JPH08134934A - Basement construction method - Google Patents

Basement construction method

Info

Publication number
JPH08134934A
JPH08134934A JP6274793A JP27479394A JPH08134934A JP H08134934 A JPH08134934 A JP H08134934A JP 6274793 A JP6274793 A JP 6274793A JP 27479394 A JP27479394 A JP 27479394A JP H08134934 A JPH08134934 A JP H08134934A
Authority
JP
Japan
Prior art keywords
wall
ground
constructed
excavated
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP6274793A
Other languages
Japanese (ja)
Inventor
Tetsuya Sasaki
哲也 佐々木
Ryoji Komatsu
亮二 小松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6274793A priority Critical patent/JPH08134934A/en
Publication of JPH08134934A publication Critical patent/JPH08134934A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: To safely construct a low-rise basement which is roughly several meters deep into the ground, with no ground subsidence caused in the adjacent ground even no earth retaining wall is provided by employing a reverse placing method by means of two step excavation. CONSTITUTION: The inner side ground of a scarecement section 4 to which a foundation work has been performed, is lightly excavated, the scarecement section 4 and its inner circumference are covered by a water proof sheet 3A, and a wall 8A formed out of reinforced concrete is then constructed along the excavated wall. Reinforced concrete 12 is then placed over the scarecement section 4 and the wall 8A, and a structural body in a reversed L shape is constructed. The ground having been lightly excavated is then excavated to a specified depth, and it is covered by a water proof sheet 3B. Subsequently, a wall formed out of reinforced shot crete is constructed along the excavated wall, and an outer wall 15 is constructed while being integrated with the existing wall 8A. A bottom board 16 is then constructed by placing concrete in the bottom section, and the floor board 17 of a first floor is then constructed by placing concrete in the crown.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、比較的小規模の低層の
地下室を構築する構築方法に関する。
FIELD OF THE INVENTION The present invention relates to a construction method for constructing a relatively small-scale low-rise basement.

【0002】[0002]

【従来の技術】市街地や住宅地などの密集地に地下室を
構築する場合は隣地(家)と近接して構築する場合が多
く、隣地(家)の地盤沈下を防止するため、構築する地
下室が比較的小規模で低層であっても周囲に仮設の土留
め壁を設置した後、その内側を掘削するのが一般的であ
る。
[Prior Art] When constructing a basement in a dense area such as an urban area or a residential area, the basement is often constructed close to the adjacent land (house). Even if it is a relatively small and low-rise building, it is common to dig the inside after installing a temporary earth retaining wall around it.

【0003】[0003]

【発明が解決しようとする課題】土留め壁はH型鋼を地
盤に打ち込み、その間に横矢板を挿入して設置されるの
が一般的であり、相当の工事費を必要とする。そして、
土留め壁は地盤の崩壊は十分防止するが、剛性が十分と
はいえないので地盤表層部分の移動による地盤沈下を完
全には防止できない場合がある。
The earth retaining wall is generally installed by driving H-section steel into the ground and inserting a transverse sheet pile between them, which requires a considerable construction cost. And
Although the earth retaining wall sufficiently prevents the ground from collapsing, it may not be able to completely prevent the ground subsidence due to the movement of the surface layer of the ground because it does not have sufficient rigidity.

【0004】[0004]

【課題を解決するための手段】本発明は、二段階掘削に
よる逆打ち工法を採用することにより、地盤の崩壊は勿
論のこと、表層部分の移動による地盤沈下を招くことな
しに比較的小規模の低層の地下室を構築することを目的
とする。
According to the present invention, by adopting the upside down construction method by two-stage excavation, not only the collapse of the ground but also the subsidence of the ground due to the movement of the surface layer is relatively small. The purpose is to build a low rise basement.

