CN202466645U - Extraction-recharge well applied to restoration work of polluted underground water on site - Google Patents

Extraction-recharge well applied to restoration work of polluted underground water on site Download PDF

Info

Publication number
CN202466645U
CN202466645U CN2012200198663U CN201220019866U CN202466645U CN 202466645 U CN202466645 U CN 202466645U CN 2012200198663 U CN2012200198663 U CN 2012200198663U CN 201220019866 U CN201220019866 U CN 201220019866U CN 202466645 U CN202466645 U CN 202466645U
Authority
CN
China
Prior art keywords
pipe
wall pipe
well
recharge
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200198663U
Other languages
Chinese (zh)
Inventor
蒋鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU CHANGHUAN ENVIRONMENT SCIENCE & TECHNOLOGY CO., LTD.
Original Assignee
CHANGZHOU ACADEMY OF ENVIRONMENTAL SCIENCE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGZHOU ACADEMY OF ENVIRONMENTAL SCIENCE filed Critical CHANGZHOU ACADEMY OF ENVIRONMENTAL SCIENCE
Priority to CN2012200198663U priority Critical patent/CN202466645U/en
Application granted granted Critical
Publication of CN202466645U publication Critical patent/CN202466645U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Filtration Of Liquid (AREA)

Abstract

The utility model discloses an extraction-recharge well applied to restoration work of polluted underground water on a site. The extraction-recharge well comprises a well casing, a filler, an extraction water outlet pipe and a recharge water inlet pipe, wherein the well casing comprises a hollow wall pipe and solid wall pipes located above and below the hollow wall pipe; the hollow wall pipe is wound with a filter screen; the filler comprises quartz sand and pottery clay; the quartz sand is filled between the hollow wall pipe and the soil as well as between the solid wall pipe below the hollow wall pipe and the soil; the pottery clay is filled between the solid wall pipe above the hollow wall pipe and the soil; the upper part of the well casing is provided with a flange; the well casing is internally provided with a water suction pump; the extraction water outlet pipe and the recharge water inlet pipe are respectively communicated with the well casing through the flange; and the water suction pump is communicated with the extraction water outlet pipe through a water pumping pipe. With the adoption of the extraction-recharge well applied to the restoration work of the polluted underground water on the site, provided by the utility model, the polluted underground water can be extracted to the ground for treatment, and clear running water can be injected the a well to supplement the underground water.

Description

A kind of extracting-recharge well that is applied to place polluted underground water reinstatement works
Technical field
The utility model relates to a kind of underground water and uses well, is specifically related to a kind of extracting-recharge well that is applied to place polluted underground water reinstatement works.
Background technology
At present, the function well that is used for the underground water reparation mainly contains two kinds of extraction well and recharge wells.Extraction well mainly be through with the underground water extracting of polluting to ground, lean on precipitation etc. to intake the supplementing water resource naturally then.Recharge water then be tap water is recharged underground, thereby the degree of reduce polluting.These single wells pollute light for some or the simple place of geologic structure also has certain effect, but the place repairing effect of complicated (heavy construction annex) is then not good near heavy contamination (chemical plant, pharmaceutical factory) or geologic structure.
The utility model content
The purpose of the utility model is to address the above problem, and a kind of extracting-recharge well that is applied to place polluted underground water reinstatement works is provided.
The technical scheme that realizes the utility model purpose is: a kind of extracting-recharge well that is applied to place polluted underground water reinstatement works comprises well casing, filler, extracting outlet pipe and recharges water inlet pipe; Said well casing is made up of with the solid wall pipe that is positioned at colored wall pipe upper and lower flower wall pipe; Said colored wall pipe is wound with filter screen outward; Said filler comprises quartz sand and potter's clay, and said quartz sand is filled out between said colored wall pipe and the soil and between the solid wall pipe and soil below the said colored wall pipe, and said potter's clay is filled out between the solid wall pipe and soil above the said colored wall pipe; Said well casing top is provided with a flange, is provided with a suction pump in the said well casing; Said extracting outlet pipe with recharge water inlet pipe and all be communicated with said well casing through said flange; Said suction pump is communicated with said extracting outlet pipe through drinking-water pipe.
Said colored wall pipe is the coating steel pipe that tube wall is provided with some equally distributed treatment holes, and the length of said colored wall pipe is 13m~17m.
Said solid wall pipe is the coating steel pipe that tube wall is not intake, and the length of the solid wall pipe of the said Hua Biguan of being positioned at top is 3m~5m; The length of the solid wall pipe of the said Hua Biguan of being positioned at below is 1m.
Said suction pump is arranged on below ground 15m~21m.
Also be connected with pressure meter on the said flange; Also be connected with sample tap on the said extracting outlet pipe.
The good effect that the utlity model has: the extracting-recharge well that is applied to place polluted underground water reinstatement works of (1) the utility model both can be handled the underground water extracting of polluting to ground; Gather the underground water sample simultaneously; Also can clean tap water be poured in the well; Replenish underground water, accelerate the phreatic replacing velocity of polluting.Be specially adapted to the place of some high pollutions, geologic structure complicacy.(2) extracting that the is applied to place polluted underground water reinstatement works-recharge well water yield of the utility model is up to 8t/h~10t/h.
Description of drawings
Fig. 1 is the structural representation of the extracting-recharge well that is applied to place polluted underground water reinstatement works of the utility model.
Fig. 2 is the A portion enlarged drawing among Fig. 1.
The specific embodiment
(embodiment 1)
See Fig. 1 and Fig. 2, the extracting-recharge well that is applied to place polluted underground water reinstatement works of present embodiment comprises well casing 1, filler 2, extracting outlet pipe 3, recharges water inlet pipe 4, filter screen 5, flange 6, suction pump 7 and pressure meter 8.
Well casing 1 is the coating steel pipe of external diameter 0.325m, internal diameter 0.314m, and it is welded with the solid wall pipe 12 that is positioned at colored wall pipe 11 upper and lowers by flower wall pipe 11.Well casing 1 is total up to 20m, and wherein spending wall pipe 11 is 15m, and the solid wall pipe 12 of Hua Biguan top is 4m, and the solid wall pipe 12 of Hua Biguan below is 1m.The tube wall of flower wall pipe 11 is provided with some equally distributed treatment holes, thereby can intake.The tube wall of solid wall pipe 12 then can not be intake.
Filler 2 comprises quartz sand 21 and potter's clay 22, and quartz sand 21 is filled out between flower wall pipe 11 and the soil 9 and between the solid wall pipe 12 and soil 9 below the Hua Biguan, can let underground water pass through the quartz sand slit like this and get in the well casing 1.Potter's clay 22 is filled out between solid wall pipe above the Hua Biguan 12 and soil 9, can prevent that like this surface water around the well head from getting in the well casing 1.
The filter screen of being made up of 3 layer of 60 purpose nylon cloth 5 is wrapped in outside the colored wall pipe 11, is used for the silt of filtering underground.
Flange 6 is welded on well casing 1 top.Recharging water inlet pipe 4 is communicated with well casing 1 through this flange 6.Extracting outlet pipe 3 is communicated with well casing 1 through this flange 6, and the sample tap 31 of a band valve 31-1 also is installed on this extracting outlet pipe 3, takes a sample when being used for the underground water periodic monitoring.Pressure meter 8 is connected on this flange 6 through a short tube.Recharge on water inlet pipe 4 and the extracting outlet pipe 3 and be separately installed with valve 4-1 and 3-1, be used for the adjustment of extracting-between recharging.
Suction pump 7 is provided with in the well casing 1, and is arranged on 18m place, below, ground (well head).This suction pump is 4 grades of deep well pumps of alloy steel composite member, and pump type is 200QJ20-54/4, and specified water yield is 20m3/h, and lift is 0.52MPa, and necessary electromotor is 5.5kW, 1 power distribution cabinet of supporting use.This suction pump 7 is communicated with extracting outlet pipe 3 through a drinking-water pipe 71.
The use of the extracting-recharge well that is applied to place polluted underground water reinstatement works of present embodiment is following:
1, extracting and sampling.
The valve 4-1 that recharges water inlet pipe 4 is closed, the valve 3-1 of extracting outlet pipe 3 is opened, open the power supply of suction pump 7 simultaneously, can extracting underground water.In addition, open the valve 31-1 of the sample tap 31 on the outlet pipe 3 that draws water, can gather the underground water sample.
2, recharge.
The valve 3-1 of extracting outlet pipe 3 is closed, the valve 4-1 that recharges water inlet pipe 4 is opened, will recharge water inlet pipe 4 and link to each other with running water pipe, tap water can pour in the well along recharging water inlet pipe 4, can directly under the condition of gravity flow, recharge.

Claims (5)

1. an extracting-recharge well that is applied to place polluted underground water reinstatement works is characterized in that: comprise well casing (1), quartz sand (21), potter's clay (22), extracting outlet pipe (3) and recharge water inlet pipe (4); Said well casing (1) is made up of Hua Biguan (11) and the solid wall pipe (12) that is positioned at Hua Biguan (11) upper and lower; The outer filter screen (5) that is wound with of said colored wall pipe (11); Said quartz sand (21) is filled out between said colored wall pipe (11) and the soil (9) and between the solid wall pipe (12) and soil (9) of said colored wall pipe below, and said potter's clay (22) is filled out between the solid wall pipe (12) and soil (9) above the said colored wall pipe;
Said well casing (1) top is provided with a flange (6), is provided with a suction pump (7) in the said well casing (1); Said extracting outlet pipe (3) and recharge water inlet pipe (4) and all be communicated with said well casing (1) through said flange (6); Said suction pump (7) is communicated with said extracting outlet pipe (3) through drinking-water pipe (71).
2. extracting-the recharge well that is applied to place polluted underground water reinstatement works according to claim 1; It is characterized in that: said colored wall pipe (11) is provided with the coating steel pipe of some equally distributed treatment holes for tube wall, and the length of said colored wall pipe (11) is 13m~17m.
3. extracting-the recharge well that is applied to place polluted underground water reinstatement works according to claim 1; It is characterized in that: the coating steel pipe that said solid wall pipe (12) is not intake for tube wall, the length of the solid wall pipe (12) of the said Hua Biguan of being positioned at top is 3m~5m; The length of the solid wall pipe (12) of the said Hua Biguan of being positioned at below is 1m.
4. extracting-the recharge well that is applied to place polluted underground water reinstatement works according to claim 1 is characterized in that: said suction pump (7) is arranged on below ground 15m~21m.
5. according to the described extracting-recharge well that is applied to place polluted underground water reinstatement works of one of claim 1 to 4, it is characterized in that: also be connected with pressure meter (8) on the said flange (6); Also be connected with sample tap (31) on the said extracting outlet pipe (3).
CN2012200198663U 2012-01-17 2012-01-17 Extraction-recharge well applied to restoration work of polluted underground water on site Expired - Fee Related CN202466645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200198663U CN202466645U (en) 2012-01-17 2012-01-17 Extraction-recharge well applied to restoration work of polluted underground water on site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200198663U CN202466645U (en) 2012-01-17 2012-01-17 Extraction-recharge well applied to restoration work of polluted underground water on site

Publications (1)

Publication Number Publication Date
CN202466645U true CN202466645U (en) 2012-10-03

Family

ID=46914813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200198663U Expired - Fee Related CN202466645U (en) 2012-01-17 2012-01-17 Extraction-recharge well applied to restoration work of polluted underground water on site

Country Status (1)

Country Link
CN (1) CN202466645U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046528A (en) * 2013-01-04 2013-04-17 天津大学 Vertical well pipe for assisting in efficiently extracting groundwater in low permeable aqueous medium in laboratory and usage method of vertical well pipe
CN107893448A (en) * 2017-11-21 2018-04-10 南京科森挤出装备有限公司 Well-digging or useless motor-pumped well filling sand recharge underground water and the method for saving water
CN108314106A (en) * 2014-12-24 2018-07-24 环境保护部南京环境科学研究所 A kind of underground water in-situ remediation method polluted by DNAPL
CN108906865A (en) * 2018-06-19 2018-11-30 绍兴市上虞众联环保有限公司 A kind of method of soil remediation
CN109047305A (en) * 2018-07-31 2018-12-21 南京格洛特环境工程股份有限公司 Chemical pollution place soil and groundwater in-situ remediation system and restorative procedure
CN109437422A (en) * 2018-12-03 2019-03-08 环境保护部环境规划院 A kind of prosthetic appliance of DNAPL contaminated site
CN109718581A (en) * 2019-01-28 2019-05-07 夏婷婷 A kind of novel extraction well
CN110344389A (en) * 2019-07-03 2019-10-18 深圳市工勘岩土集团有限公司 Tower groundwater pressure recharge equipment
CN112808757A (en) * 2020-12-29 2021-05-18 中科华鲁土壤修复工程有限公司 Group type extraction and injection integrated repair system for small-area supply-free underground water well

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046528A (en) * 2013-01-04 2013-04-17 天津大学 Vertical well pipe for assisting in efficiently extracting groundwater in low permeable aqueous medium in laboratory and usage method of vertical well pipe
CN108314106A (en) * 2014-12-24 2018-07-24 环境保护部南京环境科学研究所 A kind of underground water in-situ remediation method polluted by DNAPL
CN108314106B (en) * 2014-12-24 2020-12-29 环境保护部南京环境科学研究所 DNAPL (deoxyribonucleic acid-styrene-acrylonitrile copolymer) polluted underground water in-situ remediation method
CN107893448A (en) * 2017-11-21 2018-04-10 南京科森挤出装备有限公司 Well-digging or useless motor-pumped well filling sand recharge underground water and the method for saving water
CN108906865A (en) * 2018-06-19 2018-11-30 绍兴市上虞众联环保有限公司 A kind of method of soil remediation
CN109047305A (en) * 2018-07-31 2018-12-21 南京格洛特环境工程股份有限公司 Chemical pollution place soil and groundwater in-situ remediation system and restorative procedure
CN109437422A (en) * 2018-12-03 2019-03-08 环境保护部环境规划院 A kind of prosthetic appliance of DNAPL contaminated site
CN109437422B (en) * 2018-12-03 2023-12-29 环境保护部环境规划院 Repair equipment for DNAPL contaminated sites
CN109718581A (en) * 2019-01-28 2019-05-07 夏婷婷 A kind of novel extraction well
CN110344389A (en) * 2019-07-03 2019-10-18 深圳市工勘岩土集团有限公司 Tower groundwater pressure recharge equipment
CN112808757A (en) * 2020-12-29 2021-05-18 中科华鲁土壤修复工程有限公司 Group type extraction and injection integrated repair system for small-area supply-free underground water well

Similar Documents

Publication Publication Date Title
CN202466645U (en) Extraction-recharge well applied to restoration work of polluted underground water on site
CN205124580U (en) Irrigation system is collected with rainwater in gardens
CN202370033U (en) Collecting and utilizing system for roof rainwater filtered by high filter chamber
CN202450537U (en) Composite dewatering device of vacuum tube well
CN201321628Y (en) Pipeline layering water fetching device
CN201546730U (en) Vertical shaft provided with water conduits
CN105714863B (en) A kind of unmanned bagger and its method of work for handling industrial sludge
CN202095365U (en) Mobile irrigation equipment with functions of rolling and cleaning drip tapes
CN207794423U (en) The integrated green phytem system exterior wall tile of one kind
CN104563205A (en) Tunnel fire-fighting system employing tunnel surging water as water source
CN110980830A (en) Method for repairing underground water pollution by well digging and intercepting
CN202247921U (en) Precast dewatering well
CN206463555U (en) A kind of rainwater treatment device
CN204343383U (en) A kind of cheuch intermountain water that utilizes is as the tunnel fire protection system at water source
CN204060786U (en) Water pump suspension moving device
CN201963246U (en) Liquid collecting and flow guiding disc on top of blowout preventer
CN207073185U (en) The equipped inspection shaft for carrying mud basket
CN205667187U (en) A kind of water system being applied in Dangshan pear frost protection in early spring
CN206580591U (en) A kind of rainwater removing heavy metals apparatus and system
CN204662621U (en) A kind of concrete pump pipe cleaning tapping equipment
CN201016402Y (en) Deposition-proof uniflow valve
CN204343381U (en) A kind of Tunnel Gushing that utilizes is as the tunnel fire protection system at water source
CN208039372U (en) A kind of water storage device convenient for sand discharge
CN203308408U (en) Backwashing system of wellhead sump oil and sewage collection re-injection device
CN203701246U (en) Closed drainage system for electroplating wastewater

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANGSU CHANGHUAN ENVIRONMENTAL TECHNOLOGY CO., LT

Free format text: FORMER OWNER: CHANGZHOU ACADEMY OF ENVIRONMENTAL SCIENCE

Effective date: 20130924

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 213022 CHANGZHOU, JIANGSU PROVINCE TO: 213000 CHANGZHOU, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20130924

Address after: 213000 Jiangsu city of Changzhou province Hengshan Road New District No. 18 Jia new garden podium four side of one to two

Patentee after: JIANGSU CHANGHUAN ENVIRONMENT SCIENCE & TECHNOLOGY CO., LTD.

Address before: 213022, No. 18, Xinbei District, Jiangsu, Hengshan Road, Changzhou

Patentee before: Changzhou Academy of Environmental Science

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121003

Termination date: 20190117