CN207914881U CN201820293193.8U CN201820293193U CN207914881U CN 207914881 U CN207914881 U CN 207914881U CN 201820293193 U CN201820293193 U CN 201820293193U CN 207914881 U CN207914881 U CN 207914881U
Authority
CN
China
Prior art keywords
strut
fixing piece
tapped
transverse steel
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820293193.8U
Other languages
Chinese (zh)
Inventor
黄春水
沙凯
张森
陈丽芳
张占锋
曹启才
张�杰
王峰
闫晓华
郭继强
张亚东
钱春花
邓维辉
牛奇才
王方涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuchang University
Henan Highway Engineering Group Co Ltd
Original Assignee
Xuchang University
Henan Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuchang University, Henan Highway Engineering Group Co Ltd filed Critical Xuchang University
Priority to CN201820293193.8U priority Critical patent/CN207914881U/en
Application granted granted Critical
Publication of CN207914881U publication Critical patent/CN207914881U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of tunnel reinforced mesh processing frame, belongs to construction engineering technical field, including pedestal, vertical the first strut and the second strut being fixed on pedestal;The susceptor surface is horizontally opened with sliding slot, several vertical reinforcement fixing pieces are connected with by the sliding block slide fit to match on the sliding slot, and the vertical reinforcement fixing piece includes fixed cylinder, and the side wall of the fixed cylinder has fastening bolt by screw hole;First strut can be along the transverse steel fixing piece that the first strut moves up and down equipped with several, the transverse steel fixing piece includes the first sleeve being socketed on the first strut, fastening bolt is equipped with by threaded hole on the outer wall of the first sleeve, the arc groove for placing transverse steel is also connected with by connecting rod on the outer wall of the first sleeve, second strut has structure identical with the first strut.Transverse steel and vertical reinforcement can be fixed in the utility model, and can be used to process the reinforced mesh of different size.

Description

A kind of tunnel reinforced mesh processing frame
Technical field
The utility model belongs to construction engineering technical field, and in particular to a kind of tunnel reinforced mesh processing frame.
Background technology
Reinforced mesh is longitudinal reinforcement and transverse steel respectively with certain spacing arrangement and mutual at a right angle and whole intersections The mesh sheet that welds together of point, be mainly used in the beam column floor of industry and civic building, roof system, wall, concrete road surface, The fields such as deck paving, airfield runway, tunnel-liner, box culvert, harbour terrace, prefabricated components, currently, reinforced mesh was making Reinforcing bar is usually staggeredly placed and welds on the ground by Cheng Zhong, but inevitably will appear reinforcing bar dislocation in process Or translation the case where, needed to increase manufacture difficulty, and when human weld it is couchant crosspoint is welded, operation very It is inconvenient.
The prior art (CN206435700U) discloses a kind of reinforced mesh processing frame comprising several spaced cross Bar, perpendicular to the cross bar and spaced several montants and several horizontally disposed supporting rods, further include for connecting The connection component of cross bar and montant, it is solid that the prior art, which solves existing reinforced mesh processing frame cross tube and the position of montant, Fixed, the size of the grid of formation is also fixed, it is impossible to be used in the problem of processing the reinforced mesh of different size.But this is existing When in use, laterally disposed reinforcing bar is directly taken to be placed on supporting rod technology, the reinforcing bar vertically placed then on the basis of montant according to It leans against on supporting rod, i.e., in the welding process, reinforcing bar is not fixed and is easy to happen barrel shift, influences processing quality.
Utility model content
The utility model provides a kind of tunnel reinforced mesh processing frame, it is desirable to provide and reinforcing bar can be fixed in one kind, And the reinforced mesh processing frame of different processing specifications can be met, to solve problems of the prior art.
The utility model provides a kind of tunnel reinforced mesh processing frame, including pedestal, vertical first be fixed on pedestal Strut and the second strut, first strut and the second strut are symmetrically arranged at the both sides of pedestal;The susceptor surface is horizontally opened with Sliding slot, is connected with several vertical reinforcement fixing pieces on the sliding slot by the sliding block slide fit to match, and the vertical reinforcement is solid It includes fixed cylinder to determine part, and tapped through hole is provided on the side wall of the fixed cylinder, is equipped with for perpendicular in the tapped through hole To the fixed fastening bolt of reinforcing bar;First strut is equipped with several can be solid along the transverse steel that the first strut moves up and down Determine part, the transverse steel fixing piece includes the first sleeve being socketed on the first strut, is led on the outer wall of the first sleeve It crosses tapped through hole and is bolted with fastening bolt, be also connected with by connecting rod for placing lateral steel on the outer wall of the first sleeve The arc groove of muscle, second strut have a structure identical with the first strut, on first strut and second strut Line between the arc groove for two transverse steel fixing pieces that level is correspondingly arranged is located at the surface of the sliding slot.
Preferably, connection cross bar is equipped between first strut and the second strut, the connection cross bar is equipped with several A fastener, the fastener include the second casing being socketed on connection cross bar, pass through spiral shell on the outer wall of second casing Line through-hole is equipped with fastening bolt, is also connected with by connecting rod on the outer wall of second casing horizontally disposed perpendicular for fastening To the dead ring of reinforcing bar, fastening bolt is also bolted with by tapped through hole on the outer wall of the dead ring, in the dead ring The center of the heart and fixed cylinder is located on same vertical guide, and when use fixes the bottom of vertical reinforcement by fixed cylinder, erects It is fixed to the top of reinforcing bar across dead ring, fixed effect is more preferable, facilitates welding.
It is highly preferred that the number of transverse steel fixing piece is identical on first strut and the second strut, the connection is horizontal The number of fastener is identical as the number of vertical reinforcement fixing piece on bar, and position is corresponding up and down, by fixing correspondingly Transverse steel and vertical reinforcement is fixed in structure.
Preferably, four vertex of the pedestal are provided with tapped through hole, and fastening bolt is equipped in the tapped through hole, can To fix pedestal on the ground, the stability of processing frame is improved.
The tunnel reinforced mesh processing frame of the utility model has the advantages that compared with prior art:1, this reality It is equipped with transverse steel fixing piece with novel the first strut and the second strut, susceptor surface is equipped with vertical reinforcement fixing piece, can It is fixed with the reinforcing bar processed to needs, prevents that moving influence welding quality occurs in welding process;2, the utility model packet The first strut and the second strut for including pedestal, being fixed on pedestal, and the processing frame structure of the prior art includes several intervals The cross bar of setting, perpendicular to the cross bar and spaced several montants and several horizontally disposed supporting rods, that is, compare It is simple in prior art construction;3, the transverse steel fixing piece of the utility model can move down on the first strut and the second strut Dynamic, vertical reinforcement fixing piece can be moved left and right along sliding slot, therefore be processed to the reinforced mesh of different size.
Description of the drawings
Fig. 1 is the stereogram of tunnel reinforced mesh processing frame in the utility model embodiment;
Fig. 2 is enlarged drawing at A in Fig. 1.
Specific implementation mode
Below in conjunction with the accompanying drawings, specific embodiment of the present utility model is described in detail, it is to be understood that this practicality Novel protection domain is not restricted by specific implementation.
As shown in Figs. 1-2, a kind of tunnel reinforced mesh processing frame, including pedestal 1, vertical first be fixed on pedestal 1 Strut 2, the second strut 3 and the connection cross bar 4 being located between the first strut 2 and the second strut 3, first strut 2 are located at The left side of pedestal 1, the second strut 3 are located at the right side of pedestal 1, and first strut 2 and third strut 4 are symmetrical, the company One end and the top of the first strut 2 for connecing cross bar 4 are affixed, and the top of the other end and the second strut 3 is affixed.
Four vertex of the pedestal 1 are provided with tapped through hole 101, and bolt is equipped in the tapped through hole 101, can incite somebody to action Pedestal 1 fixes on the ground, improves the stability of processing frame;1 surface of the pedestal is horizontally opened with sliding slot 102, the sliding slot 102 Upper to be connected with several vertical reinforcement fixing pieces by the sliding block slide fit to match, the vertical reinforcement fixing piece includes fixed justifies Cylinder 103 is provided with tapped through hole on the side wall of the fixed cylinder 103, is equipped in the tapped through hole for solid to vertical reinforcement Fixed fastening bolt;The connection cross bar 4 is equipped with several fasteners, and the fastener includes being socketed on connection cross bar 4 The second casing 401, fastening bolt, second casing 401 are equipped with by tapped through hole on the outer wall of second casing 401 Outer wall on be also connected with by connecting rod it is horizontally disposed for fastening the dead ring 402 of vertical reinforcement, the dead ring 402 Outer wall on fastening bolt is bolted with by tapped through hole, the center of the center of the dead ring 402 and fixed cylinder 103 is located at On same vertical guide, the number of the fastener is identical as the number of vertical reinforcement fixing piece, and position is corresponding up and down, when use The bottom of vertical reinforcement is fixed by fixed cylinder 103, the top of vertical reinforcement passes through dead ring 402, passes through fastening bolt It is fixed, fixed effect is more preferable, facilitates welding.
First strut 2 can be along the first transverse steel fixing piece that the first strut 2 moves up and down, institute equipped with several It includes the first sleeve 201 being socketed on the first strut 2, the outer wall of the first sleeve 201 to state the first transverse steel fixing piece It is upper that fastening bolt is equipped with by through-hole, it is also connected with by connecting rod for placing transverse direction on the outer wall of the first sleeve 201 First arc groove 202 of reinforcing bar, second strut 3 are equipped with several the second transverse directions that can be moved up and down along the second strut 3 Reinforcing bar fixing piece, the second transverse steel fixing piece include the third casing 301 being socketed on the second strut 2, the third Fastening bolt is equipped with by through-hole on the outer wall of casing 301, is also connected with by connecting rod on the outer wall of the third casing 201 The second arc groove 302 for placing transverse steel, of transverse steel fixing piece on first strut, 3 and second strut 2 Number is identical, the first arc groove 202 on first strut 2 and horizontal the second arc being correspondingly arranged on second strut 3 Line between slot 302 is located at the surface of the sliding slot 102.
When the utility model is used, the distance between the first transverse steel fixing piece on the first strut 2 is first adjusted, then The distance between the second transverse steel fixing piece adjusted on the second strut 3 is allowed to and the first transverse steel on the first strut 2 Then fixing piece is adjusted on connection cross bar 4 on fastener and sliding slot 102 on a horizontal line between vertical reinforcement fixing piece again Distance, one end of transverse steel is placed on to the transverse steel of the first strut 2 to meet needed for welding, after distance adjustment and is consolidated Determine on the first arc groove 202 of part, the other end is placed on the second arc groove 302 of the lateral fixing piece of the second strut 3, will be vertical The top of reinforcing bar passes through dead ring 402, and bottom is inserted into fixed cylinder 103, and is fastened by fastening bolt, and then welding is lateral The crosspoint of reinforcing bar and vertical reinforcement.
Disclosed above is only a specific embodiment of utility model, and still, the utility model embodiment is not limited to In this, the changes that any person skilled in the art can think of should all fall into the scope of protection of the utility model.

Claims (4)

1. a kind of tunnel reinforced mesh processing frame, which is characterized in that including pedestal (1), be vertically fixed on pedestal (1) first Strut (2) and the second strut (3), first strut (2) and the second strut (3) are symmetricly set on the pedestal (1) both sides;
Pedestal (1) surface is horizontally opened with sliding slot (102), is connected by the sliding block slide fit to match on the sliding slot (102) It includes fixed cylinder (103), the fixed cylinder (103) to have several vertical reinforcement fixing pieces, the vertical reinforcement fixing piece Side wall on be provided with tapped through hole, be equipped with for the fixed fastening bolt of vertical reinforcement in the tapped through hole;
First strut (2) can be along the transverse steel fixing piece that the first strut (2) move up and down, the cross equipped with several Include being socketed in first sleeve (201) on the first strut (2) to reinforcing bar fixing piece, on the outer wall of the first sleeve (201) It is bolted with fastening bolt by tapped through hole, is also connected with by connecting rod for putting on the outer wall of the first sleeve (201) The arc groove of transverse steel is set, second strut (3) has with the first strut (2) identical structure, first strut (2) Line between the arc groove of horizontal two transverse steel fixing pieces being correspondingly arranged on second strut (3) is located at described The surface of sliding slot (102).
2. reinforced mesh processing frame in tunnel according to claim 1, which is characterized in that first strut (2) and second Connection cross bar (4) is equipped between strut (3), the connection cross bar (4) is equipped with several fasteners, and the fastener includes set It is connected on the second casing (401) connected on cross bar (4), is bolted with by tapped through hole on the outer wall of second casing (401) Fastening bolt is also connected with the dead ring for fastening vertical reinforcement on the outer wall of second casing (401) by connecting rod (402), fastening bolt, the center of the dead ring (402) are bolted with by tapped through hole on the outer wall of the dead ring (402) It is located on same vertical guide with the center of fixed cylinder (103).
3. reinforced mesh processing frame in tunnel according to claim 2, which is characterized in that first strut (2) and second The number of transverse steel fixing piece is identical on strut (3), on the connection cross bar (4) in the number and sliding slot (102) of fastener The number of vertical reinforcement fixing piece is identical, and position is corresponding up and down.
4. reinforced mesh processing frame in tunnel according to claim 1, which is characterized in that four apex angles of the pedestal (1) Place is provided with tapped through hole (101), and fastening bolt is equipped in the tapped through hole (101).
CN201820293193.8U 2018-03-01 2018-03-01 A kind of tunnel reinforced mesh processing frame Expired - Fee Related CN207914881U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820293193.8U CN207914881U (en) 2018-03-01 2018-03-01 A kind of tunnel reinforced mesh processing frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820293193.8U CN207914881U (en) 2018-03-01 2018-03-01 A kind of tunnel reinforced mesh processing frame

