CN211420880U - Integral traction hanging basket walking device - Google Patents

Integral traction hanging basket walking device Download PDF

Info

Publication number
CN211420880U
CN211420880U CN201921803820.9U CN201921803820U CN211420880U CN 211420880 U CN211420880 U CN 211420880U CN 201921803820 U CN201921803820 U CN 201921803820U CN 211420880 U CN211420880 U CN 211420880U
Authority
CN
China
Prior art keywords
track
hanging basket
steel
walking device
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921803820.9U
Other languages
Chinese (zh)
Inventor
路涛
谷兆普
聂金龙
吴鹏飞
易明
刘兴峰
代戈弋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
Original Assignee
Stecol Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Stecol Corp filed Critical Stecol Corp
Priority to CN201921803820.9U priority Critical patent/CN211420880U/en
Application granted granted Critical
Publication of CN211420880U publication Critical patent/CN211420880U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides an integral pull string basket running gear, including hanging basket and track, the track includes two worker's steels of arranging side by side and fixing on the bridge, and is in the track front end is equipped with the jack, preceding support and back support have been placed respectively at both ends around the orbital upside, hang basket fixed connection in the front on support and back support, be equipped with the left-hand thread wheel on the back support, the left-hand thread wheel lock joint is on the horizontal plate of a worker's steel upper surface, the jack rear end is connected with the cable, support fixed connection is on the left-hand thread wheel before the cable other end passes. The utility model discloses beneficial effect: the suspended operation during installation of the counter-force beam is avoided, no welding reinforcement operation exists, no desoldering phenomenon exists, the structural system is horizontally inwards, the occurrence of rail slipping accidents is avoided, and the whole walking process is safe and reliable.

Description

Integral traction hanging basket walking device
Technical Field
The utility model belongs to hang basket pulling equipment field after the bridge construction, especially, relate to an integral pulls and hangs basket running gear.
Background
In bridge construction, a common manual traction walking device is pulled by a jack or a chain block and slides on a sliding track, a traction mechanism and a track structure are separated, a traction bracket is independently arranged at the front end of the device and anchored with a poured concrete end and a steel bar, and a walking track is arranged on a beam surface and anchored.
The hanging basket has the defects that the phenomenon of pulling-off of the welding seam between the counterforce beam and the main rib is often easy to generate when the hanging basket walks, and the normal walking of the hanging basket is influenced because the field reinforcement welding is needed; the condition that the track and the hanging basket structure slide on the concrete beam synchronously easily occurs due to the fact that the walking track bears horizontal force.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model aims at providing an integral pull string basket running gear to solve the weak point of above-mentioned problem.
In order to achieve the above purpose, the technical scheme of the utility model is realized like this:
the utility model provides an integral pull string basket running gear, includes string basket and track, the track includes that two are arranged side by side and fix the worker steel on the bridge, just the track front end is equipped with the jack, preceding support and back support have been placed respectively at both ends around orbital upside, string basket fixed connection is on preceding support and back support, be equipped with the left-hand thread wheel on the back support, the left-hand thread wheel lock joint is on the horizontal plate of a worker steel upper surface, the jack rear end is connected with the cable, the cable other end passes preceding support fixed connection and takes turns to at the left-hand thread.
Further, the vertical welding of track front end has the baffle, baffle front side fixedly connected with jack, cable one end is passed the baffle and is connected on the jack.
Furthermore, the rear side of the baffle plate is welded with a transverse plate positioned on the upper surface of the track, and a plurality of reinforcing plates are arranged between the rear side of the baffle plate and the transverse plate.
Further, the track comprises a plurality of sections of sub-tracks which are fixedly spliced together end to end.
Furthermore, both ends all are equipped with a plurality of first connecting holes around the worker steel side surface, every adjacent two divide the track head and the tail to align and link together with a connecting plate with the first connecting hole on two branch tracks with the bolt.
Furthermore, the bottom surface of the I-steel is provided with a plurality of second connecting holes, the second connecting holes are provided with reinforcing steel bars, and the I-steel is anchored on the bridge through the reinforcing steel bars.
Furthermore, hang basket rear end and pass through reinforcing bar and nut cooperation and can dismantle the connection on the bridge.
Furthermore, the upper surface of the track is detachably provided with a plurality of anchor plates between the duplex steel, each anchor plate is provided with a plurality of third connecting holes, and each anchor plate is internally provided with a steel bar in one or more third connecting holes and is anchored on the bridge through the steel bar.
Compared with the prior art, integral pull string basket running gear have following advantage:
the integral traction hanging basket walking device of the utility model has reliable quality, light structure, definite stress, larger integral rigidity, difficult deformation and faster walking speed; the suspension operation during the installation of the counter-force beam is avoided, no welding reinforcement operation exists, no desoldering phenomenon exists, the structural system is horizontally inward, the occurrence of rail slipping accidents is avoided, and the whole walking process is safe and reliable; meanwhile, the main reinforcement does not need to be cut and the main reinforcement lengthening operation after one section is finished, no pollutant is generated in the construction process, and the method is environment-friendly and energy-saving and accords with the design concept of green buildings advocated by the state.
Drawings
The accompanying drawings, which form a part hereof, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the invention without undue limitation. In the drawings:
fig. 1 is a schematic structural view of an integral traction hanging basket walking device according to an embodiment of the present invention;
fig. 2 is a schematic view of a track structure according to an embodiment of the present invention.
Description of reference numerals:
1-a track; 2-a jack; 3-a guy cable; 4-a baffle plate; 5-a reinforcing plate; 6, hanging a basket; 7-front support; 8-a reverse buckling wheel; 9-bridge.
Detailed Description
It should be noted that, in the present invention, the embodiments and features of the embodiments may be combined with each other without conflict.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are used merely for convenience of description and for simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention. Furthermore, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless otherwise specified.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
As shown in fig. 1 and 2, an integral traction hanging basket traveling device comprises a hanging basket 6 and a track 1, wherein the track 1 comprises two pieces of work steel which are arranged side by side and fixed on a bridge 9, a jack 2 is arranged at the front end of the track 1, a front support 7 and a rear support are respectively placed at the front end and the rear end of the upper side of the track 1, the hanging basket 6 is fixedly connected onto the front support 7 and the rear support, a reverse buckle wheel 8 is arranged on the rear support, the reverse buckle wheel 8 is buckled on a horizontal plate on the upper surface of the work steel, a pull rope 3 is connected to the rear end of the jack 2, and the other end of the pull rope 3 penetrates through the front support 7 and is fixedly connected onto the reverse buckle wheel 8.
The vertical welding of 1 front end of track has baffle 4, 4 front side fixedly connected with jacks 2 of baffle, 3 one end of cable is passed baffle 4 and is connected on jacks 2.
The rear side of the baffle 4 is welded with a transverse plate positioned on the upper surface of the track 1, and a plurality of reinforcing plates 5 are arranged between the rear side of the baffle 4 and the transverse plate.
The track 1 comprises a plurality of sections of sub tracks which are fixedly spliced together end to end, wherein the plurality of sections of sub tracks are welded together.
Both ends all are equipped with a plurality of first connecting holes around the worker steel side surface for the multistage divides the track end to end connection, every adjacent two divide the track end to align and link together with a connecting plate with the first connecting hole on two branch tracks with the bolt.
The bottom surface of the I-steel is provided with a plurality of second connecting holes, the second connecting holes are provided with reinforcing steel bars, and the I-steel is anchored on the bridge 9 through the reinforcing steel bars.
The rear end of the hanging basket 6 is detachably connected to the bridge 9 through the matching of steel bars and nuts.
Track 1 upper surface can be dismantled between the duplex steel and be equipped with a plurality of anchor boards, every all be equipped with a plurality of third connecting holes on the anchor board, every be equipped with the reinforcing bar in the one or more third connecting hole on the anchor board, through reinforcing bar anchor on bridge 9, when hanging the basket and move forward, when moving nearest anchor board department, tear down the anchor board in the place ahead and move the position once, avoid hindering and hang 6 removals of basket.
The working process of the embodiment is as follows:
after will hang basket 6 and install on track 1, again with the end-to-end connection of cable 3 on reverse pinch roller 8, and fasten the back with the nut, adopt jack 2 pulling cable 3, cable 3 forward movement, and then drive front support 7 and the back support that hangs basket 6 and slide forward on track 1, when need not remove, with the reinforcing bar anchor of back support department, further spacing fixes on bridge 9, when moving forward once more, loosen the reinforcing bar of back support and move forward again earlier.
In the moving process, when the hanging basket 6 moves forwards, the rear end of the hanging basket 6 can lift upwards once, the pulley pressure of the reverse buckling wheel 8 moves forwards at the bottom of the horizontal plate on the upper side of the I-steel, and at the moment, the reverse buckling wheel 8 also plays a role in fixing and limiting.
When the track 1 needs to extend forwards, the following sub-tracks are only required to be detached and moved forwards for installation.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The utility model provides an integral pull string basket running gear which characterized in that: including hanging basket and track, the track includes that two are arranged side by side and fix the worker steel on the bridge, and the track front end is equipped with the jack, preceding support and back support have been placed respectively at both ends around orbital upside, hang basket fixed connection in the front on support and back support, be equipped with the left-hand thread wheel on the back support, the left-hand thread wheel lock joint is on the horizontal plate of an worker steel upper surface, the jack rear end is connected with the cable, the cable other end passes preceding support fixed connection on the left-hand thread wheel.
2. The integral traction hanging basket walking device according to claim 1, characterized in that: the vertical welding of track front end has the baffle, baffle front side fixedly connected with jack, cable one end is passed the baffle and is connected on the jack.
3. The integral traction hanging basket walking device according to claim 2, characterized in that: the baffle rear side welding has the diaphragm that is located the track upper surface, be equipped with a plurality of reinforcing plates between baffle rear side and the diaphragm.
4. The integral traction hanging basket walking device according to claim 1, characterized in that: the track comprises a plurality of sections of sub-tracks which are fixedly spliced together end to end.
5. The integral traction hanging basket walking device according to claim 4, characterized in that: the front end and the rear end of the side surface of the I-steel are respectively provided with a plurality of first connecting holes, every two adjacent sub-rails are aligned end to end and the first connecting holes on the two sub-rails are connected together with one connecting plate through bolts.
6. The integral traction hanging basket walking device according to claim 1, characterized in that: the bottom surface of the I-steel is provided with a plurality of second connecting holes, the second connecting holes are provided with reinforcing steel bars, and the I-steel is anchored on the bridge through the reinforcing steel bars.
7. The integral traction hanging basket walking device according to claim 1, characterized in that: the rear end of the hanging basket is detachably connected to the bridge through the matching of steel bars and nuts.
8. The integral traction hanging basket walking device according to claim 1, characterized in that: the upper surface of the track is detachably provided with a plurality of anchoring plates between the duplex steel, each anchoring plate is provided with a plurality of third connecting holes, and each anchoring plate is internally provided with a steel bar in one or more third connecting holes and is anchored on the bridge through the steel bar.
CN201921803820.9U 2019-10-24 2019-10-24 Integral traction hanging basket walking device Active CN211420880U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921803820.9U CN211420880U (en) 2019-10-24 2019-10-24 Integral traction hanging basket walking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921803820.9U CN211420880U (en) 2019-10-24 2019-10-24 Integral traction hanging basket walking device

