CN210624013U CN201921717195.6U CN201921717195U CN210624013U CN 210624013 U CN210624013 U CN 210624013U CN 201921717195 U CN201921717195 U CN 201921717195U CN 210624013 U CN210624013 U CN 210624013U
Authority
CN
China
Prior art keywords
articulated
hinge
frame
pipe
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921717195.6U
Other languages
Chinese (zh)
Inventor
罗便昌
贺冲
林艳杰
马强
时晓君
高纯
张灿灿
朱宗强
仲园园
仵允章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yankuang Xinlu Construction Development Co ltd
Original Assignee
Yankuang Xinlu Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yankuang Xinlu Construction Development Co ltd filed Critical Yankuang Xinlu Construction Development Co ltd
Priority to CN201921717195.6U priority Critical patent/CN210624013U/en
Application granted granted Critical
Publication of CN210624013U publication Critical patent/CN210624013U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to a freeze pipe inclinometer mounting bracket, including the collet of cover at the sleeve pipe outside freezing pipe and theodolite, fastener one can fix the sleeve pipe on the freezing pipe, and the sleeve pipe is articulated with first articulated frame, and fastener two can be with sleeve pipe and first articulated frame articulated fixed, and the collet is fixed in the articulated frame one end of second, and first articulated frame and the articulated frame of second are articulated each other, and two articulated frame length direction removal can be followed to the articulated shaft, and fastener three can be with two articulated frame articulated fixed. The utility model has the following obvious advantages: the horizontal angle inclinometry is adjustable, and the inclinometry space increase saves the deviational survey time greatly, and is light practical.

Description

Frozen pipe inclinometer mounting rack
Technical Field
The invention relates to a freezing construction technology, in particular to an installation support of an inclinometer.
Background
The subway communication channel construction is reinforced by adopting a freezing method, and because the drilling construction is a nearly horizontal hole, the inclination measurement detection must be carried out after the hole is formed by freezing, so that the hole forming quality is ensured. Adopt traditional theodolite support though can satisfy the construction requirement, but traditional support is heavier, and is inconvenient to carry, receives the tunnel space restriction, faces the problem that the theodolite erects the difficulty, causes measured data's deviation great.
Disclosure of Invention
The invention aims to provide a frozen pipe inclinometer mounting frame aiming at the defects of the prior art.
The purpose of the invention is realized by the following technical means:
including the collet of the sleeve pipe of cover outside freezing pipe and theodolite, fastener one can fix the sleeve pipe on freezing pipe, and the sleeve pipe is articulated with first articulated frame, and fastener two can be articulated fixedly with sleeve pipe and first articulated frame, and the collet is fixed in second articulated frame one end, and first articulated frame and second articulated frame are articulated each other, and two articulated frame length direction removal can be followed to the articulated shaft, and fastener three can be articulated fixedly with two articulated frames.
Preferably, the fastening member is a pair of fastening screws disposed oppositely, the side wall of the sleeve has a first threaded hole opposite, and the fastening screws are disposed in the first threaded hole.
Preferably, the first hinge frame is composed of two first hinge rods, the fastener is a pair of hinge screws which are arranged oppositely, the side wall of the sleeve is provided with opposite second threaded holes, the hinge screws penetrate through holes at one end of the first hinge rods and are arranged in the second threaded holes, and the circumferential difference between the first threaded holes and the adjacent second threaded holes is ninety degrees.
Preferably, the second hinge frame is composed of two second hinge rods, the third fastener is two bolts, the bolts are used as the hinge shafts of the first hinge frame and the second hinge frame, sliding grooves in the length direction are formed in the middles of the first hinge rods and the second hinge rods, and the bolts are arranged in the sliding grooves of the adjacent first hinge rods and the second hinge rods respectively.
Compared with the prior art, the invention has the following obvious advantages: the horizontal angle inclinometry is adjustable, and the inclinometry space increase saves the deviational survey time greatly, and is light practical.
Drawings
FIG. 1 is a front view of the present invention; FIG. 2 is a top view of the present invention; fig. 3 is a left side view of the cannula.
Detailed Description
The invention will be described in further detail with reference to the following description and specific embodiments, taken in conjunction with the accompanying drawings, in which: in the figure: the sleeve pipe of 1, 101 fastening screw, 2 first articulated rods, 201 spout, 3 second articulated rods, 301 spouts, 4 collet, 5 layer boards, 6 articulated screws, 7 bolts.
The freezing pipe inclinometer mounting frame comprises a sleeve 1 sleeved outside a freezing pipe and a bottom support 4 of a theodolite, wherein two pairs of opposite threaded holes are formed in the side face of the sleeve 1, the threaded holes are matched with flat-head screws, an upper pair of screws and a lower pair of screws are fastening screws 101, a pair of screws on two sides are hinge screws 6, the hinge screws 6 are used for being hinged with a first hinge frame, the first hinge frame is composed of an upper hinge rod and a lower hinge rod 2, a sliding groove 201 along the length direction is formed in the middle of the first hinge rod 2, a hinge hole is formed in one end of the first hinge rod, the fastening screws 101 penetrate through the hinge holes, the bottom support 4 is fixed on a support plate 5, the support plate 5 is fixed at the right end of a second hinge frame, the second hinge frame is composed of an upper hinge rod and a lower hinge rod 3, namely, the support plate 5 is fixed at the right end of the second hinge rod 3, a sliding groove 301 along the length direction, 301, and the lower first and second hinge levers 2, 3 are connected by the bolts 7 in the lower chutes 201, 301.
During the use, fix sleeve pipe 1 in freezing pipe orifice department, it is firm to tighten fastening screw 101, and the adjustment first articulated frame is convenient for deviational survey with second articulated frame angle, and two articulated frames realize reciprocating around, survey the positive and negative angle of horizontal freezing hole, tighten hinge screw 6, tighten two bolts 7 again to lock two articulated frames, put the theodolite on collet 4 and fix, measure again.

Claims (5)

1. Freezing pipe inclinometer mounting bracket, including the cover at the sleeve pipe outside freezing pipe and the collet of theodolite, fastener one can with the sleeve pipe is fixed on the freezing pipe, characterized by: the sleeve pipe is articulated with first articulated frame, fastener two can with the sleeve pipe with first articulated frame is articulated fixed, and the collet is fixed in second articulated frame one end, first articulated frame with second articulated frame is articulated each other, and the articulated shaft can be followed two articulated frame length direction and removed, and fastener three can be with two articulated frame is articulated fixed.
2. The frozen pipe inclinometer mounting rack as claimed in claim 1, wherein: the fastening piece is a pair of fastening screws which are oppositely arranged, the side wall of the sleeve is provided with a first threaded hole which is opposite, and the fastening screws are arranged in the first threaded hole.
3. The frozen pipe inclinometer mounting rack as claimed in claim 2, wherein: the first hinge frame is composed of two first hinge rods, the fastener is a pair of hinge screws which are arranged oppositely, the side wall of the sleeve is provided with opposite second threaded holes, and the hinge screws penetrate through holes in one ends of the first hinge rods and are arranged in the second threaded holes.
4. The frozen pipe inclinometer mounting rack as claimed in claim 3, wherein: the first threaded hole is circumferentially different from the adjacent second threaded hole by ninety degrees.
5. The frozen pipe inclinometer mounting rack as claimed in claim 2, wherein: the second hinge frame comprises two second hinge bars, the fastener third is two bolts, the bolt doubles first hinge frame and the articulated shaft of second, be equipped with the spout along length direction in the middle of first hinge bar and the second hinge bar, the bolt sets up respectively in the spout of adjacent first hinge bar and second hinge bar.
CN201921717195.6U 2019-10-14 2019-10-14 Frozen pipe inclinometer mounting rack Expired - Fee Related CN210624013U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921717195.6U CN210624013U (en) 2019-10-14 2019-10-14 Frozen pipe inclinometer mounting rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921717195.6U CN210624013U (en) 2019-10-14 2019-10-14 Frozen pipe inclinometer mounting rack

Publications (1)

Publication Number Publication Date
CN210624013U true CN210624013U (en) 2020-05-26

Family

ID=70761523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921717195.6U Expired - Fee Related CN210624013U (en) 2019-10-14 2019-10-14 Frozen pipe inclinometer mounting rack

Country Status (1)

Country Link
CN (1) CN210624013U (en)

Similar Documents

Publication Publication Date Title
CN111238862B (en) Soil sampling and measuring device for engineering supervision
FI89097B (en) MATNINGSBOMANORDNING VID BERGSBORR
CN210662162U (en) Geological drilling direction and angle measuring instrument
CN208223851U (en) A kind of geotechnical engineering ground sampler
CN210624013U (en) Frozen pipe inclinometer mounting rack
CN107688031A (en) A kind of glass appearance detects auxiliary mould
CN209706777U (en) geological disaster deep displacement monitoring device
CN219223563U (en) Hydraulic ring geological fracture measuring device
CN201876202U (en) Blasthole positioning and guiding device
CN214955344U (en) Vehicle identification and speed measurement system based on binocular vision
CN211421661U (en) Novel anti-drop zinc steel railing connecting piece
CN203684860U (en) Telescopic wind brace
CN210833522U (en) Sopwith staff mount is used in survey and drawing
CN103963921A (en) Two-wing fan-shaped adjustable sample plate
CN209400718U (en) A kind of improved portable advance geologic prediction instrument workbench
CN207703892U (en) Flat radar current meter
CN207214936U (en) A kind of petroleum geology project quality inspection survey tool
CN208621087U (en) The dedicated pump impulse sensor fastening device of petroleum
CN213018418U (en) Adjustable support for engineering measurement
CN210893359U (en) Refrigerant steel cylinder weighing machine
CN220893827U (en) Coring machine for building concrete detection
CN220869320U (en) Drill bit for engineering geological drilling
CN218847222U (en) Subway ring net measuring stand
CN212201904U (en) Reamer for geological exploration
CN209574992U (en) A kind of adjustable fixed frame of forearm fracture

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant