CN208899521U - A kind of peg board formula concrete retaining wall of Anti-inclining - Google Patents

A kind of peg board formula concrete retaining wall of Anti-inclining Download PDF

Info

Publication number
CN208899521U
CN208899521U CN201821394338.XU CN201821394338U CN208899521U CN 208899521 U CN208899521 U CN 208899521U CN 201821394338 U CN201821394338 U CN 201821394338U CN 208899521 U CN208899521 U CN 208899521U
Authority
CN
China
Prior art keywords
concrete
retaining wall
peg board
inclining
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821394338.XU
Other languages
Chinese (zh)
Inventor
***
周玉青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Polytechnic Institute
Original Assignee
Nanjing Polytechnic Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Polytechnic Institute filed Critical Nanjing Polytechnic Institute
Priority to CN201821394338.XU priority Critical patent/CN208899521U/en
Application granted granted Critical
Publication of CN208899521U publication Critical patent/CN208899521U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model proposes a kind of peg board formula concrete retaining walls of Anti-inclining, including several manually digging hole filling piles and the concrete column being arranged in above manually digging hole filling pile, concrete breast boards is provided between the concrete column, it is provided with the concrete collar tie beam an of formed by integrally casting between the top of several concrete columns, the concrete breast beam of a formed by integrally casting is provided between the bottom of the concrete column.The concrete collar tie beam and concrete breast beam that the utility model passes through the setting formed by integrally casting between the concrete column of retaining wall, whole concrete columns are connected to become an entirety, so that the uniform force of entire retaining wall, it can withstand forces and be greatly enhanced, the concrete column run-off the straight under by the active force on gear hillside of peg board formula concrete retaining wall can be effectively prevent.In manually digging hole filling pile far from extrusion grouting layer is arranged by gear hillside side, the anchorage effect on stratum is increased.

Description

A kind of peg board formula concrete retaining wall of Anti-inclining
Technical field
The utility model relates to Environmental Geotechnical fields, are specifically related to a kind of retaining wall.
Background technique
Retaining wall refers to bearing Roadbed Soil or the hillside soil body, prevents from banketing or the structure of soil deformation unstability, commonly uses In the middle-size and small-size landslide of improvement.Frequently with the reinforced concrete retaining wall of peg board formula structure, manually digging hole perfusion when building retaining wall The mode of stake does the column of retaining wall, is made of breast boards two parts between column and stake, Rock And Soil active force passes through breast boards Pile body is passed to, top Rock And Soil active force is transferred to good ground, utilizes the anchorage effect and passive resisting force of good ground To guarantee Rock And Soil overall stability.It since groundwater occurrence is uneven under soil layer, excavates and arrives certain depth, some stake positions occur Underground ponding draws water for high water level condition when digging, can wash in a pan away Pile side soil fine grained, cause land subsidence, lead to retaining wall Entirety falls off, and causes casualties.The particle water for the concrete that adjacent studs are newly perfused can also be taken away, cause to isolate.It is flowing Property mud in borehole, cause a large amount of mud and lateral flows occur, cause soil body slipping that pile body is extrapolated and even infer.Retaining wall is built After under the effect of retaining wall behind backfill pile body also easy run-off the straight unstability, cause security risk.
Utility model content
The technical issues of solution: the utility model proposes a kind of peg board formula concrete retaining walls of Anti-inclining, can withstand forces It is greatly enhanced, the anchorage effect on stratum is strong, and peg board formula concrete retaining wall can be effectively prevent by the active force on gear hillside Lower concrete column run-off the straight.
Technical solution: the utility model proposes a kind of peg board formula concrete retaining walls of Anti-inclining, including several excavated by manual work Hole pouring pile and the concrete column being arranged in above manually digging hole filling pile are provided with concrete between the concrete column Breast boards is provided with the concrete collar tie beam an of formed by integrally casting, the concrete between the top of several concrete columns The concrete breast beam of a formed by integrally casting is provided between the bottom of column.
Further, the peg board formula concrete retaining wall of the Anti-inclining further includes being arranged in manually digging hole filling pile far from quilt Keep off the extrusion grouting layer of hillside side.
Further, the concrete breast boards is arc concrete breast boards.
Further, the spacing of the manually digging hole filling pile is 4 meters.
Further, the height of the concrete column is 10-20 meters.
The utility model has the advantages that coagulation pedosphere of the utility model by the setting formed by integrally casting between the concrete column of retaining wall Whole concrete columns are connected to become an entirety by beam and concrete breast beam, so that the uniform force of entire retaining wall, can hold Stress is greatly enhanced, and peg board formula concrete retaining wall concrete column under by the active force on gear hillside can be effectively prevent to send out Raw inclination.In manually digging hole filling pile far from extrusion grouting layer is arranged by gear hillside side, the anchorage effect on stratum is increased.
Detailed description of the invention
Fig. 1 is the positive structure schematic of the utility model;
Fig. 2 is the side structure cross-sectional view of the utility model.
Specific embodiment
Such as Fig. 1 and Fig. 2, an embodiment of the present invention, including several manually digging hole filling piles 1 and setting are artificial The concrete column 2 of the top of digging hole filling pile 1 is provided with concrete breast boards 3 between the concrete column 2.The hillside soil body Active force concrete column 2 is passed to by concrete breast boards 3, concrete column 2 using manually digging hole filling pile 1 ground Layer anchorage effect guarantees the stability of the hillside soil body.For the run-off the straight under the action of soil body of hillside after preventing retaining wall from building up, The concrete collar tie beam 4 of one formed by integrally casting, the bottom of the concrete column 2 are set between the top of several concrete columns 2 The concrete breast beam 5 of a formed by integrally casting is provided between portion, concrete collar tie beam 4 and concrete breast beam 5 found whole concrete Column 2 is connected to become an entirety, so that the uniform force of entire retaining wall, can withstand forces and be greatly enhanced, can effectively prevent The concrete column run-off the straight under by the active force on gear hillside of peg board formula concrete retaining wall.
Underground water easily causes soil body flow after manually digging hole, and the moisture content of soil layer is uneven, leads to manually digging hole filling pile 1 Unstability, therefore the present embodiment also manually digging hole filling pile 1 far from by gear hillside side to the non-uniform soil layer of moisture content Extrusion grouting processing is carried out, extrusion grouting layer 6 is formed, increases the anchorage effect on stratum.
The concrete breast boards 3 of the present embodiment is high-intensitive arc concrete breast boards.
The spacing of the manually digging hole filling pile 1 of the present embodiment is preferably 4 meters, and the highly preferred of concrete column 2 is 10-20 Rice.

Claims (5)

1. a kind of peg board formula concrete retaining wall of Anti-inclining, including several manually digging hole filling piles (1) and setting are in excavated by manual work Concrete column (2) above hole pouring pile (1) is provided with concrete breast boards (3) between the concrete column (2), It is characterized in that: being provided with the concrete collar tie beam (4) an of formed by integrally casting between the top of the concrete column (2), it is described mixed The concrete breast beam (5) of a formed by integrally casting is provided between the bottom of solidifying soil column (2).
2. the peg board formula concrete retaining wall of Anti-inclining according to claim 1, it is characterised in that: the stake of the Anti-inclining Board-like concrete retaining wall further includes setting in manually digging hole filling pile (1) the separate extrusion grouting layer (6) by gear hillside side.
3. the peg board formula concrete retaining wall of Anti-inclining according to claim 1 or 2, it is characterised in that: the concrete Breast boards (3) is arc concrete breast boards.
4. the peg board formula concrete retaining wall of Anti-inclining according to claim 3, it is characterised in that: the manually digging hole fills The spacing for infusing stake (1) is 4 meters.
5. the peg board formula concrete retaining wall of Anti-inclining according to claim 4, it is characterised in that: the concrete column (2) height is 10-20 meters.
CN201821394338.XU 2018-08-28 2018-08-28 A kind of peg board formula concrete retaining wall of Anti-inclining Active CN208899521U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821394338.XU CN208899521U (en) 2018-08-28 2018-08-28 A kind of peg board formula concrete retaining wall of Anti-inclining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821394338.XU CN208899521U (en) 2018-08-28 2018-08-28 A kind of peg board formula concrete retaining wall of Anti-inclining

Publications (1)

Publication Number Publication Date
CN208899521U true CN208899521U (en) 2019-05-24

Family

ID=66570575

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821394338.XU Active CN208899521U (en) 2018-08-28 2018-08-28 A kind of peg board formula concrete retaining wall of Anti-inclining

Country Status (1)

Country Link
CN (1) CN208899521U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755749A (en) * 2018-08-28 2018-11-06 南京科技职业学院 A kind of the peg board formula concrete retaining wall and its method of construction of Anti-inclining
CN113818481A (en) * 2021-11-08 2021-12-21 中国航天建设集团有限公司 Pile plate type retaining wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755749A (en) * 2018-08-28 2018-11-06 南京科技职业学院 A kind of the peg board formula concrete retaining wall and its method of construction of Anti-inclining
CN113818481A (en) * 2021-11-08 2021-12-21 中国航天建设集团有限公司 Pile plate type retaining wall

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN101591904B (en) Method for strengthening composite pile foundation by prepressing drainage and following grouting for drainage body
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106759390B (en) A kind of rubble-non-uniform pile composite construction and its construction method with draining and AsA -GSH cycle
CN110847197B (en) Comprehensive treatment method for loess tunnel entrance section crossing landslide body
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN104612143A (en) Bored composite pile structure under karst cave/soil cave geological condition
CN203174619U (en) Reverse raft concrete terrace
CN207672558U (en) A kind of railroad embankment Pile slab-wall structure
CN106337413A (en) Water-draining stiff geo-textile bag cement-soil composite pile and construction method thereof
CN208899521U (en) A kind of peg board formula concrete retaining wall of Anti-inclining
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation
CN209456912U (en) A kind of abrupt slope rockfall is blocked structure
CN109183809A (en) A kind of construction method of Muddy Bottoms clay deep-foundation pit engineering composite support support replacement
CN105178285A (en) Method for widening grouting reinforcement and seepage and blockage prevention range of rock and soil
CN103806433A (en) Foundation backfill reinforcement method
CN203284786U (en) Side slope anti-slide and pre-warning system with underground water collection and utilization function
CN107841908A (en) For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope
CN105525605A (en) Basement backfill area reinforcing method
CN207646754U (en) A kind of pile body penetration type bankets body reinforcement bearing structure
CN203284795U (en) Buttressed retaining wall with anchor board
KR101924383B1 (en) A Environment-Friendly construction method of drainage channel on softground by Grouting and Mixing of Solidifying Agent
CN107700528A (en) A kind of pile body penetration type bankets body reinforcement bearing structure and construction method
CN107630706A (en) A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance
CN105926646A (en) Reinforcing method for swelling rock cut slope

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant