CN208578306U - A kind of constructing tunnel scaffold - Google Patents

A kind of constructing tunnel scaffold Download PDF

Info

Publication number
CN208578306U
CN208578306U CN201820771578.0U CN201820771578U CN208578306U CN 208578306 U CN208578306 U CN 208578306U CN 201820771578 U CN201820771578 U CN 201820771578U CN 208578306 U CN208578306 U CN 208578306U
Authority
CN
China
Prior art keywords
bottom plate
constructing tunnel
welded
fixed
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820771578.0U
Other languages
Chinese (zh)
Inventor
张立霞
韩闯
许海涛
张立范
刘洋洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changchun urban construction and maintenance Group Co., Ltd.
Original Assignee
Changchun Urban Construction Maintenance Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changchun Urban Construction Maintenance Ltd By Share Ltd filed Critical Changchun Urban Construction Maintenance Ltd By Share Ltd
Priority to CN201820771578.0U priority Critical patent/CN208578306U/en
Application granted granted Critical
Publication of CN208578306U publication Critical patent/CN208578306U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of constructing tunnel scaffold, including bottom plate;The rotating bolt is equipped with nut through the upper wall for connecting connecting box and in junction, and its underpart is socketed with wheel lift connection plate by threaded engagement rotation;The right part of the wheel lift connection plate offers threaded hole, and left part offers cavity in junction through connection connecting box, and right part lower end is welded with universal wheel;The fixed column is equipped with two groups every group three, is symmetrically distributed in the upper end of bottom plate, is fixedly installed with hydraulic cylinder on the right side of upper part;There are two the support rod settings, and lower end is weldingly fixed in fixed column;Be fixedly attached limited block in the middle part of the threaded rod, limited block two sides screw thread it is oppositely oriented, and the both ends of limited block by threaded engagement rotation be socketed with thread slider;The problems such as the utility model structure is simple, and scaffold installation is inconvenient for operation when solving constructing tunnel, is worth of widely use.

Description

A kind of constructing tunnel scaffold
Technical field
The utility model relates to constructing tunnel equipment, specifically a kind of constructing tunnel scaffold.
Background technique
Scaffold refer to construction site be worker operation and solving vertically and horizontally transport and the various brackets set up.Architecture field Generic term, refer on construction site be used in exterior wall, interior decoration or the higher place that can not directly construct of layer height.Mainly for Construction personnel works up and down or perimeter security net is gone along with sb. to guard him and high-altitude installation component etc., is plainly exactly to build a framework, scaffold production Material usually has: bamboo and wood, steel pipe or synthetic material etc..
Some engineerings are also with scaffold when template uses, furthermore in departments such as advertising, municipal administration, traffic road bridge, mines It is used extensively, constructing tunnel, is the abbreviation of new Austrian method for tunnel construction, it is Austrian scholar in long campaigns tunnel In Construction practices, a kind of reasonable construction method proposed from the viewpoint of rock mechanics is using spray anchor technology, monitoring It measures etc. and the new engineering construction method of one kind formed with a system that rock mechanics theory is constituted.A kind of constructing tunnel Constructing tunnel is greatly facilitated with the appearance of scaffold, but there are many shortcomings for the scaffold of current stage, for example, Fixed stability is poor, and security protection performance is poor, inconvenient to use.
Utility model content
The purpose of this utility model is to provide a kind of constructing tunnel scaffolds, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the utility model provides the following technical solutions:
A kind of constructing tunnel scaffold, including bottom plate;The upper end of the bottom plate is provided with connecting box;The connecting box is set It sets there are four the four corners for being symmetrically distributed in bottom plate upper end, is internally connected with rotating bolt;The rotating bolt is through connection The upper wall of connecting box and nut is installed in junction, its underpart is socketed with wheel lift connection plate by threaded engagement rotation; The right part of the wheel lift connection plate offers threaded hole, and left part is opened up in junction free through connection connecting box Chamber, right part lower end are welded with universal wheel;There are four the four corners for being mounted on bottom plate for the universal wheel setting;Bottom plate it is upper The end left and right sides is welded with fixed column;The fixed column is equipped with two groups every group three, is symmetrically distributed in the upper end of bottom plate, Upper right is fixedly installed with hydraulic cylinder;The lower end of the hydraulic cylinder is welded with support rod;The support rod is provided with two A, lower end is weldingly fixed in fixed column;The upper end of fixed column is welded with elevator chamber;The left end outer wall of the elevator chamber On be welded with loading plate;The upper end of the loading plate, which is bolted, is fixedly installed with lifting motor;The lifting electricity The right end of machine is welded with threaded rod;It is fixedly attached limited block in the middle part of the threaded rod, in the two sides of limited block Screw thread it is oppositely oriented, and the both ends of limited block by threaded engagement rotation be socketed with thread slider;The thread slider If being bolted be rotatably equipped with elevating lever thereon there are two the two sides for being symmetrically mounted on threaded rod;The elevating lever Middle part is fixedly linked by coupling bar rotation, and the upper end, which is bolted, to be rotatably installed on link block, and its underpart is run through Elevator chamber is connected, and offers cavity in junction.
As a further solution of the present invention: the lower end of the bottom plate is provided with supporting leg;The supporting leg setting There are four the four corners for being uniformly weldingly fixed on bottom plate lower end, and lower end is fixedly installed with rubber pad.
As a further solution of the present invention: there are two the left and right two for being symmetrically mounted on bottom plate for the hydraulic cylinder setting Side, the internal movement in right side are equipped with hydraulic stem.
As a further solution of the present invention: the right end of the hydraulic stem is fixedly welded with telescopic rod;It is described flexible The right end of bar is fixedly installed with fixed disk;The right end of the fixed disk is fixedly installed with rubber pad.
As a further solution of the present invention: the left part rotation of the threaded rod runs through connection elevator chamber, and even The place of connecing is equipped with connection bearing, and its right end is held in the right wall for being rotatably installed in elevator chamber also by connecting shaft;Connect bearing edge It is embedding to be mounted in the inner wall of elevator chamber.
As a further solution of the present invention: the upper end of the workbench is provided with connecting column, and its mounting height It is arranged at one meter one or so;The connecting column is provided with two groups every group three front and rear sides for being symmetrically distributed in workbench upper end, The upper end is welded with protective fence;There are two the protective fence settings, is symmetrically distributed in the front and rear sides of workbench upper end.
