JP3466520B2 - Tunnel construction method and tunnel - Google Patents

Tunnel construction method and tunnel

Info

Publication number
JP3466520B2
JP3466520B2 JP30154799A JP30154799A JP3466520B2 JP 3466520 B2 JP3466520 B2 JP 3466520B2 JP 30154799 A JP30154799 A JP 30154799A JP 30154799 A JP30154799 A JP 30154799A JP 3466520 B2 JP3466520 B2 JP 3466520B2
Authority
JP
Japan
Prior art keywords
tunnel
constructing
work
upper half
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP30154799A
Other languages
Japanese (ja)
Other versions
JP2001123788A (en
Inventor
充功 岩田
和義 藤本
博史 大屋
智寿 萩原
健 藤井
泰明 宇野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Chemical Grouting Co Ltd
Original Assignee
Kajima Corp
Chemical Grouting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Chemical Grouting Co Ltd filed Critical Kajima Corp
Priority to JP30154799A priority Critical patent/JP3466520B2/en
Publication of JP2001123788A publication Critical patent/JP2001123788A/en
Application granted granted Critical
Publication of JP3466520B2 publication Critical patent/JP3466520B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明はトンネルの構築方法
およびトンネルに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method and a tunnel.

【0002】[0002]

【従来の技術】従来、トンネルの施工においては、図1
2に示すようにトンネル101の上半部を掘削する時の
トンネル101の安定の確保および地表面103の沈下
対策として、先受け工109をトンネル101の上半部
分に施工していた。また、トンネル支保工113の沈下
対策のための脚部補強および下半掘削時の側壁防護のた
めのフットパイル111については、トンネル101坑
内より施工していた。尚、図12において、115は、
コンクリートである。
2. Description of the Related Art Conventionally, as shown in FIG.
As shown in FIG. 2, as a measure to secure the stability of the tunnel 101 when excavating the upper half of the tunnel 101 and to prevent the ground surface 103 from sinking, the front receiving work 109 was constructed on the upper half of the tunnel 101. Further, the foot pile 111 for reinforcing the leg portion for the subsidence countermeasure of the tunnel support work 113 and for protecting the side wall at the time of excavating the lower half was constructed from the inside of the tunnel 101. In FIG. 12, 115 is
It is concrete.

【0003】[0003]

【発明が解決しようとする課題】ところで、この施工方
法の場合、地表面沈下抑制効果は少ない。また、側壁防
護のためのフットパイル111を、トンネル坑内から施
工するので、トンネル掘削の工程に影響があり、工期が
延びる等の問題点がある。
By the way, in the case of this construction method, the effect of suppressing the ground subsidence is small. Further, since the foot pile 111 for protecting the side wall is constructed from inside the tunnel mine, there is a problem that the tunnel excavation process is affected and the construction period is extended.

【0004】本発明はこのような問題を鑑みてなされた
ものでその目的とするところは、トンネル掘削時におい
て地表面の沈下が少なく、また、工期を短縮できるトン
ネルの構築方法およびトンネルを提供することにある。
The present invention has been made in view of the above problems, and an object of the present invention is to provide a tunnel construction method and a tunnel in which ground subsidence is small during tunnel excavation and the construction period can be shortened. Especially.

【0005】[0005]

【課題を解決するための手段】前述した目的を達成する
ために本発明の第1の発明は、(a)トンネルの計画位
置の側方部に、地表面から注入管により固化材を地盤に
注入して改良体を設ける工程と、(b)前記トンネルの
計画位置に沿って、先受け工を施工しつつトンネルの掘
削を行う工程と、を具備し、前記先受け工の一部が前記
改良体に重複して設けられ、トンネル周辺にグランドア
ーチが形成されることを特徴とするトンネルの構築方法
である。
In order to achieve the above-mentioned object, the first invention of the present invention is: (a) In a lateral portion of a planned position of a tunnel, a solidified material is applied to the ground by an injection pipe from the ground surface. And a step of (b) excavating the tunnel while constructing a preparatory work along the planned position of the tunnel, wherein a part of the preparatory work is performed. The method for constructing a tunnel is characterized in that the ground arch is formed around the tunnel so as to be overlapped with the improved body.

【0006】第2の発明は、第1の発明によるトンネル
の構築方法により構築されたことを特徴とするトンネル
である。
A second invention is a tunnel constructed by the tunnel construction method according to the first invention.

【0007】[0007]

【発明の実施の形態】以下、図面に基づいて本発明の実
施の形態を詳細に説明する。図1から図11は、トンネ
ルの構築方法を示す図である。以下、図1から図11に
基づき、トンネルの構築方法を説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described in detail below with reference to the drawings. 1 to 11 are diagrams showing a method of constructing a tunnel. Hereinafter, a method of constructing a tunnel will be described with reference to FIGS. 1 to 11.

【0008】図1、図2、図4、図6は、トンネルの構
築方法の説明図であり、トンネルの側方から見た図であ
る。図3は図2のA−A断面図、図5は、図4のB−B
断面図、図7、図8は、図6のC−C断面図、図9、図
10は、図6のD−D断面図、図11は、完成したトン
ネルの断面図である。
1, FIG. 2, FIG. 4, and FIG. 6 are explanatory views of a method of constructing a tunnel, and are views seen from the side of the tunnel. 3 is a sectional view taken along line AA of FIG. 2, and FIG. 5 is taken along line BB of FIG.
Sectional views, FIGS. 7 and 8 are CC sectional views of FIG. 6, FIGS. 9 and 10 are DD sectional views of FIG. 6, and FIG. 11 is a sectional view of the completed tunnel.

【0009】図1に示す地表面1の下方に、計画トンネ
ル位置3にトンネルを構築する場合、図2および図3に
示すように、計画トンネル位置3の側方部に、地表面1
より、注入管7を挿入し、注入管7よりセメントミルク
等の固化材等を地盤内に注入し、改良体5を構築して、
計画トンネル位置3の側方部の地盤改良を行う。改良体
5として、高圧噴射攪拌系等を用いると、品質のよい改
良体5が得られる。このようにして、計画トンネル位置
3の側方部分に連続して改良体5を設ける。
When constructing a tunnel at the planned tunnel position 3 below the ground surface 1 shown in FIG. 1, as shown in FIGS. 2 and 3, the ground surface 1 is provided at the side of the planned tunnel position 3.
Then, the injection pipe 7 is inserted, and the solidified material such as cement milk is injected into the ground through the injection pipe 7 to construct the improved body 5,
Ground improvement on the side of the planned tunnel position 3 will be carried out. If a high-pressure jet stirring system or the like is used as the improvement body 5, the quality improvement body 5 can be obtained. In this way, the improving body 5 is provided continuously to the side portion of the planned tunnel position 3.

【0010】図4において、6aは、既に掘削が完了し
たトンネル上半の切羽面を示す。この状態で、トンネル
の上半部に、先受け工9を設ける(図5)。先受け工法
としては、長尺鋼管先受け工法等を用いる場合は、ジャ
ンボ(図示せず)等の機械により、地盤内を掘削し、こ
の孔に鋼管9を設けた後、鋼管9の周囲にセメントミル
ク等を注入する。この時、鋼管9の両外側の鋼管9a、
9b等は、改良体5に重複するように設けられる(図
5)。
In FIG. 4, 6a shows the face of the upper half of the tunnel, which has already been excavated. In this state, the front receiving work 9 is provided in the upper half part of the tunnel (FIG. 5). When the long steel pipe front receiving method is used as the front receiving method, the inside of the ground is excavated by a machine such as a jumbo (not shown), and the steel pipe 9 is provided in this hole, and then the steel pipe 9 is surrounded. Inject cement milk, etc. At this time, the steel pipes 9a on both outer sides of the steel pipe 9,
9b etc. are provided so that it may overlap with the improvement body 5 (FIG. 5).

【0011】鋼管9a、9bを改良体5に重複させるこ
とにより、トンネル掘削前にトンネル周辺に堅固なグラ
ンドアーチができることから、その内側のトンネル掘削
の安全性が増すとともに、地表面1への影響を防ぐ効果
を得る。すなわち、トンネルの掘削予定場所の上部は、
鋼管9で保護され、側部は改良体5で保護されるので、
内側のトンネル掘削時の安全性が増す。
By overlapping the steel pipes 9a and 9b with the improvement body 5, a strong ground arch can be formed around the tunnel before the tunnel is excavated. Therefore, the safety of the tunnel excavation inside the tunnel is increased and the influence on the ground surface 1 is increased. Get the effect of preventing. That is, the upper part of the tunnel excavation site is
Since it is protected by the steel pipe 9 and the side part is protected by the improvement body 5,
The safety when excavating the inner tunnel is increased.

【0012】次に、トンネルの上半掘削部11の掘削を
行う(図6、図7)。即ち、図4に示す切羽6aに対し
て、ブレーカー等を用いて掘削し、上半部分の支保工
(鋼製支保工+吹付けコンクリート)13を設ける(図
8)。この時、支保工(鋼製支保工+吹付けコンクリー
ト)13は、先行して施工してある改良体5によって支
持される。図8は、上半掘削部11が掘削された状態の
トンネルを示す。
Next, the upper half excavation portion 11 of the tunnel is excavated (FIGS. 6 and 7). That is, the face 6a shown in FIG. 4 is excavated by using a breaker or the like, and an upper half supporting work (steel supporting work + shotcrete) 13 is provided (FIG. 8). At this time, the supporting work (steel supporting work and shotcrete) 13 is supported by the improvement body 5 which was constructed in advance. FIG. 8 shows the tunnel in a state where the upper half excavation portion 11 has been excavated.

【0013】また、図9から図10に示されるように、
上半部の切羽6bよりも後方で下半掘削部17の掘削を
行う。即ち、下半掘削部17をブレーカ(図示せず)等
で距離L1ずつ掘削し(図9)、下半部分の支保工(鋼
製支保工+吹付けコンクリート)19を設ける(図1
0)。
Further, as shown in FIGS. 9 to 10,
Excavation of the lower half excavation part 17 is performed behind the face 6b of the upper half. That is, the lower half excavating portion 17 is excavated by a breaker (not shown) or the like at each distance L1 (FIG. 9), and the supporting work (steel supporting work + spraying concrete) 19 of the lower half portion is provided (FIG. 1).
0).

【0014】下半部分を掘削する時には、先行してトン
ネル側部に改良体5が施工してあるため、改良体5によ
って、側壁防護の効果が得られる。以後、図4から、図
10に示す工程を繰り返す。そして図11に示すよう
に、内側に、コンクリート15、21を更に設ける。
When excavating the lower half portion, since the improving body 5 is applied to the side of the tunnel in advance, the improving body 5 provides the side wall protection effect. Thereafter, the steps shown in FIG. 4 to FIG. 10 are repeated. Then, as shown in FIG. 11, concrete 15 and 21 are further provided inside.

【0015】以上のように、本実施の形態によれば、改
良体5を設けることにより、先受け工9と改良体5とで
形成するグランドアーチにより地表面1の沈下が防がれ
る。また、支保工(鋼製支保工+吹付けコンクリート)
13は、改良体5に支持されるので安定する。さらに、
下半掘削時には、改良体5により、側壁防護の役割が行
われ、安全にトンネルを構築できる。また、改良体5
は、地表面1から施工されるので、施工が容易であり、
工期延長の原因とはならない。
As described above, according to the present embodiment, by providing the improvement body 5, the ground arch formed by the front receiving work 9 and the improvement body 5 prevents the ground surface 1 from sinking. Also, support (steel support + shotcrete)
13 is stable because it is supported by the improving body 5. further,
At the time of excavating the lower half, the improved body 5 plays a role of protecting the side wall, so that the tunnel can be safely constructed. In addition, improved body 5
Is constructed from the ground surface 1, so construction is easy,
It does not cause the extension of the construction period.

【0016】[0016]

【発明の効果】以上、詳細に説明したように本発明によ
れば、トンネル掘削時において地表面の沈下が少なく、
また、工期を短縮できるトンネルの構築方法およびトン
ネルを提供することができる。
As described above in detail, according to the present invention, the subsidence of the ground surface during tunnel excavation is small,
Further, it is possible to provide a tunnel construction method and a tunnel that can shorten the construction period.

【図面の簡単な説明】[Brief description of drawings]

【図1】トンネルの構築方法を示す図FIG. 1 is a diagram showing a method of constructing a tunnel.

【図2】トンネルの構築方法を示す図FIG. 2 is a diagram showing a tunnel construction method.

【図3】トンネルの構築方法を示す図FIG. 3 is a diagram showing a method of constructing a tunnel.

【図4】トンネルの構築方法を示す図FIG. 4 is a diagram showing a method of constructing a tunnel.

【図5】トンネルの構築方法を示す図FIG. 5 is a diagram showing a method of constructing a tunnel.

【図6】トンネルの構築方法を示す図FIG. 6 is a diagram showing a method of constructing a tunnel.

【図7】トンネルの構築方法を示す図FIG. 7 is a diagram showing a method of constructing a tunnel.

【図8】トンネルの構築方法を示す図FIG. 8 is a diagram showing a tunnel construction method.

【図9】トンネルの構築方法を示す図FIG. 9 is a diagram showing a tunnel construction method.

【図10】トンネルの構築方法を示す図FIG. 10 is a diagram showing a method of constructing a tunnel.

【図11】トンネルの構築方法を示す図FIG. 11 is a diagram showing a method of constructing a tunnel.

【図12】従来のトンネルの断面図FIG. 12 is a sectional view of a conventional tunnel.

【符号の説明】[Explanation of symbols]

1………地表面 3………計画トンネル位置 5………改良体 9………鋼管 11………上半掘削部 13、19………支保工(鋼製支保工+吹付けコンクリ
ート) 17………下半掘削部
1 ………… Ground surface 3 ………… Planned tunnel position 5 ………… Improved body 9 ………… Steel pipe 11 ………… Upper half excavation part 13, 19 ……… Supporting work (Steel supporting work + Shotcrete) 17 ………… Lower half excavation section

フロントページの続き (72)発明者 大屋 博史 東京都新宿区西新宿三丁目7番1号 鹿 島建設株式会社関東支店内 (72)発明者 萩原 智寿 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 藤井 健 東京都港区元赤坂1丁目6番4号 ケミ カルグラウト株式会社内 (72)発明者 宇野 泰明 東京都港区元赤坂1丁目6番4号 ケミ カルグラウト株式会社内 (56)参考文献 特公 平4−15878(JP,B2) 特公 昭55−31271(JP,B2) 特公 昭46−26703(JP,B1) (58)調査した分野(Int.Cl.7,DB名) E21D 9/04 E21D 9/00 Front page continuation (72) Inventor Hiroshi Oya 3-7-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Kashima Construction Co., Ltd. Kanto Branch (72) Inventor Tomohisa Hagiwara 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Ken Fujii 1-6-4 Moto-Akasaka, Minato-ku, Tokyo Kemi Kalgrout Co., Ltd. (72) Inventor Yasuaki Uno 1-4-6 Moto-Akasaka, Minato-ku, Tokyo Kemi Kalgrout Within the corporation (56) References Japanese Patent Publication 4-15878 (JP, B2) Japanese Patent Publication 55-31271 (JP, B2) Japanese Publication 46-26703 (JP, B1) (58) Fields investigated (Int. Cl. 7 , DB name) E21D 9/04 E21D 9/00

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 (a)トンネルの計画位置の側方部に、
地表面から注入管により固化材を地盤に注入して改良体
を設ける工程と、 (b)前記トンネルの計画位置に沿って、先受け工を施
工しつつトンネルの掘削を行う工程と、 を具備し、 前記先受け工の一部が前記改良体に重複して設けられ、
トンネル周辺にグランドアーチが形成されることを特徴
とするトンネルの構築方法。
1. (a) On the side of the planned position of the tunnel,
A step of injecting a solidifying material into the ground from the ground surface with an injection pipe to provide an improved body, and (b) a step of excavating the tunnel along with the planned position of the tunnel while constructing a preparatory work. However, a part of the preceding work is provided to overlap the improved body,
A method of constructing a tunnel, characterized in that a grand arch is formed around the tunnel.
【請求項2】 前記工程(b)は、トンネルの上面に先
受け工を施工し、トンネルの上半部を掘削し、トンネル
の上半部の支保工を設け、トンネルの下半部を掘削し、
トンネルの下半部の支保工を設けるものである請求項1
記載のトンネルの構築方法。
2. In the step (b), a top receiving work is performed on the upper surface of the tunnel, the upper half of the tunnel is excavated, a support work for the upper half of the tunnel is provided, and the lower half of the tunnel is excavated. Then
The support work for the lower half of the tunnel is provided.
How to build the described tunnel.
【請求項3】 前記上半部の支保工は、前記改良体に支
持させることを特徴とする請求項2記載のトンネルの構
築方法。
3. The method for constructing a tunnel according to claim 2, wherein the support work of the upper half portion is supported by the improved body.
【請求項4】 請求項1記載のトンネルの構築方法によ
り構築されたことを特徴とするトンネル。
4. A tunnel constructed by the method for constructing a tunnel according to claim 1.
JP30154799A 1999-10-22 1999-10-22 Tunnel construction method and tunnel Expired - Fee Related JP3466520B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30154799A JP3466520B2 (en) 1999-10-22 1999-10-22 Tunnel construction method and tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30154799A JP3466520B2 (en) 1999-10-22 1999-10-22 Tunnel construction method and tunnel

Publications (2)

Publication Number Publication Date
JP2001123788A JP2001123788A (en) 2001-05-08
JP3466520B2 true JP3466520B2 (en) 2003-11-10

Family

ID=17898260

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30154799A Expired - Fee Related JP3466520B2 (en) 1999-10-22 1999-10-22 Tunnel construction method and tunnel

Country Status (1)

Country Link
JP (1) JP3466520B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016223127A (en) * 2015-05-29 2016-12-28 大成建設株式会社 Tunnel construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016223127A (en) * 2015-05-29 2016-12-28 大成建設株式会社 Tunnel construction method

Also Published As

Publication number Publication date
JP2001123788A (en) 2001-05-08

Similar Documents

Publication Publication Date Title
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN107060803A (en) A kind of method for tunnel construction of utilization pipe curtain slip casting
CN107905814A (en) Large span loess tunnel top bar CD construction methods
CN107165161A (en) The construction method of the continuous three axes agitating pile water-stop curtain interplantation support pile of foundation ditch
JP3466520B2 (en) Tunnel construction method and tunnel
JP5382432B2 (en) Excavation method of adjacent twin tunnel
JP6857097B2 (en) How to build a tunnel
JP3787796B2 (en) Construction method of tunnel wellhead on steep slope
JP2001207788A (en) Limited backfilling injection work method in underground structure construction method
JP3621880B2 (en) Tunnel construction method and tunnel
JPH11152986A (en) Protection method for shielding excavation in section covered with thin soil layer
JP4633273B2 (en) Earth retaining method and equipment
JPH0313689A (en) Construction method for tunnel
CN108708739A (en) Shallow-buried exposed construction method suitable for ultra-large section hard rock tunnel
JP3980299B2 (en) Tunnel construction method and tunnel
JP2527893B2 (en) Reinforcement of existing foundation
JP2932197B2 (en) Excavation method for large or very large tunnel
JP2599296B2 (en) How to correct the slope
JPH0776988A (en) Preliminary construction method for tunnel facing front bedrock
JP2659612B2 (en) Column type continuous underground wall construction method
JPH11336466A (en) Construction method of tunnel
JP3269606B2 (en) Tunnel receiving method
JPH04336117A (en) Landslide protection stabilizing construction method
JP3470164B2 (en) Ground improvement method of shield machine start section
JP2000337078A (en) Natural ground prelining construction for tunnel

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
R150 Certificate of patent or registration of utility model

Ref document number: 3466520

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120829

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120829

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150829

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees