JP2005023637A - Construction method of impervious wall for gutter pipe - Google Patents
Construction method of impervious wall for gutter pipe Download PDFInfo
- Publication number
- JP2005023637A JP2005023637A JP2003190004A JP2003190004A JP2005023637A JP 2005023637 A JP2005023637 A JP 2005023637A JP 2003190004 A JP2003190004 A JP 2003190004A JP 2003190004 A JP2003190004 A JP 2003190004A JP 2005023637 A JP2005023637 A JP 2005023637A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- groove
- water
- construction method
- cutter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Revetment (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、樋管内からの作業によって樋管周りの地盤中に遮水壁を構築する樋管用遮水壁の構築工法に関するものである。
【0002】
【従来の技術】
用水の河川からの取り入れまたは雨水や排水等の河川への排出を行うために、河川堤防には樋管が堤防内部を貫通して横断するように敷設されている。樋管の敷設工法としては、堤防を側方から掘削して樋管を推進させつつ順次継ぎ足して行く、いわゆる推進工法が一般的であるが、この工法によって敷設された樋管の外周には地盤との間に隙間が生じ、その隙間は水の通り道となって堤防の決壊等の災害を招くので、樋管周りに遮水壁を構築して水の通りを遮断する必要がある。
【0003】
樋管周りに遮水壁を構築するために、従来は下記の特許文献1に記載されているような工法が採用されていた。図13は、この工法を説明するための図である。最初に、堤防Tの内部に樋管Zを貫通敷設するために、図13(a)に示すように堤防Tの堤内地N側と河川K側とに発進立坑H1と到達立坑H2とをそれぞれ形成した後、発進立坑H1から到達立坑H2に向けて地盤Gを掘削して樋管Zを推進させつつ順次継ぎ足して行く。そして、堤防T内部に樋管Zを貫通敷設すると、図13(b)に示すように樋管Zと地盤Gとの隙間Saに硬化性を有する裏込め材Uを注入する。この後、注入した裏込め材Uが硬化すると、樋管Z同士の接続部に予め介装された分割接続リングRの周りの地盤Gを強化するとともに、ここへの地下水の浸透を防止するために、分割接続リングRの周りを地盤改良する。地盤改良は、図13(c)に示すように樋管Z内に設置した地盤改良装置50に備わる注入管51を分割接続リングRに形成された注入孔(図示省略)を通して地盤G中に突出させ、注入管51から地盤G中にグラウトYaをステップ注入で注入することにより行う。その際、グラウトYaの注入は樋管Z周りの360°の全範囲に対して行う。
【0004】
その後、注入したグラウトYaが硬化すると、分割接続リングRの周りに地盤改良部Pが造成されるので、分割接続リングRを解体撤去して、図13(d)に示すように環状の開口部Xを形成する。そして、樋管Z内に設置した地盤掘削機52に備わる掘削アーム53を開口部Xから地盤改良部Pに突出させて、それを樋管Zの円周方向に旋回させながら地盤改良部P内に環状の溝Mを掘削形成して行く。このとき、地盤改良部Pの造成により分割接続リングRの周辺が強化されているとともに地下水の浸透が防止されているので、地盤Gの崩壊や地下水の浸透を生じることなく樋管Zに対して垂直に環状の溝Mを形成することができる。そして、地盤改良部P内に所定深度の溝Mを形成すると、図13(e)に示すように溝M内に止水板54を挿入して、複数の止水板54を樋管Zに周方向へ順次固定して行き、止水板54を樋管Z周りに環状に設置し終えると、図13(f)に示すように溝M内にグラウトYbを注入充填する。この後は、注入充填したグラウトYbが硬化すると、溝M内に止水板54が埋設固定され、樋管X周りへの遮水壁Wbの構築が完了する。
【0005】
上記のような工法によれば、地盤Gの崩壊や地下水の浸透を生じることなく樋管Zに対して垂直に環状の溝Mを形成できるので、そこに注入したグラウトYbが均質な状態で硬化して、樋管Z周りに遮水性能の高い遮水壁Wbを構築することができる。このため、溝M内に止水板54を挿入設置せずにグラウトYbだけを注入充填し、それを硬化させて遮水壁とすることも行われている。
【0006】
【特許文献1】
特許第2929190号公報
【0007】
【発明が解決しようとする課題】
しかしながら、特許文献1のような工法では、地盤Gの崩壊や地下水の浸透を生じることなく樋管Zに対して垂直に環状の溝Mを形成するためには、分割接続リングRを解体撤去する前に、当該リングR周辺の地盤G中にグラウトYaを注入して地盤改良を行わなければならないので、この工程を行う分コストがかかり、工期が長くなるという問題がある。
【0008】
本発明は、上記問題点を解決するものであって、その課題とするところは、樋管周りに遮水性能の高い遮水壁を構築するとともに、コストを削減し工期を短縮することができる樋管用遮水壁の構築工法を提供することにある。
【0009】
【課題を解決するための手段】
本発明は、樋管の接続部に予め介装された分割接続リングの解体撤去後に形成される環状の開口部を通じて、樋管内からの作業で樋管周りに遮水壁を構築する樋管用遮水壁の構築工法において、開口部に地盤と樋管内とを隔離する隔離部材を設け、地盤掘削用のカッターと硬化性を有する構壁材注入用の注入管とを隔離部材を通して開口部から樋管の径方向に突出させる。そして、カッターによって地盤を掘削して溝を形成すると同時に当該溝内に注入管から構壁材を注入充填する工程を、カッターと注入管とを樋管の円周方向に旋回させながら繰り返し行い、その後溝内の構壁材を硬化させて樋管周りに環状の遮水壁を構築する。
【0010】
このように、開口部に隔離部材を設けて、カッターによって地盤中に溝を掘削形成すると同時に、注入管から溝内に構壁材を注入充填すると、樋管周りに閉空間状態の溝が形成されて、その溝内に充填した構壁材が溝壁を圧迫するようになる。このため、地盤の崩壊や地下水の浸透を生じることなく樋管に対して垂直に環状の溝を形成することができ、その溝内で構壁材を均質な状態で硬化させて、樋管周りに遮水性能の高い遮水壁を構築することが可能となる。そしてこの結果、特許文献1のような地盤改良工程を行う必要がなくなるので、その工程分コストを削減し、工期を短縮することが可能となる。また、溝の掘削形成と溝内への構壁材の注入充填とを同時に行うことで、工期を一層短縮することが可能となる。さらに、開口部に隔離部材を設けることで、カッターで掘削した土砂や溝内に充填した構壁材が、開口部から樋管内に漏れるのを防止することができ、樋管内で作業を安全に行えるようになる。なお、構壁材として、硬化性とともに高粘性を有する材料を用いると、溝内に充填した構壁材が、カッターと注入管とを通すためにできる隔離部材の隙間を通って樋管内に漏れ難くくなり有意義である。