Publications (1)

Publication Number Publication Date
CN207914881U true CN207914881U (en) 2018-09-28

Family

ID=63600680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820293193.8U Expired - Fee Related CN207914881U (en) 2018-03-01 2018-03-01 A kind of tunnel reinforced mesh processing frame

Country Status (1)

Country Link
CN (1) CN207914881U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109954963A (en) * 2019-04-28 2019-07-02 东莞市东晓五金制品有限公司 A kind of auxiliary welding equipment
CN111922603A (en) * 2020-08-28 2020-11-13 广东博智林机器人有限公司 Reinforcing bar net piece positioner
CN112372201A (en) * 2020-10-29 2021-02-19 广东博智林机器人有限公司 Replacing device for reinforcing mesh welding positioning die
CN112832535A (en) * 2020-12-30 2021-05-25 衡宇建设集团有限公司 Device and method for positioning and installing reinforcing steel bars for house building
CN113006491A (en) * 2021-02-25 2021-06-22 陈晓鹏 Special steel bar crossbeam of marine concrete building
CN113600954A (en) * 2021-09-02 2021-11-05 无锡鑫迈维电子设备有限公司 Modular reflow soldering machine
CN114571151A (en) * 2022-04-06 2022-06-03 河南中电工程咨询有限公司 Construction method for intensively installing construction platform on small-caliber pipeline of waste heat furnace

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109954963A (en) * 2019-04-28 2019-07-02 东莞市东晓五金制品有限公司 A kind of auxiliary welding equipment
CN111922603A (en) * 2020-08-28 2020-11-13 广东博智林机器人有限公司 Reinforcing bar net piece positioner
CN112372201A (en) * 2020-10-29 2021-02-19 广东博智林机器人有限公司 Replacing device for reinforcing mesh welding positioning die
CN112832535A (en) * 2020-12-30 2021-05-25 衡宇建设集团有限公司 Device and method for positioning and installing reinforcing steel bars for house building
CN113006491A (en) * 2021-02-25 2021-06-22 陈晓鹏 Special steel bar crossbeam of marine concrete building
CN113600954A (en) * 2021-09-02 2021-11-05 无锡鑫迈维电子设备有限公司 Modular reflow soldering machine
CN114571151A (en) * 2022-04-06 2022-06-03 河南中电工程咨询有限公司 Construction method for intensively installing construction platform on small-caliber pipeline of waste heat furnace
CN114571151B (en) * 2022-04-06 2024-02-23 河南中电工程咨询有限公司 Construction method for centralized installation of construction platform of small-caliber pipelines of waste heat furnace

Similar Documents

Publication Publication Date Title
CN207914881U (en) A kind of tunnel reinforced mesh processing frame
CN202017346U (en) Late poured band hanging formwork structure
CN107366356A (en) Assembled architecture agent structure
CN212534174U (en) Raft foundation steel bar supporting tool
CN111737803B (en) Design optimization system of ultra-thick bottom plate steel bar supporting system based on BIM technology
CN203603452U (en) Folded plate small space formwork assembly
CN204475846U (en) A kind of conversion support system for socket joint dish button steel tube frame
CN201962965U (en) Cadge ladder for construction of deep base pit
CN207553652U (en) A kind of assembled architecture wallboard combines support device
CN110485759A (en) A kind of fast spelling formula temporary house
CN207749638U (en) Steel reinforced concrete rectangular column-Special-Shaped Column transfer framework structure and its converting system
CN214498388U (en) Assembled overhanging formwork support bent
CN205025154U (en) 330kVGIS distribution device place rigid connection sail formula framework
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN103669566B (en) construction method of steel reinforced concrete base of large-span net rack roof
CN206747475U (en) Reinforced mesh processing frame
CN206468030U (en) Independent beam combined type limb protective railing
CN106760274A (en) A kind of eaves structure in steel member house
CN201344038Y (en) Mining survival active supporting net
CN206941473U (en) A kind of solar advertisement identifies pedestrian guardrail
CN208830767U (en) A kind of assembled architecture hoistway regularization protection and vertical passageway device
CN203729852U (en) Assembled building site gate
CN208587002U (en) The mobile enclosing of adjustable assembled
CN202017289U (en) Steel frame prestressed reinforcement light shock-proof plate
CN106567454A (en) Installation method of inclined steel reinforced concrete composite structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180928

Termination date: 20200301