Publications (1)

Publication Number Publication Date
CN211420880U true CN211420880U (en) 2020-09-04

Family

ID=72287432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921803820.9U Active CN211420880U (en) 2019-10-24 2019-10-24 Integral traction hanging basket walking device

Country Status (1)

Country Link
CN (1) CN211420880U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737658A (en) * 2021-09-18 2021-12-03 山东紫菜云数字科技有限公司 Track structure for hanging basket walking and mounting method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737658A (en) * 2021-09-18 2021-12-03 山东紫菜云数字科技有限公司 Track structure for hanging basket walking and mounting method thereof

Similar Documents

Publication Publication Date Title
CN101250856B (en) Echelon cradle as well as construction method thereof
JP5097313B2 (en) Suspended scaffold and its installation method
CN111172887A (en) Construction method of hollow thin-wall pier continuous rigid frame bridge main beam and No. 0 block bracket thereof
CN108411922B (en) Method for dismantling steel support
CN108265628A (en) One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method
CN107313360B (en) Sliding cable type support-free support replacing operation platform
CN110700119B (en) Design construction method of walking system on assembled bailey beam hanging basket
CN112095493B (en) Pushing device of self-correcting guy rope hanging basket for bridge construction
CN107858929B (en) Cast-in-situ Beam form fixer is filled with and removes the construction method of cast-in-place beam forms
CN112900287B (en) Cantilever perfusion bridge fabrication machine
CN211420880U (en) Integral traction hanging basket walking device
CN111379424A (en) Anti-overturning device and method for planar structure sliding construction
CN109778713A (en) A kind of steel truss girder bridge scene suspension and slipping assembly device and method
CN110080117B (en) Movable simple concrete guardrail template vehicle and manufacturing method thereof
JP5006058B2 (en) Temporary material for escalator frame installation and erection method using temporary material for escalator frame installation
CN210368669U (en) Hoisting equipment for two-span continuous construction of combined beam
CN116537063A (en) Tower column system on ladle concrete and construction method
CN114232488B (en) Method for erecting main girder of large-span cable-stayed bridge
CN115492372A (en) Cast-in-place area of assembled superimposed sheet hangs mould construction equipment
KR101730764B1 (en) Construction method of curved girder using balancing lift tool
CN211897881U (en) No. 0 block bracket
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN210395127U (en) Assembled Bailey beam hanging basket upper walking system
CN209722761U (en) A kind of steel truss girder bridge scene suspension and slipping assembly device
CN110080121B (en) Hanging basket uplink system and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant