bezogen auf eine Spannungsabweichungsnorm. Hierzu wird auf Spannungswerte an Netzknoten zurückgegriffen, die ebenfalls bevorzugt gemessen werden oder berechnet sind. Gleich zu den Lastflussgrössen, die als bevorzugte Form der Lastgrössen angesehen sind, wird beispielsweise je Netzknoten mindestens ein Spannungswert aufgenommen. Die zugeordneten Spannungsgrenzen können Maximalspannungswerte für den betreffenden Netzknoten sein, die für den Betrieb des jeweiligen Elements zulässig sind. Preferably, the maximum load variable detected across all lines and transformers also enters into the fail-safety as the maximum load value, preferably in a standardized form, i. E. based on a maximum load standard. It has been recognized that peak loads significantly affect reliability, not just the average loads mentioned above. In addition, an average deviation of voltage values of assigned voltage limit values detected for the power grid preferably additionally enters into the determination of the fail-safety, again preferably in standardized form, that is to say based on a voltage deviation standard. For this purpose, voltage values are used at network nodes, which are likewise preferably measured or calculated. Equal to the load flow quantities, which are regarded as a preferred form of the load variables, at least one voltage value is recorded per network node, for example. The assigned voltage limits may be maximum voltage values for the respective network node that are permissible for the operation of the respective element.

[0017] Basieren die bislang in die Bestimmung der Ausfallsicherheit eingehenden Grössen vorzugsweise auf einem Betrieb des Stromnetzes ohne Ausfall ein oder mehrerer Elemente, so ist für die Beurteilung der Ausfallsicherheit aber auch das Verhalten des Stromnetzes massgebend für den Fall, dass bereits ein – und bevorzugt genau ein – Element des Stromnetzes ausgefallen ist. Basierend auf den konkreten Lastgrössen des Normalbetriebs kann berechnet werden – bevorzugt in Form einer Simulation, wie sich die Lastgrössen ändern, wenn eines der Elemente ausfällt. Insofern werden in einer bevorzugten Weiterbildung unter der Annahme des Ausfalls eines ersten Elemente die Lastgrössen für die verbleibenden n-1 Elements ermittelt, vorausgesetzt, das Stromnetz enthält n Elemente, die der Berechnung zugrunde gelegt werden. Aus diesen ermittelten Lastgrössen wird ein erster Durchschnittslastwert gebildet. Dann werden unter der Annahme des Ausfalls eines anderen Elements die Lastgrössen für die wiederum verbleibenden n-1 Elemente ermittelt. Aus diesen ermittelten Lastgrössen wird ein zweiter Durchschnittslastwert gebildet, und so fort. Schliesslich wird aus den n ermittelten Durchschnittslastwerten ein Gesamtdurchschnittslastwert gebildet, der seinerseits wiederum bevorzugt normiert wird auf eine Gesamtdurchschnittslastnorm. If the variables previously used in the determination of the failure safety are preferably based on operation of the power grid without failure of one or more elements, then the behavior of the power grid is decisive for the assessment of the failure safety as well - and preferred exactly one - element of the power network has failed. Based on the concrete load variables of normal operation can be calculated - preferably in the form of a simulation, how the load sizes change when one of the elements fails. In this respect, in a preferred development, assuming the failure of a first element, the load sizes for the remaining n-1 element are determined, provided that the power network contains n elements on which the calculation is based. From these determined load variables, a first average load value is formed. Then, assuming the failure of another element, the load sizes for the remaining n-1 elements are determined. From these determined load sizes, a second average load value is formed, and so on. Finally, a total average load value is formed from the n determined average load values, which in turn is preferably normalized to a total average load standard.

[0018] Bevorzugt wird auch aus den für alle Ausfall-Varianten ermittelten Lastgrössen ein maximaler Lastwert ermittelt, der bevorzugt auf eine Ausfall-Maximallastnorm normiert wird. In einer weiteren Weiterbildung wird eine minimale Abweichung ermittelt von für das Stromnetz ermittelten Spannungsgrössen von einem zugeordneten Spannungsgrenzwert, wiederum bei Ausfall irgendeines der Elemente. Die minimale Spannungsabweichung mag auf eine Minimal-Spannungsabweichungsnorm normiert werden. Preferably, a maximum load value is determined from the determined for all failure variants load sizes, which is preferably normalized to a failure maximum load standard. In a further refinement, a minimum deviation is determined from voltage variables determined for the power network from an assigned voltage limit value, again in the event of failure of any of the elements. The minimum voltage deviation may be normalized to a minimum voltage deviation standard.

[0019] Es findet auch die Topologie des Stromnetzes Eingang in die Bestimmung der Ausfallsicherheit. Zum einen mögen je nach Vermaschung bei Ausfall eines Elements des Stromnetzes keine, kleinere oder grössere Teile des Stromnetzes in Mitleidenschaft geraten und ebenfalls betroffen sein, d.h. insbesondere ausfallen. Dabei wird beispielsweise die Anzahl derjenigen Netzknoten im Stromnetz bestimmt, die sogenannt «n-1»-sicher sind, d.h. die eine redundante Anbindung haben und bei Ausfall eines Elements in einem zum Netzknoten führenden Pfad immer noch über den weiteren Pfad / Anbindung erreichbar sind. Andererseits wird vorzugsweise die Anzahl derjenigen Netzknoten im Stromnetz bestimmt, die trotz eines Ausfalls eines Elements des Stromnetzes unversorgt bleiben, also sogenannt nur «n-0»-sicher sind. It also finds the topology of the power grid entrance into the determination of the reliability. On the one hand, depending on the meshing in case of failure of an element of the power grid, no, smaller or larger parts of the power grid may be affected and also affected, i. especially fail. In this case, for example, the number of those network nodes in the power network is determined, which are so-called "n-1" -safe, i. which have a redundant connection and in case of failure of an element in a path leading to the network node are still accessible via the other path / connection. On the other hand, it is preferable to determine the number of those network nodes in the power network that remain unprovided despite a failure of an element of the power network, that is to say so-called only "n-0" -safe.

