CN205707186U - A kind of plug in construction barrier that buries crushes workboat - Google Patents

A kind of plug in construction barrier that buries crushes workboat Download PDF

Info

Publication number
CN205707186U
CN205707186U CN201620222043.9U CN201620222043U CN205707186U CN 205707186 U CN205707186 U CN 205707186U CN 201620222043 U CN201620222043 U CN 201620222043U CN 205707186 U CN205707186 U CN 205707186U
Authority
CN
China
Prior art keywords
construction
vibration
plug
sunk
buries
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620222043.9U
Other languages
Chinese (zh)
Inventor
练学标
夏俊桥
丁海龙
项建强
张跃辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Original Assignee
JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd filed Critical JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority to CN201620222043.9U priority Critical patent/CN205707186U/en
Application granted granted Critical
Publication of CN205707186U publication Critical patent/CN205707186U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)

Abstract

This utility model relates to a kind of plug in construction barrier that buries and crushes workboat, including hull, vibration-sunk system, alignment system;Construction ship is selected according to situations such as plug in construction the construction wave in waters, current, landform;Sink to end elevation design according to hard thing or the interlayer place degree of depth, plug in construction and make pile frame, vibration hammer and pile pipe, pile pipe head welding Special crushing head are installed, complete vibration-sunk system and install;During construction, boats and ships position under the guidance of special measurement system;Opening the downward vibration-sunk of vibration hammer after having positioned, head to be broken arrives and stops and extracting when setting end absolute altitude, and then boats and ships position and vibration-sunk again, until it is complete to construct.This equipment positioning precision is high, crushing effect is good, and speed is fast, has the biggest motility.

