CN206707748U - A kind of machine tunneling fume extractor - Google Patents

A kind of machine tunneling fume extractor Download PDF

Info

Publication number
CN206707748U
CN206707748U CN201720486320.1U CN201720486320U CN206707748U CN 206707748 U CN206707748 U CN 206707748U CN 201720486320 U CN201720486320 U CN 201720486320U CN 206707748 U CN206707748 U CN 206707748U
Authority
CN
China
Prior art keywords
jet
machine
air compressor
jet pump
rock drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720486320.1U
Other languages
Chinese (zh)
Inventor
张�杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HAISHENG PETROCHEMICAL CONSTRUCTION AND INSTALLATION ENGINEERING Co Ltd
Original Assignee
TIANJIN HAISHENG PETROCHEMICAL CONSTRUCTION AND INSTALLATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HAISHENG PETROCHEMICAL CONSTRUCTION AND INSTALLATION ENGINEERING Co Ltd filed Critical TIANJIN HAISHENG PETROCHEMICAL CONSTRUCTION AND INSTALLATION ENGINEERING Co Ltd
Priority to CN201720486320.1U priority Critical patent/CN206707748U/en
Application granted granted Critical
Publication of CN206707748U publication Critical patent/CN206707748U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

A kind of machine tunneling fume extractor, including rock drill, air compressor machine and jet pump, fume collecting chamber is provided with below the rock drill, pipeline is designed with the rock drill and fume collecting chamber, the pipeline is connected with air compressor machine and jet pump respectively by threeway, the jet pump by jet-sub and hold spray joint form.Application of the utility model by Bernoulli equation principle on fume extractor, pass through switch valve in pipeline, so that rock drilling and smoke evacuation flexible conversion, convenient and reliable, easy to operation, solves the ventilating problem of light section machine tunneling, avoid smog in tunnel to damage worker, improve speed of application.

Description

A kind of machine tunneling fume extractor
Technical field
The utility model belongs to tunnel fume extractor field, more particularly to a kind of machine tunneling fume extractor.
Background technology
Tunnel is the capital construction projects for developing mineral resources, and produces mine and carry out digging up mine preparation and produce what is prospected Major project, tunnel can be used to transport ore, barren rock, material, equipment and ventilating drainage and pedestrian etc..Tunnel driving is typically adopted Tunneled with traditional drill-blasting method, tunnel is completed by processes such as rock drilling, explosion, shipment, supportings and tunneled, the tunnel tunneled Generally have the characteristics that scattered, tunnel section is small, the length of service is short.During using blasting procedure rock drilling, explosion would generally A large amount of smog are produced inside tunnel, due to the particularity that tunnel is closed, the generation of a large amount of smog has a strong impact on the body of worker Health, it also limit a rate of advance in tunnel.
The content of the invention
To solve the problems, such as that in the presence of being damaged on worker, influenceing tunnel construction speed, this uses new smog in tunnel Provide a kind of fume extractor that the smog as caused by explosion or fuel oil burning can be quickly eliminated during the pick of tunnel machine.
Technical solution adopted in the utility model is:
A kind of machine tunneling fume extractor, including rock drill, threeway, air compressor machine, jet pump, jet-sub, hold spray joint, High-pressure pipe, collection chamber and trunnion, the rock drill lower section are provided with fume collecting chamber, pipe are designed with the rock drill and fume collecting chamber Road, the pipeline are connected with air compressor machine and jet pump respectively by threeway, and the jet pump is by jet-sub and holds spray joint Composition, the jet-sub include high-pressure pipe, and the end of the high-pressure pipe is provided with nozzle, and the nozzle is inserted in gas collection The centre of room, the collection chamber side are connected with air intake duct;The jet-sub is connected with holding spray joint by screw thread, described Holding spray joint includes trunnion, and described trunnion one end is connected with the opposite side of collection chamber, and the trunnion other end is provided with anemostat, the expansion The end of separate tube is connected with blast pipe.
Described rock drill, fume collecting chamber, air compressor machine and jet pump is designed with valve between any two.
Described fume collecting chamber is in loudspeaker barrel shape.
Connecting pipe between described air compressor machine and jet pump is as short as possible.
Described collection chamber, trunnion and anemostat is pyramidal structure pipeline.
The beneficial effects of the utility model:By application of the Bernoulli equation principle on fume extractor, lead in pipeline Cross switch valve so that rock drilling and smoke evacuation flexible conversion, convenient and reliable, easy to operation, solve the logical of light section machine tunneling Wind problem, avoid smog in tunnel and worker is damaged, improve speed of application.
Brief description of the drawings
Fig. 1 is schematic diagram of the present utility model
Fig. 2 is the operation principle schematic diagram of jet pump
Wherein:1- jet pumps;2- air compressor machines;3- pipelines;4- rock drills;5- fume collecting chamber;6- threeways;7- valves;71- valves A;72- valves B;73- valves C;74- valves D;8- jet-subs;9- holds spray joint;11- high-pressure pipes;12- nozzles;13- Trunnion;14- anemostats;15- blast pipes;16- air intake ducts;17- collection chambers.
Embodiment
It is new to this practicality below in conjunction with accompanying drawing to make the purpose of this utility model, technical scheme and advantage clearer The embodiment of type is set forth in.
As depicted in figs. 1 and 2, a kind of machine tunneling fume extractor, including rock drill 4, threeway 6, air compressor machine 2, jet pump 1st, jet-sub 8, hold spray joint 9, high-pressure pipe 11, collection chamber 17 and trunnion 13, the lower section of rock drill 4 is provided with fume collecting chamber 5, be designed with pipeline 3 on the rock drill 4 and fume collecting chamber 5, the pipeline 3 by threeway 6 respectively with air compressor machine 2 and jet pump 1 It is connected, the jet pump 1 is made up of jet-sub 8 with spray joint 9 is held, and the jet-sub 8 includes high-pressure pipe 11, institute The end for stating high-pressure pipe 11 is provided with nozzle 12, and the nozzle 12 is inserted in the centre of collection chamber 17, the side of collection chamber 17 It is connected with air intake duct 16;The jet-sub 8 is connected with holding spray joint 9 by screw thread, and the spray joint 9 that holds includes trunnion 13, described one end of trunnion 13 is connected with the opposite side of collection chamber 17, and the other end of trunnion 13 is provided with anemostat 14, the anemostat 14 End be connected with blast pipe 15.
Described rock drill 4, fume collecting chamber 5, air compressor machine 2 and jet pump 1 is designed with valve 7 between any two.
Described fume collecting chamber 5 is in loudspeaker barrel shape.
Connecting pipe 3 between described air compressor machine 2 and jet pump 1 is as short as possible.
Described collection chamber 17, trunnion 13 and anemostat 14 is pyramidal structure pipeline.
During utility model works, when rock drilling finishes, breeching explosion after, Open valve A71, valve B72, valve C73, close Valve closing door 7 and valve D74, the compressed air of air compressor machine 2 is sent into nozzle 12 through high pressure admission, 11, because the inner chamber of nozzle 12 is taper, Outlet Section is gradually reduced, and compressed air injects anemostat 14 with high speed through collection chamber 17, trunnion 13, when spouting velocity is very big When, outlet pressure greatly reduces, while brings the gas of near exit into anemostat 14 by the air-flow that nozzle 12 sprays, and makes spray Pressure subatmospheric power near nozzle 12, negative pressuren zone is formed, smog enters through fume collecting chamber 5, pipeline 3 and air intake duct 16 in tunnel Collection chamber 17, high velocity air are mixed with the smog sucked in collection chamber 17, and energy transmission or exchange are carried out in collection chamber 17, High-speed compressed air loses energy, and low speed smog obtains energy, and last both reach similar flow velocity, together into trunnion 13, In trunnion 13, mixed airflow forms stable flow regime, after air-flow enters anemostat 14 by trunnion 13, flows decrease, and pressure Power raises, and is discharged through blast pipe 15;Valve A71, valve B72, valve C73 are closed, opens valve 7 and valve D74, you can is carried out Rock drilling works.
One embodiment of the present utility model is described in detail above, but the content is only of the present utility model Preferred embodiment, it is impossible to be considered as being used to limit practical range of the present utility model.It is all to be made according to present utility model application scope Equivalent change with improve etc., all should still belong within patent covering scope of the present utility model.