[0020] Als zusätzliche Einflussgrösse wird bevorzugt die technische Auslegung der Schaltanlagen in den Netzknoten verwendet, auch als Layout bezeichnet. Hierzu werden bevorzugt die Schaltanlagen in Schaltanlagenklassen klassiert und die Anzahl von Schaltanlagen im Stromnetz je Schaltanlagenklasse ermittelt. Beispielhafte Schaltanlagenklassen können beispielsweise aufgefächert werden anhand der folgenden Eigenschaften von Schaltanlagen: <tb>1)<SEP>mit Doppelsammelschiene/mit Einzelschiene, <tb>2)<SEP>mit Kuppelfeld / ohne Kuppelfeld, <tb>3)<SEP>mit / ohne Längstrennung.As an additional influence variable, the technical design of the switchgear in the network node is preferably used, also referred to as layout. For this purpose, the switchgear is preferably classified in switchgear classes and determines the number of switchgear in the power grid per switchgear class. Exemplary switchgear classes can, for example, be fanned out using the following properties of switchgear: <tb> 1) <SEP> with double busbar / with single rail, <tb> 2) <SEP> with dome field / without dome field, <tb> 3) <SEP> with / without longitudinal separation.

[0021] Hier trägt beispielsweise die Anlagenklasse am meisten zur Ausfallsicherheit bei, deren Schaltanlage die meiste Redundanz aufweist, das ist beispielsweise die Schaltanlage mit Doppelschiene mit Kuppelfeld und Längstrennung. Vorzugsweise werden die Anzahl der Schaltanlagen je Anlagenklasse ermittelt. Here, for example, the asset class contributes the most to the reliability, whose switchgear has the most redundancy, that is, for example, the switchgear with double rail with dome field and longitudinal separation. Preferably, the number of switchgear systems per asset class are determined.

[0022] Aufgrund der Tatsache, dass zwar die Anzahl nicht-versorgter Verbraucher bei einem Ausfall im Stromnetz bedeutend ist, es jedoch in den Konsequenzen einen Unterscheid machen mag ob ein Haushalt oder ein Betrieb unversorgt bleibt, wird vorzugsweise die Gesamtlast (beispielsweise in MW) aller Verbraucher ermittelt anstelle deren Anzahl, die trotz eines Ausfalls eines Elements des Stromnetzes versorgt bleiben. Dies entspricht dem Aufaddieren der Lasten aller Verbraucher, die von einem «n-1»-sicheren Netzzweig versorgt sind, wohingegen auch die Lasten aller Verbraucher aufsummiert werden, die nur von einem «n-0»-sicheren Netzzweig versorgt sind und damit bei einem Ausfall eines Elements des Stromnetzes unversorgt bleiben. Vorgängig ist hier jeweils der Verbrauch der einzelnen Verbraucher zu erfassen, beispielweise durch Messung, statistische Mittelwertbildung, und / oder Abschätzung. Bevorzugt wird auch die nicht gelieferte Leistung bei Ausfall eines Elements mit einbezogen. Due to the fact that, although the number of non-powered consumers is significant in the event of a power failure, it may make a difference in the consequences of whether a household or a business is left unattended, preferably the total load (for example in MW) of all consumers instead of their number, which remain powered despite a failure of an element of the power grid. This corresponds to adding up the loads of all loads powered by a "n-1" -secure network branch, while also summing up the loads of all consumers that are powered by only one "n-0" -secure network branch and thus one Failure of an element of the power network to be left unattended. In each case, the consumption of the individual consumers must be recorded in advance, for example by measurement, statistical averaging, and / or estimation. Preferably, the undelivered power is included in case of failure of an element.

[0023] In einer vorteilhaften Weiterbildung wird zusätzlich der Zustand von Elementen des Stromnetzes, und damit die Ausfallwahrscheinlichkeit dieser einzelnen Elemente, in die Ermittlung des Ausfallsicherheitswertes für das betrachtete Netz mit einbezogen. In an advantageous development of the state of elements of the power grid, and thus the probability of failure of these individual elements is included in the determination of the resilience value for the considered network in addition.

[0024] Ein weiterer Aspekt der Erfindung betrifft ein Computerprogrammelement, enthaltend Computerprogrammcode zur Durchführung des Verfahrens nach einem der vorhergehenden Ausführungsbeispiele bei Ausführung des Computerprogrammelements auf einem Prozessor. Another aspect of the invention relates to a computer program element containing computer program code for carrying out the method according to one of the preceding embodiments when the computer program element is executed on a processor.

Kurze Beschreibung der ZeichnungenBrief description of the drawings

[0025] Weitere Ausgestaltungen, Vorteile und Anwendungen der Erfindung ergeben sich aus den abhängigen Ansprüchen und aus der nun folgenden Beschreibung anhand der Figuren. Dabei zeigen: <tb>Fig. 1<SEP>eine schematische Ansicht eines Stromnetzes, <tb>Fig. 2<SEP>ein System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes gemäss einem Ausführungsbeispiel der Erfindung, beispielsweise des Stromnetzes nach Fig. 1 , <tb>Fig. 3<SEP>in Diagrammen a) bis c) diverse Topologien eines Stromnetzes, und in Diagrammen d) und e) diverse Anlageauslegungen, <tb>Fig. 4<SEP>eine Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung, <tb>Fig. 5<SEP>eine weitere Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung, <tb>Fig. 6<SEP>eine dritte Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung, und <tb>Fig. 7<SEP>ein Diagramm darstellend ein Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes gemäss einem Ausführungsbeispiel der Erfindung.Further embodiments, advantages and applications of the invention will become apparent from the dependent claims and from the following description with reference to the figures. Showing: <Tb> FIG. 1 <SEP> is a schematic view of a power grid, <Tb> FIG. 2 <SEP> a system for computer-aided determination of the failure safety of a power network according to an exemplary embodiment of the invention, for example of the power network according to FIG. 1, <Tb> FIG. 3 <SEP> in diagrams a) to c) various topologies of a power network, and in diagrams d) and e) various system designs, <Tb> FIG. 4 <SEP> is a table for explaining the method according to an embodiment of the invention, <Tb> FIG. 5 <SEP> another table for explaining the method according to an embodiment of the invention, <Tb> FIG. FIG. 6 shows a third table for explaining the method according to an embodiment of the invention, and FIG <Tb> FIG. 7 is a diagram illustrating a method for computer-aided determination of the reliability of a power network according to an embodiment of the invention.

Detaillierte Beschreibung der ZeichnungenDetailed description of the drawings

[0026] Fig. 1 zeigt eine schematische Ansicht eines Stromnetzes 1, welches in diesem Fall ein Teilstromnetz repräsentiert. Ein Energieerzeuger 2 speist das Stromnetz 1. Des Weiteren wird das Stromnetz 1 über Sammelschienen 14, in diesem Fall über eine erste Sammelschiene 141 und eine zweite Sammelschiene 141 aus einem anderen Teilstromnetz gespeist. Das Stromnetz 1 selbst weist einen Trafo 12 sowie diverse Leitungen 11 auf. Die Leitungen 11 sind über Netzknoten 13 miteinander verbunden. Insbesondere ist eine Leitung 111 über einen Netzknoten 131 mit einer Leitung 112 verbunden, welche ihrerseits über einen Netzknoten 132 mit einer Leitung 113 verbunden ist. Verbraucher 13 sind an das Stromnetz 1 angeschlossen: Ein Verbraucher 31 ist an den Netzknoten 132 angeschlossen. Ein weiterer Verbraucher 32 ist über einen Netzknoten 133 angeschlossen. Fig. 1 shows a schematic view of a power grid 1, which represents a partial flow network in this case. A power generator 2 feeds the power grid 1. Furthermore, the power grid 1 is fed via bus bars 14, in this case via a first bus bar 141 and a second bus bar 141 from another partial power grid. The power grid 1 itself has a transformer 12 and various lines 11. The lines 11 are connected to each other via network nodes 13. In particular, a line 111 is connected via a network node 131 to a line 112, which in turn is connected via a network node 132 to a line 113. Consumers 13 are connected to the power grid 1: A consumer 31 is connected to the network node 132. Another consumer 32 is connected via a network node 133.

[0027] Fig. 2 zeigt ein System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes gemäss einem Ausführungsbeispiel der Erfindung, beispielsweise des Stromnetzes nach Fig. 1 . Das System enthält eine Recheneinheit 7 zum Ermitteln eines Wertes für die Ausfallsicherheit des Stromnetzes. Mittel 4 zum Erfassen von Lastgrössen für das betreffende Stromnetz erhält liefern diese als Eingangsgrössen an die Recheneinheit 7. Dies sind insbesondere Lastflussgrössen je Leitung des Stromnetzes, Lastflussgrössen je Trafo des Stromnetzes und Spannungsgrössen je Netzknoten und Sammelschiene. Für den Fall, dass das Stromnetz gemäss Fig. 1 hinsichtlich seiner Ausfallsicherheit bewertet werden soll, werden die Lastgrössen P111, P112und P113für die Leitungen 111, 112 und 113 erfasst, die Lastgrösse P12für den Trafo 12, sowie die Spannungsgrössen V141, V142, V131, V132, V133. Mit diesen Lastgrössen wird die Recheneinheit 7 gespeist. Ferner greift die Recheneinheit 7 auf Daten hinsichtlich der Netztopologie des Stromnetzes zum Ermitteln der Ausfallsicherheit zu, beispielsweise auf Daten einer Datenbank 5 oder eines sonstigen Speichers, sowie auf Informationen zu einem Betriebszustand von Elementen des Stromnetzes, beispielsweise aus einer Datenbank 6 oder einem sonstigen Speicher. 2 shows a system for computer-aided determination of the failure safety of a power grid according to an exemplary embodiment of the invention, for example of the power grid according to FIG. 1. The system includes a computing unit 7 for determining a value for the reliability of the power grid. Means 4 for detecting load variables for the relevant power grid receive these as input variables to the computing unit 7. These are in particular load flow variables per line of the power grid, load flow variables per transformer of the power grid and voltage variables per network node and busbar. 1, the load sizes P111, P112 and P113 for the lines 111, 112 and 113 are detected, the load size P12for the transformer 12, as well as the voltage variables V141, V142, V131, V132, V133. With these load variables, the arithmetic unit 7 is fed. Furthermore, the arithmetic unit 7 accesses data regarding the network topology of the power network for determining the reliability, for example, data of a database 5 or other memory, as well as information about an operating state of elements of the power network, for example, from a database 6 or other memory.

[0028] Die Recheneinheit 7, beispielsweise enthaltend einen Prozessor, ermittelt basierend auf den Eingangsgrössen einen Wert X, der die Ausfallsicherheit des Stromnetzes repräsentiert. Dieser Wert X wird an eine Einrichtung 8 geliefert, beispielsweise eine Anzeige, und wird dort ausgegeben bzw. angezeigt. Bevorzugt wird in der Recheneinheit 7 zudem der Ausfallsicherheitswert X mit einem Schwellwert S verglichen. Wird der Schwellwert S durch den Ausfallsicherheitswert X überschritten, so wird bevorzugt eine Warnung W an eine optische oder akustische Warneinrichtung 9 übermittelt und dort ausgegeben. The arithmetic unit 7, for example containing a processor, determined based on the input variables a value X, which represents the reliability of the power grid. This value X is supplied to a device 8, for example a display, and is output or displayed there. In addition, the fail-safe value X is preferably compared to a threshold value S in the arithmetic unit 7. If the threshold value S is exceeded by the fail-safe value X, a warning W is preferably transmitted to an optical or acoustic warning device 9 and output there.

[0029] Fig. 5 zeigt eine Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung. Die erfassten Lastgrössen werden gemäss dieser Tabelle wie folgt verarbeitet: Zeile 1: Die erfassten Lastgrössen («Belastung») je Leitung werden gemittelt zu einem Leitungsdurchschnittslastwert, welcher seinerseits normiert wird auf eine Leitungslastnorm («Ideal»), welcher beispielsweise den idealen gemittelten Lastfluss auf den Leitungen angibt. Gleiche Berechnung wird in Zeile 2 angestellt hinsichtlich der Lastgrössen von Trafos im Stromnetz. Hierbei wird im vorliegenden Beispiel hinsichtlich mehrerer verschiedener Trafospannungen unterschieden, die unterschiedliche ideale Trafolastnormen aufweisen. Aus den erfassten Lastgrössen für die Leitungen und die Trafos des Stromnetzes wird gemäss Zeile 3 die maximal im Stromnetz auftretende Lastgrösse als maximaler Lastwert ermittelt und normiert auf eine Maximallastnorm, und zur Ermittlung des Ausfallsicherheitswertes herangezogen, sofern der maximale Lastwert auch grösser ist als die Maximallastnorm. Gemäss Zeile 4 werden an Netzknoten erfasste Spannungen mit zugehörigen Spannungsgrenzen verglichen. Die Abweichungen werden gemittelt über alle Messpunkte und bezogen auf zugehörige Spannungsabweichungsnormen, welche sich unterscheiden je nach Spannungsebene. Alle oben stehenden Ermittlungen erfolgen vorzugsweise bei einem Stromnetz im Normalbetrieb, d.h. ohne Ausfall von einem oder mehreren seiner Elemente. Dies ist vorliegend durch den «n-1»-Betrieb für die Zeilen 1 bis 4 gekennzeichnet. Fig. 5 shows a table for explaining the method according to an embodiment of the invention. The recorded load quantities are processed according to this table as follows: Line 1: The recorded load values ("load") per line are averaged to a line average load value, which in turn is normalized to a line load standard ("ideal"), which, for example, the ideal averaged load flow indicates the lines. The same calculation is made in line 2 with regard to the load sizes of transformers in the power grid. In the present example, a distinction is made between several different transformer voltages, which have different ideal transformer load standards. From the recorded load variables for the lines and the transformers of the power grid, the maximum occurring in the power grid load size is determined as maximum load and normalized to a maximum load standard, and used to determine the fail-safe value, provided that the maximum load value is greater than the maximum load standard. According to line 4, voltages detected at network nodes are compared with associated voltage limits. The deviations are averaged over all measuring points and related voltage deviation norms, which differ depending on the voltage level. All the above investigations are preferably carried out on a power grid in normal operation, i. without failure of one or more of its elements. In the present case, this is indicated by the "n-1" operation for lines 1 to 4.

[0030] In den Zeilen 5 bis 7 erfolgen Berechnungen, denen ein «n-0»-Betrieb zugrunde gelegt ist, d.h. es ist bereits ein Element des Stromnetzes ausgefallen. Hier wird nun gemäss Zeile 5 in dieser Betriebsart – unter der Annahme, dass das Stromnetz n Elemente aufweist – die Lastgrössen der verbleibenden n-1 Elemente ermittelt, basierend auf den Lastgrössen für den Normalbetrieb. Diese «Ausfall»-Lastgrössen werden gemittelt. Diese Berechnungen werden vorzugsweise mittels einer Simulation des Stromnetzes angestellt, welche Simulation die zugehörigen «Ausfall»-Lastgrössen berechnet. Im Folgenden wird ein Gesamtdurchschnittslastwert über alle zuvor berechneten Durchschnittslastwertes gebildet, der wiederum auf eine Gesamtdurchschnittslastnorm bezogen wird und nur in die Berechnung des Ausfallsicherheitswertes eingeht für den Fall, dass der Gesamtdurchschnittslastwert grösser als die Gesamtdurchschnittslastnorm, d.h. der Idealwert ist. Aus den ermittelten Lastgrössen für den «n-0»-Betrieb wird über alle Ausfall-Varianten die grösste Lastgrösse als maximaler Ausfall-Lastwert ermittelt und auf eine Ausfall-Maximallastnorm normiert, der nur in die Berechnung des Ausfallsicherheitswertes eingeht für den Fall, dass der maximale Ausfall-Lastwert grösser ist als die Ausfall-Maximallastnorm, d.h. der Idealwert, siehe Zeile 6. Schliesslich wird in Zeile 7 noch eine minimale Abweichung ermittelt, und zwar aus allen für die verschiedenen Ausfall-Varianten berechneten Spannungswerte an den Netzknoten bezüglich zugeordneter Spannungsgrenzen. Diese minimale Spannungsabweichung wird auf Minimal-Spannungsabweichungsnormen normiert je nach Spannungsebene. In lines 5 to 7, calculations are made based on an "n-0" operation, i. it has already failed an element of the power grid. Here, according to line 5 in this mode - assuming that the power grid has n elements - the load sizes of the remaining n-1 elements determined based on the load sizes for normal operation. These «failure» load sizes are averaged. These calculations are preferably made by means of a simulation of the power grid, which simulation calculates the associated «failure» load sizes. Hereinafter, a total average load value is formed over all the previously calculated average load value, which in turn is related to an overall average load standard and is included only in the calculation of the fail-safe value in the case where the total average load value exceeds the overall average load standard, i. the ideal value is. From the determined load variables for "n-0" operation, the largest load size is determined as the maximum failure load value for all failure variants and normalized to a failure maximum load standard, which is only included in the calculation of the fail-safe value for the case maximum failure load value is greater than the failure maximum load standard, ie the ideal value, see line 6. Finally, a minimal deviation is determined in line 7, namely from all voltage values calculated at the network nodes for the different failure variants with respect to assigned voltage limits. This minimum voltage deviation is normalized to minimum voltage deviation norms depending on the voltage level.

[0031] Vorzugsweise werden die so einzeln (je Zeile) ermittelten Werte – auch Indikatoren genannt – gewichtet und addiert zu einer Zwischengrösse, dem sogenannten Lastflussparameter. Dieser Lastflussparameter wird dann gewichtet mit 1/3 und addiert zu weiteren gewichteten Parametern. Preferably, the values determined individually (per line) - also called indicators - are weighted and added to an intermediate variable, the so-called load flow parameter. This load flow parameter is then weighted 1/3 and added to other weighted parameters.

[0032] Generell, und unabhängig von dem vorliegenden Ausführungsbeispiel werden last- und spannungsgrössenabhängige Kennzahlen ermittelt, zueinander relativiert durch Normierung, gewichtet, dann vorzugsweise aufaddiert, wiederum gewichtet, und addiert zu weiteren ihrerseits gewichteten Parametern betreffend die Topologie und vorzugsweise den Betriebszustand des Stromnetzes. In general, and independent of the present embodiment, load and voltage magnitude-dependent ratios are determined, relative to each other by normalization, weighted, then preferably added, again weighted, and added to other in turn weighted parameters concerning the topology and preferably the operating state of the power grid.

[0033] Fig. 6 zeigt eine Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung für die Ermittlung eines Netztopologieparameters, der gewichtet in den Ausfallsicherheitswert eingeht neben zumindest dem gewichteten Lastflussparameterwert. Zur Ermittlung des Netztopolgieparameters werden die von Verbrauchern abgenommenen Lasten in MW erfasst, beispielsweise durch Messung oder durch die Verwendung bekannter Werte, beispielsweise aus der Vergangenheit. Gemäss Zeile 1 wird dann berechnet, wie viele Megawatt an Leistungsverbrauch über «n-1»-sichere Netzknoten versorgt werden, die also gemäss der Definition von «n-1»-sicher auch noch versorgt werden trotz Ausfalls eines einzigen Elements im Stromnetz. Ein «n-1»-sicheres Netz mit «n-1»-sicheren Netzknoten wird beispielhaft in Fig. 3b ) skizziert: Bei Ausfall irgendeines Elements, beispielhaft einer Leitung zwischen zwei Netzknoten, kann ein «n-1»-sicherer Netzknoten wie etwa der doppelt eingekreiste Netzknoten dennoch über einen jeweils anderen Leitungspfad erreicht werden. Fig. 6 shows a table for explaining the method according to an embodiment of the invention for the determination of a network topology parameter, which weighted enters the fail-safe value in addition to at least the weighted load flow parameter value. In order to determine the network policy parameter, the loads taken by consumers are recorded in MW, for example by measurement or by the use of known values, for example from the past. According to line 1, it is then calculated how many megawatts of power consumption are supplied via "n-1" -safe network nodes, which are thus also supplied according to the definition of "n-1" - despite the failure of a single element in the power grid. An "n-1" secure network with "n-1" secure network nodes is exemplified in Fig. 3b): In case of failure of any element, for example a line between two network nodes, an "n-1" secure network node such as about the doubly circled network node can still be achieved via a respective different line path.

[0034] Gemäss Zeile 2 von Fig. 6 wird berechnet, wie viele Megawatt an Leistung über «n-0»-sichere Netzknoten versorgt werden, d.h. wie viele Megawatt an Leistung nicht durch redundante Vorkehrungen im Stromnetz gegen den Ausfall eines Elements abgesichert sind. Ein «n-0»-sicheres Netz mit «n-0»-sicheren Knoten wird beispielhaft in Fig. 3a ) skizziert: Bei Ausfall irgendeines Elements, beispielhaft einer Leitung zwischen zwei Netzknoten, kann ein «n-0»-sicherer Netzknoten wie etwa der doppelt eingekreiste Netzknoten nicht mehr erreicht werden. According to line 2 of Fig. 6, it is calculated how many megawatts of power are supplied via "n-0" secure network nodes, i. How many megawatts of power are not protected by redundant provisions in the power grid against the failure of an element. An "n-0" secure network with "n-0" secure nodes is exemplified in Fig. 3a): In case of failure of any element, for example a line between two network nodes, an "n-0" secure network node such as about the double circled network node can not be reached.

[0035] Als Idealwert für beide Betrachtungen aus den Zeilen 1 und 2 von Fig. 6 dienen 0 MW, da ein «n-2»-abgesichertes Netz ideal wäre sowohl gegenüber einem «n-0»-sicheren Netz als auch gegenüber einem «n-1»-sicheren Netz. 0 MW is the ideal value for both considerations from lines 1 and 2 of FIG. 6, since an "n-2" secured network would be ideal both for a "n-0" secure network and for a "n-0" secure network. n-1 »secure network.

[0036] Zeile 3 aus Tabelle 6 betrifft die nicht gelieferte Leistung, d.h. die nicht versorgten Verbraucher oder die nicht eingespeiste Erzeugungsleistung. Line 3 of Table 6 relates to the undelivered power, i. the consumers who are not supplied or the output that has not been fed in.

[0037] Gemäss Zeilen 4 bis 6 werden die Anzahl der Netzknoten im Stromnetz ermittelt, die «n-1»-sicher sind (Zeile 4), beziehungsweise die «n-0»-sicher sind (Zeile 5. In Zeile 6 sind die nicht versorgten Unterwerke UW (Netzknoten und Sammelschienen) aufgeführt. According to lines 4 to 6, the number of network nodes are determined in the power grid, the "n-1" are safe (line 4), or the "n-0" are safe (line 5. In line 6 are the unsupported substations UW (network nodes and busbars).

[0038] Ferner wird gemäss Zeilen 7 bis 10 das Schaltanlagenlayout berücksichtigt. Wie bereits offenbart können Schaltanlagen in Netzknoten von unterschiedlicher technischer Ausbildung sein und damit unterschiedliche Redundanz und damit Sicherheit bieten. So werden vorliegend als Schaltanlagenklassen eine Doppelsammelschiene mit Kuppelfeld mit Längstrennung, eine Doppelsammelschiene mit Kuppelfeld ohne Längstrennung, siehe auch Fig. 3d ) als Beispiel hierfür, eine Doppelsammelschiene ohne Kuppelfeld und ohne Längstrennung geführt, wie auch eine Einzelsammelschiene mit Längstrennung, als auch eine Einzelsammelschiene ohne Längstrennung, siehe auch Fig. 3e . Hier können auch weitere oder andere Schaltanlagenklassen geführt werden. Es wird die Anzahl von Schaltanlagen je Schaltanlagenklasse ermittelt und geht als Differenz zum Idealwert in die Ermittlung des Ausfallsicherheitswertes ein. Further, according to lines 7 to 10, the switchgear layout is taken into account. As already disclosed, switchgear can be in network nodes of different technical training and thus provide different redundancy and thus security. Thus, in the present case as switchgear classes a double busbar with dome with longitudinal separation, a double busbar with dome without longitudinal separation, see also Fig. 3d) as an example, a double busbar without dome and without longitudinal separation out, as well as a single busbar with longitudinal separation, as well as a single busbar without Longitudinal separation, see also Fig. 3e. Here also other or other switchgear classes can be led. The number of switchgear units per switchgear class is determined and entered as difference to the ideal value in the determination of the fail-safe value.

[0039] Vorzugsweise werden die so einzeln (je Zeile) ermittelten Werte addiert zu einer Zwischengrösse, dem sogenannten topologischen Parameter. Dieser topologische Parameter wird dann gewichtet mit 1/3 und addiert zu weiteren gewichteten Parametern, die anhand der Fig. 4 und 5 erläutert werden. Preferably, the values thus determined individually (per line) are added to an intermediate variable, the so-called topological parameter. This topological parameter is then weighted by 1/3 and added to further weighted parameters, which are explained with reference to FIGS. 4 and 5.

[0040] Fig. 4 zeigt eine Tabelle zur Erläuterung des Verfahrens gemäss einem Ausführungsbeispiel der Erfindung für die Ermittlung eines Zustandsparameters für das Stromnetz, der gewichtet vorzugsweise in den Ausfallsicherheitswert eingeht neben dem gewichteten Lastflussparameterwert und dem gewichteten topologischen Parameter. Zur Ermittlung des Zustandsparameters des Stromnetzes wird auf den Zustand der einzelnen Netzelemente und damit der Ausfallwahrscheinlichkeit einzelner Netzelemente zugegriffen. Netzelemente sind typischerweise Leitungen, Schaltanlagen und Trafos, deren Zustand wiederum aus den Zuständen der einzelnen Komponenten aggregiert werden kann, wie im Beispiel gemäss Fig. 4 für Leitungen aus den Zuständen der Tragwerke (Mast und Mastfundament), der Isolatorenketten und der Beseilungen. Grundsätzlich fliessen in die Erhebung diejenigen Zustandsgrössen ein, aus welchen sich die Ausfallwahrscheinlichkeit näherungsweise ableiten lässt, wie Alter, Inspektionsergebnisse, aber auch Ausfalldauer im Eintretensfall, wie Ersatzteilverfügbarkeit. Fig. 4 shows a table for explaining the method according to an embodiment of the invention for the determination of a state parameter for the power grid, which is weighted preferably received in the fail-safe value in addition to the weighted load flow parameter value and the weighted topological parameter. To determine the state parameter of the power grid, the state of the individual network elements and thus the probability of failure of individual network elements are accessed. Network elements are typically lines, switchgear and transformers, the state of which in turn can be aggregated from the states of the individual components, as in the example according to FIG. 4 for lines from the states of the structures (mast and mast foundation), the insulator chains and the Beseilungen. In principle, the variables of state which influence the probability of default, such as age, inspection results, but also the duration of emergencies, such as spare parts availability, are included in the survey.

[0041] Vorzugsweise werden die so einzeln (je Zeile) ermittelten Werte addiert zu einer Zwischengrösse, dem sogenannten Zustandsparameter. Dieser Zustandsparameter wird dann gewichtet mit 1/3 und addiert zu weiteren gewichteten Parametern, die anhand der Fig. 5 und 6 erläutert werden. Preferably, the values determined individually (per line) are added to an intermediate variable, the so-called state parameter. This state parameter is then weighted by 1/3 and added to other weighted parameters, which will be explained with reference to FIGS. 5 and 6.

[0042] Fig. 7 zeigt ein Diagramm darstellend ein Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes gemäss einem Ausführungsbeispiel der Erfindung. In Schritt S1 werden die Lastflüsse als Lastgrössen erfasst und Daten zur Netztopologie und zum Zustand von Elementen des Netzes abgegriffen. Im Schritt S2 werden abhängig von den erfassten Lastgrössen und den bereitgestellten Daten zunächst einzelne Indikatoren für die Bewertung der Ausfallsicherheit ermittelt, beispielsweise als Resultate je Zeile der Tabellen aus den Fig. 4 bis 6 . Schliesslich werden in Schritt S22 diese Indikatoren gewichtet und aufsummiert zu den Parametern Lastfluss, Topologie und Betrieb, bevor diese wiederum gewichtet und dann addiert werden zum Ausfallsicherheitswert X in Schritt S3. Fig. 7 shows a diagram representing a method for computer-aided determination of the reliability of a power grid according to an embodiment of the invention. In step S1, the load flows are detected as load variables and data on the network topology and the status of elements of the network are tapped. In step S2, depending on the recorded load variables and the data provided, first individual indicators for evaluating the reliability are determined, for example as results per row of the tables from FIGS. 4 to 6. Finally, in step S22, these indicators are weighted and added up to the parameters load flow, topology and operation, before these are again weighted and then added to the failsafe value X in step S3.

[0043] Es ist darauf hinzuweisen, dass nicht alle Indikatoren aus den Tabellen 4 bis 6 stets Eingang in die Ermittlung des Ausfallsicherheitswertes finden müssen. It should be noted that not all indicators from Tables 4 to 6 must always be included in the calculation of the resilience value.

[0044] Während in der vorliegenden Anmeldung bevorzugte Ausführungen der Erfindung beschrieben sind, ist klar darauf hinzuweisen, dass die Erfindung nicht auf diese beschränkt ist und in auch anderer Weise innerhalb des Umfangs der folgenden Ansprüche ausgeführt werden kann. While preferred embodiments of the invention are described in the present application, it should be clearly understood that the invention is not limited to these and may be practiced otherwise within the scope of the following claims.

Claims (10)

1. Verfahren zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes (1), enthaltend die Schritte Erfassen von Lastgrössen (P) für das betreffende Stromnetz (1), Ermitteln eines Wertes (X) für die Ausfallsicherheit in Abhängigkeit von zumindest den erfassten Lastgrössen (P) und einer Netztopologie des Stromnetzes (1), und Ausgeben des Ausfallsicherheitswertes (X).1. A method for computer-aided determination of the reliability of a power grid (1), comprising the steps Detecting load variables (P) for the relevant power grid (1), Determining a value (X) for the failure safety as a function of at least the recorded load variables (P) and a network topology of the power grid (1), and Output of the fail-safe value (X). 2. Verfahren nach Anspruch 1, enthaltend Anzeigen des Ausfallsicherheitswertes (X) auf einem Anzeigegerät (8), und insbesondere Ausgeben einer Warnung (W) auf einer optischen oder akustischen Einheit (9) bei Überschreiten eines Schwellwerts (S) durch den Ausfallsicherheitswert (X).2. The method of claim 1, comprising displaying the fail-safe value (X) on a display device (8), and in particular, issuing a warning (W) on an optical or acoustic unit (9) when a threshold value (S) is exceeded by the fail-safe value (X). 3. Verfahren nach Anspruch 1 oder Anspruch 2, bei dem das Erfassen der Lastgrössen (P) das Erfassen von Lastgrössen für einzelne Elemente (11, 12) des Stromnetzes (1) umfasst, und insbesondere bei dem das Stromnetz (1) Leitungen (11) und Trafos (12) als Elemente (11, 12) enthält und das Erfassen der Lastgrössen (P) umfasst: – Erfassen mindestens einer Lastgrösse (P11) j e Leitung (11), – Erfassen mindestens einer Lastgrösse (P12) ’ je Trafo (12).3. The method of claim 1 or claim 2, wherein detecting the load quantities (P) the Detecting load quantities for individual elements (11, 12) of the power network (1), and in particular in which the power network (1) contains lines (11) and transformers (12) as elements (11, 12) and the detection of the load variables (P) comprises: Detecting at least one load variable (P11) j e line (11), - Detecting at least one load variable (P12) 'per transformer (12). 4. Verfahren nach Anspruch 3, bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit umfasst: – Bilden eines Durchschnittslastwertes über die für die Leitungen (11) erfassten Lastgrössen (P11), – Normieren des Leitungsdurchschnittslastwertes auf eine Leitungslastnorm; – Bilden eines Durchschnittswertes über die für die Trafos (12) erfassten Lastgrössen (P12), – Normieren des Trafodurchschnittslastwertes auf eine Trafolastnorm, und vorzugsweise bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit zusätzlich umfasst: – Ermitteln eines maximalen Lastwertes aus den erfassten Lastgrössen (P11, P12) für die Leitungen (11) und den erfassten Lastgrössen (P12) für die Trafos (12), – Normieren des maximalen Lastwertes auf eine Maximallastnorm, und vorzugsweise bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit vorzugsweise zusätzlich umfasst: – Bilden einer durchschnittlichen Abweichung von zulässigen Grenzwerten von für das Stromnetz (1) erfassten Spannungsgrössen, – Normieren der durchschnittlichen Spannungsabweichung auf eine Spannungsabweichungsnorm.4. The method according to claim 3, where determining the value (X) for failover comprises: Forming an average load value over the load quantities (P11) detected for the lines (11), - normalizing the line average load value to a line load standard; Forming an average value over the load variables (P12) detected for the transformers (12), - normalizing the transformer average load value to a transformer load standard, and preferably wherein determining the value (X) for fail-safety additionally comprises: Determining a maximum load value from the detected load variables (P11, P12) for the lines (11) and the detected load variables (P12) for the transformers (12), - normalizing the maximum load value to a maximum load standard, and preferably in which the determination of the value (X) for the failure safety preferably additionally comprises: Forming an average deviation from permissible limits of voltage values detected for the power grid (1), - Normalizing the average voltage deviation to a voltage deviation standard. 5. Verfahren nach Anspruch 3 oder Anspruch 4, bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit weiter umfasst, basierend auf den erfassten Lastgrössen (P), und für jedes Element i aus 1 bis n Elementen (11, 12) des Stromnetzes (1): – bei Ausfall eines Elements i Ermitteln von Lastgrössen (P) für die anderen n-1 Elemente im Stromnetz (1), – Bilden eines Durchschnittslastwertes über die für die anderen n-1 Elemente erfassten Lastgrössen, bei dem ein Gesamtdurchschnittslastwert über alle gebildeten Durchschnittslastwerte gebildet wird, und bei dem vorzugsweise – der Gesamtdurchschnittslastwert normiert wird auf eine Gesamtdurchschnittslastnorm, – ein maximaler Lastwert aus den ermittelten Lastgrössen bei Ausfall irgendeines Elements i ermittelt wird, – der maximale Ausfall-Lastwert auf eine Ausfall-Maximallastnorm normiert wird; – eine minimale Abweichung von zulässigen Grenzwerten ermittelt wird von für das Stromnetz (1) ermittelten Spannungsgrössen bei Ausfall irgendeines der Elemente; – die minimale Spannungsabweichung auf eine Minimal-Spannungsabweichungsnorm normiert wird.5. A method according to claim 3 or claim 4, wherein determining the value (X) for fail-safe further comprises, based on the detected load quantities (P), and for each element i from 1 to n elements (11, 12) of Electricity network (1): - if one element fails, i determining load variables (P) for the other n-1 elements in the power grid (1), Forming an average load value over the load sizes detected for the other n-1 elements, in which a total average load value is formed over all average load values formed, and preferably - the total average load value is normalized to an overall average load standard, A maximum load value is determined from the determined load variables in case of failure of any element i, - the maximum failure load value is normalized to a failure maximum load standard; A minimum deviation from permissible limit values is determined by voltage quantities determined for the power grid (1) in the event of failure of any of the elements; - the minimum voltage deviation is normalized to a minimum voltage deviation standard. 6. Verfahren nach einem der vorhergehenden Ansprüche, bei dem das Erfassen der Lastgrössen das Erfassen von Lastgrössen für an das Stromnetz (1) angeschlossene Verbraucher (3) und in das Stromnetz (1) einspeisende Produzenten (2) umfasst, bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit umfasst: – Ermitteln einer Gesamtlast aller Verbraucher (3), die trotz eines Ausfalls eines Elements (11, 12) des Stromnetzes (1) versorgt bleiben; – Ermitteln einer Gesamtlast aller Verbrauchern, die bei einem Ausfall eines Elements (11, 12) des Stromnetzes (1) unversorgt bleiben; – Ermitteln einer nicht gelieferten Leistung bei Ausfall eines Elements (2).6. The method according to any one of the preceding claims, in which the detection of the load variables comprises the detection of load variables for consumers (3) connected to the power grid (1) and producers (2) feeding into the power grid (1), where determining the value (X) for failover comprises: - Determining a total load of all consumers (3), which remain supplied despite a failure of an element (11, 12) of the power grid (1); - Determining a total load of all consumers who remain unprovided in case of failure of an element (11, 12) of the power grid (1); - Determining an undelivered power in case of failure of an element (2). 7. Verfahren nach Anspruch 6, bei dem das Ermitteln des Wertes (X) für die Ausfallsicherheit umfasst: – Ermitteln einer Anzahl von Netzknoten (13) im Stromnetz (1), die trotz eines Ausfalls eines Elements (11, 12) des Stromnetzes (1) versorgt bleiben; – Ermitteln einer Anzahl von Netzknoten (13), die bei einem Ausfall eines Elements (11, 12) des Stromnetzes (1) unversorgt bleiben; – Klassifizieren von Schaltanlagen von Netzknoten (13) in Schaltanlagenklassen und Ermitteln der Anzahl von Schaltanlagen im Stromnetz je Schaltanlagenklasse.7. The method according to claim 6, where determining the value (X) for failover comprises: - Determining a number of network nodes (13) in the power grid (1), which remain powered despite a failure of an element (11, 12) of the power grid (1); - determining a number of network nodes (13) which remain unprovided in the event of a failure of an element (11, 12) of the power network (1); - Classifying switchgear of network nodes (13) in switchgear classes and determining the number of switchgears in the power grid per switchgear class. 8. Verfahren nach einem der vorhergehenden Ansprüche, enthaltend Ermitteln des Ausfallsicherheitswertes (X) zusätzlich in Abhängigkeit von einem Betriebszustand von Elementen (11, 12) des Stromnetzes (1).8. The method according to any one of the preceding claims, comprising Determining the fail-safe value (X) additionally in dependence on an operating state of elements (11, 12) of the power grid (1). 9. Computerprogrammelement, enthaltend Computerprogrammcode zur Durchführung des Verfahrens nach einem der vorhergehenden Ansprüche bei Ausführung des Computerprogrammelements auf einem Prozessor.9. Computer program element containing computer program code for carrying out the method according to one of the preceding claims when the computer program element is executed on a processor. 10. System zum computergestützten Ermitteln der Ausfallsicherheit eines Stromnetzes, enthaltend Mittel (4) zum Erfassen von Lastgrössen (P) für das betreffende Stromnetz (1), eine Recheneinheit (7) zum Ermitteln eines Wertes (X) für die Ausfallsicherheit des Stromnetzes (1) in Abhängigkeit von zumindest den erfassten Lastgrössen (P) und einer Netztopologie des Stromnetzes (1), und eine Einrichtung (8) zum Ausgeben des Ausfallsicherheitswertes (X).10. System for computer-aided determination of the reliability of a power network, comprising Means (4) for detecting load variables (P) for the relevant power grid (1), a computing unit (7) for determining a value (X) for the reliability of the power grid (1) as a function of at least the detected load variables (P) and a network topology of the power grid (1), and means (8) for outputting the fail-safe value (X).
CH01109/15A 2015-07-30 2015-07-30 Reliability of power grids. CH711365B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CH01109/15A CH711365B1 (en) 2015-07-30 2015-07-30 Reliability of power grids.
DE102016211275.9A DE102016211275A1 (en) 2015-07-30 2016-06-23 Resilience of power grids

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH01109/15A CH711365B1 (en) 2015-07-30 2015-07-30 Reliability of power grids.

Publications (2)

Publication Number Publication Date
CH711365A2 true CH711365A2 (en) 2017-01-31
CH711365B1 CH711365B1 (en) 2020-06-15

Family

ID=57795655

Family Applications (1)

Application Number Title Priority Date Filing Date
CH01109/15A CH711365B1 (en) 2015-07-30 2015-07-30 Reliability of power grids.

Country Status (2)

Country Link
CH (1) CH711365B1 (en)
DE (1) DE102016211275A1 (en)

Also Published As

Publication number Publication date
CH711365B1 (en) 2020-06-15
DE102016211275A1 (en) 2017-02-02

Similar Documents

Publication Publication Date Title
EP2845286B1 (en) Fault detection in energy supply networks
EP3107174B1 (en) Method, control device and system for operating a sub- network of an energy supply network
EP2697888B1 (en) Method for determining the topology of a low-voltage distribution grid
EP3336995B1 (en) Method, control device and system for determining state values for describing operating states in a subnetwork of an energy supply network
EP3540911B1 (en) Method for operating an electrical power supply network and control unit for controlling devices in an electrical distribution network
DE112014002933T5 (en) Converter station power setpoint analysis system and method
DE102012105184A1 (en) System, method and apparatus for operating an energy distribution system
EP2143185A1 (en) Method and device for capturing a fault in an electrical supply grid
EP3355073B1 (en) Generation of patterns for the identification of errors in electric power grids
DE102014115119A1 (en) Method and system for monitoring a mains voltage in a low voltage network
EP2748907B1 (en) Method for ascertaining parameters for power supply systems, and system for carrying out the method
EP2978096B1 (en) Method, system and computer program product for controlling and/or regulating an electric energy system
WO2013149899A1 (en) Method for determining measuring points in low-voltage networks, and network management subsystem for carrying out the method
EP2388602B1 (en) Method for diagnosing contacts of a photovoltaic assembly and device
CH711365A2 (en) Failure safety of power networks.
EP3667851B1 (en) Creation of dynamic models of network nodes in a low and / or medium voltage distribution network by use of a self learning algorithm
EP2618458B1 (en) Method for determining circuit states in energy supply networks and system for performing the method
EP3376622A1 (en) Method, system and protection device for producing an error signal indicating a fault type of a fault in a polyphase electrical power supply
EP2664939B1 (en) Method for validating measurements of multiple measurement channels which depend on the position of the sun
DE102018113627B4 (en) Method and device for fault diagnosis in an electrical network having a ring structure, and computer program product
DE102016112005A1 (en) Method for designing the network protection of a low-voltage electrical supply network
DE102023203985B3 (en) Method for generating input data for a state estimation of a power grid, state estimation and control of a power grid
EP3621169A1 (en) Isolated network and method for operating same
DE112018007008T5 (en) Monitoring device and determination method
DE102020206672A1 (en) Low-voltage distribution network, electricity network, method for operating a low-voltage distribution network