AU2010273768B2 - System and method for intermittent gas lift - Google Patents

System and method for intermittent gas lift Download PDF

Info

Publication number
AU2010273768B2
AU2010273768B2 AU2010273768A AU2010273768A AU2010273768B2 AU 2010273768 B2 AU2010273768 B2 AU 2010273768B2 AU 2010273768 A AU2010273768 A AU 2010273768A AU 2010273768 A AU2010273768 A AU 2010273768A AU 2010273768 B2 AU2010273768 B2 AU 2010273768B2
Authority
AU
Australia
Prior art keywords
string
gas
annulus
liquid
flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2010273768A
Other versions
AU2010273768A1 (en
Inventor
James Robert Brewer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shell Internationale Research Maatschappij BV
Original Assignee
Shell Internationale Research Maatschappij BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shell Internationale Research Maatschappij BV filed Critical Shell Internationale Research Maatschappij BV
Publication of AU2010273768A1 publication Critical patent/AU2010273768A1/en
Application granted granted Critical
Publication of AU2010273768B2 publication Critical patent/AU2010273768B2/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/12Methods or apparatus for controlling the flow of the obtained fluid to or in wells
    • E21B43/121Lifting well fluids
    • E21B43/122Gas lift

Landscapes

  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physical Or Chemical Processes And Apparatus (AREA)
  • Organic Low-Molecular-Weight Compounds And Preparation Thereof (AREA)
  • Pipe Accessories (AREA)
  • Feeding, Discharge, Calcimining, Fusing, And Gas-Generation Devices (AREA)

Abstract

A gas-lift apparatus and method for use in a well in which liquids accumulate in a liquid zone. The apparatus comprises a first string extending into the liquid zone and having upper and lower ends; a second string surrounding the first string and defining an annulus therewith, the second string extending a distance from the first string lower end such that the annulus has upper and lower ends, the annulus being closed at its upper and lower ends and defining a chamber, the chamber being in fluid communication with the inside of the first string; a check valve controlling the flow of liquid into from the wellbore into the lower end of said annulus; a gas valve allowing the flow of gas from the first string into the upper end of the chamber; and a valve for controlling the flow of gas into the upper end of said inner string.

Description

WO 2011/008522 PCT/US2010/040311 SYSTEM AND METHOD FOR INTERMITTENT GAS LIFT RELATED CASES The present application claims benefit of U.S. Application Serial No. 61/221,169, filed on 29 June 2009, which is incorporated herein by reference. FIELD OF THE INVENTION [0001] The present invention relates to a system and apparatus for removing water from a deep gas well. BACKGROUND OF THE INVENTION [0002] Hydrocarbon gas from subsurface earth formations is initially produced by the inherent formation pressure of the gas in the formation. Over time, however, water vapor in the gas stream condenses on the way to surface. As production rates decline, the velocity is no longer able to lift fluids to the surface. Water droplets coalesce, run down tubulars, and collect at the bottom of the wellbore. Eventually, the fluid level rises above the level of the well perforations. This increases bottom hole flowing pressure and restricts production. When this occurs, it is advantageous to remove the liquids from the well in order to increase the gas flow rate. [0003] Possible solutions to this problem include velocity strings, capillary string injecting foamers, and pumps to continuously or intermittently pump the water to the surface to remove the hydrostatic barrier that the water creates. [0004] A common practice is to use a plunger to intermittently lift the liquids. Referring briefly to Figures 1-2, in conventional techniques a system 10 is used that comprises a wellbore 12, gas lift tubing string 14, and an inner tubing string 16. Wellbore 12 may be cased. It will be understood that the Figures are not drawn to scale and that the total depth of the well may be several thousand feet. [0005] An annulus 22 is defined between the wellbore or casing and gas lift tubing string 14. A gas production valve 32, gas lift inlet valve 34, and gas lift outlet valve 36 control the flow of fluids at the upper ends of annulus 22, tubing string 14, and inner string 16, respectively. At the bottom of gas lift string 14, a standing valve 38 controls the flow of fluid into tubing string 14 through an opening 28. There is fluid communication between 2 the inside of tubing string 14 and the inside of inner string 16. One or more perforations 42 enhance the flow of fluids out of the formation and into the well bore. [0006] An optional slidable plunger 40 sealingly engages the inside of inner string 16. Plunger 40 is designed to allow fluids to flow up through or around the plunger and into inner string 16 until plunger 40 starts moving upward, whereupon plunger changes shape such that it forms a seal with the inside of inner string 16. For example, plunger 40 may comprise chevron type seals that allow the fluid to flow past in one direction, but tend to prevent fluid from flowing past in the other direction. [0007] In operation, gas coming out of the formation flows up annulus 22 and out through valve 32. As it does, water enters the well from the formation and/or condenses and falls to the bottom of the well. Without significant backpressure in gas lift tubing string 14, water collecting at the bottom of the well enters gas lift tubing string 14 through opening 28. [0008] At some point, it will be desirable to remove a portion of the collected water. This may occur when the water level rises to the level of the perforations (as shown in Figure 1 at 44), after a predetermined period of time, or when a predetermined amount of liquid has collected. At this point, gas lift inlet valve 34 is opened, increasing the pressure inside string 14 and forcing standing valve 38 closed, as shown in Figure 2. With standing valve 38 closed, lift gas is forced into inner string 16, advancing plunger 40 upward, along with a slug of accumulated fluids above and perhaps below it. This system will work with or without the plunger, providing there is a long enough water column. [0009] After the plunger reaches the surface, the lift gas vents until hydrostatic pressure at the bottom of the well is sufficient to open the standing valve and the cycle repeats. While fluids enter the tubing, the plunger falls back to bottom. [0010] One advantage of intermittent gas lift techniques is that they lift fluids without putting any backpressure on the formation. While useful in shallow wells, conventional intermittent gas lift techniques require produced gas to flow up the annulus. Flowing gas up the annulus is acceptable in shallow low pressure gas applications; however, issues such as high pressure, hydrogen sulfide, sulphur deposition, paraffin deposition, and local regulations may prohibit 3 flow up the annulus. Thus, there remains a need for an effective technique for removing water from deep gas wells. OBJECT OF THE INVENTION [0010a] It is an object of the present invention to substantially overcome or at least ameliorate one or more of the above disadvantages, or to at least provide a useful alternative. SUMMARY OF THE INVENTION [0011] In accordance with preferred embodiments of the invention a system and technique are provided for removing water from deep gas wells. [0012] In one aspect of the present disclosure, there is provided an intermittent gas-lift apparatus for use in a well that produces gas and liquid, in which liquids accumulate in a liquid zone in the wellbore, comprising: a first string for lifting liquid from the wellbore extending through the interior of a production string into the liquid zone and having an upper end and a lower end; a second string surrounding the first string and defining an annulus therewith, said second string extending a predetermined axial distance from the first string lower end such that said annulus has an upper end and a lower end, said annulus being closed at its upper and lower ends so as to define a chamber, said chamber being in fluid communication with the inside of said first string; a check valve controlling the flow of liquid into from the wellbore into the lower end of said annulus; a gas valve allowing the flow of gas from the first string into the upper end of the chamber; and a valve for controlling the flow of gas into the upper end of said first string. [0013] The first string may comprise coiled tubing and the second string may comprise production tubing. The system includes an optional plunger slidably disposed in the first string.
3a [0014] In another aspect of the present disclosure, there is provided a method for producing gas from a well that produces gas and liquid, in which liquids accumulate in a liquid zone in the wellbore, comprising the steps of: a) providing in the well an apparatus comprising: a first string for lifting liquid from the wellbore extending through the interior of a production string into the liquid zone and having an upper end and a lower end; a second string surrounding the first string and defining an annulus therewith, said second string extending a predetermined axial distance from the first string lower end such that said annulus has an upper end and a lower end, said annulus being closed at its upper and lower ends so as to define a chamber, said chamber being in fluid communication with the inside of said first string; a check valve controlling the flow of liquid into from the wellbore into the lower end of said annulus; a gas valve allowing the flow of gas from the first string into said chamber; and a valve for controlling the flow of gas through the upper end of said first string; b) allowing liquid to flow from the wellbore into the annulus; c) pumping gas into the annulus via the gas valve and preventing liquid from flowing out of the annulus until a desired pressure is reached; d) allowing gas to flow out of the annulus via the first string while preventing gas from flowing out of the annulus via the gas valve, such that the gas flowing out of the annulus propels a slug of liquid through the first string toward the surface.
WO 2011/008522 PCT/US2010/040311 BRIEF DESCRIPTION OF THE DRAWINGS [0015] For a more detailed understanding of the invention, reference is made to the accompanying wherein: [0016] Figures 1 and 2 are schematic illustrations of two modes of a prior art system; [0017] Figures 3 - 5 are schematic illustrations of three modes of a system constructed in accordance with an embodiment of the invention; and [0018] Figure 6 is a schematic illustration of a system constructed in accordance with an alternative embodiment of the invention. [0019] It will be understood that the Figures illustrate a system that is designed for use in a hydrocarbon production well. Positions of equipment are illustrated relative to the top of the well (the earth's surface) or the bottom of the well, but such illustration is schematic only. The Figures are not to scale and the distance between the top and bottom of the well may be several thousand feet. DETAILED DESCRIPTION OF A PREFERRED EMBODIMENT [0020] Referring now to Figures 3-5, a system 100 according to the preferred embodiments of the present invention is positioned in a wellbore 12. The system 100 includes a production string 114 and an inner string 116. Inner string 116 preferably but not necessarily comprises coiled tubing. At the surface, a production valve 124 controls the flow of fluids out of production string 114 and a lift gas inlet valve 126 and a lift gas vent valve 128 control the fluid into and out of, respectively, inner string 116. Lift gas is preferably provided to lift gas inlet valve 126 via a high pressure lift gas feed line (not shown). A packer 115 is preferably set at the bottom of production string 114 so as to isolate the portion of the annulus above that point. [0021] The system preferably includes a crossover 130 that is preferably located several thousand feet from the bottom of the hole. Below crossover 130, a concentric outer string 118 surrounds inner string 116, forming an annulus 117 therebetween. A gas check valve 144 is preferably disposed in the wall of inner string 116 near crossover 130. An unloading valve 146 is preferably disposed in the wall of outer string 118 near the bottom of string 118. A standing valve 129 controls the flow of fluids from the borehole into the bottom of outer string 118. One or more passageways 123 provide fluid communication between the inside of outer string 118 and the inside of inner string 116. 4 WO 2011/008522 PCT/US2010/040311 [0022] Referring now to Figure 3, during production, lift gas inlet valve 126 is normally closed and vent valve 128 is open. Water flows accumulates at the bottom of the wellbore and flows into the concentric tubing through standing valve 129, and produced gas flows out through production string 114, as indicated by arrow 145. [0023] Referring now to Figure 4, when it is desired to lift fluids, vent valve 128 closes and lift gas inlet valve 126 opens. This allows pressurized gas to flow down through inner string 116. Standing valve 129 closes as a result of the pressure differential between the inside of outer string 118 and the wellbore and gas check valve 144 allows high pressure lift gas to pass from the coiled tubing into annulus 117. Because the system is closed, the pressure inside inner string 116 and annulus 117 will rise until it reaches line pressure, i.e. the pressure in the high pressure lift gas feed line. [0024] Referring now to Figure 5, once the pressure inner string 116 and annulus 117 reaches line pressure, lift gas inlet valve 126 closes. Vent valve 128 opens, allowing gas inside the coiled tubing to flow back to the surface and decreasing the pressure in inner string 116. Check valve 144 prevents the pressurized gas in annulus 117 from flowing back into inner string 116, with the result that the pressurized gas trapped in annular space 117 expands toward the bottom of the well and up through inner string 116. As the expanding gas from annulus 117 flows up through inner string 116, it pushes a slug of liquid 150 ahead of it to the surface, thereby reducing the amount of liquid in the bottom of the well. After expelling slug 150, the lift gas continues to vent through valve 128 until the pressure inside the tubing equals the vent pressure. [0025] As liquid continues to accumulate at the bottom of the well, the hydrostatic pressure of liquid below standing valve 129 eventually becomes higher than the pressure inside concentric outer string 118, at which point standing valve 129 opens, allowing liquid to again enter concentric string 118 and the cycle repeats. [0026] If desired, valve 146 at the bottom of the concentric string may be included and used for initial unloading of downhole liquids. [0027] An advantage of the present invention is that produced gas is able to flow out of the formation and up though production string 114 without restriction throughout the entire lift cycle, as indicated by arrow 145. Standing valve 129 ensures that all lift gas is confined within the inner and outer tubing 116, 118. Thus, water can be removed from the well without changing the bottom hole flowing pressure. This is in contrast to conventional systems, which put additional backpressure on the formation during lift cycles or require 5 WO 2011/008522 PCT/US2010/040311 the well to be shut in in order to build up sufficient downhole pressure to intermittently lift fluids. With the present system, the well will continue to flow at normal rates with the normal bottom hole flowing pressure. [0028] A further advantage of the present system is that it does not require the installation of concentric tubing strings extending the full depth of the well. By contrast, the system shown in Figures 1 and 2 requires concentric tubing strings from the surface to the bottom of the well. For deep wells, the amount of gas required to be injected in order to perform a gas lift operation using the system of Figure 1 would be significant. In addition, by providing a chamber that extends to less than the full depth of the well, significant equipment cost savings may be realized. Still further, the present system avoids the need for a downhole pump or similar equipment. [0029] It is believed that the suitable pressures for application to annulus 117 during the pressurization portion of the cycle range between 400 psig and 1,400 psig, depending on the volume of water per lift, depth, and the axial length of annulus 117. The length of annulus 117 can be determined using the expected line pressure and the ratio of the annulus volume to the total tubing volume. In some embodiments, it may be desirable to design the system such that the ratio of the volume of the gas in the pressured annulus, when expanded to vent pressure, to the volume of inner string 116 is in the range of 5 to 15. [0030] As mentioned above, the Figures are not to scale. The distance between crossover 130 and the bottom of inner string 116 is likely to be several thousand feet. By way of example only, a 10,000' well might have a production string packer 115 at around 6,000', crossover 130 at 6,500', and the bottom of standing valve 129 at 9,990', with casing perforations in stages from 7,000' to 9,500'. Thus, the axial length of annulus 117 may, in various embodiments, be less than 75%, less than 67%, less than 50%, less than 40%, or even less than 25% of the total length of inner string 116. [0031] Not all wells are vertical. If, for example, the well is highly deviated, liquid in the well may accumulate in a liquid zone that is not at the remote end of the wellbore. It will be understood that references to a liquid accumulation zone include any such zone, regardless of whether it is at the end of the wellbore. [0032] In an alternative embodiment, the principles described above can be applied using a combination of a production tubing and an inner string instead of an inner string supporting an outer string on a crossover. Referring to Figure 6, such a system preferably includes a production string 214 and packer 115 as described above. Instead of a length of coiled 6 WO 2011/008522 PCT/US2010/040311 tubing, an inner tubing string 216 extends through the production string 214. Both inner tubing string 216 and production string 214 terminate near the bottom of the hole. An annulus 217 is defined between inner tubing string 216 and production string 214. The upper and lower ends of annulus 217 are preferably sealed by a packer 215 and a seating assembly 219, respectively. [0033] A standing valve 229 controls the flow of fluids into the bottom of inner string 216. Fluid passageways 222 through the wall of inner string 216 allow fluids to flow between annulus 217 and the inside of inner tubing string 216. Passageways 224 through the wall of production tubing 114 allow produced gas to flow from the wellbore into annulus 217. Thus, as in the embodiment described above, valve 229 controls the flow of fluids into annulus 217. [0034] The system illustrated in Figure 6 functions in the same manner as the system of Figure 3. Thus, pressurized gas is supplied to annulus 217 via inner tubing string 216 and the expansion of that gas is used to propel a slug of liquid up out of the well. An optional plunger (not shown) may be included within inner string 216 to keep lift gas from over riding the fluid. In some embodiments, standing valve 129 and gas valve 244 can be maintained with wireline. [0035] In yet another embodiment (not shown), an intermediate-diameter conventional tubing string may be hung from a flow-through tubing hanger disposed between the production tubing and an inner string. The inner string may comprise coiled tubing or conventional tubing. A seal is provided between the intermediate string and the inner string so that the annulus therebetween can receive and contain the pressurized gas. Once the annulus has reached line pressure, the pressure in the inner string is released, the check valve closes to prevent backflow, and the gas in the annulus expands, propelling a slug of liquid upward. [0036] In each of the embodiments disclosed herein, it will be understood that the upper and lower ends of the inner and outer string, the annulus, and the standing valve could be configured differently, so long as a chamber is defined and liquids can flow into the chamber, gas can be pumped into the chamber, and the expanding gas can be used to propel a slug of liquid from the chamber to the surface or a predetermined outflow point. 7

Claims (11)

1. An intermittent gas-lift apparatus for use in a well that produces gas and liquid, in which liquids accumulate in a liquid zone in the wellbore, comprising: a first string for lifting liquid from the wellbore extending through the interior of a production string into the liquid zone and having an upper end and a lower end; a second string surrounding the first string and defining an annulus therewith, said second string extending a predetermined axial distance from the first string lower end such that said annulus has an upper end and a lower end, said annulus being closed at its upper and lower ends so as to define a chamber, said chamber being in fluid communication with the inside of said first string; a check valve controlling the flow of liquid into from the wellbore into the lower end of said annulus; a gas valve allowing the flow of gas from the first string into the upper end of the chamber; and a valve for controlling the flow of gas into the upper end of said first string.
2. The apparatus according to claim 1, wherein the axial length of said annulus is less than 50% of the length of said first string.
3. The apparatus according to claim 1, wherein the first string comprises coiled tubing and is configured to lift slugs of liquid to the surface, thereby reducing the amount of liquid in the liquid zone.
4. The apparatus according to claim 1, wherein the apparatus further comprises a passageway which permits produced gas to flow out of the formation and up though production string without restriction throughout the entire lift cycle, as indicated by arrow.
5. The apparatus according to claim 1, further including a plunger slidably disposed in said first string.
6. A method for producing gas from a well that produces gas and liquid, in which liquids accumulate in a liquid zone in the wellbore, comprising the steps of: a) providing in the well an apparatus comprising: 9 a first string for lifting liquid from the wellbore extending through the interior of a production string into the liquid zone and having an upper end and a lower end; a second string surrounding the first string and defining an annulus therewith, said second string extending a predetermined axial distance from the first string lower end such that said annulus has an upper end and a lower end, said annulus being closed at its upper and lower ends so as to define a chamber, said chamber being in fluid communication with the inside of said first string; a check valve controlling the flow of liquid into from the wellbore into the lower end of said annulus; a gas valve allowing the flow of gas from the first string into said chamber; and a valve for controlling the flow of gas through the upper end of said first string; b) allowing liquid to flow from the wellbore into the annulus; c) pumping gas into the annulus via the gas valve and preventing liquid from flowing out of the annulus until a desired pressure is reached; d) allowing gas to flow out of the annulus via the first string while preventing gas from flowing out of the annulus via the gas valve, such that the gas flowing out of the annulus propels a slug of liquid through the first string toward the surface.
7. The method according to claim 6, wherein the axial length of the annulus is less than 50% of the length of the first string.
8. The method according to claim 6, wherein the first string comprises coiled tubing.
9. The method according to claim 6, wherein a passageway permits produced gas to flow out of the formation and up though production string without restriction throughout the entire lift cycle, as indicated by arrow.
10. The method according to claim 6, wherein the first string includes a plunger slidably disposed therein. 10
11. An intermittent gas-lift apparatus for use in a well that produces gas and liquid, in which liquids accumulate in a liquid zone in the wellbore, the apparatus substantially as hereinbefore described with reference to Figures 3 to 5; or 6 of the accompanying drawings. Shell Internationale Research Maatschappij B.V. Patent Attorneys for the Applicant/Nominated Person SPRUSON & FERGUSON
AU2010273768A 2009-06-29 2010-06-29 System and method for intermittent gas lift Ceased AU2010273768B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US22116909P 2009-06-29 2009-06-29
US61/221,169 2009-06-29
PCT/US2010/040311 WO2011008522A2 (en) 2009-06-29 2010-06-29 System and method for intermittent gas lift

Publications (2)

Publication Number Publication Date
AU2010273768A1 AU2010273768A1 (en) 2012-02-09
AU2010273768B2 true AU2010273768B2 (en) 2014-06-05

Family

ID=43450081

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2010273768A Ceased AU2010273768B2 (en) 2009-06-29 2010-06-29 System and method for intermittent gas lift

Country Status (8)

Country Link
US (1) US20120125625A1 (en)
EP (1) EP2449209A4 (en)
CN (1) CN102472089A (en)
AU (1) AU2010273768B2 (en)
BR (1) BRPI1011900A2 (en)
CA (1) CA2766786A1 (en)
WO (1) WO2011008522A2 (en)
ZA (1) ZA201200156B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747993B (en) * 2012-06-27 2015-01-28 中国石油大学(华东) Liquid foaming agent injection method
CN105358831A (en) * 2013-05-28 2016-02-24 利夫特克国际股份有限公司 Downhole pumping apparatus and method
US9725995B2 (en) * 2013-06-11 2017-08-08 Lufkin Industries, Llc Bottle chamber gas lift systems, apparatuses, and methods thereof
RU2671372C1 (en) * 2014-12-22 2018-10-30 Тоталь Са Device for removing liquids that accumulate in the well
WO2016156187A1 (en) * 2015-03-27 2016-10-06 Shell Internationale Research Maatschappij B.V. Method and system for operating a gas well
CN106592692A (en) * 2016-10-31 2017-04-26 北京建工环境修复股份有限公司 Underground fluid gas extraction device and process
CN107558962A (en) * 2017-07-21 2018-01-09 山西晋城无烟煤矿业集团有限责任公司 Concentric tube type batch-type gaslift drainage technology
CN109025911A (en) * 2018-08-23 2018-12-18 山西晋城无烟煤矿业集团有限责任公司 A kind of coal bed gas well gaslift draining reservoir protection device and water discharge method
CN112539047A (en) * 2020-12-22 2021-03-23 西安荣达石油工程有限公司 Process pipe column capable of protecting oil-gas layer and realizing efficient gas lift liquid drainage and process
CN116104456B (en) * 2023-04-14 2023-06-30 陕西航天德林科技集团有限公司 Drainage gas production system and drainage gas production method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4708595A (en) * 1984-08-10 1987-11-24 Chevron Research Company Intermittent oil well gas-lift apparatus
US5911278A (en) * 1997-06-20 1999-06-15 Reitz; Donald D. Calliope oil production system
US20040216886A1 (en) * 2003-05-01 2004-11-04 Rogers Jack R. Plunger enhanced chamber lift for well installations

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR9404096A (en) * 1994-10-14 1996-12-24 Petroleo Brasileiro Sa Method and apparatus for intermittent oil production with mechanical interface
US6672392B2 (en) * 2002-03-12 2004-01-06 Donald D. Reitz Gas recovery apparatus, method and cycle having a three chamber evacuation phase for improved natural gas production and down-hole liquid management
CN2639520Y (en) * 2003-08-15 2004-09-08 中国石油化工股份有限公司***分公司采油工程技术研究院 Deflector-type gas lift valve
US7766085B2 (en) * 2008-02-04 2010-08-03 Marathon Oil Company Apparatus, assembly and process for injecting fluid into a subterranean well

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4708595A (en) * 1984-08-10 1987-11-24 Chevron Research Company Intermittent oil well gas-lift apparatus
US5911278A (en) * 1997-06-20 1999-06-15 Reitz; Donald D. Calliope oil production system
US20040216886A1 (en) * 2003-05-01 2004-11-04 Rogers Jack R. Plunger enhanced chamber lift for well installations

Also Published As

Publication number Publication date
CA2766786A1 (en) 2011-01-20
EP2449209A4 (en) 2014-03-19
BRPI1011900A2 (en) 2017-06-27
EP2449209A2 (en) 2012-05-09
WO2011008522A2 (en) 2011-01-20
US20120125625A1 (en) 2012-05-24
WO2011008522A3 (en) 2011-03-31
ZA201200156B (en) 2012-09-26
CN102472089A (en) 2012-05-23
AU2010273768A1 (en) 2012-02-09

Similar Documents

Publication Publication Date Title
AU2010273768B2 (en) System and method for intermittent gas lift
US8006756B2 (en) Gas assisted downhole pump
CA2376701C (en) Gas recovery apparatus, method and cycle having a three chamber evacuation phase for improved natural gas production and down-hole liquid management
AU753037B2 (en) Method and apparatus for increasing fluid recovery from a subterranean formation
RU2551715C2 (en) Device for fluid streaming with pressure-dependent flow switching unit
US8997870B2 (en) Method and apparatus for separating downhole hydrocarbons from water
US20030141073A1 (en) Advanced gas injection method and apparatus liquid hydrocarbon recovery complex
RU2328590C1 (en) Separate maintenance process for injection or production well and implementation variants
US8316950B2 (en) Systems and methods for deliquifying a commingled well using natural well pressure
US8794305B2 (en) Method and apparatus for removing liquid from a horizontal well
US10337296B2 (en) Gas lift assembly
CA2775105C (en) Producing gas and liquid from below a permanent packer in a hydrocarbon well
US20170191355A1 (en) Two-step artificial lift system and method
US3482526A (en) Gas lift system
CA2485035C (en) Gas recovery apparatus, method and cycle having a three chamber evacuation phase and two liquid extraction phases for improved natural gas production
RU2194854C1 (en) Device for well research
WO2016156187A1 (en) Method and system for operating a gas well

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
MK14 Patent ceased section 143(a) (annual fees not paid) or expired