As a further solution of the present invention: the upper end is weldingly fixed on workbench there are two the link block sets Lower end at left and right sides of;The left and right ends of the workbench are welded with connecting plate.
As a further solution of the present invention: the lower end of the connecting plate is welded with roller mounting plate;It is described Roller mounting plate is equipped with two groups every group two its lower end interference and is socketed with connecting rod;Rotation is socketed with rolling in the connecting rod Wheel.
The scroll wheel sets that there are two be symmetrically distributed in the left and right of workbench as a further solution of the present invention, Both ends are wound with drawstring thereon;The left side lower end of the drawstring is fastened on haul basket, and right side lower end bolt is in drawstring fixed handle On;The right end of the drawstring fixed handle is weldingly fixed on the left upper portion of elevator chamber.
Compared with prior art, the utility model has the beneficial effects that
The utility model is fixedly installed with rubber pad in the lower end of supporting leg, play fixed supporting role, and compound rubber pad Use, prevent scaffold in constructing tunnel in use, because ground water and soil miriness due to slide, security risk is caused to construction personnel, And fixed disk is installed at the both ends of fixed column, it is used cooperatively with right end rubber pad, scaffold fixation is prevented into operator It causes danger during the work time because scaffold shakes, elevating lever is installed in the lower end of workbench, it can will be on operator It moves on to specified position to use, and is mounted with protective fence on the table, protect the safety of operator, set at the both ends of workbench Set haul frame, inside be placed with the articles such as construction equipment, moved up by drawstring, solve operator in high altitude operation When shipping supply the problem of, and the apparatus structure is simple, easy to operate, scaffold installation operation not side when solving constructing tunnel Just the problems such as, is worth of widely use.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of constructing tunnel scaffold.
Fig. 2 is a kind of structural schematic diagram of side view in constructing tunnel scaffold.
Fig. 3 is a kind of structural schematic diagram of top view in constructing tunnel scaffold.
Fig. 4 is the structural schematic diagram of A-A in constructing tunnel scaffold a kind of.
In figure: 1- supporting leg, 2- universal wheel, 3- wheel lift connection plate, 4- support rod, 5- loading plate, 6- lifting motor, 7- threaded rod, 8- connection bearing, 9- haul basket, 10- scroll wheel, 11- drawstring, 12- connecting plate, 13- link block, 14- protective fence, 15- connecting column, 16- coupling bar, 17- elevating lever, 18- roller mounting plate, 19- connecting rod, 20- elevator chamber, 21- drawstring are fixed Handle, 22- limited block, 23- thread slider, 24- hydraulic cylinder, 25- fixed disk, 26- rubber pad, 27- telescopic rod, 28- hydraulic stem, 29- fixed column, 30- rotating bolt, 31- connecting box, 32- bottom plate, 33- workbench.
Specific embodiment
The technical solution of the patent is explained in further detail With reference to embodiment.
Please refer to Fig. 1-4, a kind of constructing tunnel scaffold, including bottom plate 32;The lower end of the bottom plate 32 is provided with branch Support leg 1 provides work and installation space for part connecting part thereon;There are four be uniformly welded and fixed for the setting of supporting leg 1 Four corners in 32 lower end of bottom plate, lower end are fixedly installed with rubber pad 26, play fixed supporting role, and compound rubber pad 26 makes With, prevent scaffold in constructing tunnel in use, because ground water and soil miriness due to slide, security risk is caused to construction personnel;Bottom The upper end of plate 32 is provided with connecting box 31;The connecting box 31 is arranged there are four the four corners for being symmetrically distributed in 32 upper end of bottom plate, It is internally connected with rotating bolt 30, provides working space for its internal rotatable parts;The rotating bolt 30 is through connection The upper wall of connecting box 31 and nut is installed in junction, its underpart is socketed with wheel lift connection plate by threaded engagement rotation 3, lower rotation is artificially being turned, so that its connecting component be driven to move up and down;The right part of the wheel lift connection plate 3 offers Threaded hole, left part offer cavity in junction through connection connecting box 31, and right part lower end is welded with universal wheel 2;There are four the four corners for being mounted on bottom plate 32 for the universal wheel 2 setting, under the drive of wheel lift connection plate 3 on move down It is dynamic, by artificially rotate rotating bolt 30 moved down with ground face contact, the mobile working of scaffold may be implemented, work as scaffold It is moved up when being moved to designated position, drags fixation work of the ground realization to scaffold away from;At left and right sides of the upper end of bottom plate 32 It is welded with fixed column 29;The fixed column 29 is equipped with two groups every group three, is symmetrically distributed in the upper end of bottom plate 32, upper part Right side is fixedly installed with hydraulic cylinder 24, plays fixed support the upper end connecting component;There are two the settings of hydraulic cylinder 24 It is symmetrically mounted on the left and right sides of bottom plate 32, the internal movement in right side is equipped with hydraulic stem 28;The right end of the hydraulic stem 28 is solid Surely it is welded with telescopic rod 27, is moved left and