【0005】即ち、本発明は、(A)基礎地業を施した
犬走り部分の内側地盤を土留め壁を必要としない程度に
浅く掘削し、犬走り部分および内周辺を防水シートで覆
う工程、(B)掘削壁に沿って鉄筋コントクリート造り
の壁を構築する工程、(C)犬走り部分および上記鉄筋
コントクリート造り壁の上にコンクリートを打設して鉄
筋コンクリート造り板と上記鉄筋コントクリート造り壁
とを一体化した逆L字型構造体を構築する工程、(D)
浅く掘削された地盤を所定の深さまで掘削し、掘削面を
防水シートで覆う工程、(E)新たに掘削された掘削壁
に沿って鉄筋ショットクリート造りの壁を構築して既設
の鉄筋コントクリート造りの壁と一体化した外壁を構築
する工程、(F)底にコンクリートを打設して鉄筋コン
クリート造りの底板を構築する工程、(G)天端にコン
クリートを打設して鉄筋コンクリート造りの1階床板を
構築する工程、よりなる地下室の構築方法である。
That is, according to the present invention, (A) a step of excavating the inner ground of a dog running portion that has been subjected to basic groundwork to a depth that does not require a retaining wall, and covering the dog running portion and the inner periphery with a waterproof sheet. , (B) a step of constructing a reinforced concrete wall along the excavation wall, (C) a dog running portion and concrete laid on the reinforced concrete wall and the reinforced concrete plate and the reinforced concrete wall Step of constructing an inverted L-shaped structure integrated with a building wall, (D)
The process of excavating the shallow excavated ground to a predetermined depth and covering the excavation surface with a waterproof sheet, (E) Constructing a rebar shotcrete wall along the newly excavated excavation wall to construct an existing rebar control The process of constructing the outer wall integrated with the built wall, the process of (F) placing concrete on the bottom to construct the bottom plate made of reinforced concrete, and (G) the first floor of the reinforced concrete structure placing concrete on the top. It is a method of constructing a basement, which comprises the steps of constructing a floorboard.

【0006】本発明の第一の要点は、犬走り部分で取り
囲まれた地盤の掘削を二段階に分けて行い、第一段目の
掘削を0.5〜1m程度の土留めを必要としない深さに
留めておき、掘削壁面および犬走り部分に跨がって一体
となった逆L字型の鉄筋コンクリート造り構造体を構築
することによって、犬走り部分下の基礎で逆L字型構造
体の荷重を支持し、掘削した地山の土圧に抵抗して地山
表層部分の移動を防止する点である。
The first point of the present invention is to excavate the ground surrounded by the dog running portion in two stages, and the excavation of the first stage does not require earth retaining of about 0.5 to 1 m. By keeping it at the depth and constructing an inverted L-shaped reinforced concrete structure that is integrated over the excavation wall surface and the dog running portion, the inverted L-shaped structure is formed on the foundation under the dog running portion. This is to support the load of, and resist the earth pressure of the excavated ground and prevent the movement of the surface layer of the ground.

【0007】本発明の第二の要点は、犬走り部分および
掘削面を防水シートで覆い、施工時の雨水の浸入による
地山の流動化を防止するとともに、地下室構築後の防水
層としての機能を発揮させる点である。
The second essential point of the present invention is to cover the dog running portion and the excavated surface with a waterproof sheet to prevent fluidization of the ground due to infiltration of rainwater during construction and to function as a waterproof layer after construction of the basement. It is a point to demonstrate.

【0008】上記の各要点の相乗効果により、土留め壁
を設置しなくても隣地の地盤沈下を招くことなしに地下
数m程度の低層の地下室を構築することが可能となる。
Due to the synergistic effect of each of the above-mentioned points, it becomes possible to construct a low-rise basement of about several meters underground without inviting ground subsidence in the adjacent land without installing a retaining wall.

【0009】本発明の上記(B)工程の鉄筋コントクリ
ート造りの壁の構築は配筋後、型枠を組みコントクリー
トを打設する通常の工法によってもよいし、配筋−吹付
けを繰り返して所定の厚さの鉄筋コントクリート造りと
するショットクリート工法によってもよい。
In the above step (B) of the present invention, the wall of the reinforcing bar contcrete structure may be constructed by a normal construction method in which the formwork is assembled after the reinforcing bar is arranged and the contcrete is placed, or the reinforcing bar-spraying is repeated. Alternatively, the shotcrete construction method may be used, in which a reinforcing bar control cleat having a predetermined thickness is formed.

【0010】[0010]

【実施例】以下図面を参照しながら本発明を説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings.