【0011】
また、本発明においては、カッターによって掘削された土砂を一定の背圧をかけながら排出して、溝内の構壁材の圧力を一定に保持する。このようにすると、溝内に充填した構壁材が常に一定の圧力で溝壁を圧迫するようになるので、地盤の崩壊や地下水の浸透を安定かつ確実に防止することができる。また、樋管の上方に形成された溝内の構壁材は下方に流れ易いため、上方の溝内に空隙が生じるおそれがあるが、上記のようにすると、構壁材が下方に流れ難くなって、上方の溝内に空隙が生じるのを防止することができる。
【0012】
また、本発明においては、地盤中にカッターによる掘削が困難となる障害物がある場合に、障害物除去用のロッドを隔離部材を通して開口部から突出させて障害物を除去する。このようにすると、樋管周りに岩や石等の障害物があっても、カッターによって環状の溝を着実に掘削形成することができる。
【0013】
また、本発明においては、カッターによる地盤掘削と注入管からの構壁材の注入充填とを繰り返し行った後、溝内の構壁材が未硬化の状態にある間に、開口部から溝内に止水板を挿入して樋管周りに環状に設置する。このようにすると、溝内の構壁材が硬化したときに、遮水壁内に止水板が埋設されるので、遮水壁の遮水性能を長期間維持することが可能となる。また、止水板挿入時には、地盤の崩壊や地下水の浸透を生じることなく樋管に対して垂直に環状の溝を形成して、その溝内に構壁材を均質な状態で充填しているので、構壁材が未硬化の状態にある間は、小さな挿入力で溝内に止水板を容易に挿入することができる。
【0014】
さらに、本発明においては、溝内の構壁材が流動性を失う半硬化の状態まで硬化したときに、止水板を挿入する。このようにすると、止水板挿入時に溝内の構壁材が樋管内に漏れるのを防止することができる。
【0015】
【発明の実施の形態】
図1〜図6は、本発明に係る樋管用遮水壁の構築工法を実施するために用いる遮水壁構築装置を示す図である。同装置は、堤防内部に貫通敷設された樋管内に設置されている。図1は(a)が遮水壁構築装置の隔離部材を示す図、(b)が同装置の旋回ユニットを示す図、図2は旋回ユニットを図1(b)のA方向から見た図である。図3は遮水壁構築装置の掘削ユニットを示す図、図4は掘削ユニットの図3におけるB−B断面図、図5は掘削ユニットの図4におけるC−C断面図、図6は掘削ユニットを示す斜視図である。
【0016】
図1(a)において、Gは堤防の地盤、Zは堤防内部に推進工法によって貫通敷設された樋管、Uは樋管Zと地盤Gとの隙間に注入されて硬化した裏込め材である。Rは樋管Z同士の接続部に介装された分割式の分割接続リングである。分割接続リングRは、図1(a)ではボルトで樋管Zに取り付けられているが、ボルトを外すと、解体して図1(b)に示すように樋管Zから撤去することができる。分割接続リングRを撤去すると、樋管Z内から遮水壁を構築するための作業口となる環状の開口部Xが形成される。100は樋管Z内に設置された遮水壁構築装置である。1は同装置100の構成部品の1つである環状の全周シールパッキン(以下、全周シールと記す。)であって、開口部Xを閉じて地盤Gと樋管Z内とを隔離する。この全周シール1はゴム製で、端部が樋管Zに固定され、中央の切れ目1aで分割されている。なお、図1(a)では、全周シール1を分割接続リングRを撤去する前から予め樋管Zに固定しているが、分割接続リングRを撤去した後に樋管Zに固定してもよい。全周シール1は、本発明における隔離部材を構成する。
【0017】
2は遮水壁構築装置100の旋回ユニットであって、分割接続リングRの解体撤去後に樋管Z内に設置される。3はこのユニット2の本体を構成する一対の本体リングであって、開口部Xを挟むように配置されている。4は本体リング3同士を一体となるように連結する鋼材である。各本体リング3には、図2に示すように4つの連結部材5が連結されていて、それぞれの連結部材5にはガイドローラ6が樋管Zの内周面Zaを転動可能に支持されている。7は樋管Zに固定された固定部材である。8は固定部材7に回動自在に連結された油圧式の旋回用シリンダであって、このシリンダ8のロッド8aの先端には貫通孔8bが形成されている。この貫通孔8bと本体リング3に所定間隔で複数形成された連通孔3aとに、図1(b)に示すようにピン9を通すと、旋回用シリンダ8と本体リング3とは係合する。そして、その係合状態でロッド8aを伸張させると、ガイドローラ6が内周面Zaを転動するので、旋回用シリンダ8が図2の2点鎖線で示すように回動して、本体リング3が樋管Zの中心軸Oを回転中心として樋管Zの円周方向Qへ所定角度回転する。このように所定角度回転した後、ピン9を抜いてロッド8aを収縮させ、本体リング3の別の連通孔、例えば3zと貫通孔8bとにピン9を通し直すと、旋回用シリンダ8と本体リング3とは再び係合するので、その係合状態で再びロッド8aを伸張させると、本体リング3がさらにQ方向へ所定角度回転する。つまり、上記のような旋回用シリンダ8と本体リング3との係合作業と、ロッド8aの伸縮動作とを繰り返し行うことで、本体リング3を樋管Z内でQ方向へ360°回転させることができる。
【0018】
図3に示す本体リング3間に配置された10は遮水壁構築装置100の掘削ユニットであって、このユニット10の本体を構成する保持部材11は、ガイド保持部11aが全周シール1を押しのけるように通って開口部Xから地盤G中に突出した状態となるように、本体リング3にブラケットを介してボルトで固定されている。なお、ガイド保持部11aの地盤G中への突出は、保持部材11に固定された2つの油圧式の押出用シリンダ12のロッド12aの先端に本体リング3に支持された突出用ブラケット13を連結し、その連結状態でロッド12aを伸張させて保持部材11を樋管Zの径方向Fへ押すことにより行う。保持部材11は、上述したように本体リング3が樋管Zの円周方向Qへ回転すると、ガイド保持部11aで全周シール1を押し開きながら本体リング3にともなって円周方向Qへ旋回する。その際、ガイド保持部11aがD方向から見ると、図6に示すように円周方向Qの前方と後方に向かって先細になる舟形形状をしているので、ガイド保持部11aで全周シール1を押し開きながら保持部材11をスムーズに旋回させることができ、また、ガイド保持部11aと全周シール1との隙間Sを小さくすることができる。
【0019】
図3に示す14は樋管Z内からガイド保持部11aを貫通して樋管Zの径方向Fの地盤G中に突出したガイド部材であって、底部14aを保持部材11にボルトで固定することによって保持部材11に保持される。なお、ガイド部材14の地盤G中への突出は、2つの押出用シリンダ12のロッド12aの先端に突出用ブラケット13に代えて押し出し用のバー(図示省略)を架設し、そのバーに直接、またはスペーサ(図示省略)を介してガイド部材14の底部14aを取り付けた状態でロッド12aを収縮させてガイド部材14を樋管Zの径方向Fへ押し出すことにより行う。15は先端に刃部15a(図4に図示)を備えた地盤掘削用のカッターである。16はロッド16aの先端にカッター15を連結した油圧式の掘削用シリンダであって、底部16bがガイド部材14の底部14aを介して保持部材11にボルトで固定されている。カッター15が図4の実線で示すようにガイド保持部11a内に収容された状態でロッド16aを伸張させると、カッター15はガイド部材14に沿ってガイド保持部11aから突出して樋管Zの径方向Fに移動して行き、2点鎖線で示すようにガイド部材14の先端に位置する。そして、伸張させたロッド16aを収縮させると、カッター15はガイド部材14に沿って樋管Zの径方向Dに移動して行き、ガイド保持部11a内に没入する。このD方向への移動時に、カッター15は刃部15aで地盤Gを掘削し、地盤G中に樋管Zに対して垂直な溝を形成する。
【0020】
図4に示す17a、17bはガイド部材14に内装された構壁材注入用の注入管であって、これらには樋管Z外に設置された構壁材供給装置(図示省略)から構壁材が供給される。17c、17dは各注入管17a、17bの先端に設けられた注入口である。注入口17cは、カッター15が2点鎖線で示す位置にあるときはカッター15によって閉じられ、その位置からカッター15が地盤G中に溝を掘削形成するためにD方向へ移動すると開かれる。注入口17cが開くと、注入管17aに供給されている構壁材が、カッター15によって掘削形成された溝内に注入充填される。注入口17dは常時開かれていて、注入管17bに供給されている構壁材が、カッター15によって掘削形成された溝内に補足的に注入される。なお、溝内への構壁材の注入量や注入圧は図示しない調整バルブ等で調整される。また、構壁材には、硬化性を有するセメント系の硬化剤を用いるが、好ましくは粘性が高くて、注入後24時間経過しても指で押して変形する程度の強度となる強度発現の遅いベンドナイト等を用いる。
【0021】
18はカッター15が溝形成時に掘削した土砂を取り込む土砂取込部である。19は土砂取込部18に取り込まれた土砂を樋管Z外へ排出する排土管である。排土管19の内部には、図5に示すようにエアーで膨張収縮するゴムチューブからなる背圧弁20が設けられていて、この背圧弁20によって土砂取込部18に取り込まれた土砂を一定の背圧をかけながら排出する。これにより、溝内に充填された構壁材の圧力が上記一定の背圧に保持される。なお、この背圧は、地盤G中に含まれる地下水の水頭圧以上、または溝内に充填された構壁材の水頭圧以上に設定する(具体的には、0.2〜0.3kg/cm2程度)。21a、21bは後述する障害物除去用のロッド(図示省略)や、送水用のホース(図示省略)等を地盤G中に突出させるための挿通孔である。22a、22bは挿通孔21a、21bを閉じるためのキャップである。23はガイド保持部11aを囲むように保持部材11に取り付けられたゴム製で枠状のシールパッキンであって、図3に示すように保持部材11と全周シール1との間に設けられている。このシールパッキン23は、ガイド保持部11aと全周シール1との隙間S(図6に図示)から漏れて来る土砂や構壁材を塞ぎ止めて、それ以上樋管Z内に漏れないようにする。
【0022】
図7〜図10は、本発明に係る樋管用遮水壁の構築工法を説明するための図である。本工法は、上述した遮水壁構築装置100を用いて実施する。図7において、樋管Z同士の接続部に介装された分割接続リングR(図1(a)に図示)を解体撤去して、樋管Zに環状の開口部X(例えば、図1(b)に図示)を形成した後、樋管Z内に本体リング3等の旋回ユニット2を設置すると、続けて、図7(a)に示すように樋管Z内に保持部材11を配置する。そして、保持部材11を前述の押出用シリンダ12(例えば、図1(b)に図示)によって樋管Zの径方向Fへ押して、ガイド保持部11aを図7(b)に示すように全周シール1を通して開口部Xから地盤G中に突出させ、その突出状態で保持部材11を本体リング3に固定する。なお、全周シール1の周辺の地盤Gを予め乱しておくと、ガイド保持部11aをスムーズに地盤G中に突出させることができる。保持部材11を本体リング3に固定すると、図7(c)に示すように、ボーリング機24のロッド24aを回転させながらガイド保持部11aを通して地盤G中に突出させつつ、ロッド24aの先端から水を噴射させることにより、地盤Gをボーリングしてガイド部材14を挿入できる程度の大きさの溝状の削孔Vを施す。削孔Vを施すと、ボーリング機24を撤去し、その後、図7(d)に示すようにガイド部材14を押出用シリンダ12によって削孔Vに挿入して保持部材11に固定し、カッター15を連結している掘削用シリンダ16を保持部材11に固定し、さらに、排土管19を保持部材11に取り付けて、掘削ユニット10を組み立てる。組み立て後は、削孔Vに注入管17a、17bから構壁材Yを注入充填する。
【0023】
削孔Vに構壁材Yを注入充填すると、直ぐに、掘削用シリンダ16によってカッター15をガイド保持部11aから突出させてF方向に移動させ、図8(e)に示すようにガイド部材14の先端に位置させる。そして、前述の旋回用シリンダ8(例えば、図2に図示)によって本体リング3を樋管Zの円周方向Qへ所定角度回転させることにより、保持部材11のガイド保持部11aで全周シール1を押し開きながら、ガイド部材14とカッター15とを円周方向Qへ所定角度旋回させて、図8(f)に示すようにカッター15の刃部15aを地盤Gに食い込ませる。なお、このときの刃部15aの地盤Gへの食い込み量は、30〜50mm程度に設定する。この後、図8(g)に示すように掘削用シリンダ16によってカッター15をD方向に移動させながら刃部15aで地盤Gを掘削して樋管Zに対して垂直に溝Mを形成して行き、これと同時に溝M内に注入管17a、17bから構壁材Yを注入充填して行く。またこのとき、カッター15のD方向への移動にともなって掘削した土砂が構壁材Yと混じって土砂取込部18に取り込まれて来るので、その土砂を排土管19を通じて一定の背圧をかけながら樋管Z外へ排出する。これにより、溝M内に充填した構壁材Yの圧力が上記一定の背圧に保持される。なお、構壁材Yは、セメント等の粒子が大きくて溝Mの壁に目詰まりするため、地盤G中へ殆ど浸透せずに溝Mの壁を圧迫する。また、構壁材Yは粘性が高いため、溝M内から全周シール1の切れ目1a(例えば、図1(b)に図示)や全周シール1とガイド保持部11aとの隙間S(図6に図示)を通って樋管Z内に漏れ難い。カッター15をD方向へ移動させた後、図8(h)に示すようにカッター15がガイド保持部11a内に没入すると、形成した溝Mにおいて掘削した土砂と構壁材Yとが着実に置き換わった状態となる。このとき、土砂取込部18はカッター15によって閉じられるので、土砂や構壁材Yが土砂取込部18へ入ることはない。
【0024】
その後、再び、図8(e)に示すようにカッター15をF方向に移動させてガイド部材14の先端に位置させ、図8(f)に示すようにカッター15を所定角度旋回させて(このときのカッター15は図8(f)よりもさらにQ方向へ旋回する)刃部15aを地盤Gに食い込ませた後、図8(g)に示すようにカッター15をD方向に移動させながら刃部15aで地盤Gを掘削して溝Mを形成すると同時に、溝M内に注入管17aから構壁材Yを注入充填し、図8(h)に示すようにカッター15をガイド保持部11a内に没入させる。このような一連の工程を何度も繰り返し行うと、図9(i)に示すように樋管Z周りに構壁材Yを充填した溝Mが拡大されて行く。なお、地盤G中にカッター15によって掘削するのが困難となる石や岩等の障害物がある場合は、図9(j)に示すようにボーリング機24のロッド24aを挿通孔21aを通して地盤G中に突出させて、ロッド24aの先端で障害物Eを砕いたり、障害物Eを溝Mを掘削形成するのに邪魔にならない位置に移動させて除去する。
【0025】
そして、図8(e)〜(h)で説明した一連の工程を何度も繰り返し行いながら、ガイド部材14とカッター15とが円周方向Qに360°旋回すると、図10(k)に示すように樋管Z周りに構壁材Yを充填した環状の溝Mが形成された状態となる。この後、溝M内の構壁材Yが流動性を失う半硬化の状態まで硬化すると、掘削ユニット10を解体して、カッター15とガイド部材14とを保持部材11から外して溝M内から除去し、さらに保持部材11を本体リング3から外してガイド保持部11aを溝M内から除去する。このように構壁材Yが半硬化の状態でガイド保持部11aを溝M内から除去すると、その除去時に構壁材Yが全周シール1の切れ目1aから樋管Z内に入り込むことを防止することができる。保持部材11を本体リング3から外すと、旋回ユニット2全体を撤去し、その後、図10(l)に示すように樋管Z同士の接続部に分割接続リングRを組み付けて元に戻し、溝M内の構壁材Yを硬化させる。この後、構壁材Yが硬化すると、樋管Z周りに環状の遮水壁Wが樋管Zに対して垂直に構築される。
【0026】
以上のように、開口部Xに全周シール1を設けて、カッター15によって地盤G中に溝Mを掘削形成すると同時に、注入管17aから溝M内に構壁材Yを注入充填すると、樋管Z周りに閉空間状態の溝Mが形成されて、その溝M内に充填した構壁材Yが溝Mの壁を圧迫するようになる。このため、溝M内への地盤Gの崩壊や地下水の浸透を生じることなく樋管Zに対して垂直に環状の溝Mを形成することができ、その溝M内で構壁材Yを均質な状態で硬化させて、樋管Z周りに遮水性能の高い遮水壁Wを構築することが可能となる。そしてこの結果、特許文献1のような地盤改良工程を行う必要がなくなり、その工程分コストを削減し、工期を短縮することが可能となる。
【0027】
また、溝Mの掘削形成と溝M内への構壁材Yの注入充填とを同時に行うことで、工期を一層短縮することが可能となる。また、開口部Xに全周シール1を設けることで、カッター15で掘削した土砂や溝M内に充填した構壁材Yが、開口部Xから樋管Z内に漏れるのを防止することができ、樋管Z内で作業を安全に行えるようになる。
【0028】
また、カッター15によって掘削した土砂を一定の背圧をかけながら排出して、溝M内の構壁材Yの圧力を一定に保持することで、溝M内に充填した構壁材Yが常に一定の圧力で溝Mの壁を圧迫するようになるので、地盤Gの崩壊や地下水の浸透を安定かつ確実に防止することができる。また、樋管Zの上方に形成された溝M内の構壁材Yは下方に流れ易いため、上方の溝M内に空隙が生じるおそれがあるが、上記のように構壁材Yの圧力を一定に保持することで、構壁材Yが下方に流れ難くなって、上方の溝M内に空隙が生じるのを防止することができる。
【0029】
さらに、地盤G中にカッター15による掘削が困難となる障害物Eがある場合に、ボーリング機24のロッド24aで障害物Eを除去することで、樋管Z周りに障害物Eがあっても、カッター15によって環状の溝Mを着実に掘削形成することができる。
【0030】
図11および図12は、本発明の他の実施形態に係る樋管用遮水壁の構築工法を説明するための図であって、カッター15によって掘削形成された環状の溝M内に止水板を挿入設置する工程と状態を示している。図10(k)に示したように樋管Z周りに構壁材Yを充填した環状の溝Mが形成された状態になると、溝M内の構壁材Yを半硬化の状態まで硬化させた後、掘削ユニット10を解体して、カッター15とガイド部材14とを保持部材11から外して溝M内から除去し、さらに保持部材11を本体リング3から外してガイド保持部11aを溝M内から除去する。そして、構壁材Yが未硬化の状態にある間に、図11(m)に示すように鋼材からなる扇形の止水板25を全周シール1を押しのけて開口部Xから溝M内に挿入し、止水板25の底部25aを樋管Zにボルトで固定する。なお、止水板25の挿入は、ジャッキやシリンダ等を用いて行う。止水板25を1枚固定すると、別の止水板25を固定済みの止水板25に沿わせながら全周シール1を押しのけて溝M内に挿入し、底部25aを樋管Zに固定する。そして、次々に止水板25を溝M内に挿入して樋管Zに固定して行くと、最終的に、図11(n)に示すように樋管Z周りに止水板25が環状に設置された状態になる。このような状態になると、樋管Zの開口部Xが、図12に示すように止水板25の底部25aで閉じられるので、そのまま溝M内の構壁材Yを硬化させる。なおこのとき、底部25aの上に分割接続リングRを組み付けて元に戻してもよい。この後、構壁材Yが硬化すると、樋管Z周りに止水板25を埋設した環状の遮水壁Waが樋管Zに対して垂直に構築される。
【0031】
上記のようにすると、溝M内の構壁材Yが硬化したときに、遮水壁Wa内に止水板25が埋設されるので、遮水壁Waの遮水性能を長期間維持することが可能となる。また、止水板25の挿入時には、地盤Gの崩壊や地下水の浸透を生じることなく樋管Zに対して垂直に環状の溝Mを形成して、その溝M内に構壁材Yを均質な状態で充填しているので、構壁材Yが未硬化の状態にある間は、ジャッキやシリンダ等の小型の機材を用いて、小さな挿入力で溝M内に止水板25を容易に挿入することができる。さらに、構壁材Yが半硬化の状態にあるときに止水板25を溝M内に挿入すると、止水板25の挿入時に止水板25と全周シール1との隙間から構壁材Yが樋管Z内に漏れるのを防止することができる。
【0032】
以上述べた実施形態においては、本発明に係る隔離部材として、中央に切れ目1aが設けられた一層構造で環状の全周シールパッキン1を、分割接続リングRを解体撤去する前から開口部Xに設けた例を挙げているが、本発明はこれのみに限定するものではない。これ以外に、隔離部材として、例えば切れ目が設けられていない一層構造の環状シールパッキンや、切れ目が設けられた層と切れ目が設けられていない層とを備えた多層構造の環状シールパッキン等を、分割接続リングRを解体撤去した後に開口部Xに設けてもよい。このような場合、環状シールパッキンの切れ目が設けられていない層の一部分を切り開いて保持部材11のガイド保持部11aを地盤G中に突出させ、保持部材11が円周方向Qへ旋回するときに、残りの部分をガイド保持部11aの先端で切り開いて行くのが好ましい。このようにすると、ガイド保持部11aの先端の環状シールパッキンとの間に隙間ができなくなり、カッター15で掘削した土砂や溝M内に充填した構壁材Yが樋管Z内に漏れるのを確実に防止することができる。また、隔離部材として、一対の本体リング3に代えて開口部Xよりも幅広の筒状のリングを用い、そのリングの周面で開口部Xを樋管Z内から閉蓋して地盤Gと樋管Z内とを隔離してもよい。この場合、リングの周面にカッター15やガイド部材14を開口部Xから地盤G中に突出させるための突出口を設け、開口部Xの両側の樋管Zとリングとの間に環状のシールパッキンを介在させておくと、カッター15によって溝Mを掘削形成すると同時に、注入管17a、17bから溝M内に構壁材Yを注入充填することができ、また、掘削した土砂や溝M内の構壁材Yが樋管Z内に漏れるのを確実に防止することができる。
【0033】
また、上記実施形態では、障害物除去用のロッドとしてボーリング機24のロッド24aを用いて、地盤G中にある石や岩等の障害物Eを砕く等して除去した例を挙げているが、本発明はこれのみに限定するものではなく、これ以外に、例えば、はつり機のロッドを用いて障害物Eを砕いて除去してもよい。つまり、障害物除去用のロッドとしては、地盤G中にある障害物Eをカッター15で溝Mを掘削形成するのに邪魔にならないように除去できるものであればよい。
【0034】
また、上記実施形態では、分割接続リングRの組み付け作業や、止水板25の挿入設置作業を、旋回ユニット2を撤去した後に行っているが、これらの作業は、旋回ユニット2を樋管Zに設置したまま行ってもよい。但し、保持部材11等の掘削ユニット10は撤去しておく。
【0035】
さらに、上記実施形態では、溝Mの掘削形成工程や、溝M内への止水板25の挿入設置作業を、樋管Zの下方から開始した例を挙げているが、本発明はこれのみに限定するものではなく、これらの工程および作業は、環状の開口部Xの全体に渡って全周シール1を設けているため、樋管Zのどの方向からでも開始することができる。
【0036】
【発明の効果】
本発明によれば、開口部に隔離部材を設けて、カッターによって地盤中に溝を掘削形成すると同時に注入管から溝内に構壁材を注入充填することで、地盤の崩壊や地下水の浸透を生じることなく樋管に対して垂直に環状の溝を形成でき、その溝内で構壁材を均質な状態で硬化させて、樋管周りに遮水性能の高い遮水壁を構築することが可能となり、この結果、地盤改良工程を行う必要がなくなるので、コストを削減し工期を短縮することが可能となる。
【図面の簡単な説明】
【図1】遮水壁構築装置の隔離部材と旋回ユニットを示す図である。
【図2】旋回ユニットを図1のA方向から見た図である。
【図3】遮水壁構築装置の掘削ユニットを示す図である。
【図4】掘削ユニットの図3におけるB−B断面図である。
【図5】掘削ユニットの図4におけるC−C断面図である。
【図6】掘削ユニットを示す斜視図である。
【図7】本発明に係る樋管用遮水壁の構築工法を説明するための図である。
【図8】同工法を説明するための図である。
【図9】同工法を説明するための図である。
【図10】同工法を説明するための図である。
【図11】他の実施形態の工法を説明するための図である。
【図12】他の実施形態の工法を説明するための図である。
【図13】従来の工法を説明するための図である。
【符号の説明】
1 全周シールパッキン
15 カッター
17a 注入管
17b 注入管
24a ボーリング機のロッド
25 止水板
E 障害物
F 樋管の径方向
G 地盤
M 溝
Q 樋管の円周方向
R 分割接続リング
W 遮水壁
Wa 遮水壁
X 開口部
Y 構壁材
Z 樋管[0001]
BACKGROUND OF THE INVENTION
TECHNICAL FIELD The present invention relates to a construction method for a water shielding wall for a steel pipe that constructs a water shielding wall in the ground around the steel pipe by work from inside the steel pipe.
[0002]
[Prior art]
In order to take in irrigation water from the river or to discharge rainwater or drainage into the river, the river levee is laid so as to cross through the levee. The so-called propulsion method is generally used as a method of laying the dredging pipe, where the embankment is excavated from the side and the dredging pipes are pushed forward one after another, but the so-called propulsion method is generally used. There is a gap between the two, and the gap becomes a passage for water and causes disasters such as breakage of the embankment. Therefore, it is necessary to construct a water-impervious wall around the pipe and block the passage of water.
[0003]
In order to construct a water-impervious wall around the pipe, a construction method as described in
[0004]
Thereafter, when the injected grout Ya is hardened, the ground improvement portion P is formed around the split connection ring R. Therefore, the split connection ring R is dismantled and removed as shown in FIG. 13 (d). X is formed. Then, the
[0005]
According to the above construction method, the annular groove M can be formed perpendicular to the vertical pipe Z without causing the ground G to collapse or the infiltration of groundwater, so that the grout Yb injected therein is hardened in a homogeneous state. Thus, a water shielding wall Wb having a high water shielding performance can be constructed around the tub tube Z. For this reason, it is also practiced to fill and fill only the grout Yb without inserting the
[0006]
[Patent Document 1]
Japanese Patent No. 2929190
[0007]
[Problems to be solved by the invention]
However, in the construction method such as
[0008]
The present invention solves the above-mentioned problems, and the problem is that it is possible to construct a water-blocking wall having high water-blocking performance around the pipe and reduce the cost and the construction period. The purpose is to provide a construction method for water-impervious walls for dredging pipes.
[0009]
[Means for Solving the Problems]
According to the present invention, a shield for a dredger that constructs a water-impervious wall around the dredger through work from inside the dredger through an annular opening formed after dismantling and removing the split connection ring previously installed in the joint of the dredger. In the construction method of the water wall, an isolation member for isolating the ground and the inside of the dredging pipe is provided at the opening, and the cutter for ground excavation and the injection pipe for injecting the hard wall material are injected from the opening through the separating member. Project in the radial direction of the tube. Then, the step of excavating the ground with a cutter to form a groove and simultaneously injecting and filling the wall material from the injection pipe into the groove is repeated while turning the cutter and the injection pipe in the circumferential direction of the vertical pipe, After that, the structural wall material in the groove is hardened to construct an annular impermeable wall around the pipe.
[0010]
In this way, when the isolation member is provided in the opening and the groove is excavated and formed in the ground by the cutter, simultaneously, when the wall material is injected and filled into the groove from the injection pipe, a closed space state groove is formed around the vertical pipe. Thus, the wall material filled in the groove presses the groove wall. For this reason, it is possible to form an annular groove perpendicular to the pipe without causing collapse of the ground or infiltration of groundwater. It is possible to construct a water-impervious wall with high water-impervious performance. As a result, it is not necessary to perform the ground improvement process as in
[0011]
Further, in the present invention, the earth and sand excavated by the cutter is discharged while applying a constant back pressure, and the pressure of the wall material in the groove is kept constant. If it does in this way, since the construction wall material with which it filled in the groove will always press a groove wall with a fixed pressure, it will be possible to prevent the collapse of the ground and the penetration of groundwater stably and reliably. In addition, since the wall material in the groove formed above the tub tube easily flows downward, there is a possibility that a gap may be formed in the upper groove. However, if the above is performed, the wall material hardly flows downward. Thus, it is possible to prevent a void from being generated in the upper groove.
[0012]
Further, in the present invention, when there is an obstacle in the ground that makes it difficult to excavate by a cutter, the obstacle removing rod is protruded from the opening through the isolation member to remove the obstacle. In this way, even if there are obstacles such as rocks and stones around the pipe, an annular groove can be steadily excavated and formed by the cutter.
[0013]
Further, in the present invention, after the ground excavation by the cutter and the injection and filling of the wall material from the injection pipe are repeatedly performed, the wall material in the groove is in the groove from the opening while the wall material in the groove is in an uncured state. Insert a water stop plate into and place it in a ring around the soot tube. If it does in this way, when the construction wall material in a groove | channel hardens | cures, since the water stop board is embed | buried in a water shielding wall, it becomes possible to maintain the water shielding performance of a water shielding wall for a long term. In addition, when inserting the water stop plate, an annular groove is formed perpendicular to the vertical pipe without causing ground collapse or groundwater infiltration, and the wall material is uniformly filled in the groove. Therefore, while the wall material is in an uncured state, the water stop plate can be easily inserted into the groove with a small insertion force.
[0014]
Further, in the present invention, the water stop plate is inserted when the wall material in the groove is cured to a semi-cured state in which the fluidity is lost. If it does in this way, it can prevent that the wall material in a groove | channel leaks in a soot pipe at the time of a water stop board insertion.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
1-6 is a figure which shows the impermeable wall construction apparatus used in order to implement the construction method of the impermeable wall for dredging pipes concerning this invention. The device is installed in a dredger that penetrates the embankment. 1A is a view showing a separating member of the impermeable wall construction device, FIG. 1B is a view showing a turning unit of the device, and FIG. 2 is a view of the turning unit as viewed from the direction A in FIG. It is. 3 is a diagram showing a drilling unit of the impermeable wall construction apparatus, FIG. 4 is a sectional view taken along the line BB in FIG. 3 of the drilling unit, FIG. 5 is a sectional view taken along the line CC in FIG. FIG.
[0016]
In FIG. 1 (a), G is the ground of the dike, Z is a vertical pipe penetrating through the dike by the propulsion method, and U is a backfill material that is injected into the gap between the horizontal pipe Z and the ground G and hardened. . R is a split-type split connection ring interposed at the connecting portion between the vertical pipes Z. The split connection ring R is attached to the soot tube Z with a bolt in FIG. 1 (a), but can be disassembled and removed from the soot tube Z as shown in FIG. 1 (b) when the bolt is removed. . When the split connection ring R is removed, an annular opening X serving as a work port for constructing a water shielding wall from the inside of the tub tube Z is formed.
[0017]
[0018]
3 arranged between the body rings 3 shown in FIG. 3 is an excavation unit of the impermeable
[0019]
3 shown in FIG. 3 is a guide member that penetrates the
[0020]
[0021]
18 is an earth and sand taking-in part which takes in the earth and sand which the
[0022]
FIGS. 7-10 is a figure for demonstrating the construction method of the impermeable wall for dredging pipes which concerns on this invention. This construction method is carried out using the above-described impermeable
[0023]
Immediately after injecting and filling the wall material Y into the drilling hole V, the
[0024]
Thereafter, the
[0025]
Then, when the
[0026]
As described above, when the
[0027]
Moreover, the construction period can be further shortened by simultaneously performing the excavation formation of the groove M and the filling and filling of the wall material Y into the groove M. Further, by providing the
[0028]
Further, the soil and sand excavated by the
[0029]
Further, when there is an obstacle E in the ground G that makes it difficult to excavate by the
[0030]
FIGS. 11 and 12 are diagrams for explaining a construction method of a water-impervious wall for dredging according to another embodiment of the present invention, and a water stop plate in an annular groove M excavated by a
[0031]
If it does as mentioned above, since the
[0032]
In the embodiment described above, as the isolation member according to the present invention, the annular all-round seal packing 1 having a single-layer structure provided with a cut 1a in the center is provided in the opening X before the split connection ring R is disassembled and removed. Although provided examples are given, the present invention is not limited to this. Other than this, as a separating member, for example, a single-layered annular seal packing without a cut, a multi-layered annular seal packing having a layer with a cut and a layer without a cut, etc. The split connection ring R may be provided in the opening X after dismantling and removal. In such a case, when a part of the layer where the cut of the annular seal packing is not provided is cut open, the
[0033]
In the above embodiment, the
[0034]
Moreover, in the said embodiment, although the assembly | attachment operation | work of the division | segmentation connection ring R and the insertion installation operation | work of the
[0035]
Furthermore, in the said embodiment, although the excavation formation process of the groove | channel M and the insertion installation work of the
[0036]
【The invention's effect】
According to the present invention, an isolation member is provided in the opening, and a groove is excavated and formed in the ground by a cutter. It is possible to form a circular groove perpendicular to the dredging pipe without generating it, and to harden the structural wall material in a homogeneous state in the groove to construct a water-blocking wall with high water shielding performance around the dredging pipe As a result, it is not necessary to perform the ground improvement process, so that the cost can be reduced and the construction period can be shortened.
[Brief description of the drawings]
FIG. 1 is a view showing a separating member and a turning unit of a water shielding wall construction device.
FIG. 2 is a view of the swivel unit as viewed from the direction A in FIG.
FIG. 3 is a diagram showing an excavation unit of the impermeable wall construction device.
4 is a cross-sectional view of the excavation unit taken along line BB in FIG. 3. FIG.
FIG. 5 is a cross-sectional view of the excavation unit taken along the line CC in FIG.
FIG. 6 is a perspective view showing an excavation unit.
FIG. 7 is a diagram for explaining a construction method for a water-impervious wall for dredging according to the present invention.
FIG. 8 is a diagram for explaining the construction method.
FIG. 9 is a view for explaining the construction method.
FIG. 10 is a view for explaining the construction method.
FIG. 11 is a diagram for explaining a construction method according to another embodiment.
FIG. 12 is a diagram for explaining a construction method according to another embodiment.
FIG. 13 is a diagram for explaining a conventional construction method.