Description

A kind of plug in construction barrier that buries crushes workboat
Technical field:
This utility model relates to a kind of plug in construction barrier that buries and crushes workboat.
Background technology:
It is widely used many at present in the water project processs of construction such as harbour, bridge, breakwater, dock Cylinder combination or the plug in construction in storehouse more than single barrel, this class formation can use concrete, armored concrete or steel knot The materials such as structure make;This class formation is bottomless lid, carries out, by qi of chong channel ascending adversely in storehouse, transport of swimming, utilize deadweight, The negative pressure that water pressure and aerofluxus, draining are formed sinks in soil.Plug in construction, in sinking watching, runs into soil Above-mentioned strength is relied on to pass during body backbone hard interbedded layer, the meeting when local runs into the hard obstructing objects in soil Produce and hinder plug in construction to sink further.This kind of structure construction needs hard folder before sinking Layer, locally hard objects are broken or extrude, and enable plug in construction by deadweight, water pressure, negative pressure etc. Make a concerted effort just to pass through and sink.
Summary of the invention:
The purpose of this utility model is to provide a kind of plug in construction barrier that buries and crushes workboat, it is possible to By broken to hard interlayer, locally hard objects or extrusion before plug in construction sinks, make plug in construction energy Enough make a concerted effort just to pass through and sink by deadweight, water pressure, negative pressure etc..
Above-mentioned purpose is realized by following technical scheme:
A kind of plug in construction barrier that buries crushes workboat, including hull, vibration-sunk system, fixed Position system, selects construction ship according to situations such as plug in construction the construction wave in waters, current, landform, Boats and ships are advisable with barge;
Sink to end elevation design according to hard thing or the interlayer place degree of depth, plug in construction and make pile frame, peace Dress vibration hammer and pile pipe, pile pipe head welding Special crushing head, complete vibration-sunk system and install;
During construction, boats and ships position under the guidance of special measurement system;
Opening the downward vibration-sunk of vibration hammer after having positioned, head to be broken arrives and stops when setting end absolute altitude And extract, then boats and ships position and vibration-sunk again, until it is complete to construct;
Further, as preferably, vibration-sunk system includes construction ship, pile frame, vibration hammer, construction Boats and ships are selected from navigating by water barge, and according to water area condition vessel displacement not preferably less than 1000 tons, pile frame uses Steel construction or steel truss structure, steel pipe uses wall thickness to make not less than 10mm steel, and often set pile pipe is all joined Putting vibration hammer, vibration hammer power is not preferably less than 100kw, and pile pipe tip is equipped with crushing head;
Further, as preferably, alignment system uses and is arranged on hull no less than 3 GPS, Send elevation, plan-position to computer information processing system by radio station, calculate display by computer Pile pipe position, first inputs computer by construction coordinate in work progress, survey crew refers to according to display position Wave ship's fix;
Further, as preferably, special crushing head is devised in order to abolish hard objects, due to repeatedly The earth that buries can enter crushing head, for this crushing head needs energy spoil disposal rapidly the most quickly to use, for Hard objects crushing head is required to quick crashing, and crushing head uses steel plate cell structure, and crushing head is more than knot Structure width.
This utility model by construction ship, pile frame, vibration hammer and welds Special crushing head at pile pipe head, Achieve broken to hard interlayer, locally hard objects or extrusion before plug in construction sinks, make plug-in type Structure can make a concerted effort just to pass through and sink by deadweight, water pressure, negative pressure etc..This equipment positioning accurate Degree is high, crushing effect is good, and speed is fast, has the biggest motility, it is also possible to increase pile pipe according to quantities Configuration quantity improves speed of application, it is also possible to by adjusting crushing head size to adapt to various sizes of structure.
Accompanying drawing explanation
When considered in conjunction with the accompanying drawings, by referring to detailed description below, it is possible to be more completely more fully understood that This utility model and easily learn the advantage that many of which is adjoint, but accompanying drawing described herein is used for providing Be further appreciated by of the present utility model, constitute a part of the present utility model, of the present utility model schematically Embodiment and explanation thereof are used for explaining this utility model, are not intended that improper restriction of the present utility model, its In:
The front view of Fig. 1 construction ship.
Fig. 2 is this utility model embodiment steel plate barrier crushing head.
Fig. 3 is that this utility model embodiment construction ship positions schematic diagram.
Detailed description of the invention
With reference to Fig. 1, embodiments of the invention are illustrated.
Understandable for enabling above-mentioned purpose, feature and advantage to become apparent from, real with concrete below in conjunction with the accompanying drawings This utility model is described in further detail by mode of executing.
A kind of plug in construction barrier that buries crushes workboat, according to the ripple in plug in construction construction waters The situations such as wave, current, landform select construction ship, and boats and ships are advisable with barge;According to hard thing or interlayer institute Sink to end elevation design make pile frame at the degree of depth, plug in construction, vibration hammer and pile pipe, pile pipe head are installed Welding Special crushing head, completes vibration-sunk system and installs;During construction, boats and ships are in the guidance of special measurement system Lower location;Opening the downward vibration-sunk of vibration hammer after having positioned, head to be broken arrives and stops when setting end absolute altitude Stopping and extract, then boats and ships position and vibration-sunk again, until it is complete to construct.
As it is shown in figure 1, a kind of plug in construction of this utility model offer buries, barrier crushes workboat.
Require to select barge according to hydrogeology and design, make pile frame, vibration hammer and pile pipe, stake are installed Tube head welding Special crushing head, completes sinking system installation of shaking.Shown in Figure 1, construction ship mainly wraps Include hull 1, pile frame 2, pile pipe 3, vibration hammer 4, crushing head 5, pulling force windlass 6.
Construction ship is selected and is advisable with barge, and the exemplary parameter of hull 1 is as follows: displacement 2116 tons, Captain 60 meters, ship molded breadth 19.6 meters, ship type is high 3.4 meters, the designed draft degree of depth 1.93 meters.Pile pipe height 47 meters (distance face, boat deck).
Unrestricted as an example, hull 1 is a Barge Self-Propelled, independently navigates by water when dispatching.
On the main deck of hull 1, backup has 6 20 tons of pulling force windlass 6,5 tons of anchors of can dishing out, and enters Row ship's fix.
Unrestricted as an example, hull 1 is arranged side by side 3 lag pile tube apparatus, has been furnished with 135# and shakes Dynamic hammer, hammer weighs 7.2 tons, 3 set pile pipes.
As an example, vibration hammer power 135Kw, eccentric moment 806Nm, exciting force 0-883Kn, turn Speed 0-1000r/min, amplitude 0-8.2Mm, maximum extract force 420Kn, long 2.1m, wide 1.45m are high 3m, weight 7200kg.
As in figure 2 it is shown, crushing head uses steel plate grille structure, in one embodiment, pile top projection profile Being designed to rectangle, centre is steel plate grid, along long axial length 1.8m, vertically long axial length 1.1m, To guarantee that a heart plane deviation is less than 300mm, when perpendicularity deviation is less than 3 ‰, sinkage type structure Big drum wall and partition wall sink and solve region in the broken shake of barrier.
GPS is utilized to position with Computer Aided Ship, as it is shown on figure 3, in one embodiment, hull 1 Main deck on backup have 6 20 tons of pulling force windlass 6,5 tons of anchors of can dishing out, carry out ship's fix.Adopt It is arranged on hull 1 with no less than 3 GPS, sends elevation, plan-position to letter by radio station Breath processing system, shows pile pipe position by software checkout.First by construction coordinate input electricity in work progress Brain, survey crew is according to the commander's ship's fix of display position.
Opening the downward vibration-sunk of vibration hammer, in one embodiment, boats and ships position successively according to piling foundation plan, Opening vibration hammer after having positioned and squeeze into soil layer, crushing head exceedes and sinks to the bottom mark under the staving of sinkage type structure basis High.Head to be broken arrive set the end absolute altitude time stop and extracting, then boats and ships again position vibration-sunk until Construct complete.
Although this utility model discloses as above with preferred embodiment, so it is not limited to this practicality newly Type, any those skilled in the art, without departing from spirit and scope of the present utility model, a little when making Amendment and perfect, protection domain the most of the present utility model is when with being as the criterion that claims are defined.