【0011】図1は本発明方法の施工例の施工手順を示
す工程縦断面図である。図2(a)は犬走り部分にコン
クリートを打設する直前の1次掘削壁周辺の縦断面図、
図2(b)は地下室完成時の平面図である。図1、図2
を参照しながら施工例の施工手順を説明する。(本施工
例は外壁上部の構築はショットクリート工法で行い、外
壁の施工に引き続いて内壁を構築した例である。) (1)隣地との境界線1に近い土地に掘削穴2を設け、
そこに地下室を構築することにする。(図1(a)) (2)犬走り部分4に基礎地業を施工し、その内側地盤
を1m程度総掘りして1次掘削穴2Aを形成し犬走り部
分4表面および1次掘削穴2Aの外周部を防水シート3
Aで覆う。(図1(b)) (3)1次掘削壁に沿って1次配筋を行う。1次配筋は
縦筋6A、横筋10A、および後で構築される内壁との
接合筋7が主なもので縦筋6A、横筋10Aにはショッ
トクリート工法のための平金網9Aが取付けられてい
る。縦筋6Aの下方は十分に土中に挿入されている。シ
ョットクリートを吹付け1次ショットクリート層8Aを
形成する。(図1(c)、図2(a)) (4)1次ショットクリート層8Aの内側に壁に沿って
2次配筋を行う。2次配筋は縦筋6B、横筋10Bの配
筋であり、縦筋6B、横筋10Bには(3)と同様に平
金網9Bが取付けられている。縦筋6Bの下方も同様に
十分に土中に挿入されている。この際、犬走り部分にも
鉄筋11を配筋する。その後、ショットクリートを吹付
け2次ショットクリート層8Bを形成する。(図1
(d)、図2(a)) (5)犬走り部分にコンクリートを打設して鉄筋コンク
リート板12を形成する。鉄筋コンクリート板12は既
に形成された鉄筋ショットクリート壁8と一体化し逆L
字型構造体となる。(図1(e)、図2(a)) (6)所定の深さまで総掘りによる2次掘削を行ない、
掘削穴2Bを形成し、掘削面全面を防水シート3Bで覆
う。防水シート3Bの取付けは2次掘削により露出した
防水シート3Aの下端を適宜切断し、それに防水シート
3Bの上端を重ね合わせて接着して行う。上記(3)、
(4)と同様に2次掘削壁に沿って1次配筋−1次吹付
け−2次配筋−2次吹付けを行ない、2次掘削壁に沿っ
た鉄筋ショットクリート壁を既設の鉄筋ショットクリー
ト壁8の下方に一体として形成し、外壁15を構築す
る。(図1(f)) (7)外壁15の内面に墨出し、底板の配筋(内壁接合
筋を含めて)をし、コンクリートを打設して底板16を
構築する。(図1(g)) (8)内壁18の構築については図示してないが、既設
の接合筋に合わせて内壁の配筋、型枠の組立を行ないコ
ンクリートを打設して鉄筋コンククリート内壁を構築す
る方法やショットクリート工法用パネル(例えば、プラ
スチックフォーム板の両面に平金網を配置し、プラスチ
ックフォーム板を斜めに貫通するラチス線で両面の平金
網を相互に溶接した立体金網パネルなど)を既設の接合
筋に合わせて建て込み、所定の配筋を行った後、ショッ
トクリートを吹付ける方法が採用される。施工性の面か
らは当然後者を採用するのが好ましい。
FIG. 1 is a process vertical sectional view showing a construction procedure of a construction example of the method of the present invention. Fig. 2 (a) is a vertical cross-sectional view of the area around the primary excavation wall immediately before placing concrete in the dog running part,
FIG. 2 (b) is a plan view of the completed basement. 1 and 2
The construction procedure of the construction example will be described with reference to. (This construction example is an example in which the upper part of the outer wall is constructed by the shotcrete method, and the inner wall is constructed following the construction of the outer wall.) (1) The excavation hole 2 is provided in the land near the boundary line 1 with the adjacent land,
I will build a basement there. (Fig. 1 (a)) (2) A basic ground work was applied to the dog running part 4 and the inner ground was digged about 1 m to form a primary drilling hole 2A, and the surface of the dog running part 4 and the primary drilling hole were formed. 2A outer peripheral part of the waterproof sheet 3
Cover with A. (Fig. 1 (b)) (3) Primary bar arrangement is performed along the primary excavation wall. The primary bars are mainly vertical bars 6A, horizontal bars 10A, and connecting bars 7 that are connected to the inner wall to be constructed later. The vertical bars 6A and horizontal bars 10A have flat wire nets 9A for the shotcrete construction method attached. There is. The lower part of the vertical line 6A is sufficiently inserted in the soil. Shotcrete is sprayed to form primary shotcrete layer 8A. (FIGS. 1 (c) and 2 (a)) (4) Secondary reinforcement is performed along the wall inside the primary shot cleat layer 8A. The secondary reinforcing bar is a vertical bar 6B and a horizontal bar 10B, and a flat wire net 9B is attached to the vertical bar 6B and the horizontal bar 10B as in (3). Similarly, the lower part of the vertical line 6B is also sufficiently inserted in the soil. At this time, the reinforcing bar 11 is also arranged in the dog running part. Then, shotcrete is sprayed to form the secondary shotcrete layer 8B. (Figure 1
(D), FIG. 2 (a)) (5) Concrete is cast in the dog running portion to form the reinforced concrete plate 12. The reinforced concrete plate 12 is integrated with the already formed reinforced shotcrete wall 8 to form an inverted L
It becomes a character type structure. (Fig. 1 (e), Fig. 2 (a)) (6) Perform secondary digging by total digging to a predetermined depth,
The excavation hole 2B is formed, and the entire excavation surface is covered with the waterproof sheet 3B. The attachment of the waterproof sheet 3B is performed by appropriately cutting the lower end of the waterproof sheet 3A exposed by the secondary excavation, and stacking and adhering the upper end of the waterproof sheet 3B on it. Above (3),
Similar to (4), primary reinforcement-primary spraying-secondary reinforcement-secondary spraying is performed along the secondary excavation wall, and reinforcing bar shotcrete wall along the secondary excavation wall is used for existing reinforcement. It is integrally formed below the shotcrete wall 8 to construct the outer wall 15. (FIG. 1 (f)) (7) The inner surface of the outer wall 15 is marked, the bottom plate is reinforced (including the inner wall joints), and concrete is cast to construct the bottom plate 16. (Fig. 1 (g)) (8) Although the construction of the inner wall 18 is not shown, the inner wall is reinforced and the formwork is assembled in accordance with the existing joints, and concrete is laid to reinforce concrete inner wall. Panel for construction and shotcrete method (for example, three-dimensional wire mesh panel in which flat wire nets are placed on both sides of a plastic foam plate, and flat wire nets on both sides are welded to each other by lattice lines that obliquely penetrate the plastic foam plate) A method is adopted in which the slab is built in accordance with the existing joint reinforcement, the predetermined reinforcement is performed, and then shotcrete is sprayed. From the viewpoint of workability, it is naturally preferable to adopt the latter.

【0012】(9)外壁15、内壁18の天端に所定の
配筋後、コンクリートを打設して鉄筋コンクリート造り
の1階床板17を構築する。(図1(h)) 1階床板17の構築に際しても、型枠の組立、配筋を行
ないコンクリートを打設する方法、波型鋼板やプレキャ
ストコンクリート板を捨て型枠として敷設し、配筋、コ
ンクリート打設を行う方法などの通常の方法が採用され
る。1階床板17の構築の場合も施工性の面から後者を
採用するのが好ましい。
(9) After arranging a predetermined amount of reinforcement on the top ends of the outer wall 15 and the inner wall 18, concrete is placed to construct the first floor slab 17 made of reinforced concrete. (Fig. 1 (h)) When constructing the first-floor floorboard 17, a method of assembling the formwork, placing the concrete and placing concrete, laying a corrugated steel plate or a precast concrete plate as a discard formwork, A normal method such as a method of placing concrete is adopted. Also in the case of constructing the first-floor floor board 17, it is preferable to adopt the latter from the viewpoint of workability.

【0013】このようにして、施工例の地下室の構築が
完了する。(図2(b)) 上記の施工例は平地に地下室を構築する場合で犬走りは
外壁天端を一周している。しかし、傾斜地に地上部と地
下部を同時に構築する場合も多い。その場合には図3に
示すように山側の比較的深く掘削する部分と谷側の比較
的浅く掘削する部分とに区分し、本発明による構築方法
は山側のみに適用し、比較的浅く掘削する谷側はオープ
ンカット方式で施工する。従って、谷側部分の底板は山
側部分の外壁下部の構築に先行して構築されることにな
り、逆L字型構造体は図3(c)に示すように山側の1
辺のみに構築されることになる。傾斜地ではこのように
逆L字型構造体の設置面積は小さくなるが、土圧がかか
るのは山側からが殆どであり、谷側に構築した躯体が逆
L字型構造体とともにこの土圧に抵抗するので、山側隣
地の地盤沈下を招く恐れはない。
In this way, the construction of the basement of the construction example is completed. (FIG. 2 (b)) The above construction example is a case where a basement is constructed on a flat ground, and dog running runs around the top of the outer wall. However, there are many cases where the above-ground part and the underground part are simultaneously constructed on the sloping land. In that case, as shown in FIG. 3, it is divided into a relatively deep excavation portion on the mountain side and a relatively shallow excavation portion on the valley side, and the construction method according to the present invention is applied only to the mountain side to excavate relatively shallowly. The valley side will be constructed using the open cut method. Therefore, the bottom plate of the valley side portion is constructed prior to the construction of the lower portion of the outer wall of the mountain side portion, and the inverted L-shaped structure is formed on the mountain side as shown in FIG. 3 (c).
It will be built only on the edges. In the sloping ground, the installation area of the inverted L-shaped structure is small in this way, but most of the earth pressure is applied from the mountain side, and the skeleton built on the valley side is exposed to this earth pressure together with the inverted L-shaped structure. Since it resists, there is no fear of causing land subsidence on the land adjacent to the mountain side.

【0014】[0014]

【発明の効果】土留め壁を設置しなくても隣地の地盤沈
下を招くことなしに地下数m程度の低層の地下室を構築
することが可能となる。
[Effects of the Invention] It is possible to construct a low-rise basement of about several meters underground without inviting ground subsidence in the adjacent land without installing a retaining wall.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明方法の施工例の施工手順を示す工程縦断
面図である。
FIG. 1 is a process vertical sectional view showing a construction procedure of a construction example of a method of the present invention.

【図2】(a)は犬走り部分にコンクリートを打設する
直前の1次掘削壁周辺の縦断面図、(b)は地下室完成
時の平面図である。
FIG. 2 (a) is a vertical cross-sectional view around the primary excavation wall immediately before placing concrete on the dog running portion, and FIG. 2 (b) is a plan view of the completed basement.

【図3】本発明方法の傾斜地での適用例を示すもので、
(a)、(b)は施工中の縦断面図であり、(c)は完
成時の平面図である。
FIG. 3 shows an example of application of the method of the present invention on a sloping land,
(A), (b) is a longitudinal cross-sectional view during construction, (c) is a plan view at the time of completion.

【符号の説明】[Explanation of symbols]

1・・境界線、2・・掘削穴、2A・・1次掘削穴、2
B・・2次掘削穴、3・・防水シート、3A・・上部防
水シート、3B・・下部防水シート、4・・犬走り、6
A・・1次掘削穴1次配筋縦筋、6B・・1次掘削穴2
次配筋縦筋、7・・内壁接合筋、8・・1次掘削穴鉄筋
ショットクリート壁、8A・・1次掘削穴1次ショット
クリート層、8B・・1次掘削穴2次ショットクリート
層、9A,9B・・平金網、10A・・1次配筋横筋、
10B・・2次配筋横筋、11・・犬走り部鉄筋、12
・・犬走り部鉄筋コンクリート板、13A・・2次掘削
穴1次配筋縦筋、13B・・2次掘削穴2次配筋縦筋、
14A・・2次掘削穴1次ショットクリート層、14B
・・2次掘削穴2次ショットクリート層、15・・外
壁、16・・底板、17・・1階床板。
1 ... Boundary line, 2 ... Drilling hole, 2A ... Primary drilling hole, 2
B ... Secondary drilling hole, 3 ... Waterproof sheet, 3A ... Upper waterproof sheet, 3B ... Lower waterproof sheet, 4 ... Dog running, 6
A ... Primary drilling hole primary reinforcement longitudinal bar, 6B ... Primary drilling hole 2
Secondary bar longitudinal bar, 7 ... inner wall joint, 8 ... primary drilling hole rebar shotcrete wall, 8A ... primary drilling hole primary shotcrete layer, 8B ... primary drilling hole secondary shotcrete layer , 9A, 9B ··· Flat wire mesh, 10A ··
10B ... Secondary bar arrangement horizontal bar, 11 ... Dog running rebar, 12
..In dog running part reinforced concrete plate, 13A ... Secondary drilling hole primary reinforcing bar longitudinal bar, 13B ... Secondary drilling hole secondary reinforcing bar longitudinal bar,
14A ... Secondary drill hole primary shotcrete layer, 14B
..Secondary drilling hole secondary shotcrete layer, 15 ... outer wall, 16 ... bottom plate, 17 ... first floor.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 (A)基礎地業を施した犬走り部分の内
側地盤を土留め壁を必要としない程度に浅く掘削し、犬
走り部分および内周辺を防水シートで覆う工程、(B)
掘削壁に沿って鉄筋コンクリート造りの壁を構築する工
程、(C)犬走り部分および上記鉄筋コントクリート造
り壁の上にコンクリートを打設して鉄筋コンクリート造
り板と上記鉄筋コントクリート造り壁とを一体化した逆
L字型構造体を構築する工程、(D)浅く掘削された地
盤を所定の深さまで掘削し、掘削面を防水シートで覆う
工程、(E)新たに掘削された掘削壁に沿って鉄筋ショ
ットクリート造りの壁を構築して既設の鉄筋コントクリ
ート造りの壁と一体化した外壁を構築する工程、(F)
底にコンクリートを打設して鉄筋コンクリート造りの底
板を構築する工程、(G)天端にコンクリートを打設し
て鉄筋コンクリート造りの1階床板を構築する工程、よ
りなる地下室の構築方法。
1. A process of (A) excavating the inner ground of a dog running portion that has been subjected to basic groundwork to a depth that does not require a retaining wall, and covering the dog running portion and the inner periphery with a waterproof sheet, (B)
The step of constructing a reinforced concrete wall along the excavation wall, (C) Injecting concrete on the dog running part and the reinforced concrete wall, and integrating the reinforced concrete plate and the reinforced concrete wall The step of constructing the inverted L-shaped structure, (D) the step of excavating the shallowly excavated ground to a predetermined depth, and the step of covering the excavation surface with the waterproof sheet, (E) the excavation wall along the newly excavated wall Building a wall made of reinforced shotcrete and an outer wall integrated with the existing wall made of reinforced concrete, (F)
A method of constructing a basement, comprising the steps of placing concrete on the bottom to construct a reinforced concrete bottom plate, and (G) placing concrete on the top to construct a reinforced concrete first-floor floorboard.
JP6274793A 1994-11-09 1994-11-09 Basement construction method Withdrawn JPH08134934A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6274793A JPH08134934A (en) 1994-11-09 1994-11-09 Basement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6274793A JPH08134934A (en) 1994-11-09 1994-11-09 Basement construction method

Publications (1)

Publication Number Publication Date
JPH08134934A true JPH08134934A (en) 1996-05-28

Family

ID=17546646

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6274793A Withdrawn JPH08134934A (en) 1994-11-09 1994-11-09 Basement construction method

Country Status (1)

Country Link
JP (1) JPH08134934A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018009336A (en) * 2016-07-12 2018-01-18 株式会社 Showa Underground space construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018009336A (en) * 2016-07-12 2018-01-18 株式会社 Showa Underground space construction method

Similar Documents

Publication Publication Date Title
US7500807B2 (en) Method of construction using sheet piling sections
JPH09268583A (en) Structural steel embedded half precast concrete member and construction method of underground structure using the same member
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JP5169638B2 (en) Construction method of underground structure
JPH0684690B2 (en) Building basement extension method
JPH08134934A (en) Basement construction method
JP3641227B2 (en) Construction method of underground structure
JPH1136296A (en) Pc hollow pile and construction method for underground structure
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JP2973815B2 (en) Construction method of pressure-resistant wall under the building
JP3173701B2 (en) Basic structure of building and its construction method
CN205557573U (en) Underground structure
KR100592397B1 (en) storey spacing support ssoldier pile soil retaining wall
JPS601458B2 (en) Precast concrete basement construction method
JPH11152762A (en) Structure and its construction method
JPH08134936A (en) Basement construction method
JP2565452B2 (en) Construction method of self-supporting retaining wall
JPS5841227Y2 (en) Element for mountain retainer
KR100999410B1 (en) Assembled wale beam and construction method of underground structure using the same
JPS5853321Y2 (en) Element for mountain retainer
JP2022091053A (en) Reinforcement body of earth retaining wall, and installation method of reinforcement body
JP3269599B2 (en) How to build an underground tank
JPH03228921A (en) Execution method for concrete foundation work
JP2556415B2 (en) Construction method of self-supporting retaining wall
JP4072118B2 (en) Underfloor storage space and construction method

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020115