right under the drive of hydraulic cylinder 24 and drives its connecting component mobile;The telescopic rod 27 Right end is fixedly installed with fixed disk 25;The right end of the fixed disk 25 is fixedly installed with rubber pad 26, in the drive of telescopic rod 27 Under move to right, hydraulic cylinder 24 is closed when the two sides inner wall in itself and tunnel contacts, will by being used cooperatively with its right end rubber pad 26 Scaffold is fixed to prevent operator from causing danger during the work time because scaffold shakes;The lower end welding of hydraulic cylinder 24 is solid Surely there is support rod 4;There are two the settings of support rod 4, and lower end is weldingly fixed in fixed column 29, is played a supportive role;It is fixed The upper end of column 29 is welded with elevator chamber 20;It is welded with loading plate 5 on the left end outer wall of the elevator chamber 20, for lifting Component provides work and installation space;The upper end of the loading plate 5, which is bolted, is fixedly installed with lifting motor 6, support The weight of bearer connection component;The right end of the lifting motor 6 is welded with threaded rod 7, is the power resources of lifting part; The left part rotation of the threaded rod 7 is equipped with connection bearing 8 through connection elevator chamber 20, and in junction, and its right end also leads to It crosses connection bearing 8 to be rotatably installed in the right wall of elevator chamber 20, rotates under the drive of lifting motor 6, connect thereon to drive Relay part rotation;Connection bearing 8, which is inlayed, to be mounted in the inner wall of elevator chamber 20, and rotatable parts are connected;The middle part of threaded rod 7 is fixed Be socketed with limited block 22, limited block 22 two sides screw thread it is oppositely oriented, and pass through spiral shell at the both ends of limited block 22 Line occlusion rotation is socketed with thread slider 23;The thread slider 23 is set there are two the two sides of threaded rod 7 are symmetrically mounted on, thereon Be bolted and be rotatably equipped with elevating lever 17, under the drive of threaded rod 7 simultaneously inwardly or be displaced outwardly simultaneously;The liter The middle part of drop bar 17 is fixedly linked by the rotation of coupling bar 16, and the upper end, which is bolted, to be rotatably installed on link block 13, And connection elevator chamber 20 is run through in its underpart, and offers cavity in junction, when thread slider 23 moves inward, drives thereon It rises;There are two the link block 13 is set, the upper end is weldingly fixed at left and right sides of the lower end of workbench 33;The workbench 33 Upper end is provided with connecting column 15, works for operator station above, and its mounting height is arranged at one meter one or so, can allow behaviour It steps up as member, and is moved up under the drive of elevating lever 17, operator is transported to designated position;The connecting column 15 is provided with Two groups every group three are symmetrically distributed in the front and rear sides of 33 upper end of workbench, and the upper end is welded with protective fence 14;It is described anti- There are two the settings of guardrail 14, is symmetrically distributed in the front and rear sides of 33 upper end of workbench, plays protective action, protects the person of operator Safety;The left and right ends of workbench 33 are welded with connecting plate 12;The lower end of the connecting plate 12 is welded with idler wheel Mounting plate 18, is connected and fixed component;The roller mounting plate 18 is equipped with two groups every group two its lower end interference and is socketed with connecting rod 19;Rotation is socketed with scroll wheel 10 in the connecting rod 19;The scroll wheel 10 is symmetrically distributed in workbench 33 there are two setting Left and right ends are wound with drawstring 11 thereon;The left side lower end of the drawstring 11 is fastened on haul basket 9, and right side lower end bolt exists On drawstring fixed handle 21, drives haul basket 9 to move up and down under artificial pull, haul basket 9 is transported to upper end designated position;Fortune There are two charging basket 9 is set, inside be placed with the articles such as construction equipment, moved up by drawstring 11, solve operator in height When idle job the problem of shipping supply;The right end of the drawstring fixed handle 21 is weldingly fixed on the left upper portion of elevator chamber 20.
The working principle of the utility model is: device using when universal wheel 2 is moved down by artificially turning rotating bolt 30 To with ground face contact, and entire scaffold is propped up, pushes scaffold to be moved to job site, universal wheel 30 is moved up, Fix support leg 1 by device with ground face contact;Starting hydraulic cylinder 24 drives fixed disk 25 mobile to two sides at this time, when it is fixed When in tunnel-side, hydraulic cylinder 24 is closed;Operator is cross on workbench 33, starts lifting motor 6, in the band of elevating lever 17 Dynamic lower table 33 moves up, and designated position will be moved on on operator, closes motor;Protective fence 14 on workbench 33 can protect The personal safety of operator;When operator carries out high altitude operation, the personnel of lower end can be by pulling drawstring 11 by material and device Material is shipped for operator by haul basket 9, completes constructing tunnel work.
The preferred embodiment of the patent is described in detail above, but this patent is not limited to above-mentioned embodiment party Formula within the knowledge of one of ordinary skill in the art can also be under the premise of not departing from this patent objective It makes a variety of changes.

Claims (9)

1. a kind of constructing tunnel scaffold, including bottom plate (32);It is characterized in that, the upper end of the bottom plate (32) is provided with company Connect case (31);Connecting box (31) setting is internally connected with there are four the four corners for being symmetrically distributed in bottom plate (32) upper end Rotating bolt (30);The rotating bolt (30) through the upper wall for connecting connecting box (31) and is equipped with nut in junction, Lower part is socketed with wheel lift connection plate (3) by threaded engagement rotation;The right part of the wheel lift connection plate (3) offers Threaded hole, left part offer cavity in junction through connection connecting box (31), and right part lower end is welded with universal It takes turns (2);There are four the four corners for being mounted on bottom plate (32) for universal wheel (2) setting;Weldering at left and right sides of the upper end of bottom plate (32) It connects and is fixed with fixed column (29);The fixed column (29) is equipped with two groups every group three, is symmetrically distributed in the upper end of bottom plate (32), Upper right is fixedly installed with hydraulic cylinder (24);The lower end of the hydraulic cylinder (24) is welded with support rod (4);The support There are two bar (4) settings, and lower end is weldingly fixed on fixed column (29);The upper end of fixed column (29) is welded with elevator chamber (20);Loading plate (5) are welded on the left end outer wall of the elevator chamber (20);The upper end of the loading plate (5) passes through spiral shell It tethers to connect and is fixedly installed with lifting motor (6);The right end of the lifting motor (6) is welded with threaded rod (7);The screw thread Limited block (22) have been fixedly attached in the middle part of bar (7), limited block (22) two sides screw thread it is oppositely oriented, and limiting The both ends of block (22) are socketed with thread slider (23) by threaded engagement rotation;The thread slider (23) sets that there are two symmetrical The two sides of threaded rod (7) are mounted on, is bolted is rotatably equipped with elevating lever (17) thereon;In the elevating lever (17) Portion is fixedly linked by coupling bar (16) rotation, and the upper end, which is bolted, to be rotatably installed on link block (13), and under it Portion offers cavity in junction through connection elevator chamber (20).
2. a kind of constructing tunnel scaffold according to claim 1, which is characterized in that the lower end of the bottom plate (32) is set It is equipped with supporting leg (1);The uniform four corners for being weldingly fixed on bottom plate (32) lower end that there are four supporting leg (1) settings, Lower end is fixedly installed with rubber pad (26).
3. a kind of constructing tunnel scaffold according to claim 1, which is characterized in that the hydraulic cylinder (24) is provided with Two are symmetrically mounted on the left and right sides of bottom plate (32), and the internal movement in right side is equipped with hydraulic stem (28).
4. a kind of constructing tunnel scaffold according to claim 3, which is characterized in that the right end of the hydraulic stem (28) It is fixedly welded with telescopic rod (27);The right end of the telescopic rod (27) is fixedly installed with fixed disk (25);The fixed disk (25) Right end be fixedly installed with rubber pad (26).
5. a kind of constructing tunnel scaffold according to claim 1, which is characterized in that the left part of the threaded rod (7) Rotation is equipped with connection bearing (8) through connection elevator chamber (20), and in junction, and its right end is also by connection bearing (8) It is rotatably installed in the right wall of elevator chamber (20);Connection bearing (8), which is inlayed, to be mounted in the inner wall of elevator chamber (20).
6. a kind of constructing tunnel scaffold according to claim 1, which is characterized in that the upper end of the workbench (33) It is provided with connecting column (15), and its mounting height is arranged at one meter one;The connecting column (15) be provided with two groups every group three it is right Claim the front and rear sides for being distributed in workbench (33) upper end, the upper end is welded with protective fence (14);The protective fence (14) sets There are two setting, it is symmetrically distributed in the front and rear sides of workbench (33) upper end.
7. a kind of constructing tunnel scaffold according to claim 1, which is characterized in that the link block (13) is equipped with two A, the upper end is weldingly fixed at left and right sides of the lower end of workbench (33);Weld solid in the left and right ends of the workbench (33) Surely there are connecting plate (12).
8. a kind of constructing tunnel scaffold according to claim 7, which is characterized in that the lower end of the connecting plate (12) It is welded with roller mounting plate (18);The roller mounting plate (18) is equipped with two groups every group two its lower end interference and is socketed with company Extension bar (19);Rotation is socketed with scroll wheel (10) on the connecting rod (19).
9. a kind of constructing tunnel scaffold according to claim 8, which is characterized in that the scroll wheel (10) is equipped with two A left and right ends for being symmetrically distributed in workbench (33) are wound with drawstring (11) thereon;It fastens the left side lower end of the drawstring (11) On haul basket (9), right side lower end bolt is on drawstring fixed handle (21);The right end welding of the drawstring fixed handle (21) is solid It is scheduled on the left upper portion of elevator chamber (20).
CN201820771578.0U 2018-05-23 2018-05-23 A kind of constructing tunnel scaffold Active CN208578306U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820771578.0U CN208578306U (en) 2018-05-23 2018-05-23 A kind of constructing tunnel scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820771578.0U CN208578306U (en) 2018-05-23 2018-05-23 A kind of constructing tunnel scaffold

