JPH10280863A - Construction method for tunnel pit mouth in steep slope - Google Patents

Construction method for tunnel pit mouth in steep slope

Info

Publication number
JPH10280863A
JPH10280863A JP8698797A JP8698797A JPH10280863A JP H10280863 A JPH10280863 A JP H10280863A JP 8698797 A JP8698797 A JP 8698797A JP 8698797 A JP8698797 A JP 8698797A JP H10280863 A JPH10280863 A JP H10280863A
Authority
JP
Japan
Prior art keywords
tunnel
entrance
main
work
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8698797A
Other languages
Japanese (ja)
Other versions
JP3787796B2 (en
Inventor
Futoshi Kusumoto
太 楠本
Tsutomu Kiuchi
勉 木内
Kosuke Kakimi
康介 垣見
Atsuyuki Kimura
厚之 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP08698797A priority Critical patent/JP3787796B2/en
Publication of JPH10280863A publication Critical patent/JPH10280863A/en
Application granted granted Critical
Publication of JP3787796B2 publication Critical patent/JP3787796B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To obtain a method for constructing a tunnel pit mouth safely and economically without a temporarily provided road along a steep slope. SOLUTION: At the time of constructing a tunnel pit mouth 3 on a steep slope 1, a work tunnel 11 is excavated from an existing road 6 toward a final pit tunnel projected line on the inside of the natural ground from a construction projected part of the tunnel pit mouth 3, and when the work tunnel 11 intersets the final tunnel projected line, the final pit tunnel 5 is excavated from the intersecting position toward the construction projected part of the tunnel pit mouth to construct the tunnel pit mouth 3 from the inside of the final pit tunnel 5. Simultaneously, the final pit tunnel 5 is excavated from the intersecting position in the opposite direction to the construction projected part of the tunnel pit mouth 3.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、急峻斜面における
トンネル坑口の施工方法に関する。
The present invention relates to a method for constructing a tunnel entrance on a steep slope.

【0002】[0002]

【従来の技術】図14に示すように、急峻地形(図中2
は等高線を示す)における斜面1にトンネル坑口付けを
行う場合、従来では、トンネル坑口位置と同じ標高レベ
ルで現有道路6からトンネル坑口位置に至る仮設道路7
を設け、これをアクセス道路としてトンネル坑口位置に
作業構台8を構築し、この作業構台8を利用してトンネ
ル坑口3を施工し、その後、本坑トンネル5の掘削を開
始するという方法がとられている。
2. Description of the Related Art As shown in FIG.
When a tunnel entrance is formed on the slope 1 at the same time, a temporary road 7 extending from the existing road 6 to the tunnel entrance at the same elevation level as the tunnel entrance is conventionally used.
A work gantry 8 is constructed at the position of the tunnel entrance using this as an access road, the tunnel entrance 3 is constructed using the work gantry 8, and then the excavation of the main tunnel 5 is started. ing.

【0003】[0003]

【発明が解決しようとする課題】ところが、急峻斜面で
のこれまでの方法による坑口付けでは、以下の点が改善
課題となっている。 (1)急峻斜面を切り盛りしながら仮設道路を造築する
ため、工期と工事費が多くかかる。 (2)自然環境保全上、急峻斜面での仮設道路工事など
は少なくしたい。 (3)トンネル接続は高架橋となることから、その作業
構台と資機材の搬入出を行う必要があるが、その搬入出
を、急峻斜面に設けた仮設道路を利用して行うのは、安
全面及び経済面を考慮した場合、できれば避けたい。
However, the following points are issues to be improved in the conventional method of attaching a wellhead on a steep slope. (1) Construction of temporary roads while cutting steep slopes requires a lot of construction time and construction costs. (2) In order to protect the natural environment, we want to reduce the construction of temporary roads on steep slopes. (3) Since the tunnel connection will be viaduct, it is necessary to carry in and out the work gantry and equipment, but it is safe to carry in and out using the temporary road provided on the steep slope. And considering the economics, we want to avoid it if possible.

