Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120413780.8U
Other languages
Chinese (zh)
Inventor
张煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Yinengfu Environmental Protection Technology Co ltd
Original Assignee
Shaanxi Yinengfu Environmental Protection Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Yinengfu Environmental Protection Technology Co ltd filed Critical Shaanxi Yinengfu Environmental Protection Technology Co ltd
Priority to CN202120413780.8U priority Critical patent/CN214747346U/en
Application granted granted Critical
Publication of CN214747346U publication Critical patent/CN214747346U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model discloses a closed cooling tower with high-efficient cooling structure, comprising a tower body, the water tank has been placed to tower body bottom inner wall, and the bottom inner wall fixed mounting of water tank has a water pump, the delivery port of water pump is pegged graft and is had fixed pipe, and the one end fixed mounting that the water pump was kept away from to fixed pipe has a spiral pipe, the top fixed mounting of spiral pipe has the connecting pipe, and the bottom outer wall through connection of connecting pipe has the shower nozzle that the equidistance distributes, the equal fixedly connected with in top both ends of water tank places the piece. The utility model discloses a water in the water pump with the water tank is carried to the connecting pipe in via fixed pipe and spiral pipe, and a plurality of shower nozzles of rethread connecting pipe bottom spray water, realize cooling down to the tower body is inside, and the water droplet that sprays falls on collecting and fights, flows back to the water tank in, realizes the cyclic utilization of water resource, through fighting the filter screen on the intubate of pegging graft with the collection, can filter the impurity of the aquatic of retrieving, can be better utilize the water resource.

Description

Closed cooling tower with high-efficient cooling structure
Technical Field
The utility model relates to a cooling tower technical field especially relates to a closed cooling tower with high-efficient cooling structure.
Background
The closed cooling tower is a closed cooling tower for short, a tubular heat exchanger is arranged in the tower, and the cooling effect is ensured through the heat exchange of circulating air, spray water and circulating water. When the outside air temperature is low, the spray water system can be stopped, and the water-saving effect is achieved. The implementation of national energy conservation and emission reduction policies and the increasing shortage of water resources are pushed forward, and in recent years, the closed cooling tower is widely applied to industries such as metallurgy, aviation, electric power, chemical industry, machinery, petroleum, food, plastics, rubber and the like. With the development of industrial technology, a plurality of devices need to dissipate heat in time in the using process or the material processing process, and cooling towers are mostly used for achieving the purpose of heat dissipation.
Closed cooling tower with high-efficient cooling structure on market has the serious problem of waste water resource usually, is unfavorable for practicing thrift the cost, does not good to the dustproof measure of cooling tower simultaneously, leads to the inside of cooling tower to receive the pollution of dust easily, for this reason, we propose a closed cooling tower with high-efficient cooling structure.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a closed cooling tower with a high-efficiency cooling structure.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a closed cooling tower with a high-efficiency cooling structure comprises a tower body, wherein a water tank is placed on the inner wall of the bottom of the tower body, a water pump is fixedly installed on the inner wall of the bottom of the water tank, a fixed pipe is inserted into a water outlet of the water pump, a spiral pipe is fixedly installed at one end, away from the water pump, of the fixed pipe, a connecting pipe is fixedly installed at the top of the spiral pipe, spray heads distributed at equal intervals are penetratingly connected to the outer wall of the bottom of the connecting pipe, placing blocks are fixedly connected to two ends of the top of the water tank, a collecting hopper is placed at the top of the two placing blocks, an inserting pipe is inserted into the bottom of the inner wall of the collecting hopper, a lantern ring is sleeved at the top of the outer wall of the inserting pipe, a drainage plate is fixedly connected to the inner wall of one side of the tower body, a ventilation assembly is arranged on one side of the drainage plate, the ventilation assembly comprises a fixed frame, connecting blocks are welded to the top and the bottom of the fixed frame, and a dust removal net is bonded to the inner wall around the fixed frame, the equal fixed mounting of both sides inner wall of tower body has the V template, and pegs graft at the top of tower body and have the ventilation pipe, the inner wall one end fixed mounting that the tower body was kept away from to the ventilation pipe has the fan, and the one end outer wall spiro union that the ventilation pipe is close to the fan has the tube cap, the through-hole with ventilation pipe looks adaptation is seted up to one side outer wall of tube cap, and the inner wall all bonds all around of through-hole has the dust screen.
Preferably, the one end that fixed pipe is close to the spiral pipe runs through one side outer wall of tower body and pegs graft with the bottom of spiral pipe, and the one end that the connecting pipe is close to the spiral pipe runs through one side outer wall of tower body and pegs graft with the top of spiral pipe, the one end that the spiral pipe was kept away from to the connecting pipe is airtight structure, and the connecting pipe keeps away from the one end of spiral pipe and the inner wall fixed connection of tower body.
Preferably, the outer diameter of the insertion pipe is matched with the inner diameter of the bottom of the collecting hopper, and the filter screen is bonded to the bottom of the inner wall of the insertion pipe.
Preferably, the outer wall of one side of the tower body is provided with a socket positioned on one side of the drainage plate, and the specification of the socket is matched with that of the fixing frame.
Preferably, the outer walls of the two sides of the V-shaped plate are provided with openings, and stainless steel nets are welded on the peripheral inner walls of the openings.
Preferably, the water pump and the fan are both connected with a switch on the outer wall of one side of the tower body through wires, and the switch is connected with an external power supply through wires.
The utility model has the advantages that:
1. the water in the water tank is conveyed to the connecting pipe through the fixed pipe and the spiral pipe through the water pump, and then is sprayed out through the plurality of spray heads at the bottom of the connecting pipe, so that the interior of the tower body is cooled, the sprayed water drops on the collecting hopper and flows back to the water tank, the recycling of water resources is realized, impurities in the recovered water can be filtered through the filter screen on the insertion pipe inserted with the collecting hopper, the water resources can be better utilized, a plurality of pipelines connected with the water tank can be prevented from being blocked by excessive impurities, and the cost is saved;
2. rotate the inside air escape of tower body through the fan, outside air enters into the inside of tower body through the ventilation subassembly, and then realize the inside air flow of tower body, can filter the dust that gets into in the inside air of tower body through the dust removal net among the ventilation subassembly, stainless steel net through on the V template can make vapor condense into the drop of water, and then reduce the loss of water in the tower body, can further prevent through the dust screen of setting on the ventilation pipe that the dust in the air from entering into the tower body in, be favorable to keeping the inside clean of tower body.