Publications (1)

Publication Number Publication Date
CN208578306U true CN208578306U (en) 2019-03-05

Family

ID=65506244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820771578.0U Active CN208578306U (en) 2018-05-23 2018-05-23 A kind of constructing tunnel scaffold

Country Status (1)

Country Link
CN (1) CN208578306U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111321670A (en) * 2020-03-14 2020-06-23 山西省交通规划勘察设计院有限公司 Movable protective device for bridge engineering construction
CN111720146A (en) * 2020-06-12 2020-09-29 甘肃路桥建设集团有限公司 Many sectional shapes form bow member manipulator
CN113579013A (en) * 2021-07-07 2021-11-02 安徽省伊锡尔重工科技有限公司 Continuous bending machine for right-angle bending of metal plate

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111321670A (en) * 2020-03-14 2020-06-23 山西省交通规划勘察设计院有限公司 Movable protective device for bridge engineering construction
CN111720146A (en) * 2020-06-12 2020-09-29 甘肃路桥建设集团有限公司 Many sectional shapes form bow member manipulator
CN111720146B (en) * 2020-06-12 2022-05-31 甘肃路桥建设集团有限公司 Many sectional shapes form bow member manipulator
CN113579013A (en) * 2021-07-07 2021-11-02 安徽省伊锡尔重工科技有限公司 Continuous bending machine for right-angle bending of metal plate

Similar Documents

Publication Publication Date Title
CN208578306U (en) A kind of constructing tunnel scaffold
CN210482956U (en) Intelligent attached lifting construction platform
CN110424270B (en) Anti-falling device for urban bridge construction
CN213204900U (en) Lifting device for be used for fitment
CN111998182B (en) Platform for environment management
CN205933125U (en) Portable flexible crane that falls of preventing
CN209891409U (en) Modular fire station with alarm monitoring device
CN201099575Y (en) Hanging basket rotatable material lifting equipment
CN111851973A (en) Intelligent attached lifting construction platform
CN214531134U (en) Fast-assembling steel structure for building
CN213171212U (en) A hoisting apparatus for building engineering
CN212295587U (en) Horizontal annular welding construction platform for bin
CN209670301U (en) A kind of scaffold with stress monitoring protection
CN206707248U (en) A kind of hanging basket for overflow weir
CN220224941U (en) Platform for road bridge tunnel construction
CN206091254U (en) Whole construction scaffold frame of track formula of climbing
CN219158336U (en) Building construction frame
CN219909860U (en) Guard bar scaffold
CN110965844A (en) Novel underground extraction type warning fence
CN219887628U (en) Detachable protective structure for elevator shaft mouth
CN219011888U (en) Lifting platform for building construction
CN214885319U (en) Vertical greening steel structure house building construction device
CN108240100A (en) A kind of annexable legerity type scaffold of working at height for building
CN220485274U (en) Anti-falling climbing device
CN215447998U (en) Building energy conservation monitoring devices

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 688, Wanfu street, Changchun, Jilin Province, Jilin

Patentee after: Changchun urban construction and maintenance Group Co., Ltd.

Address before: Luyuan District in Jilin province Changchun Wanfu Street 130000 No. 688

Patentee before: Changchun urban construction maintenance Limited by Share Ltd