【0004】本発明は、上記事情を考慮し、急峻斜面に
沿って仮設道路を設ける必要が全くなく、自然環境の保
全が可能であり、しかも安全で経済的にトンネル坑口を
施工することができる方法を提供することを目的とす
る。
[0004] In consideration of the above circumstances, the present invention does not require any temporary roads along steep slopes, can preserve the natural environment, and can safely and economically construct tunnel tunnels. The aim is to provide a method.

【0005】[0005]

【課題を解決するための手段】請求項1の発明は、急峻
斜面にトンネル坑口を施工するに当たり、前記トンネル
坑口の施工予定部よりも地山内部側の本坑トンネル予定
線に向かって現有道路から作業トンネルを掘削し、本坑
トンネル予定線に作業トンネルが交差したら、その交差
位置からトンネル坑口の施工予定部に向かって本坑トン
ネルを掘削し、この本坑トンネル内から前記トンネル坑
口の施工を行うことを特徴とする。
According to the first aspect of the present invention, when constructing a tunnel entrance on a steep slope, the existing road is directed toward the main tunnel planned line on the inner side of the ground than the planned construction site of the tunnel entrance. When the working tunnel intersects with the planned tunnel of the main tunnel, the main tunnel is excavated from the intersection position toward the planned site of the tunnel entrance, and the construction of the tunnel entrance is performed from within the main tunnel. Is performed.

【0006】請求項2の発明は、請求項1において、前
記本坑トンネル内からトンネル坑口を施工するに際し、
本坑トンネルの掘削を、トンネル坑口の施工予定部の手
前で一旦止め、その位置から地山及び斜面の補強工事を
行いながら、導坑方式で本坑トンネルを斜面に開口させ
て、トンネル坑口を施工することを特徴とする。
According to a second aspect of the present invention, in the first aspect, when the tunnel entrance is constructed from within the main tunnel,
The excavation of the main tunnel is temporarily stopped just before the planned part of the tunnel entrance, and while the reinforcement of the ground and slope is performed from that position, the main tunnel is opened on the slope by the tunnel method, and the tunnel entrance is opened. It is characterized by construction.

【0007】請求項3の発明は、請求項1または2にお
いて、前記本坑トンネルを斜面に開通させた後、外部に
作業構台を構築し、該作業構台を利用して橋台を構築す
ることを特徴とする。
According to a third aspect of the present invention, in the first or second aspect, after the main tunnel is opened on a slope, a work gantry is constructed outside and the abutment is constructed using the work gantry. Features.

【0008】請求項4の発明は、請求項1〜3のいずれ
かにおいて、前記トンネル坑口の施工予定部へ向けての
本坑トンネルの掘削と同時に、前記交差位置からトンネ
ル坑口の施工予定部と反対方向に本坑トンネルを掘削す
ることを特徴とする。
According to a fourth aspect of the present invention, in any one of the first to third aspects, simultaneously with excavation of the main pit tunnel toward the planned site of the tunnel entrance, the construction site of the tunnel entrance is constructed from the intersection position. The main tunnel is excavated in the opposite direction.

【0009】[0009]