Claims (4)

1. the plug in construction barrier that buries crushes workboat, it is characterised in that:
Hull, described hull is for from navigating by water barge;
Vibration-sunk system, is located at the gunwale of hull, and described vibration-sunk system includes: construction ship, pile frame, vibration hammer, and construction ship selects barge;
Alignment system, is located on the deck of hull.
The most according to claim 1, the plug in construction barrier that buries crushes workboat, it is characterized in that, described vibration-sunk system includes: construction ship, pile frame, vibration hammer, construction ship selects barge, and according to water area condition vessel displacement not preferably less than 1000 tons, pile frame uses steel construction or steel truss structure, steel pipe uses wall thickness to make not less than 10mm steel, often set pile pipe all configures vibration hammer, and vibration hammer power is not preferably less than 100kw, and pile pipe tip is equipped with crushing head.
The most according to claim 1, the plug in construction barrier that buries crushes workboat, it is characterized in that, described alignment system uses and is arranged on hull no less than 3 GPS, elevation, plan-position is sent to computer information processing system by radio station, display pile pipe position is calculated by computer, first construction coordinate inputs in work progress computer, and survey crew is according to the commander's ship's fix of display position.
The most according to claim 2, the plug in construction barrier that buries crushes workboat, it is characterised in that described crushing head uses steel plate cell structure, and crushing head is more than structure width.
CN201620222043.9U 2016-03-16 2016-03-16 A kind of plug in construction barrier that buries crushes workboat Active CN205707186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620222043.9U CN205707186U (en) 2016-03-16 2016-03-16 A kind of plug in construction barrier that buries crushes workboat

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620222043.9U CN205707186U (en) 2016-03-16 2016-03-16 A kind of plug in construction barrier that buries crushes workboat

Publications (1)

Publication Number Publication Date
CN205707186U true CN205707186U (en) 2016-11-23

Family

ID=57314801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620222043.9U Active CN205707186U (en) 2016-03-16 2016-03-16 A kind of plug in construction barrier that buries crushes workboat

Country Status (1)

Country Link
CN (1) CN205707186U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115305985A (en) * 2022-07-22 2022-11-08 三一重机有限公司 Breaking hammer operation control method and system and operation machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115305985A (en) * 2022-07-22 2022-11-08 三一重机有限公司 Breaking hammer operation control method and system and operation machine
CN115305985B (en) * 2022-07-22 2023-10-31 三一重机有限公司 Breaking hammer operation control method and system and operation machine

Similar Documents

Publication Publication Date Title
CN205653814U (en) Marine wind finding radar foundation structure of caisson type
CN102322069B (en) Underwater combination base of open caisson and steel pipe piles and construction method
CN102561371B (en) Steel caisson enclosure structure at island-tunnel combination part and construction method thereof
CN104196026A (en) A method for pulling out underwater steel pipe piles for temporary projects of bridges
NO343178B1 (en) Seabed base structure and method for installation of same
CN109113086A (en) A kind of steel reinforced concrete combined cofferdam construction method in deep water exposed bedrock riverbed area
CN102409613B (en) Construction method for installing steel beam of plank road built along mountain and near river
CN205707186U (en) A kind of plug in construction barrier that buries crushes workboat
CN103603364A (en) Deepwater suction-type gravity foundation and deepwater mounting device and deepwater mounting method thereof
CN104975612A (en) Novel water open caisson construction technology
CN104929116A (en) Precision pile sinking foundation structure of underwater engineering and underwater chute pile foundation structure construction method
CN109707002A (en) Large-scale water intake is accurately positioned sinking mounting device and method
CN101289860A (en) Underwater slope protection construction method for foundation ditch in water
CN106223355A (en) A kind of high bearing platform supported on piles in deep water Hold Hoop method has device and the construction method of end steel jacket box
CN103693176A (en) Caisson dock gate
CN104912093A (en) Deepwater pile foundation positioning and guiding structure and construction method
CN104164885A (en) Caisson towing method
CN203583509U (en) Deepwater suction type gravity foundation and deepwater mounting device thereof
KR101540519B1 (en) Maintenance apparatus for underwater tidal current generator
CN205822125U (en) The interim breakwater structure of packaged type
CN104099894B (en) A kind of without anchor deep-cement sheet-pile wharf
CN103556640A (en) Method for sinking vertical piles in shallow sea reclamation area
CN203977414U (en) Novel spiral stake
CN204694255U (en) A kind of square installs and measures frame
CN103758096B (en) A kind of offshore exploration platform and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant