CN214696294U - Innovative building curtain wall dry hanging system - Google Patents

Innovative building curtain wall dry hanging system Download PDF

Info

Publication number
CN214696294U
CN214696294U CN202023084879.2U CN202023084879U CN214696294U CN 214696294 U CN214696294 U CN 214696294U CN 202023084879 U CN202023084879 U CN 202023084879U CN 214696294 U CN214696294 U CN 214696294U
Authority
CN
China
Prior art keywords
shaped frame
curtain wall
inverted
screw
building curtain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023084879.2U
Other languages
Chinese (zh)
Inventor
吕正源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huabaoshi Shanghai Wall Material Co ltd
Original Assignee
Huabaoshi Shanghai Wall Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huabaoshi Shanghai Wall Material Co ltd filed Critical Huabaoshi Shanghai Wall Material Co ltd
Priority to CN202023084879.2U priority Critical patent/CN214696294U/en
Application granted granted Critical
Publication of CN214696294U publication Critical patent/CN214696294U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Curtains And Furnishings For Windows Or Doors (AREA)

Abstract

The utility model belongs to the field of building curtain walls, in particular to an innovative building curtain wall dry hanging system, which comprises a first L-shaped frame fixed on a wall body, wherein a second L-shaped frame is arranged on the first L-shaped frame, a first buckling type tooth socket is fixedly arranged on one side of the vertical section of the second L-shaped frame, which is close to the first L-shaped frame, a curtain wall is sleeved on the second L-shaped frame, the curtain wall comprises an inverted U-shaped frame and a T-shaped frame, the horizontal end of the T-shaped frame is fixedly connected with one end of the inverted U-shaped frame, a second buckling type tooth socket is fixedly arranged on the inner wall of one side of the inverted U-shaped frame, which is far away from the T-shaped frame, the inverted U-shaped frame is sleeved on the vertical section of the second L-shaped frame, and the second buckling type tooth socket is matched with the first buckling type tooth socket, the first L-shaped frame and the second L-shaped frame are convenient and firm to install, and the curtain wall is more convenient to install through the buckling type tooth socket, the fixation is firmer, and the safety factor is high.

Description

Innovative building curtain wall dry hanging system
Technical Field
The utility model relates to a building curtain technical field especially relates to an innovative building curtain hangs system futilely.
Background
The curtain wall is the outer wall enclosure of the building, does not bear the weight, hangs like a curtain, so is also called as a curtain wall, and is a light wall with decorative effect commonly used by modern large-scale and high-rise buildings. The building outer protective structure or decorative structure is composed of a panel and a supporting structure system, can have certain displacement capacity or certain self deformation capacity relative to the main structure, and does not play a role of the main structure. The curtain wall is an outer wall construction method which utilizes various strong, light and beautiful building materials to replace the traditional masonry or window wall combination, and is an outer wall construction method which surrounds the periphery of a main structure to ensure that the whole building is beautiful, and has sound and safe use functions. In short, a building is put on a beautiful coat. The curtain wall mainly comprises an outer wall of a building, a daylighting roof and a rain cover. Along with the high-speed development of national economy and the continuous improvement of the living standard of people in China and the improvement of the design concept of architects 'humanity is better than construction', buildings are developed to the direction of high-rise, high-grade and multifunctional more and more. However, the existing building curtain wall is inconvenient and not firm to install, and the safety factor is not high.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing an innovative building curtain wall dry hanging system.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an innovative building curtain hangs system futilely, is including fixing the first L type frame on the wall body, install second L type frame on the first L type frame, one side fixed mounting that the vertical section of second L type frame is close to first L type frame has first buckle formula tooth's socket, the curtain has been cup jointed on the second L type frame, the curtain includes inverted U type frame and T type frame, and the horizontal end of T type frame and the one end fixed connection of inverted U type frame, fixed mounting has second buckle formula tooth's socket on the one side inner wall that T type frame was kept away from to inverted U type frame, inverted U type frame cup joints on the vertical section of second L type frame, and second buckle formula tooth's socket and first buckle formula tooth's socket looks adaptation.
Preferably, a plurality of first square grooves are formed in the top of the first L-shaped frame horizontal section, a plurality of second square grooves are formed in the bottom of the second L-shaped frame horizontal section, the first square grooves and the second square grooves are arranged correspondingly, and first screw holes and second screw holes are formed in the inner wall, close to each other, of one side of the first square grooves and the second square grooves on the same horizontal plane respectively.
Preferably, the same screw rod is installed to first screw and second screw internal thread, and the both ends of screw rod extend to in first square groove and the second square groove respectively.
Preferably, a first nut and a second nut are respectively placed in the first square groove and the second square groove, and the first nut and the second nut are respectively sleeved at two ends of the screw rod in a threaded manner.
Preferably, the threads at the two ends of the screw rod are arranged oppositely, and the bottom of the screw rod is provided with an inner hexagonal groove.
The utility model discloses in, an innovative building curtain hangs system futilely, owing to be provided with first L type frame and second L type frame, first L type frame and second L type frame simple to operate are firm, then, firmly block the curtain through buckle formula tooth's socket, it is more convenient to install, and is fixed more firm, and factor of safety is high.
Drawings
Fig. 1 is a schematic view of a first L-shaped frame structure of an innovative building curtain wall dry hanging system proposed by the present invention;
fig. 2 is a schematic structural view of a second L-shaped frame of the innovative building curtain wall dry hanging system provided by the present invention;
fig. 3 is a schematic view of a curtain wall structure of an innovative building curtain wall dry hanging system provided by the utility model;
fig. 4 is a schematic view of the overall structure of an innovative building curtain wall dry hanging system provided by the utility model;
fig. 5 is a schematic view of a connection structure of a first L-shaped frame and a second L-shaped frame of an innovative building curtain wall dry hanging system provided by the utility model;
fig. 6 is the utility model provides an innovative building curtain wall hangs a part a schematic structure of system futilely.
In the figure: the curtain wall structure comprises a first L-shaped frame 1, a second L-shaped frame 2, a curtain wall 3, a first square groove 4, a first nut 5, a first screw hole 6, a second square groove 7, a second nut 8, a second screw hole 9, a screw rod 10, an inner hexagonal groove 11, a first buckling type tooth groove 21, an inverted U-shaped frame 31, a 32T-shaped frame 33 and a second buckling type tooth groove 33.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-6, an innovative building curtain wall dry hanging system comprises a first L-shaped frame 1 fixed on a wall body, a second L-shaped frame 2 is installed on the first L-shaped frame 1, a first buckling type tooth groove 21 is fixedly installed on one side, close to the first L-shaped frame 1, of a vertical section of the second L-shaped frame 2, a curtain wall 3 is sleeved on the second L-shaped frame 2, the curtain wall 3 comprises an inverted U-shaped frame 31 and a T-shaped frame 32, a horizontal end of the T-shaped frame 32 is fixedly connected with one end of the inverted U-shaped frame 31, a second buckling type tooth groove 33 is fixedly installed on an inner wall of one side, far away from the T-shaped frame 32, of the inverted U-shaped frame 31, the inverted U-shaped frame 31 is sleeved on the vertical section of the second L-shaped frame 2, and the second buckling type tooth groove 33 is matched with the first buckling type tooth groove 21.
The utility model discloses in, a plurality of first square grooves 4 have been seted up at the top of 1 horizontal segment of first L type frame, and a plurality of second square grooves 7 have been seted up to the bottom of 2 horizontal segments of second L type frame, and a plurality of first square grooves 4 and the corresponding setting of a plurality of second square grooves 7, have seted up first screw 6 and second screw 9 respectively on the one side inner wall that first square groove 4 and second square groove 7 that are located on the same horizontal plane are close to each other.
The utility model discloses in, same screw rod 10 is installed to first screw 6 and the 9 internal threads of second screw, and the both ends of screw rod 10 extend to in first square groove 4 and the second square groove 7 respectively.
The utility model discloses in, first nut 5 and second nut 8 have been placed respectively in first square groove 4 and the second square groove 7, and first nut 5 and second nut 8 respectively the screw thread cup joint at the both ends of screw rod 10, first square groove 4 and second square groove 7 restrict the rotation of first nut 5 and second nut 8.
The utility model discloses in, the both ends screw thread of screw rod 10 sets up on the contrary, and the bottom of screw rod 10 has seted up interior hexagonal groove 11, is convenient for select rotatory operation to screw rod 10 through the hexagonal spanner.
The utility model discloses in, the theory of operation, fix first L type frame 1 on the wall body through the inflation screw, then, place second L type frame 2 on first L type frame 1, insert in hexagonal groove 11 through the hexagonal spanner, the tight screw rod of spiral shell 10, screw rod 10 is at first screw 6 and the 9 internal rotations of second screw, and simultaneously, at first nut 5 and the 8 internal rotations of second nut, make first L type frame 1 and second L type frame 2 fix together, then, overlap curtain 3 on second L type frame 2, the type of falling U31 covers on the vertical section of second L type frame 2, second buckle formula tooth's socket 33 and first buckle formula tooth's socket 21 looks block, make curtain 3 fix.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. An innovative building curtain wall dry hanging system comprises a first L-shaped frame (1) fixed on a wall body, it is characterized in that a second L-shaped frame (2) is arranged on the first L-shaped frame (1), a first buckle type tooth groove (21) is fixedly arranged on one side of the vertical section of the second L-shaped frame (2) close to the first L-shaped frame (1), the second L-shaped frame (2) is sleeved with a curtain wall (3), the curtain wall (3) comprises an inverted U-shaped frame (31) and a T-shaped frame (32), and the horizontal end of the T-shaped frame (32) is fixedly connected with one end of the inverted U-shaped frame (31), a second buckle type tooth socket (33) is fixedly arranged on the inner wall of one side of the inverted U-shaped frame (31) far away from the T-shaped frame (32), the inverted U-shaped frame (31) is sleeved on the vertical section of the second L-shaped frame (2), and the second snap-in tooth groove (33) is matched with the first snap-in tooth groove (21).
2. The innovative building curtain wall dry hanging system according to claim 1, characterized in that a plurality of first square grooves (4) are opened at the top of the horizontal section of the first L-shaped frame (1), a plurality of second square grooves (7) are opened at the bottom of the horizontal section of the second L-shaped frame (2), the plurality of first square grooves (4) and the plurality of second square grooves (7) are correspondingly arranged, and a first screw hole (6) and a second screw hole (9) are respectively opened on the inner wall of one side, close to each other, of the first square grooves (4) and the second square grooves (7) on the same horizontal plane.
3. The innovative building curtain wall dry hanging system according to claim 2, characterized in that the same screw (10) is mounted in the first screw hole (6) and the second screw hole (9) with internal threads, and both ends of the screw (10) extend into the first square groove (4) and the second square groove (7), respectively.
4. The innovative building curtain wall dry hanging system according to claim 2, characterized in that a first nut (5) and a second nut (8) are placed in the first square groove (4) and the second square groove (7), respectively, and the first nut (5) and the second nut (8) are respectively sleeved at both ends of the screw (10) in a threaded manner.
5. The innovative building curtain wall dry hanging system according to claim 3, characterized in that the threads at both ends of the screw (10) are arranged in opposite directions, and the bottom of the screw (10) is provided with an internal hexagonal groove (11).
CN202023084879.2U 2020-12-21 2020-12-21 Innovative building curtain wall dry hanging system Expired - Fee Related CN214696294U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023084879.2U CN214696294U (en) 2020-12-21 2020-12-21 Innovative building curtain wall dry hanging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023084879.2U CN214696294U (en) 2020-12-21 2020-12-21 Innovative building curtain wall dry hanging system

Publications (1)

Publication Number Publication Date
CN214696294U true CN214696294U (en) 2021-11-12

Family

ID=78558551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023084879.2U Expired - Fee Related CN214696294U (en) 2020-12-21 2020-12-21 Innovative building curtain wall dry hanging system

Country Status (1)

Country Link
CN (1) CN214696294U (en)

Similar Documents

Publication Publication Date Title
CN206667649U (en) Wallboard dry-hang top fixing element
CN214696294U (en) Innovative building curtain wall dry hanging system
CN201351433Y (en) Multifunctional inward and outward casement window profile with window screen and anti-theft device
CN206941913U (en) Hanging structure on the outside of a kind of large span type unitized curtain wall
CN208455981U (en) A kind of drag-line decoration device for guaranteeing sunshade grid and being in horizontality
CN212836139U (en) Photovoltaic curtain wall supporting structure
CN105863133A (en) Building curtain wall
CN211472999U (en) Cable type glass curtain wall clamp structure form
CN202280369U (en) Axial open window used in building curtain wall
CN207296096U (en) Energy saving building curtain wall
CN205035947U (en) Window curtain is opened to reentrant corner
CN220620598U (en) Curtain wall with height adjusting function
CN207686076U (en) A kind of building curtain wall ventilation device
CN220058498U (en) Aluminum ceiling convenient to installation
CN206279668U (en) A kind of connector for connecting open type aluminum mainboard and crossbeam
CN207332132U (en) A kind of crossbeam on energy-saving lighting top
CN218060933U (en) Integrated aluminum plate dry-hanging curtain wall
CN211396182U (en) Curtain wall
CN205063118U (en) Component formula curtain
CN220395461U (en) Anti-drop device for casement window
CN213488283U (en) Curtain box part for glass curtain wall
CN214090501U (en) Curtain wall connecting structure based on high-rise building
CN211903189U (en) Ventilator for glass curtain wall
CN217897719U (en) Building energy-saving outer facade structure
CN2589552Y (en) Breathing dynamic double-layer curtain wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211112