Claims (5)

1. a kind of machine tunneling fume extractor, it is characterised in that including rock drill(4), threeway(6), air compressor machine(2), jet pump (1), jet-sub(8), hold spray joint(9), high-pressure pipe(11), collection chamber(17)And trunnion(13), the rock drill(4) Lower section is provided with fume collecting chamber(5), the rock drill(4)And fume collecting chamber(5)On be designed with pipeline(3), the pipeline(3)Pass through threeway (6)Respectively with air compressor machine(2)And jet pump(1)It is connected, the jet pump(1)By jet-sub(8)With hold spray joint(9)Group Into the jet-sub(8)Including high-pressure pipe(11), the high-pressure pipe(11)End be provided with nozzle(12), institute State nozzle(12)It is inserted in collection chamber(17)Centre, the collection chamber(17)Side is connected with air intake duct(16);The injection connects Head(8)With holding spray joint(9)It is connected by screw thread, it is described to hold spray joint(9)Including trunnion(13), the trunnion(13)One end With collection chamber(17)Opposite side be connected, trunnion(13)The other end is provided with anemostat(14), the anemostat(14)End connect It is connected to blast pipe(15).
A kind of 2. machine tunneling fume extractor according to claim 1, it is characterised in that described rock drill(4), collection cigarette Room(5), air compressor machine(2)And jet pump(1)Valve is designed between any two(7).
A kind of 3. machine tunneling fume extractor according to claim 1, it is characterised in that described fume collecting chamber(5)In loudspeaker Barrel shape.
A kind of 4. machine tunneling fume extractor according to claim 1, it is characterised in that described air compressor machine(2)With penetrate Flow pump(1)Between connecting pipe(3)It is as short as possible.
A kind of 5. machine tunneling fume extractor according to claim 1, it is characterised in that described collection chamber(17), larynx Pipe(13)And anemostat(14)It is pyramidal structure pipeline.
CN201720486320.1U 2017-05-04 2017-05-04 A kind of machine tunneling fume extractor Expired - Fee Related CN206707748U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720486320.1U CN206707748U (en) 2017-05-04 2017-05-04 A kind of machine tunneling fume extractor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720486320.1U CN206707748U (en) 2017-05-04 2017-05-04 A kind of machine tunneling fume extractor

Publications (1)

Publication Number Publication Date
CN206707748U true CN206707748U (en) 2017-12-05

Family

ID=60465224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720486320.1U Expired - Fee Related CN206707748U (en) 2017-05-04 2017-05-04 A kind of machine tunneling fume extractor

Country Status (1)

Country Link
CN (1) CN206707748U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627873A (en) * 2020-12-15 2021-04-09 西南交通大学 Rock burst prevention and treatment device and prevention and treatment method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627873A (en) * 2020-12-15 2021-04-09 西南交通大学 Rock burst prevention and treatment device and prevention and treatment method
CN112627873B (en) * 2020-12-15 2021-11-30 西南交通大学 Rock burst prevention and treatment device and prevention and treatment method

Similar Documents

Publication Publication Date Title
CN103352718B (en) Fully-sealed wind power slagging gas-drainage deep well drilling system and method
CN202913992U (en) Underground coal mine dry-type drilling three-stage dust removal device
CN102191935A (en) Water vapor rotating jet dust settling device for comprehensive driving working face
CN108301799A (en) A kind of hole pumping and mining dust-extraction unit and its application method
CN103046948A (en) Device and method for preventing coal drilling and cutting or gas emission
CN106869834A (en) A kind of coal bed drilling drilling hole dust collector device
CN102102497B (en) Blowout prevention and dust prevention device
CN102345648A (en) Injection pump and suction method thereof
CN203296725U (en) Through type DTH hammer reverse circulation drilling dust collecting device
CN103195469A (en) Pneumatic type gas and slag separation device and method
CN206707748U (en) A kind of machine tunneling fume extractor
CN206338031U (en) A kind of underground self-advancing type high-pressure abrasive material gas jet drilling prosthetic device
CN203412533U (en) Wet dust removal system for coal-mine gas pumping-exhaust drill hole
CN103161415A (en) Negative pressure drilling system
CN104373064A (en) Wet dust removing system of coal mine gas drainage borehole
CN203097768U (en) Dust removal device of dry-type drilling hole
CN111734475B (en) Method for cleaning coal dust at sealing section of gas extraction drill hole
CN208546149U (en) A kind of gas injection formula coal bed drilling drilling hole dust collector device
CN201474637U (en) Mine drilling orifice dust catcher
CN206722755U (en) A kind of hot cold shock three-level breaks device for coal
CN104879158A (en) Dry type drilled hole orifice dust elimination and noise reduction device and implementation method thereof
CN202970548U (en) Gas jet flow dust collector for mine drilling
CN105673047B (en) A kind of Full pneumatic mine laneway paint finishing and method
CN201082519Y (en) Middle and small diameter long-distance pipeline inner sand spraying device
CN209549027U (en) A kind of mineral water-jet deduster

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171205

Termination date: 20180504

CF01 Termination of patent right due to non-payment of annual fee