JP2995508B2 - Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method - Google Patents

Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method

Info

Publication number
JP2995508B2
JP2995508B2 JP3256986A JP25698691A JP2995508B2 JP 2995508 B2 JP2995508 B2 JP 2995508B2 JP 3256986 A JP3256986 A JP 3256986A JP 25698691 A JP25698691 A JP 25698691A JP 2995508 B2 JP2995508 B2 JP 2995508B2
Authority
JP
Japan
Prior art keywords
excavated soil
pile
rod
spiral
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP3256986A
Other languages
Japanese (ja)
Other versions
JPH0598880A (en
Inventor
等 尾田
Original Assignee
三谷セキサン 株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三谷セキサン 株式会社 filed Critical 三谷セキサン 株式会社
Priority to JP3256986A priority Critical patent/JP2995508B2/en
Publication of JPH0598880A publication Critical patent/JPH0598880A/en
Application granted granted Critical
Publication of JP2995508B2 publication Critical patent/JP2995508B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、杭穴の中掘工法で、
掘削ロッド逆回転時に、掘削土が杭穴根固め部へ逆流す
ることを防止する杭穴の中掘工法における掘削土の杭穴
根固め部への逆流防止方法に関する。
The present invention relates to a method of digging a pile hole,
The present invention relates to a method for preventing a backflow of excavated soil to a pile-hole consolidation part in a borehole excavation method for preventing excavated soil from flowing back to a pile-hole consolidation part during a reverse rotation of a drilling rod.

【0002】[0002]

【従来の技術】従来、杭穴の中掘工法に用いる掘削ロッ
ドでは掘削土を効率良く排土する為に、掘削ヘッドの直
上から掘削ロッドにスパイラルを取り付けて構成した掘
削ロッドを使用して杭穴を掘削していた。
2. Description of the Related Art Conventionally, in a drilling rod used in a drilling method for a pile hole, in order to efficiently excavate the excavated soil, a pile is formed by attaching a spiral to the drilling rod directly above a drilling head. Drilling a hole.

【0003】[0003]

【発明が解決しようとする課題】前記従来の技術では、
掘削完了時に掘削ヘッドを一旦逆回転して、掘削ヘッド
先端からセメントミルクを注入しながら引き上げ、再び
正回転してあるいは回転 をせずに、中空杭内を地上まで
引き上げる。この際に、掘削ロッドを逆回転するので、
スパイラル内に残っている掘削土が逆流して下方に運ば
れ、杭穴内に押し付けられる。従って、この掘削土がセ
メントミルク内に混入するので、セメントミルクの固化
後の強度が低下する問題点があった。
In the above prior art,
When the drilling is completed, rotate the drilling head in the reverse direction once, pull up while injecting cement milk from the tip of the drilling head , and again
With or without rotating , inside the hollow pile to the ground
Raising Ru. At this time, since the drill rod is rotated in reverse,
The excavated soil remaining in the spiral flows backward and is carried downward, and is pressed into the pile hole. Therefore, since the excavated soil is mixed into the cement milk, there is a problem that the strength of the cement milk after solidification is reduced.

【0004】[0004]

【課題を解決するための手段】然るにこの発明は、逆回
転時に掘削ヘッド上方に撹拌された掘削土層を形成して
掘削土の逆流を防止したので、前記問題点を解決した。
However, the present invention has solved the above-mentioned problem by forming an agitated excavated soil layer above the excavation head during reverse rotation to prevent backflow of excavated soil.

【0005】即ちこの発明は、削ヘッドの上方に撹拌
手段を介してスパイラルを取付けた掘削ロッドを、中空
杭内に挿入して使用し、該ロッドの正回転時に掘削土を
持ち上げるようにした杭穴の中掘工法において、杭穴掘
削完了後に、前記掘削ロッドを逆回転して、掘削ロッド
の下端から杭穴内にセメントミルクを放出しながら前記
掘削ロッドを引き上げる際に、前記掘削ロッドを前記撹
拌手段が前記中空杭内に至るまで引き上げ、前記掘削ロ
ッドの逆回転により、前記スパイラルから下方に押圧さ
れて逆送される掘削土を、前記撹拌手段で撹拌して、撹
拌手段の周辺に、撹拌された掘削土層を形成し、杭穴の
根固め部のセメントミルク内へ、前記スパイラル上から
掘削土が強制的に押し込まれることを防止することを特
徴とした杭穴の中掘工法における掘削土の逆流防止方法
である。
Namely this invention, agitation above the drilling head
Drilling rod with a spiral mounted through the means , hollow
It is inserted into the pile used in drilling method in the Kuiana you lift the excavated soil during forward rotation of the rod, Kuianaho
After cutting is completed, the drilling rod is rotated in the reverse direction to
While discharging the cement milk into the pile hole from the lower end of the
When raising the drilling rod, the drilling rod is
拌means pulling until reaching the hollow pile, and more reverse rotation of the drill rod, pressing of the said spiral downward
Is in the backhaul is the excavated soil, and stirred at the stirring means,
A stirred excavated soil layer is formed around the stirring means ,
From the top of the spiral into the cement milk of the root consolidation part
This is a method for preventing backflow of excavated soil in a borehole excavation method characterized by preventing excavated soil from being forcibly pushed .

【0006】[0006]

【作用】この発明は、掘削ロッドの逆回転時に、掘削
ッドの上方に撹拌された掘削土層を形成できるので、ス
パイラルから下方に送られる掘削土と杭穴の根固め部内
の根固め液(セメントミルク)とを撹拌された掘削土層
で隔離して、掘削土の根固め液内への逆流を防止させ
る。また、掘削土を撹拌してなる撹拌された掘削土層と
根固め液とは比重が違うので、互いに混ざりにくい。
[Action] The present invention, during the reverse rotation of the drill rod, drill f
The agitated excavated soil layer can be formed above the pad, so that the excavated soil sent downward from the spiral and the consolidation liquid (cement milk) in the pile consolidation section are isolated by the agitated excavated soil layer. To prevent backflow of excavated soil into the consolidation liquid. In addition, since the agitated excavated soil layer formed by agitating the excavated soil and the root consolidation liquid have different specific gravities, they are hardly mixed with each other.

【0007】[0007]

【実施例】図面に基づきこの発明の実施例を説明する。An embodiment of the present invention will be described with reference to the drawings.

【0008】杭穴掘削用の中空の掘削ロッド本体1の下
端部に、先端に掘削刃2、2を突設した掘削ヘッド3を
取り付ける。前記掘削ロッド本体1の上方に所定距離L
の無スパイラル部4を設けた上方に、スパイラル5を取
り付ける。前記において、距離Lは、杭の外径をDとし
た時、L=2D、とする。前記掘削ロッド本体1の無ス
パイラル部4に等間隔で放射状に撹拌棒6、6を突設
し、杭穴掘削ロッド7を構成する(図1)。前記におい
て、スパイラル5は杭穴掘削ロッド7を正回転した際
に、掘削土を上方に移送できるように形成されている。
また、図中8はセメントミルク放出口、9は拡底掘削刃
である。
An excavating head 3 having excavating blades 2 and 2 at its tip is attached to the lower end of a hollow excavating rod body 1 for excavating a pile hole. A predetermined distance L above the drill rod body 1
The spiral 5 is attached above the non-spiral portion 4 provided. In the above, the distance L is L = 2D, where D is the outer diameter of the pile. Stir bars 6, 6 are radially provided at equal intervals on the non-spiral portion 4 of the drill rod body 1 to form a pile hole drill rod 7 (FIG. 1). In the above, the spiral 5 is formed so that the excavated soil can be transferred upward when the pile hole excavating rod 7 is rotated forward.
In the figure, reference numeral 8 denotes a cement milk discharge port, and reference numeral 9 denotes an enlarged bottom excavation blade.

【0009】次に、杭穴掘削ロッド7を正回転して、杭
10を沈設しながら、所定の杭穴11を掘削する(図
1)。次に、拡底掘削刃9を開き、杭穴掘削ロッド7を
逆回転して、杭穴の拡底部11aを掘削し、掘削は完了
する(図2(a))。
Next, the pile hole excavating rod 7 is rotated forward to excavate a predetermined pile hole 11 while the pile 10 is being laid (FIG. 1). Next, the bottom excavation blade 9 is opened, and the pile hole excavation rod 7 is rotated in the reverse direction to excavate the bottom portion 11a of the pile hole, and the excavation is completed (FIG. 2A).

【0010】次に、杭穴掘削ロッド7を逆回転し、セメ
ントミルク放出口8からセメントミルク12を杭穴11
内に放出しながら、杭穴掘削ロッド7を引き上げる。こ
の際、スパイラル5上の掘削土13は下方に押圧されて
逆流するが、杭10内に収容された前記撹拌棒6、6の
周辺で撹拌された掘削土層14を形成する(図2
(b))。従って、セメントミルク12内に掘削土を混
入することを防止できる。
Next, the pile hole drilling rod 7 is rotated in the reverse direction, and the cement milk 12 is discharged from the cement milk discharge port 8 into the pile hole 11.
While releasing within, bring can pull the Kuiana drill rod 7. In this case, excavated soil 13 on the spiral 5 is flow back is pressed downward, around the stirring rod 6, 6 accommodated in the pile 10, to form a Kezudoso 14 drilling which is stirred (Figure 2
(B)). Therefore, it is possible to prevent the excavated soil from being mixed into the cement milk 12.

【0011】前記実施例において、無スパイラル部4の
距離Lは、L=2D、としたが、「L=D」乃至「L=
3D」程度であれば可能であり、「L<D」では粗の掘
削土層14の厚さが薄くなり、隔離効果が少なく「L>
3D」では、正回転時の掘削土の上方への移送効率が悪
い。また、前記実施例に使用した掘削ロッドにおいて、
杭穴掘削ヘッド7の無スパイラル部4に撹拌棒6を突設
したが、他の撹拌手段でも可能である。掘削ヘッドに拡
底用掘削刃を設けたが作動形式は任意であり、また、拡
底用掘削刃9は設けなくてもよい。
In the above embodiment, the distance L of the non-spiral portion 4 is L = 2D, but "L = D" to "L = D".
3D ”is possible. In“ L <D ”, the thickness of the rough excavated soil layer 14 is small, and the isolation effect is small and“ L> D ”.
In “3D”, the efficiency of transferring the excavated soil upward during forward rotation is poor. In the drill rod used in the above embodiment,
Although the stirring rod 6 protrudes from the non-spiral portion 4 of the pile hole excavating head 7, other stirring means can be used. Although the excavating head is provided with the excavating blade for enlarging the bottom, the operation type is arbitrary, and the excavating blade 9 for enlarging the bottom may not be provided.

【0012】[0012]

【発明の効果】この発明は、杭の中掘工法において、掘
削ロッドの掘削ヘッドの上方に、撹拌された掘削土層を
形成できるので、杭穴掘削ロッドの正回転時に、掘削土
を効率良く上方へ移送することができると共に、逆回転
時に、スパイラルから下方に送られる掘削土が押圧され
た状態で、根固め用のセメントミルク内に混入すること
を防止できる。従って、撹拌した掘削土層から掘削土
が、落下した場合であっても、比重の大きなセメントミ
ルク層の上面に留めることができ、セメントミルクと掘
削土とが混じり合うことはなく、かつ根固め部予定位置
を十分に撹拌混合できるので、強固な根固め部を形成で
きる効果がある。
According to the present invention, the excavated soil can be efficiently formed at the time of forward rotation of the pile hole excavation rod because the agitated excavated soil layer can be formed above the excavation head of the excavation rod in the pile excavation method. The excavated soil sent downward from the spiral is pressed during the reverse rotation while being transported upward.
In the state, Ru can be prevented from being mixed into the cement milk for the root firm. Therefore, the excavated soil is
However, even if it falls, a cement
Can be fastened on top of the luk layer and can be dug with cement milk
Since the excavated soil does not mix with each other, and the expected location of the rooting portion can be sufficiently stirred and mixed, there is an effect that a strong rooting portion can be formed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の実施例の正面図である。FIG. 1 is a front view of an embodiment of the present invention.

【図2】(a)(b)はこの発明の装置の使用状態を示
す正面図である。
FIGS. 2A and 2B are front views showing a state of use of the apparatus of the present invention.

【符号の説明】[Explanation of symbols]

3 掘削ヘッド 4 無スパイラル部 5 スパイラル 6 撹拌棒(撹拌手段) 7 杭穴掘削ヘッド10 杭(中空杭) 13 掘削土 14 撹拌された掘削土層3 drilling head 4 No spiral portion 5 Spiral 6 stirring rod (stirring means) 7 Kuiana drilling head 10 piles (hollow pile) 13 excavated soil 14 stirred excavated soil layer

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 削ヘッドの上方に撹拌手段を介して
パイラルを取付けた掘削ロッドを、中空杭内に挿入して
使用し、該ロッドの正回転時に掘削土を持ち上げるよう
にした杭穴の中掘工法において、杭穴掘削完了後に、前
記掘削ロッドを逆回転して、掘削ロッドの下端から杭穴
内にセメントミルクを放出しながら前記掘削ロッドを引
き上げる際に、前記掘削ロッドを前記撹拌手段が前記中
空杭内に至るまで引き上げ、前記掘削ロッドの逆回転に
より、前記スパイラルから下方に押圧されて逆送される
掘削土を、前記撹拌手段で撹拌して、撹拌手段の周辺
に、撹拌された掘削土層を形成し、杭穴の根固め部のセ
メントミルク内へ、前記スパイラル上から掘削土が強制
的に押し込まれることを防止することを特徴とした杭穴
の中掘工法における掘削土の逆流防止方法。
(1)DiggingAbove the grinding headVia stirring meansS
Attached a spiralInsert the drill rod into the hollow pile
use,Lift the excavated soil when the rod rotates forward
In the drilling method of the pile holeAfter excavation of pile hole, before
Rotate the drilling rod in the reverse direction to
Pull the drill rod while discharging cement milk into the
When the drilling rod is lifted, the stirring means
Pull up to the empty pile,For reverse rotation of the drilling rod
More, it is pushed downward from the spiral and sent back
Excavated soil is stirred by the stirring means.StirAround the stirring means
ToAgitatedForming excavated soil layers,At the bottom of the pile hole
Into the ment milk,From above the spiralExcavated soil forced
Prevent intrusionPile holes characterized by
For preventing backflow of excavated soil in underground mining method.
JP3256986A 1991-09-09 1991-09-09 Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method Expired - Lifetime JP2995508B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3256986A JP2995508B2 (en) 1991-09-09 1991-09-09 Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3256986A JP2995508B2 (en) 1991-09-09 1991-09-09 Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method

Publications (2)

Publication Number Publication Date
JPH0598880A JPH0598880A (en) 1993-04-20
JP2995508B2 true JP2995508B2 (en) 1999-12-27

Family

ID=17300141

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3256986A Expired - Lifetime JP2995508B2 (en) 1991-09-09 1991-09-09 Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method

Country Status (1)

Country Link
JP (1) JP2995508B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5024692B2 (en) * 1999-12-27 2012-09-12 三谷セキサン株式会社 Construction method of foundation pile, ready-made pile, pile hole drilling rod

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5944486A (en) * 1982-09-08 1984-03-12 株式会社武智工務所 Drilling machine

Also Published As

Publication number Publication date
JPH0598880A (en) 1993-04-20

Similar Documents

Publication Publication Date Title
KR102222835B1 (en) Ground improvement method for organic soil
JP2995508B2 (en) Prevention method of backflow of excavated soil to the pile consolidation part in pile digging method
JP4589813B2 (en) How to build an enlarged bulb for root consolidation
JPS5829374B2 (en) Mixing stirring blade device for cut soil in soil improvement machine
JPH0813473A (en) Boring rod for soil improvement and soil improvement method
JPH04185813A (en) Formation of soil-cement composite pile
JP4501249B2 (en) Steel pipe pile and its construction method
JP3626619B2 (en) Construction method of reinforced mixed solidified pile
JPH11200750A (en) Excavation bit for winding hole and execution method using it
JPH07109732A (en) Construction device of soil cement column with knot
JP2000144727A (en) Construction method of footing pile
JP2886365B2 (en) Construction method of pile
JPH09268554A (en) Construction method of basic pile and device thereof
JPS60156821A (en) Construction of pile
JP3067380U (en) Bit for stirring ground foundation pile
JP3182674B2 (en) Construction method of agitated mixing reinforcement
JPH11209970A (en) Synthetic pile constructing excavator-agitator
JP3679377B2 (en) Construction method of underground pile
JPH07138935A (en) Accompanied turning prevention device in soil improving machine
JP2836808B2 (en) Drill stirrer for soil cement pile method
JP2578388B2 (en) Ground reinforcement method using large diameter tensile reinforcement
JP2866248B2 (en) Construction method of hollow pipe pile
JPS5829375B2 (en) Mixing stirring blade device for cut soil in soil improvement machine
JP2823953B2 (en) Core material of cast-in-place pile
JP2002275884A (en) Soft ground improving method and pile constructing device

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071029

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081029

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091029

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101029

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111029

Year of fee payment: 12

EXPY Cancellation because of completion of term