[Explanation of symbols]
1 All-round seal packing
15 cutter
17a Injection tube
17b Injection tube
24a Boring machine rod
25 Water stop plate
E Obstacle
F Radial direction of the pipe
G ground
M groove
Q Circumferential direction of pipe
R Split connection ring
W impermeable wall
Wa impermeable wall
X opening
Y wall material
Z
Claims (6)
前記開口部に地盤と樋管内とを隔離する隔離部材を設け、地盤掘削用のカッターと、硬化性を有する構壁材注入用の注入管とを前記隔離部材を通して前記開口部から樋管の径方向に突出させ、前記カッターによって地盤を掘削して溝を形成すると同時に当該溝内に前記注入管から前記構壁材を注入充填する工程を、前記カッターと前記注入管とを樋管の円周方向に旋回させながら繰り返し行い、その後前記溝内の構壁材を硬化させて樋管周りに環状の遮水壁を構築することを特徴とする樋管用遮水壁の構築工法。Construction of a water shielding wall for dredging pipes that builds a water shielding wall around the dredging pipe through an annular opening formed after dismantling and removal of the split connection ring previously installed in the dredging pipe connection part In the construction method,
The opening is provided with an isolation member for isolating the ground and the inside of the dredger pipe, and the diameter of the dredger pipe from the opening through the isolation member is a ground excavation cutter and an injection pipe for injecting hard wall construction material. Projecting in the direction, forming a groove by excavating the ground with the cutter, and simultaneously injecting and filling the wall material from the injection pipe into the groove. A construction method for a water-impervious wall for dredging pipes, which is repeatedly performed while swiveling in a direction, and thereafter a wall material in the groove is cured to construct an annular impermeable wall around the dredger pipe.
前記カッターによって掘削された土砂を一定の背圧をかけながら排出して、前記溝内の構壁材の圧力を一定に保持することを特徴とする樋管用遮水壁の構築工法。In the construction method of the impermeable wall for pipes according to claim 1,
The construction method of a water-impervious wall for dredging pipes, wherein the earth and sand excavated by the cutter is discharged while applying a constant back pressure, and the pressure of the wall material in the groove is kept constant.
地盤中に前記カッターによる掘削が困難となる障害物がある場合に、障害物除去用のロッドを前記隔離部材を通して前記開口部から突出させて前記障害物を除去することを特徴とする樋管用遮水壁の構築工法。In the construction method of the water-impervious wall for dredging pipes according to claim 1 or claim 2,
When there is an obstacle in the ground that makes it difficult to excavate by the cutter, the obstacle removing rod protrudes from the opening through the isolation member to remove the obstacle. Water wall construction method.
前記カッターによる地盤掘削と前記注入管からの前記構壁材の注入充填とを繰り返し行った後、前記溝内の構壁材が未硬化の状態にある間に、前記開口部から前記溝内に止水板を挿入して樋管周りに環状に設置することを特徴とする樋管用遮水壁の構築工法。In the construction method of the water-impervious wall for dredging pipes according to any one of claims 1 to 3,
After repeatedly performing ground excavation by the cutter and injection filling of the wall material from the injection pipe, while the wall material in the groove is in an uncured state, the opening enters the groove. A construction method for water barrier walls for dredging pipes, characterized in that a water stop plate is inserted and installed around the dredger pipe in an annular shape.
前記溝内の構壁材が流動性を失う半硬化の状態まで硬化したときに、前記止水板を挿入することを特徴とする樋管用遮水壁の構築工法。In the construction method of the impermeable wall for pipes according to claim 4,
A construction method for a water-impervious wall for dredging pipes, wherein the water blocking plate is inserted when the wall material in the groove is cured to a semi-cured state in which fluidity is lost.
前記構壁材として、硬化性とともに高粘性を有する材料を用いることを特徴とする樋管用遮水壁の構築工法。In the construction method of the water-impervious wall for dredging pipes according to any one of claims 1 to 5,
A construction method for a water-impervious wall for dredging pipes, wherein a material having high viscosity as well as curability is used as the construction wall material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003190004A JP2005023637A (en) | 2003-07-02 | 2003-07-02 | Construction method of impervious wall for gutter pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003190004A JP2005023637A (en) | 2003-07-02 | 2003-07-02 | Construction method of impervious wall for gutter pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2005023637A true JP2005023637A (en) | 2005-01-27 |
Family
ID=34188012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003190004A Pending JP2005023637A (en) | 2003-07-02 | 2003-07-02 | Construction method of impervious wall for gutter pipe |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2005023637A (en) |
-
2003
- 2003-07-02 JP JP2003190004A patent/JP2005023637A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5163424B2 (en) | Groundwater drainage structure and tunnel construction method having the drainage structure | |
EP0810327B1 (en) | Method and device for laying underground continuous walls | |
CN111396067B (en) | Comprehensive shield steel sleeve receiving construction method in complex environment | |
JP5981792B2 (en) | Construction method of press-fit continuous wall | |
JP2003206691A (en) | Shield machine arrival construction method | |
US11603760B2 (en) | Shield method | |
JP2005023637A (en) | Construction method of impervious wall for gutter pipe | |
JP3971241B2 (en) | Method of laying pipe in submarine ground and excavation tip device used for pipe laying method | |
JP3233346B2 (en) | How to lay a conduit that penetrates the embankment without excavation | |
JP4643234B2 (en) | Wall building apparatus and method around pipe | |
JP3401177B2 (en) | Sewer renewal shield excavator | |
JP2002194988A (en) | Receiving method of tunnel excavator to arrival shaft and facility for it | |
JP4829593B2 (en) | Shield machine and shield method using the same | |
JP3356083B2 (en) | How to lay a conduit that penetrates the embankment without excavation | |
KR100652187B1 (en) | Grouting method to the underdrain-installed point in a hillside road | |
JP3394672B2 (en) | Updating existing pipeline | |
CN107059839A (en) | A kind of construction method of armored concrete waveform sheet pile underground structure | |
JP7303756B2 (en) | Open shield machine and tunnel construction method | |
JPH11241593A (en) | Ground collapse preventing method in shield construction | |
JP2005023638A (en) | Wall construction device for circumference of pipe | |
JP4180347B2 (en) | Construction method of underground continuous wall and underground continuous wall | |
JP6837364B2 (en) | How to repair the culvert drainage pipe confluence drainage mass | |
JPH0261600B2 (en) | ||
JP3944005B2 (en) | Chemical injection method to press-fit shaft and its excavation ground | |
KR20220167623A (en) | the half exit method of the excavator in which excavation is completed in the underground tunnel excavation |