JPH10298981A - Construction method for cast-in-place pile in confined ground water zone - Google Patents

Construction method for cast-in-place pile in confined ground water zone

Info

Publication number
JPH10298981A
JPH10298981A JP10885397A JP10885397A JPH10298981A JP H10298981 A JPH10298981 A JP H10298981A JP 10885397 A JP10885397 A JP 10885397A JP 10885397 A JP10885397 A JP 10885397A JP H10298981 A JPH10298981 A JP H10298981A
Authority
JP
Japan
Prior art keywords
small
casing
diameter casing
diameter
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10885397A
Other languages
Japanese (ja)
Other versions
JP3810882B2 (en
Inventor
Akitoshi Nagasaki
昭敏 長崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Company Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP10885397A priority Critical patent/JP3810882B2/en
Publication of JPH10298981A publication Critical patent/JPH10298981A/en
Application granted granted Critical
Publication of JP3810882B2 publication Critical patent/JP3810882B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To prevent ground water from flowing out from the confined ground water layer. SOLUTION: The tip of a large-diameter casing 16 is intruded in the lower side of an aquiclude 10b by a specified length, and then intruded into the ground 10 of a small-diameter casing 20. In the small-diameter casing 20, similarly to the large-diameter casing 16, sediment in the inside is excavated and removed by a crab bucket 18, and the casing 20 is rotated by an excavator 14 holding the small-diameter casing 20 to be intruded into the ground 10. When the small- diameter casing 20 is intruded into the ground, water filling for both casings 16, 20 is performed. In this case, the water filling height is equal to the confined water level of the confined ground water layer 10c, and just before the tip of the small-diameter casing 20 pierces the aquiclude layer 10b, it is necessary to always hold the water level.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、被圧地下水帯にお
ける場所打ち杭の構築工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a cast-in-place pile in a confined groundwater zone.

【0002】[0002]

【従来の技術】扇状地などの地盤中には、被圧地下水層
の存在が認められる場合があり、この種の被圧地下水層
の上部側には、通常、難透水層が存在している。このよ
うな性状の地盤中に、例えば、送電鉄塔などの基礎を構
築する場合には、マット基礎やディープウェルによる地
下水位低下工法などが実施されている。
2. Description of the Related Art In some cases, a pressurized groundwater layer is present in the ground such as a fan, and a poorly permeable layer is usually present on the upper side of this type of pressurized groundwater layer. In the case of constructing a foundation such as a transmission tower in the ground having such properties, for example, a method of lowering the groundwater level using a mat foundation or a deep well has been implemented.

【0003】ところが、送電用鉄塔の基礎では、風荷重
に伴うモーメントにより、引揚げ荷重が大きく働くた
め、基礎体の自重で引揚げに対抗するマット基礎は、経
済的な面で非常に不利になり、採用することが難しい。
[0003] However, in the foundation of a power transmission tower, since a lifting load acts greatly due to a moment due to a wind load, a mat foundation against lifting by its own weight is very disadvantageous in terms of economy. It is difficult to adopt.

【0004】また、ディープウェルによる地下水位の低
下は、周辺の水環境に悪影響を及ぼすおそれがある。こ
のような条件を勘案すると、場所打ち杭による杭基礎
が、施工性,経済性から有利である。
[0004] Further, a decrease in the groundwater level due to the deep well may adversely affect the surrounding water environment. Taking these conditions into consideration, a pile foundation made of cast-in-place piles is advantageous in terms of workability and economy.

【0005】しかしながら、被圧地下水帯において場所
打ち杭基礎を構築する際には、以下に説明する技術的な
課題があった。
[0005] However, when constructing a cast-in-place pile foundation in a pressurized groundwater zone, there were the following technical problems.

【0006】[0006]

【発明が解決しようとする課題】すなわち、場所打ち杭
の構築工法に関して、「道路橋示方書」では、被水頭圧
がGL+2mを越える場合には、適さないと記載されて
いるが、オールケーシング工法で杭を溝築する方法であ
れば、被圧地下水帯においても場所内打ち杭基礎の構築
は、可能であると考えられる。
In other words, regarding the construction method of cast-in-place piles, the "Road Bridge Specification" states that the method is not suitable if the head to be wet exceeds GL + 2 m, but the all-casing method is used. It is considered that the in-place pile foundation can be constructed even in the confined groundwater zone if the method of constructing the pile is used.

【0007】ところが、このようなオールケーシング工
法を採用した場合にも、以下に説明する解決すべき課題
がある。図10は、被圧地下水帯において、オールケー
シング工法により場所打ち杭を溝築する際の、一般的な
施工状態を示している。
However, even when such an all casing method is employed, there are problems to be solved as described below. FIG. 10 shows a general construction state when a cast-in-place pile is grooved by the all-casing method in the pressurized groundwater zone.

【0008】杭基礎が溝築される地盤1中には、深度方
向に沿って、それぞれ所定の厚みを有する不圧滞水層1
a,難透水層1b,被圧地下水層1cが存在している。
このような地盤1中に、オールケーシング工法により場
所打ち杭を溝築する際には、両端が開口したケーシング
2を、内部を掘削しながら回転させて地盤1中の所定深
度までに貫入し、この後に、ケーシング2内に鉄筋籠を
建て込んで、ケーシング2を抜き出しながらコンクリー
トを打設する。
An unpressurized aquifer layer 1 having a predetermined thickness is provided along the depth direction in the ground 1 on which the pile foundation is built.
a, a poorly permeable layer 1b, and a pressurized groundwater layer 1c.
When digging a cast-in-place pile in such a ground 1 by the all-casing method, the casing 2 having both ends opened is rotated while excavating the inside to penetrate to a predetermined depth in the ground 1. Later, a steel cage is erected in the casing 2 and concrete is poured while the casing 2 is pulled out.

【0009】ところが、図10(A)に示すように、ケ
ーシング2の先端が、難透水層1bを貫通する間際に、
被圧地下水層1cの水圧によって、これが破壊され、ケ
ーシング2の先端側の土砂が、地下水とともに地上側に
噴出し、ボイリング,地盤の緩み,杭支持力の低下に繋
がる。
However, as shown in FIG. 10A, when the tip of the casing 2 penetrates through the poorly permeable layer 1b,
This is destroyed by the water pressure of the pressurized groundwater layer 1c, and the earth and sand on the tip side of the casing 2 gushes to the ground side together with the groundwater, leading to boiling, loosening of the ground, and lowering of the pile supporting force.

【0010】このような問題に対しては、同図に示すよ
うに、ケーシング2内に注水し、注水の水頭圧により被
圧地下水の圧力を押えながら、ケーシング2の貫入を行
えばよい。ところが、このような手段を講じたとして
も、被圧地下水層1cから地下水の流出を押えることが
できない。
To solve such a problem, as shown in FIG. 1, the casing 2 may be penetrated while water is injected into the casing 2 and the pressure of the pressurized groundwater is suppressed by the head pressure of the injected water. However, even if such measures are taken, the outflow of groundwater from the pressurized groundwater layer 1c cannot be suppressed.

【0011】この理由は、オールケーシング工法では、
ケーシング2と地盤1との間に、フリクションカットの
ために隙間を設けており、このような隙間が設けられて
いると、図10(B)に示すように、ケーシング2の先
端が被圧地下水層1cに到達すると、この隙間から地下
水が上方に流出するという問題があった。
The reason for this is that the all-casing method uses
A gap is provided between the casing 2 and the ground 1 for friction cutting, and if such a gap is provided, as shown in FIG. When the layer 1c is reached, there is a problem that groundwater flows upward from this gap.

【0012】本発明は、このような従来の問題点に鑑み
てなされたものであって、その目的とするところは、被
圧地下水層から地下水が流出すことがない被圧地下水帯
における場所打ち杭の溝築工法を提供することにある。
The present invention has been made in view of such a conventional problem, and an object of the present invention is to provide an in-situ pressurized groundwater zone in which groundwater does not flow out of a pressurized groundwater layer. An object of the present invention is to provide a method of constructing a pile groove.

【0013】[0013]

【課題を解決するための手段】上記目的を達成するた
め、本発明は、難透水層の下方に被圧地下水層が存在す
る地盤中に、下端が前記被圧地下水層に到達する場所打
ち杭を構築する工法において、内部の土砂を掘削しなが
ら下端が前記難透水層に到達するように大径ケーシング
を貫入する工程と、前記大径ケーシング内に小径ケーシ
グを挿入し、前記大径および小径ケーシング内に前記被
圧地下水層の被圧水位と同等の水位まで注水を行いなが
ら、前記小径ケーシング内の土砂を掘削して、その下端
が前記被圧地下水層まで到達するように貫入する工程
と、前記小径ケーシング内に鉄筋籠を建て込んで、前記
ケーシングを引き抜きながらコンクリートを打設する工
程ないしは前記ケーシング内にコンクリートを打設した
後に前記ケーシングを引き抜く工程とで構成した。この
ように構成された場所打ち杭の溝築工法によれば、大径
ケーシング内に小径ケーシグを挿入し、大径および小径
ケーシング内に被圧地下水層の被圧水位と同等の水位ま
で注水を行いながら、小径ケーシング内の土砂を掘削し
て、その下端が被圧地下水層まで到達するように貫入す
るので、大径および小径ケーシング内の水圧と被圧地下
水層の水圧とがそれぞれ均衡している。従って、被圧地
下水層の地下水が、小径ケーシング内に流入すことが防
止されるとともに、難透水層を貫通する小径ケーシング
の外周面の隙間を通って、地下水が上方に流出すること
も防げる。前記コンクリートの打設は、先端が難透水層
に留められている小径ケーシング内に、トレミー管によ
りコンクリートを充填した後に、前記小径ケーシングを
引き抜くことにより前記大径ケーシング内に充填するこ
とができる。この構成を採用すると、コンクリートを一
旦、小径ケーシングの上端まで充填した後に、大径ケー
シング内に充填することにより、径が小径から大径にな
る杭の継ぎ目の縁切れ,杭鉄筋の偏心が防止できる。ま
た、大径ケーシング内にコンクリートを補充充填する際
に、小径ケーシングとトレミー管を2重のトレミー管と
して使用することで、コンクリートの品質の劣化を防止
することができる。前記場所打ち杭の溝築に先立ち、必
要に応じて前記難透水層に薬液を注入して、前記難透水
層の地盤改良を行うことができる。この構成を採用する
と、難透水層が強化されて、被圧地下水層からの地下水
の流出をより確実に防止することができる。
In order to achieve the above object, the present invention relates to a cast-in-place pile having a lower end reaching the pressurized groundwater layer in a ground where a pressurized groundwater layer exists below the poorly permeable layer. In the construction method, a step of penetrating a large-diameter casing so that the lower end reaches the impervious layer while excavating internal soil and sand, and inserting a small-diameter casing into the large-diameter casing, the large-diameter and small-diameter Excavating earth and sand in the small-diameter casing while pouring water into the casing to a water level equivalent to the pressure level of the pressurized groundwater layer, and penetrating so that the lower end reaches the pressurized groundwater layer. A step of laying a steel cage in the small-diameter casing and casting concrete while pulling out the casing or casting concrete in the casing and then removing the casing. Was constructed in the process of Nuku come. According to the casting method for cast-in-place piles constructed in this way, a small-diameter casing is inserted into a large-diameter casing, and water is injected into the large-diameter and small-diameter casings to a water level equivalent to the pressure level of the pressurized groundwater layer. While doing, excavate the earth and sand in the small diameter casing and penetrate so that the lower end reaches the confined groundwater layer, so that the water pressure in the large diameter and small diameter casing and the water pressure of the confined groundwater layer are balanced respectively. I have. Therefore, the groundwater in the pressurized groundwater layer is prevented from flowing into the small-diameter casing, and the groundwater is also prevented from flowing upward through the gap in the outer peripheral surface of the small-diameter casing that penetrates the poorly permeable layer. The concrete can be cast by filling concrete into a small-diameter casing whose tip is fixed to a water-impermeable layer by a tremy tube, and then extracting the small-diameter casing to fill the large-diameter casing. By adopting this configuration, concrete is filled to the upper end of the small-diameter casing once and then filled into the large-diameter casing to prevent the edge of the joint of the pile from small diameter to large diameter from being cut off and eccentricity of the pile reinforcement. it can. Further, when the large diameter casing is refilled with concrete, the quality of the concrete can be prevented from being deteriorated by using the small diameter casing and the tremy tube as a double tremy tube. Prior to the construction of the cast-in-place pile, a chemical solution can be injected into the impervious layer as needed to improve the ground of the impervious layer. When this configuration is employed, the poorly permeable layer is strengthened, and the outflow of groundwater from the pressurized groundwater layer can be more reliably prevented.

【0014】[0014]

【発明の実施の形態】以下、本発明の好ましい実施の形
態について添付図面を参照して詳細に説明する。図1か
ら図9は、本発明にかかる被圧地下水帯における場所打
ち杭の溝築工法の一実施例を示している。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 to FIG. 9 show an embodiment of a method for constructing a cast-in-place pile in a pressurized groundwater zone according to the present invention.

【0015】同図に示した場所打ち杭の溝築工法では、
杭が溝築される地盤10中には、深度方向に沿って、そ
れぞれ所定の厚みを有する不圧滞水層10a,難透水層
10b,被圧地下水層10cが存在している。
In the method of constructing a cast-in-place pile shown in FIG.
An unpressurized aquifer 10a, a hardly permeable layer 10b, and a pressurized groundwater layer 10c each having a predetermined thickness are present along the depth direction in the ground 10 on which the pile is built.

【0016】図1から図6は、場所打ち杭の施工手順を
示しており、被圧地下水層10cに下端が到達する場所
打ち杭を溝築する際には、まず、地盤10上に盛土12が
形成される。
FIG. 1 to FIG. 6 show a construction procedure of a cast-in-place pile. When a cast-in-place pile whose lower end reaches the pressurized groundwater layer 10c is to be trenched, first, an embankment 12 is placed on the ground 10. Is formed.

【0017】盛土12の形成状態の一例を図7に示して
いる。同図に示した盛土12の形成状態は、被圧地下水
層10cの被圧水頭高さの最大値よりも若干低い高さの
盛土12を形成している。
FIG. 7 shows an example of a state in which the embankment 12 is formed. The state of formation of the embankment 12 shown in the figure forms the embankment 12 having a height slightly lower than the maximum value of the pressurized head height of the pressurized groundwater layer 10c.

【0018】このような高さの盛土12を形成しておく
と、後述する小径および大径ケーシング16,20内に
注水して、被圧地下水の圧力に対抗させる際に、大径ケ
ーシング16を安定した状態に保ことができるととも
に、小径ケーシング20を掘削機14により把持するこ
とが可能になる。
When the embankment 12 having such a height is formed, water is injected into small- and large-diameter casings 16 and 20, which will be described later, to prevent the large-diameter casing 16 from being pressed against the pressure of the groundwater. The small diameter casing 20 can be held by the excavator 14 while maintaining a stable state.

【0019】なお、盛土12を形成する場合には、この
ような形成状態が望ましいが、この盛土12は、例え
ば、ステージなどで代替することができる。
When the embankment 12 is formed, such a formation state is desirable, but the embankment 12 can be replaced by, for example, a stage.

【0020】盛土12の形成が終了すると、図1に示す
ように、盛土12上に全施工ベノト掘削機14を設置し
て、両端が開口した円形断面の大径ケーシング16を地
盤10中に貫入する。
When the formation of the embankment 12 has been completed, as shown in FIG. 1, a full construction Venoto excavator 14 is installed on the embankment 12, and a large-diameter casing 16 having a circular cross section with both ends opened penetrates into the ground 10. I do.

【0021】この大径ケーシング16を地盤10中に貫
入する際には、グラブバケット18により内部の土砂を
掘削除去するとともに、大径ケーシング16を把持して
いる掘削機14により、大径ケーシング16を回転させ
る。
When the large-diameter casing 16 penetrates into the ground 10, the inside of the large-diameter casing 16 is excavated and removed by the grab bucket 18, and the large-diameter casing 16 is gripped by the excavator 14 holding the large-diameter casing 16. To rotate.

【0022】このような回転と掘削とにより、大径ケー
シング16の先端が、難透水層10bの下方に所定長さ
だけ貫入すると、大径ケーシング16の貫入を停止す
る。この場合の、大径ケーシング16先端の難透水層1
0bへの貫入長は、施工誤差や難透水層10bの出現深
度の推定誤差などを勘案して、少なくとも1m程度に設
定することが望ましい。
When the tip of the large diameter casing 16 penetrates a predetermined length below the poorly permeable layer 10b by such rotation and excavation, the penetration of the large diameter casing 16 is stopped. In this case, the water-impermeable layer 1 at the tip of the large-diameter casing 16
The penetration length to 0b is desirably set to at least about 1 m in consideration of a construction error, an estimation error of the appearance depth of the poorly permeable layer 10b, and the like.

【0023】大径ケーシング16の貫入が終了すると、
その内部のスライム処理が行われる。ここでスライム処
理を行う理由は、大径ケーシング16内に小径ケーシン
グ20を挿入して地盤10中に貫入した後には、小径ケ
ーシング20の存在が邪魔になり、十分なスライム処理
ができなくなるからである。
When the penetration of the large-diameter casing 16 is completed,
The slime treatment inside is performed. The reason for performing the slime treatment here is that after the small-diameter casing 20 is inserted into the large-diameter casing 16 and penetrates into the ground 10, the presence of the small-diameter casing 20 hinders sufficient slime treatment. is there.

【0024】大径ケーシング16内のスライム処理が終
了すると、図2に示すように、小径ケーシング20の地
盤10中への貫入作業が行われる。小径ケーシング20
は、例えば、大径ケーシング16の1/2程度の直径を
有する両端が開口した円形断面の筒体であり、大径ケー
シング16の中心軸上に挿入される。
When the slime treatment in the large-diameter casing 16 is completed, the small-diameter casing 20 is penetrated into the ground 10 as shown in FIG. Small diameter casing 20
Is, for example, a cylindrical body having a diameter of about の of the large-diameter casing 16 and having both ends opened and having a circular cross section, and is inserted on the central axis of the large-diameter casing 16.

【0025】この場合、小径ケーシング20を大径ケー
シング16の軸心に一致させるために、本実施例では、
図8に示すように、位置決め部材22を使用した。同図
に示した位置決め部材22は、井桁状に組合わせた4本
の角形鋼管を用い、角形鋼管の下面側に、小径ケーシン
グ20の外周面に摺接するガイドプレート24を取付け
ている。
In this case, in order to make the small-diameter casing 20 coincide with the axis of the large-diameter casing 16, in this embodiment,
As shown in FIG. 8, a positioning member 22 was used. The positioning member 22 shown in the figure uses four rectangular steel pipes combined in a cross-girder shape, and a guide plate 24 that slides on the outer peripheral surface of the small-diameter casing 20 is attached to the lower surface side of the rectangular steel pipe.

【0026】小径ケーシング20は、大径ケーシング1
6と同様に、グラブバケット18により内部の土砂を掘
削除去するとともに、小径ケーシング20を把持してい
る掘削機14により、回転させることで地盤10中に貫
入するが、掘削機14により小径ケーシング20を把持
させるために、図示省略のアダプタを用いた。
The small-diameter casing 20 is a large-diameter casing 1
6, the earth and sand inside is excavated and removed by the grab bucket 18, and the excavator 14 holding the small-diameter casing 20 penetrates the ground 10 by rotating. An adapter (not shown) was used in order to grip the camera.

【0027】小径ケーシング20を地盤中に貫入する際
には、図2に示すように、両ケーシング16,20内
に、注水を行う。この場合の注水高さは、被圧地下水層
10cの被圧水位と同等の高さであり、小径ケーシング
20の先端が、難透水層10bを貫通する間際からは、
常時その水位を保必要がある。
When the small-diameter casing 20 penetrates into the ground, water is injected into both casings 16 and 20, as shown in FIG. The water injection height in this case is the same height as the pressurized water level of the pressurized groundwater layer 10c, and immediately before the tip of the small-diameter casing 20 penetrates the poorly permeable layer 10b,
It is necessary to keep the water level at all times.

【0028】そして、小径ケーシング20の先端が、難
透水層10bを貫通して、被圧地下水層10cの所定深
度まで到達すると、小径ケーシング20の貫入を終了
し、図3に示すように、小径ケーシング20内のスライ
ム処理が行われる。
When the distal end of the small-diameter casing 20 penetrates through the impervious layer 10b and reaches a predetermined depth of the pressurized groundwater layer 10c, the penetration of the small-diameter casing 20 ends, and as shown in FIG. The slime treatment in the casing 20 is performed.

【0029】このスライム処理が終了すると、図4に示
すように、小径ケーシング20内に鉄筋籠26が建て込
まれる。スライム処理と鉄筋籠26の建込を行う間は、
ケーシング16,20内の水位は、前述した状態に保た
れている。
When the slime treatment is completed, a reinforcing basket 26 is set in the small-diameter casing 20, as shown in FIG. During the slime treatment and the construction of the reinforcing cage 26,
The water levels in the casings 16 and 20 are maintained in the above-described state.

【0030】鉄筋籠26の建込が終了すると、図5に示
すように、コンクリートCの打設が、トレミー管28を
用いて行われる。トレミー管28によるコンクリートC
の打設は、小径ケーシング20を引き抜きながら行い、
小径ケーシング20の引き抜きは、その先端が難透水層
10bから離間しないように、その範囲内に留めて、天
端まで充填する。
When the rebar basket 26 has been set up, the concrete C is cast using the tremy tube 28 as shown in FIG. Concrete C with tremy tube 28
Is performed while pulling out the small diameter casing 20,
When the small-diameter casing 20 is pulled out, the tip is kept in the range so as not to be separated from the poorly permeable layer 10b, and is filled up to the top end.

【0031】打設したコンクリートCが小径ケーシング
20の天端に到達すると、トレミー管28によりコンク
リートを供給しながら、小径ケーシング20を引き抜
き、大径ケーシング16内にコンクリートCを供給す
る。つまり、本実施例の場合には、小径ケーシング20
内にコンクリートCを充填した後は、小径ケーシング2
0もトレミー管として使用しコンクリートCの打設を行
う。
When the cast concrete C reaches the top end of the small-diameter casing 20, the small-diameter casing 20 is pulled out while the concrete is supplied by the tremy tube 28, and the concrete C is supplied into the large-diameter casing 16. That is, in the case of the present embodiment, the small-diameter casing 20
After the concrete C is filled in the small casing 2
0 is also used as a tremee pipe to cast concrete C.

【0032】このようなコンクリートCの打設方法を採
用するのは、以下に説明する理由に基づいている。図9
には、トレミー管28を使用して、大径ケーシング16
内にコンクリートCを打設する際の状態が示されてい
る。
The method of placing the concrete C is adopted for the following reasons. FIG.
The large diameter casing 16 using the tremy tube 28
The state when concrete C is poured into the inside is shown.

【0033】小径トレミー管20を引き抜きながらトレ
ミー管28からコンクリートCを打設する過程におい
て、図9(A)に示すように、小径ケーシング20の先
端が、大径ケーシング16内に打設されているコンクリ
ートCの天端面から離間しない状態にある間は、問題が
ない。
In the process of placing concrete C from the tremy tube 28 while pulling out the small-diameter tremy tube 20, the tip of the small-diameter casing 20 is driven into the large-diameter casing 16 as shown in FIG. There is no problem while the concrete C is not separated from the top end surface.

【0034】ところが、図9(B)に示すように、小径
ケーシング20の先端が、大径ケーシング16内に打設
されているコンクリートCの天端面から離間すると、大
径ケーシング16内に注水されている水が、小径ケーシ
ング20の抜き出しに伴って、小径ケーシング20側に
流動し、この糧道によりコンクリートCが洗われて、骨
材とセメントとが分離し、コンクリートが硬化したとき
にこの部分の品質が低下する。
However, as shown in FIG. 9B, when the tip of the small diameter casing 20 is separated from the top end surface of the concrete C cast in the large diameter casing 16, water is injected into the large diameter casing 16. Water flowing to the small-diameter casing 20 side with the extraction of the small-diameter casing 20, the concrete C is washed by the feed passage, the aggregate and the cement are separated, and when the concrete hardens, this portion is removed. The quality will be reduced.

【0035】このような品質の低下を防ぐために、本実
施例の場合には、小径ケーシング20内にコンクリート
Cを充填した後は、トレミー管28と小径ケーシング2
0とを2重のトレミー管として用い、これらによりコン
クリートCの打設を行うようにした。
In order to prevent such deterioration in quality, in this embodiment, after the small diameter casing 20 is filled with the concrete C, the tremee pipe 28 and the small diameter casing 2 are filled.
0 was used as a double tremy tube, and concrete C was cast by these.

【0036】このようなコンクリートの打設方法を採用
すると、杭基礎のコンクリートの品質低下を効果的に防
ぐことができる。小径ケーシング20を引き抜きなが
ら、大径ケーシング16内にコンクリートCを充填し、
図6に示すように、小径ケーシング20の引き抜きが終
了した後に、トレミー管28を使用してコンクリートC
を補充充填して、大径ケーシング16を引き抜くと、場
所打ち杭の施工が終了する。
By adopting such a method for placing concrete, it is possible to effectively prevent the deterioration of the concrete of the pile foundation. While pulling out the small diameter casing 20, the concrete C is filled into the large diameter casing 16,
As shown in FIG. 6, after the drawing of the small diameter casing 20 is completed, the concrete C
When the large-diameter casing 16 is pulled out, the construction of the cast-in-place pile is completed.

【0037】さて、以上のように構成された被圧地下水
帯における場所打ち杭の溝築工法によれば、大径ケーシ
ング16内に小径ケーシグ20を挿入し、大径および小
径ケーシング16,20内に被圧地下水層10cの被圧
水位と同等の水位まで注水を行いながら、小径ケーシン
グ20内の土砂を掘削して、その下端が被圧地下水層1
0cまで到達するように貫入するので、大径および小径
ケーシング16,20内の水圧と被圧地下水層10cの
水圧とがそれぞれ均衡している。
According to the method for constructing a cast-in-place pile in the pressurized groundwater zone constructed as described above, the small-diameter casing 20 is inserted into the large-diameter casing 16 and the large-diameter and small-diameter casings 16, 20 are inserted. The soil in the small-diameter casing 20 is excavated while pouring water to a water level equivalent to the confined water level of the confined groundwater layer 10c.
Since it penetrates so as to reach 0c, the water pressure in the large-diameter and small-diameter casings 16, 20 and the water pressure of the pressurized groundwater layer 10c are balanced.

【0038】従って、被圧地下水層10cの地下水が、
小径ケーシング20内に流入すことが防止されるととも
に、難透水層10bを貫通する小径ケーシング20の外
周面の隙間を通って、地下水が上方に流出することも防
げる。
Therefore, the groundwater in the pressurized groundwater layer 10c is
In addition to being prevented from flowing into the small-diameter casing 20, groundwater can also be prevented from flowing upward through a gap in the outer peripheral surface of the small-diameter casing 20 that penetrates the poorly permeable layer 10b.

【0039】また、本実施例の場合には、コンクリート
Cの打設は、先端が難透水層10bに留められている小
径ケーシング20内に、トレミー管28によりコンクリ
ートCを一旦充填した後に、小径ケーシング20を引き
抜くことにより大径ケーシング16内に充填するので、
径が小径から大径になる杭の継ぎ目の縁切れ,鉄筋籠2
6の偏心が防止できる。
In the case of the present embodiment, the concrete C is cast by temporarily filling the concrete C with the tremy tube 28 into the small-diameter casing 20 whose tip is fixed to the impervious layer 10b. Since the large diameter casing 16 is filled by pulling out the casing 20,
Edge of seam of pile from small diameter to large diameter, steel cage 2
6 can be prevented.

【0040】また、大径ケーシング16内にコンクリー
トを補充充填する際に、小径ケーシング20とトレミー
管28を2重のトレミー管として使用することで、コン
クリートの品質の劣化を防止することができる。
In addition, when the large diameter casing 16 is refilled with concrete, the quality of concrete can be prevented from being deteriorated by using the small diameter casing 20 and the tremy tube 28 as a double tremy tube.

【0041】なお、上記実施例で示した場所打ち杭の溝
築工法では、場所打ち杭の溝築に先立ち、必要に応じて
難透水層10bに薬液を注入して、難透水層10bの地
盤改良を行うことができる。
In the method of constructing a cast-in-place pile, which has been described in the above embodiment, a chemical solution is injected into the impervious layer 10b as necessary prior to constructing the cast-in-place pile, and the ground of the impervious layer 10b is grounded. Improvements can be made.

【0042】この構成を採用すると、難透水層10bが
強化されて、被圧地下水層10cからの地下水の流出を
より確実に防止することができる。
When this configuration is adopted, the poorly permeable layer 10b is strengthened, and the outflow of groundwater from the pressurized groundwater layer 10c can be more reliably prevented.

【0043】[0043]

【発明の効果】以上実施例で詳細に説明したように、本
発明にかかる被圧地下水帯における場所打ち杭の溝築工
法によれば、被圧地下水の流出を防止しつつ、杭基礎の
溝築が可能になる。
As described in detail in the above embodiment, according to the method for constructing a cast-in-place pile in a pressurized groundwater zone according to the present invention, the groove of a pile foundation is prevented while preventing the pressurized groundwater from flowing out. Construction becomes possible.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる被圧地下水帯における場所打ち
杭の溝築工法の一実施例の最初の工程を示す縦断面図で
ある。
FIG. 1 is a longitudinal sectional view showing a first step of an embodiment of a method for constructing a cast-in-place pile in a pressurized groundwater zone according to the present invention.

【図2】図1の工程に引き続いて行われる工程の縦断面
図である。
FIG. 2 is a longitudinal sectional view of a step performed subsequent to the step of FIG. 1;

【図3】図2の工程に引き続いて行われる工程の縦断面
図である。
FIG. 3 is a longitudinal sectional view of a step performed subsequent to the step of FIG. 2;

【図4】図3の工程に引き続いて行われる工程の縦断面
図である。
FIG. 4 is a longitudinal sectional view of a step performed subsequent to the step of FIG. 3;

【図5】図4の工程に引き続いて行われる工程の縦断面
図である。
FIG. 5 is a vertical sectional view of a step performed subsequent to the step of FIG. 4;

【図6】図5の工程に引き続いて行われる工程の縦断面
図である。
FIG. 6 is a longitudinal sectional view of a step performed subsequent to the step of FIG. 5;

【図7】図1に示した盛土の形成状態の説明図である。FIG. 7 is an explanatory diagram of a formation state of the embankment shown in FIG. 1;

【図8】図2に示した位置決め部材の説明図である。FIG. 8 is an explanatory diagram of the positioning member shown in FIG.

【図9】トレミー管によりコンクリートの打設を行う際
に発生する不都合の説明図である。
FIG. 9 is an explanatory diagram of inconvenience that occurs when concrete is poured by a tremy tube.

【図10】オールケーシング工法で場所打ち杭を溝築す
る際に発生する不都合の説明図である。
FIG. 10 is an explanatory view of a problem that occurs when a cast-in-place pile is grooved by the all-casing method.

【符号の説明】[Explanation of symbols]

10 地盤 10a 不圧滞水層 10b 難透水層 10c 被圧地下水層 12 盛土 14 掘削機 16 大径ケーシング 18 グラブバケット 20 小径ケーシング 22 位置決め部材 26 鉄筋籠 28 トレミー管 DESCRIPTION OF SYMBOLS 10 Ground 10a Unpressurized aquifer 10b Impervious layer 10c Pressurized groundwater layer 12 Embankment 14 Excavator 16 Large-diameter casing 18 Grab bucket 20 Small-diameter casing 22 Positioning member 26 Rebar cage 28 Tremy pipe

─────────────────────────────────────────────────────
────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成9年5月26日[Submission date] May 26, 1997

【手続補正1】[Procedure amendment 1]

【補正対象書類名】図面[Document name to be amended] Drawing

【補正対象項目名】図10[Correction target item name] FIG.

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【図10】 FIG. 10

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 難透水層の下方に被圧地下水層が存在す
る地盤中に、下端が前記被圧地下水層に到達する場所打
ち杭を構築する工法において、 内部の土砂を掘削しながら下端が前記難透水層に到達す
るように大径ケーシングを貫入する工程と、 前記大径ケーシング内に小径ケーシグを挿入し、前記大
径および小径ケーシング内に前記被圧地下水層の被圧水
位と同等の水位まで注水を行いながら、前記小径ケーシ
ング内の土砂を掘削して、その下端が前記被圧地下水層
まで到達するように貫入する工程と、 前記小径ケーシング内に鉄筋籠を建て込んで、前記ケー
シングを引き抜きながらコンクリートを打設する工程な
いしは前記ケーシング内にコンクリートを打設した後に
前記ケーシングを引き抜く工程とからなることを特徴と
する被圧地下水帯における場所打ち杭の構築工法。
1. A method for constructing a cast-in-place pile having a lower end reaching a pressurized groundwater layer in a ground where a pressurized groundwater layer exists below a poorly permeable layer. A step of penetrating a large-diameter casing to reach the poorly permeable layer, a small-diameter casing is inserted into the large-diameter casing, and a pressure level equivalent to the pressure level of the pressurized groundwater layer in the large-diameter and small-diameter casings. Excavating earth and sand in the small-diameter casing while injecting water to a water level, and penetrating so that the lower end thereof reaches the pressurized underground water layer; embedding a steel cage in the small-diameter casing; And placing the concrete in the casing and then pulling out the casing. Construction method of cast-in-place pile in obi.
【請求項2】 前記コンクリートの打設は、先端が難透
水層に留められている小径ケーシング内に、トレミー管
によりコンクリートを充填した後に、前記小径ケーシン
グを引き抜くことにより前記大径ケーシング内に充填す
ることを特徴とする請求項1記載の被圧地下水帯におけ
る場所打ち杭の構築工法。
2. The concrete is poured into a small-diameter casing whose tip is fixed to a water-impermeable layer by filling concrete with a tremy tube and then extracting the small-diameter casing to fill the large-diameter casing. The method of constructing a cast-in-place pile in a pressurized groundwater zone according to claim 1.
【請求項3】 前記場所打ち杭の溝築に先立ち、必要に
応じて前記難透水層に薬液を注入して、前記難透水層の
地盤改良を行うことを特徴とする請求項1または2記載
の被圧地下水帯における場所打ち杭の構築工法。
3. The soil improvement of the water-impermeable layer by injecting a chemical solution into the water-impermeable layer as necessary prior to the construction of the cast-in-place pile. Construction method of cast-in-place piles in a confined groundwater zone.
JP10885397A 1997-04-25 1997-04-25 Construction method of cast-in-place pile in confined groundwater zone Expired - Fee Related JP3810882B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10885397A JP3810882B2 (en) 1997-04-25 1997-04-25 Construction method of cast-in-place pile in confined groundwater zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10885397A JP3810882B2 (en) 1997-04-25 1997-04-25 Construction method of cast-in-place pile in confined groundwater zone

Publications (2)

Publication Number Publication Date
JPH10298981A true JPH10298981A (en) 1998-11-10
JP3810882B2 JP3810882B2 (en) 2006-08-16

Family

ID=14495264

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10885397A Expired - Fee Related JP3810882B2 (en) 1997-04-25 1997-04-25 Construction method of cast-in-place pile in confined groundwater zone

Country Status (1)

Country Link
JP (1) JP3810882B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008013999A (en) * 2006-07-05 2008-01-24 Riyouken Kiso Kk Construction method of cast-in-place concrete pile
CN105155518A (en) * 2015-09-01 2015-12-16 中国十七冶集团有限公司 Safe pile-forming construction method for manual hole digging pile in quicksand lot
JP2015229860A (en) * 2014-06-04 2015-12-21 株式会社横山基礎工事 Method to control groundwater movement in excavated pit, grout filling method, and water storage means

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008013999A (en) * 2006-07-05 2008-01-24 Riyouken Kiso Kk Construction method of cast-in-place concrete pile
JP2015229860A (en) * 2014-06-04 2015-12-21 株式会社横山基礎工事 Method to control groundwater movement in excavated pit, grout filling method, and water storage means
CN105155518A (en) * 2015-09-01 2015-12-16 中国十七冶集团有限公司 Safe pile-forming construction method for manual hole digging pile in quicksand lot

Also Published As

Publication number Publication date
JP3810882B2 (en) 2006-08-16

Similar Documents

Publication Publication Date Title
WO2020062940A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN108166483A (en) Bored pile construction method
JP5282541B2 (en) How to prevent lifting of the lining body
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN110130427A (en) The reinforcement means and organizational pile foundation of precast hollow tubular pole
JP2019019633A (en) Construction method of continuous underground wall and steel pipe pile
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
JP2008014000A (en) Construction method of cast-in-place concrete pile
JP2007009505A (en) Foundation reinforcing method
KR20100035349A (en) Construction method of retaining wall using cast-in-place pile
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile
JPH10298981A (en) Construction method for cast-in-place pile in confined ground water zone
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
JP3827309B2 (en) Auxiliary pile method and embedded pile method
CN108487273A (en) A kind of foundation in water construction method
CN109898515A (en) Support of Foundation Pit Excavation method of the slope in conjunction with tubular pole
JP2002097639A (en) Pile burying method and jig
JP4336828B2 (en) Substructure
JP2874906B2 (en) Shaft construction method
JPS61254716A (en) Setting of in-place concrete pile
JPH08209687A (en) Partial casing pile construction method
KR20040097762A (en) Grouting method for improving Bearing power of ground of Grouted Bored File and Structure of Erecton reinforcing bar using of the same
JPH0325121A (en) Sinking of pile in inner drilling pile method

Legal Events

Date Code Title Description
A977 Report on retrieval

Effective date: 20051226

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20060110

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060309

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060516

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060525

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20100602

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20100602

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20110602

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 6

Free format text: PAYMENT UNTIL: 20120602

LAPS Cancellation because of no payment of annual fees