【発明の実施の形態】以下、本発明の実施形態を図面に
基づいて説明する。本実施形態の施工方法では、図1に
示すように、トンネル坑口3の施工予定部よりも地山内
部側の本坑トンネル予定線(図中、本坑トンネル5で代
用)に向かって、現有道路6から作業トンネル11を掘
削し、本坑トンネル予定線に作業トンネル11が交差し
たら、その交差位置からトンネル坑口3の施工予定部に
向かって矢印(イ)のように本坑トンネル5を掘削し、
この本坑トンネル5の内部からトンネル坑口3の施工を
行う。また、交差位置からトンネル坑口3の施工予定部
と反対方向に向かって矢印(ロ)のように本坑トンネル
5を同時掘削する。なお、図中10で示すものは、現有
道路6に隣接して設けた作業ヤードである。
Embodiments of the present invention will be described below with reference to the drawings. In the construction method of the present embodiment, as shown in FIG. 1, the construction of the existing tunnel is performed toward the planned main tunnel tunnel line (in the figure, the main tunnel 5 is substituted) from the planned construction site of the tunnel entrance 3. When the work tunnel 11 is excavated from the road 6 and the work tunnel 11 intersects the planned main tunnel tunnel, the main tunnel 5 is excavated from the intersection position toward the construction site of the tunnel entrance 3 as shown by an arrow (a). And
The tunnel entrance 3 is constructed from the inside of the main tunnel 5. Further, the main tunnel 5 is simultaneously excavated from the intersection position in the direction opposite to the planned portion of the tunnel entrance 3 as shown by an arrow (b). In addition, what is shown by 10 in the figure is a work yard provided adjacent to the existing road 6.

【0010】本坑トンネル5内からトンネル坑口3を施
工するに当たっては、次の手順で工事を進める。図2〜
図13を用いて説明する。なお、説明の便宜上、工事内
容自体に符号を付すこともある。
In constructing the tunnel entrance 3 from inside the main tunnel 5, construction is performed in the following procedure. Figure 2
This will be described with reference to FIG. In addition, for convenience of explanation, reference numerals may be given to construction contents themselves.

【0011】(1)図2参照。土被り厚Hが直径の1.
5〜2倍程度の位置まで本坑トンネル5を掘削したら、
トンネル坑口の施工予定部の手前で、いったん本坑断面
での掘削を停止する。
(1) See FIG. The overburden thickness H is 1.
After excavating the main tunnel 5 to about 5 to 2 times,
Stop the excavation in the section of the main pit once before the planned section of the tunnel entrance.

【0012】(2)図3参照。本坑トンネル5の先端底
部に埋戻し工21を行って、スムースブラスティングお
よび制御発破により頂設導坑22を掘削する。その際、
先受け工(フォアパイリング)、高強度スチールファイ
バ吹き付け工、斜面防護ネット工を実施して、地山及び
斜面の補強を行う。23は防護ネット、24は先受け工
を示す。
(2) See FIG. A backfilling 21 is performed at the bottom of the tip of the main tunnel 5, and a top pit 22 is excavated by smooth blasting and controlled blasting. that time,
Perform fore piling, high-strength steel fiber spraying, and slope protection netting to reinforce ground and slopes. Reference numeral 23 denotes a protection net, and 24 denotes a precedent.

【0013】(3)図4参照。頂設導坑22の盤下げ工
25を行うと共に、頂設部ロックボルト工26を行う。 (4)図5参照。補強ロックボルト工27及び注入補強
工28等の斜面安定工を実施する。 (5)図6参照。制御発破により上半切拡げ掘削工29
を行う。 (6)図7参照。下半掘削工30及び斜面安定工31を
行う。
(3) See FIG. The lowering work 25 of the top shaft 22 and the lock bolt work 26 of the top part are performed. (4) See FIG. Slope stabilization works such as reinforcement rock bolt construction 27 and injection reinforcement construction 28 are performed. (5) See FIG. Upper excavation excavator 29 by control blasting
I do. (6) See FIG. Lower half excavation work 30 and slope stabilization work 31 are performed.

【0014】(7)図8参照。トンネル底部のインバー
ト33の打設、埋戻し、及び作業構台8の構築を行う。 (8)図9参照。作業構台8を利用して橋台部の掘削工
事41を行う。 (9)図10参照。深礎杭42及び橋台コンクリート工
43を実施し、片側の橋台40を構築する。 (10)図11参照。作業構台8の盛り換えを行い、他
側の橋台部の掘削工事41を行う。 (11)図12参照。深礎杭42及び橋台コンクリート
工43を実施する。 (12)図13参照。作業構台8の増設、覆工及び坑門
工事50を行う。
(7) See FIG. Casting and backfilling of the invert 33 at the bottom of the tunnel and construction of the work gantry 8 are performed. (8) See FIG. An abutment excavation 41 is performed using the work gantry 8. (9) See FIG. The deep foundation pile 42 and the abutment concrete work 43 are carried out to construct the abutment 40 on one side. (10) See FIG. The work gantry 8 is changed, and excavation work 41 of the abutment on the other side is performed. (11) See FIG. The deep foundation pile 42 and the abutment concrete work 43 are implemented. (12) See FIG. The work gantry 8 is added, the lining and the gate work 50 are performed.

【0015】以上のように施工を進めることで、仮設道
路を設けることなく、本坑トンネル5内から安全にトン
ネル坑口3を施工することができる。その際、作業構台
8や橋台40を構築するための資材は、作業トンネル1
1及び本坑トンネル5を介して搬入出できるため、安全
で経済的に工事を進めることができる。
By proceeding as described above, the tunnel entrance 3 can be constructed safely from inside the main tunnel 5 without providing a temporary road. At this time, materials for constructing the work gantry 8 and the abutment 40 are the work tunnel 1
Since it can be carried in and out through the tunnel 1 and the main tunnel 5, construction can be carried out safely and economically.

【0016】なお、大まかな手順を守れば、詳細な工事
内容は、地山の状況等に応じて適宜変更可能である。
If the general procedure is followed, the details of the construction can be changed as appropriate according to the conditions of the ground.

【0017】[0017]

【発明の効果】以上説明したように、請求項1の発明に
よれば、作業トンネルを介して掘削した本坑トンネル内
からトンネル坑口を施工するので、仮設道路を設ける必
要がなくなり、急峻な斜面での切り盛り工事が不要とな
る。従って、自然環境を保全しながら、安全、確実で経
済的に坑口付けを行うことが可能になる。また、本坑ト
ンネル内からトンネル坑口を施工する際に、請求項2の
発明のように、補強工事を行いながら、導坑方式で本坑
トンネルを斜面に開口させるようにすれば、地山及び斜
面の安定を維持しながら、安全に作業を進めることがで
きる。
As described above, according to the first aspect of the present invention, since the tunnel entrance is constructed from the main tunnel excavated through the work tunnel, there is no need to provide a temporary road, and a steep slope is not required. It is not necessary to perform the work of cutting and filling. Therefore, it becomes possible to perform safe, reliable and economical digging while preserving the natural environment. Further, when constructing the tunnel entrance from inside the main tunnel, as in the invention of claim 2, if the main tunnel is opened on the slope by the pit tunnel method while performing reinforcement work, the ground and Work can proceed safely while maintaining the stability of the slope.

【0018】また、請求項3の発明のように、外部に作
業構台や橋台を構築する場合に、作業トンネル及び本坑
トンネルを利用して資材等の搬入出ができるから、安全
で経済的な施工が可能となる。さらに、請求項4の発明
のように、坑口付けと橋台工事等と並行して、地山奥部
への本坑トンネルの掘進を同時に進めることができるか
ら、工期短縮が図れる。
Further, when a work gantry or an abutment is constructed outside as in the third aspect of the present invention, materials and the like can be carried in and out using the work tunnel and the main tunnel, so that it is safe and economical. Construction becomes possible. Furthermore, as in the invention of claim 4, the excavation of the main shaft tunnel to the inner part of the ground can be simultaneously advanced in parallel with the pit opening and the abutment construction, so that the construction period can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の実施形態の施工方法の説明に用いる
平面図である。
FIG. 1 is a plan view used for describing a construction method according to an embodiment of the present invention.

【図2】 本発明の実施形態の施工方法の工程説明図
で、(a)は側面断面図、(b)は正面から見た断面図
である。
FIGS. 2A and 2B are process explanatory views of a construction method according to an embodiment of the present invention, wherein FIG. 2A is a side sectional view, and FIG.

【図3】 図2の次の工程の説明図で、(a)は側面断
面図、(b)は正面から見た断面図である。
FIGS. 3A and 3B are explanatory views of a process subsequent to FIG. 2, in which FIG. 3A is a side sectional view, and FIG.

【図4】 図3の次の工程の説明図で、(a)は側面断
面図、(b)は正面から見た断面図である。
FIGS. 4A and 4B are explanatory views of a process subsequent to FIG. 3, wherein FIG. 4A is a side cross-sectional view and FIG.

【図5】 図4の次の工程の説明図で、(a)は側面断
面図、(b)は正面から見た断面図である。
5A and 5B are explanatory views of the next step of FIG. 4, wherein FIG. 5A is a side sectional view, and FIG. 5B is a sectional view seen from the front.

【図6】 図5の次の工程の説明図で、(a)は側面断
面図、(b)は正面から見た断面図である。
FIGS. 6A and 6B are explanatory views of the next step of FIG. 5, wherein FIG. 6A is a side sectional view, and FIG.

【図7】 図6の次の工程の説明図で、(a)は側面断
面図、(b)は正面から見た断面図である。
FIGS. 7A and 7B are explanatory views of a step subsequent to FIG. 6, wherein FIG. 7A is a side sectional view and FIG.

【図8】 図7の次の工程の説明図で、(a)は側面断
面図、(b)は平面図である。
FIGS. 8A and 8B are explanatory views of a process subsequent to FIG. 7, wherein FIG. 8A is a side sectional view and FIG. 8B is a plan view.

【図9】 図8の次の工程の説明図で、(a)は側面断
面図、(b)は平面図である。
FIGS. 9A and 9B are explanatory views of the next step of FIG. 8, in which FIG. 9A is a side sectional view and FIG. 9B is a plan view.

【図10】 図9の次の工程の説明図で、(a)は側面
断面図、(b)は平面図である。
FIGS. 10A and 10B are explanatory views of the next step of FIG. 9, in which FIG. 10A is a side sectional view and FIG. 10B is a plan view.

【図11】 図10の次の工程の説明図で、(a)は側
面断面図、(b)は平面図である。
FIGS. 11A and 11B are explanatory views of the next step of FIG. 10, wherein FIG. 11A is a side sectional view and FIG. 11B is a plan view.

【図12】 図11の次の工程の説明図で、(a)は側
面断面図、(b)は平面図である。
FIGS. 12A and 12B are explanatory views of the next step of FIG. 11, wherein FIG. 12A is a side sectional view and FIG. 12B is a plan view.

【図13】 図12の次の工程の説明図で、(a)は側
面断面図、(b)は平面図である。
13 is an explanatory view of a step subsequent to FIG. 12, (a) is a side sectional view, and (b) is a plan view. FIG.

【図14】 従来の施工方向の説明に用いる平面図であ
る。
FIG. 14 is a plan view used to explain a conventional construction direction.

【符号の説明】[Explanation of symbols]

1 斜面 3 トンネル坑口 5 本坑トンネル 6 現有道路 8 作業構台 11 作業トンネル 22 導坑 40 橋台 DESCRIPTION OF SYMBOLS 1 Slope 3 Tunnel entrance 5 Main tunnel 6 Existing road 8 Working gantry 11 Working tunnel 22 Tunnel 40 Abutment

───────────────────────────────────────────────────── フロントページの続き (72)発明者 木村 厚之 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Atsuyuki Kimura 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 急峻斜面にトンネル坑口を施工するに当
たり、前記トンネル坑口の施工予定部よりも地山内部側
の本坑トンネル予定線に向かって現有道路から作業トン
ネルを掘削し、本坑トンネル予定線に作業トンネルが交
差したら、その交差位置からトンネル坑口の施工予定部
に向かって本坑トンネルを掘削し、この本坑トンネル内
から前記トンネル坑口の施工を行うことを特徴とする急
峻斜面におけるトンネル坑口の施工方法。
When constructing a tunnel entrance on a steep slope, a work tunnel is excavated from an existing road toward a main tunnel planned line on the inner side of the ground than a planned construction site of the tunnel entrance, and a main tunnel is planned. When the work tunnel intersects the line, the main tunnel is excavated from the intersection to the construction site of the tunnel entrance, and the tunnel entrance is constructed from within the main tunnel. Wellhead construction method.
【請求項2】 前記本坑トンネル内からトンネル坑口を
施工するに際し、本坑トンネルの掘削を、トンネル坑口
の施工予定部の手前で一旦止め、その位置から地山及び
斜面の補強工事を行いながら、導坑方式で本坑トンネル
を斜面に開口させて、トンネル坑口を施工することを特
徴とする請求項1記載の急峻斜面におけるトンネル坑口
の施工方法。
2. When constructing a tunnel entrance from inside the main tunnel, excavation of the main tunnel is temporarily stopped just before a planned portion of the tunnel entrance, and reinforcement of the ground and the slope is performed from that position. 2. The method according to claim 1, wherein the tunnel tunnel is opened on a slope by a sloping method, and the tunnel entrance is constructed.
【請求項3】 前記本坑トンネルを斜面に開通させた
後、外部に作業構台を構築し、該作業構台を利用して橋
台を構築することを特徴とする請求項1または2記載の
急峻斜面におけるトンネル坑口の施工方法。
3. The steep slope according to claim 1, wherein after the main tunnel is opened to a slope, a work gantry is constructed outside and the abutment is constructed using the work gantry. Construction method of tunnel tunnel entrance.
【請求項4】 前記トンネル坑口の施工予定部へ向けて
の本坑トンネルの掘削と同時に、前記交差位置からトン
ネル坑口の施工予定部と反対方向に本坑トンネルを掘削
することを特徴とする請求項1〜3のいずれかに記載の
急峻斜面におけるトンネル坑口の施工方法。
4. The main tunnel is excavated from the intersection at the same time as the main tunnel is excavated toward the planned site of the tunnel entrance in a direction opposite to the planned site of the tunnel entrance. Item 5. A method for constructing a tunnel entrance on a steep slope according to any one of Items 1 to 3.
JP08698797A 1997-04-04 1997-04-04 Construction method of tunnel wellhead on steep slope Expired - Fee Related JP3787796B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08698797A JP3787796B2 (en) 1997-04-04 1997-04-04 Construction method of tunnel wellhead on steep slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08698797A JP3787796B2 (en) 1997-04-04 1997-04-04 Construction method of tunnel wellhead on steep slope

Publications (2)

Publication Number Publication Date
JPH10280863A true JPH10280863A (en) 1998-10-20
JP3787796B2 JP3787796B2 (en) 2006-06-21

Family

ID=13902226

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08698797A Expired - Fee Related JP3787796B2 (en) 1997-04-04 1997-04-04 Construction method of tunnel wellhead on steep slope

Country Status (1)

Country Link
JP (1) JP3787796B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010281174A (en) * 2009-06-08 2010-12-16 Shimizu Corp Excavation method for proximity twin tunnel
CN103774691A (en) * 2014-02-10 2014-05-07 朱海涛 Three types of tunnel transverse traffic tubes and application methods thereof
JP2017008568A (en) * 2015-06-22 2017-01-12 大成建設株式会社 Tunnel joint structure and tunnel construction method
CN108004913A (en) * 2018-01-16 2018-05-08 中交公局第三工程有限公司 Steep cliff position Bridge-wire fusing time overall structure
JP2020159061A (en) * 2019-03-26 2020-10-01 株式会社奥村組 Method for constructing work pit intersection in mountain tunnel construction
CN113482630A (en) * 2021-08-06 2021-10-08 中铁二局第四工程有限公司 Pilot construction method applied to small-clear-distance double-hole tunnel
CN113832990A (en) * 2020-06-24 2021-12-24 中国电建集团华东勘测设计研究院有限公司 Arrangement structure for rapid excavation and support of giant high slope and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518447B (en) * 2011-11-17 2014-07-30 山东盛泉矿业有限公司 Roadway layout method for controlling roadway floor heave

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010281174A (en) * 2009-06-08 2010-12-16 Shimizu Corp Excavation method for proximity twin tunnel
CN103774691A (en) * 2014-02-10 2014-05-07 朱海涛 Three types of tunnel transverse traffic tubes and application methods thereof
CN103774691B (en) * 2014-02-10 2016-06-15 江西省交通设计研究院有限责任公司 The setting of three kinds of tunnel Lateral Holes and using method thereof
JP2017008568A (en) * 2015-06-22 2017-01-12 大成建設株式会社 Tunnel joint structure and tunnel construction method
CN108004913A (en) * 2018-01-16 2018-05-08 中交公局第三工程有限公司 Steep cliff position Bridge-wire fusing time overall structure
JP2020159061A (en) * 2019-03-26 2020-10-01 株式会社奥村組 Method for constructing work pit intersection in mountain tunnel construction
CN113832990A (en) * 2020-06-24 2021-12-24 中国电建集团华东勘测设计研究院有限公司 Arrangement structure for rapid excavation and support of giant high slope and construction method thereof
CN113482630A (en) * 2021-08-06 2021-10-08 中铁二局第四工程有限公司 Pilot construction method applied to small-clear-distance double-hole tunnel
CN113482630B (en) * 2021-08-06 2024-01-12 中铁二局第四工程有限公司 Advanced pilot pit construction method applied to small-clear-distance double-hole tunnel

Also Published As

Publication number Publication date
JP3787796B2 (en) 2006-06-21

Similar Documents

Publication Publication Date Title
CN107842368B (en) City tunnel Drilling mills the non-quick-fried excavation technology of mechanical combination
CN106703814A (en) Mined metro station hole pile construction method
CN106246201A (en) The excavation in tunnel and karst cave treatment method when small-sized solution cavity is positioned at tunneling surrounding
CN104847362B (en) Ground consisting of hard rock construction method across underground digging in subway station greatly
CN102535474A (en) Construction method for deep-foundation pit excavation
CN107060803A (en) A kind of method for tunnel construction of utilization pipe curtain slip casting
CN106121675A (en) Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
CN110130922A (en) A kind of construction method of line tunnel portal
CN108286442A (en) Excavation method suitable for a Support System in Soft Rock Tunnels quick closure cyclization of two steps
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN106121659B (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind
CN107288642A (en) PBA construction technologies
JPH11159275A (en) Whale bone construction method of large cross-section tunnel
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN109057802A (en) Shallow tunnel with big cross-section underpass of freeways construction method
JPH10280863A (en) Construction method for tunnel pit mouth in steep slope
CN110145315A (en) A kind of driving method weakening city shallow tunnel concussion of blasting
CN205605215U (en) Big section loess tunnel is grooving method construction structures in advance
KR101283663B1 (en) Method for digging two arch type tunnel
CN109386289A (en) A kind of explosion, sealing of hole, slip casting integral construction method
JP2594864B2 (en) Widening method of underground tunnel
KR100355946B1 (en) Construction method for open cutting tunnel
CN107013222A (en) A kind of the middle regions of the Yunnan Province red beds tunnel milling digging construction method close to existing railway
CN203925505U (en) A kind of preliminary bracing structure and constructing structure of underground construction
JP2003055985A (en) Connecting method of column to pile

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041129

A131 Notification of reasons for refusal

Effective date: 20050517

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050629

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060307

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060317

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100407

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20110407

LAPS Cancellation because of no payment of annual fees