Drawings
Fig. 1 is a schematic overall front sectional structural view of a closed cooling tower with a high-efficiency cooling structure according to the present invention;
fig. 2 is an enlarged schematic view of a structure a of a closed cooling tower with a high-efficiency cooling structure according to the present invention;
fig. 3 is a schematic side sectional view of a ventilation assembly of a closed cooling tower with a high-efficiency cooling structure according to the present invention;
fig. 4 is the utility model provides a V-shaped plate front section structure schematic diagram of closed cooling tower with high-efficient cooling structure.
In the figure: 1 tower body, 2 water tanks, 3 water pumps, 4 fixed pipes, 5 spiral pipes, 6 connecting pipes, 7 spray heads, 8 placing blocks, 9 collecting hoppers, 10 inserting pipes, 11 lantern rings, 12 filter screens, 13 drainage plates, 14 ventilation components, 15 fixing frames, 16 connecting blocks, 17 dust removing nets, 18V-shaped plates, 19 stainless steel nets, 20 ventilation pipes, 21 fans, 22 pipe covers and 23 dust preventing nets.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-4, a closed cooling tower with a high-efficiency cooling structure comprises a tower body 1, a water tank 2 is placed on the inner wall of the bottom of the tower body 1, a water pump 3 is fixedly installed on the inner wall of the bottom of the water tank 2, a fixed pipe 4 is inserted into a water outlet of the water pump 3, a spiral pipe 5 is fixedly installed at one end, far away from the water pump 3, of the fixed pipe 4, a connecting pipe 6 is fixedly installed at the top of the spiral pipe 5, a sprayer 7 which is distributed equidistantly is connected to the outer wall of the bottom of the connecting pipe 6 in a penetrating manner, one end, close to the spiral pipe 5, of the fixed pipe 4 penetrates through the outer wall of one side of the tower body 1 to be inserted into the bottom of the spiral pipe 5, one end, near the spiral pipe 5, of the connecting pipe 6 penetrates through the outer wall of one side of the tower body 1 to be inserted into the top of the spiral pipe 5, one end, far away from the spiral pipe 5, of the connecting pipe 6 is of the closed structure, and is fixedly connected with the inner wall of the tower body 1, the water tank is characterized in that the two ends of the top of the water tank 2 are fixedly connected with the placing blocks 8, the collecting hoppers 9 are placed on the tops of the two placing blocks 8, the bottom of the inner wall of each collecting hopper 9 is inserted with the insertion pipe 10, the top of the outer wall of each insertion pipe 10 is sleeved with the lantern ring 11, the outer diameter of each insertion pipe 10 is matched with the inner diameter of the bottom of each collecting hopper 9, the bottom of the inner wall of each insertion pipe 10 is bonded with the filter screen 12, water in the water tank 2 is conveyed into the connecting pipe 6 through the fixed pipe 4 and the spiral pipe 5 by the water pump 3, then the water is sprayed out through the plurality of spray heads 7 at the bottom of the connecting pipe 6, the interior of the tower body 1 is cooled, the sprayed water drops on the collecting hoppers 9 and flows back to the water tank 2, the water resource is recycled, impurities in the recycled water can be filtered through the filter screens 12 on the insertion pipes 10 inserted with the collecting hoppers 9, and the water resource can be better utilized, the multiple pipelines connected with the water tank 2 can be prevented from being blocked by excessive impurities, and the cost is saved;
the inner wall of one side of the tower body 1 is fixedly connected with a drainage plate 13, one side of the drainage plate 13 is provided with a ventilation assembly 14, the ventilation assembly 14 comprises a fixed frame 15, connecting blocks 16 are welded at the top and the bottom of the fixed frame 15, a socket positioned at one side of the drainage plate 13 is arranged on the outer wall of one side of the tower body 1, the specification of the socket is matched with that of the fixed frame 15, dust removing nets 17 are bonded on the peripheral inner walls of the fixed frame 15, V-shaped plates 18 are fixedly arranged on the inner walls of two sides of the tower body 1, a ventilation pipe 20 is inserted into the top of the tower body 1, openings are arranged on the outer walls of two sides of the V-shaped plates 18, stainless steel nets 19 are welded on the peripheral inner walls of the openings, a fan 21 is fixedly arranged at one end of the inner wall of the ventilation pipe 20 far away from the tower body 1, a pipe cover 22 is screwed on the outer wall of one end of the ventilation pipe 20 close to the fan 21, and a switch positioned on the outer wall of one side of the tower body 1 is connected with the water pump 3 and the fan 21 through wires, and the switch is connected with external power source through the wire, the through-hole with 20 looks adaptations of ventilation pipe is seted up to one side outer wall of tube cap 22, and the inner wall all bonds of through-hole has dust screen 23 all around, rotate the air escape with tower body 1 inside through fan 21, outside air enters into the inside of tower body 1 through ventilation subassembly 14, and then realize the inside air flow of tower body 1, dust screen 17 through among the ventilation subassembly 14 can filter the dust that gets into in the air of tower body 1 inside, stainless steel net 19 through on the V template 18 can make vapor condense into the drop of water, and then reduce the loss of water in the tower body 1, dust in can further preventing the air through the dust screen 23 that sets up on ventilation pipe 20 enters into tower body 1, be favorable to keeping the clean of tower body 1 inside.
The working principle is as follows: water in the water tank 2 is conveyed to the connecting pipe 6 through the fixed pipe 4 and the spiral pipe 5 by the water pump 3, then the water is sprayed out through a plurality of spray heads 7 at the bottom of the connecting pipe 6, the interior of the tower body 1 is cooled, the sprayed water drops on the collecting hopper 9 and flows back to the water tank 2, the recycling of water resources is realized, impurities in the recycled water can be filtered through the filter screen 12 on the inserting pipe 10 inserted with the collecting hopper 9, the water resources can be better utilized, a plurality of pipelines connected with the water tank 2 can be prevented from being blocked by the impurities too much, air in the tower body 1 is discharged by the rotation of the fan 21, external air enters the interior of the tower body 1 through the ventilation assembly 14, further, the air flow in the tower body 1 is realized, dust in the air entering the tower body 1 can be filtered through the dust removal net 17 in the ventilation assembly 14, can make vapor condense into the drop of water through the stainless steel net 19 on the V-arrangement board 18, and then reduce the loss of water in the tower body 1, can further prevent through the dust screen 23 that sets up on ventilation pipe 20 that the dust in the air from entering into in the tower body 1, can keep the inside clean of tower body 1.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and to simplify the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The closed cooling tower with the efficient cooling structure comprises a tower body (1) and is characterized in that a water tank (2) is placed on the inner wall of the bottom of the tower body (1), a water pump (3) is fixedly installed on the inner wall of the bottom of the water tank (2), a water outlet of the water pump (3) is connected with a fixed pipe (4) in an inserting mode, a spiral pipe (5) is fixedly installed at one end, away from the water pump (3), of the fixed pipe (4), a connecting pipe (6) is fixedly installed at the top of the spiral pipe (5), spray heads (7) distributed equidistantly are connected to the outer wall of the bottom of the connecting pipe (6) in a penetrating mode, placing blocks (8) are fixedly connected to two ends of the top of the water tank (2), a collecting hopper (9) is placed at the tops of the two placing blocks (8), an inserting pipe (10) is connected to the bottom of the inner wall of the collecting hopper (9) in an inserting mode, and a lantern ring (11) is sleeved at the top of the outer wall of the inserting pipe (10), a drainage plate (13) is fixedly connected with the inner wall of one side of the tower body (1), a ventilation assembly (14) is arranged on one side of the drainage plate (13), the ventilation assembly (14) comprises a fixed frame (15), the top and the bottom of the fixed frame (15) are welded with connecting blocks (16), the inner walls around the fixed frame (15) are bonded with dust removing nets (17), the inner walls of two sides of the tower body (1) are both fixedly provided with V-shaped plates (18), a ventilation pipe (20) is inserted at the top of the tower body (1), a fan (21) is fixedly arranged at one end of the ventilation pipe (20) far away from the inner wall of the tower body (1), and a pipe cover (22) is screwed on the outer wall of one end of the ventilation pipe (20) close to the fan (21), the outer wall of one side of tube cap (22) is seted up with ventilation pipe (20) looks adaptation's through-hole, and the inner wall all bonds all around of through-hole has dust screen (23).
2. The closed cooling tower with the efficient cooling structure as claimed in claim 1, wherein one end of the fixed pipe (4) close to the spiral pipe (5) penetrates through an outer wall of one side of the tower body (1) to be inserted into a bottom end of the spiral pipe (5), one end of the connecting pipe (6) close to the spiral pipe (5) penetrates through an outer wall of one side of the tower body (1) to be inserted into a top end of the spiral pipe (5), one end of the connecting pipe (6) far away from the spiral pipe (5) is of a closed structure, and one end of the connecting pipe (6) far away from the spiral pipe (5) is fixedly connected with an inner wall of the tower body (1).
3. The closed cooling tower with the high-efficiency cooling structure is characterized in that the outer diameter of the insertion pipe (10) is matched with the inner diameter of the bottom of the collecting hopper (9), and the bottom of the inner wall of the insertion pipe (10) is adhered with the filter screen (12).
4. The closed cooling tower with the efficient cooling structure as claimed in claim 1, wherein the outer wall of one side of the tower body (1) is provided with a socket on one side of the flow guide plate (13), and the specification of the socket is matched with that of the fixed frame (15).
5. The closed cooling tower with the efficient cooling structure as claimed in claim 1, wherein the outer walls of the two sides of the V-shaped plate (18) are opened, and stainless steel nets (19) are welded on the inner walls of the periphery of the opening.
6. The closed cooling tower with the efficient cooling structure as claimed in claim 1, wherein the water pump (3) and the fan (21) are connected with a switch on the outer wall of one side of the tower body (1) through wires, and the switch is connected with an external power supply through wires.
CN202120413780.8U 2021-02-25 2021-02-25 Closed cooling tower with high-efficient cooling structure Expired - Fee Related CN214747346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120413780.8U CN214747346U (en) 2021-02-25 2021-02-25 Closed cooling tower with high-efficient cooling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120413780.8U CN214747346U (en) 2021-02-25 2021-02-25 Closed cooling tower with high-efficient cooling structure

Publications (1)

Publication Number Publication Date
CN214747346U true CN214747346U (en) 2021-11-16

Family

ID=78589819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120413780.8U Expired - Fee Related CN214747346U (en) 2021-02-25 2021-02-25 Closed cooling tower with high-efficient cooling structure

Country Status (1)

Country Link
CN (1) CN214747346U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116336701A (en) * 2023-05-25 2023-06-27 山东大华环境节能科技有限公司 Evaporative condenser with multistage heat exchange

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116336701A (en) * 2023-05-25 2023-06-27 山东大华环境节能科技有限公司 Evaporative condenser with multistage heat exchange

Similar Documents

Publication Publication Date Title
CN107589814B (en) Computer cabinet
CN214747346U (en) Closed cooling tower with high-efficient cooling structure
CN108476987A (en) A kind of environment-friendly temperature-reducing pig house
CN112023632A (en) Working method of agricultural waste gas circulating and purifying device
CN214287541U (en) Pesticide composition recovery unit for pesticide production waste gas
CN212701078U (en) Water circulation spraying and absorbing device
CN212901806U (en) Industrial low-energy-consumption industrial refrigeration equipment
CN211204609U (en) Efficient circulating air cooler for bearing carburizing and quenching
CN210522224U (en) Environment-friendly exhaust gas desulfurization processing apparatus
CN210543877U (en) Comprehensive treatment device for dust-containing waste gas
CN206889084U (en) A kind of automobile water tank radiation device
CN217210444U (en) Energy-saving closed cooling tower
CN218901299U (en) Environment-friendly device for processing dust
CN211852299U (en) Mine ventilation unit is used in mining
CN213668404U (en) Defogging device for net part of paper machine
CN214855902U (en) Sharing rack for umbrella based on public economy
CN212158204U (en) Multi-circulation cooling tower for water-based paint
CN212914992U (en) Air purification device for mixing station
CN211451878U (en) Cooling device for metallurgical equipment
CN217752695U (en) Cooling water circulation energy-saving device for producing plastic pipeline
CN214279756U (en) Respirator capable of efficiently and quickly replacing moisture absorbent
CN216516530U (en) Snow removing device for top of air film building
CN211739566U (en) Novel elliptical tube evaporative condenser
CN218723495U (en) Water circulation treatment device for cooling tower
CN214700748U (en) Energy-saving environment-friendly catalytic combustion device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211116