CN115581986A CN202211154750.5A CN202211154750A CN115581986A CN 115581986 A CN115581986 A CN 115581986A CN 202211154750 A CN202211154750 A CN 202211154750A CN 115581986 A CN115581986 A CN 115581986A
Authority
CN
China
Prior art keywords
building construction
pipe
water
frame
drain pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202211154750.5A
Other languages
Chinese (zh)
Inventor
宋祖瑞
万建玲
宋敏
万学军
孙凤英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fengyang County Ruilong Construction Engineering Co ltd
Original Assignee
Fengyang County Ruilong Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fengyang County Ruilong Construction Engineering Co ltd filed Critical Fengyang County Ruilong Construction Engineering Co ltd
Priority to CN202211154750.5A priority Critical patent/CN115581986A/en
Publication of CN115581986A publication Critical patent/CN115581986A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • B01D47/08Spray cleaning with rotary nozzles

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Special Spraying Apparatus (AREA)

Abstract

The invention relates to the field of building construction equipment, in particular to a green civilized building construction dust settling system and a using method thereof; the green civilization building construction dust fall system includes: the base is used for supporting the whole green civilized building construction dust settling system; the mounting frame is movably mounted at the upper end of the base; the top frame is fixedly arranged at the upper end of the mounting frame; the drain pipe is fixedly arranged on the mounting frame; the horizontal pipe is communicated with the top end of the drain pipe, is installed and fixed on the top frame and is used for introducing water flow required by dust fall; the spray heads are arranged on the transverse pipe and the drain pipe simultaneously and are used for atomizing introduced water flow so as to realize atomization operation during building construction operation; the green civilized building construction dust suppression system does not need the construction worker to hold the shower nozzle when carrying out the dust suppression operation to construction building position department, consequently can accomplish the construction worker and carry out the dust suppression operation simultaneously when the construction, avoids producing a large amount of dusts in the construction worker work progress.

Description

Green civilized building construction dust settling system and application method thereof
Technical Field
The invention relates to the field of building construction equipment, in particular to a green civilized building construction dust settling system and a using method thereof.
Background
Wall grooving, cutting, painting and the like can generate a large amount of dust in the building construction process, and the dust is diffused in the air, so that the air environment can be polluted, the physical and mental health of building workers can be influenced, and the dust falling is required to be carried out in the building construction process.
In the prior art, ventilation and dust reduction are carried out at building construction positions generally in a mist spraying mode, and after the mist spraying is communicated with a flow guide pipe, an operator holds the mist spraying positions by hands to carry out dust reduction on all positions of building construction; after the dust fall is carried out for a period of time, a construction worker starts to operate, a large amount of dust is generated in the construction process of the construction worker, the dust fall is carried out next time, the dust fall can be carried out only after the construction worker is constructed for a period of time, the same worker cannot be used for simultaneously carrying out construction and dust fall, and therefore the dust fall effect at the construction position is limited.
Aiming at the problems in the prior art, the invention aims to provide a green civilized building construction dust settling system and a using method thereof.
Disclosure of Invention
The invention aims to provide a green civilized building construction dust suppression system and a using method thereof, and aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme:
a green civilization building construction dust suppression system, the green civilization building construction dust suppression system comprising:
the base is used for supporting the whole green civilized building construction dust suppression system;
the mounting frame is movably mounted at the upper end of the base and used for improving the dust falling height;
the top frame is fixedly arranged at the upper end of the mounting frame and used for transversely expanding the dust fall range;
the drain pipe is fixedly arranged on the mounting frame and is used for introducing water flow required by dust fall;
the horizontal pipe is communicated with the top end of the drain pipe, is installed and fixed on the top frame and is used for introducing water flow required by dust fall; and
the shower nozzle sets up on violently managing and on the drain pipe simultaneously for carry out the atomizing to the rivers that let in, atomizing operation when realizing the construction operation
As a further scheme of the invention: further comprising: the motor is arranged in the base and used for providing power for rotating the rotating shaft to adjust the direction of the spray head; the two sides of the fixing frame are fixedly arranged on the mounting frame or the top frame through bolts; the locking device is used for locking and fixing the horizontal pipe arranged on the top frame or the drain pipe arranged on the mounting frame.
As a further scheme of the invention: a slot is formed in one side of the base, and a cushion block is movably arranged in the slot.
As a further scheme of the invention: the other end of the base is fixedly provided with a mounting seat, a backing plate and a water tank are respectively arranged on the mounting seat from left to right, a water pump is fixedly arranged on the backing plate, and the upper end of the water tank is provided with a feeding pipe and a water inlet pipe; one end of the water inlet pipe extends into the water tank, and the other end of the water inlet pipe is communicated with the inlet end of the water pump; the discharge end of the water pump is communicated with a drain pipe.
As a further scheme of the invention: the shower nozzle includes atomizing frame and connecting pipe, the filtration pore has been seted up to connecting pipe bottom surface, and connecting pipe upper end outside surface is the thread groove, and the connecting pipe top is equipped with the end, and the end both sides and atomizing frame welded fastening, the atomizing frame correspond the position department installation at the export of end and are fixed with the dog-ear.
The use method of the green civilized building construction dust suppression system comprises the following steps:
1. starting a water pump, sucking a water source in a water tank by the water pump through a water inlet pipe and conveying the water source into a drain pipe, wherein the water source reaches the position of a transverse pipe along the inside of the drain pipe and is finally atomized and sprayed out through spray heads arranged on the transverse pipe and the drain pipe so as to reduce dust at the building construction position;
2. at the in-process of shower nozzle to building construction position department atomizing dust fall, can start base internally mounted's motor, the motor operation drives the mounting bracket of installation in the pivot and rotates, and the atomizing direction of adjustment shower nozzle enlarges the atomizing scope of shower nozzle.
Compared with the prior art, the invention has the beneficial effects that:
when the green civilized building construction dust-settling system is used for performing dust-settling operation on a construction building position, a construction worker does not need to hold a spray head, so that the construction worker can perform dust-settling operation simultaneously during construction, and a large amount of dust is prevented from being generated in the construction process of the construction worker;
moreover, the arranged spray heads are longitudinally and transversely arranged, so that dust falling operation in different ranges can be simultaneously carried out at the building construction position; in addition, the mounting rack provided with the spray head can be adjusted within an angle range through the arranged rotating shaft, so that the dust falling operation can be carried out in multiple directions;
more importantly, the shower nozzle and the honeycomb duct that set up are dismantled simple to operate, and the shower nozzle can also filter the diffusion operation behind the foreign particles of aquatic moreover.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention.
Fig. 1 is a schematic structural diagram of a green civilized building construction dust suppression system according to an embodiment of the present invention.
Fig. 2 is a schematic structural diagram of a spray head of a green civilized building construction dust suppression system according to an embodiment of the present invention.
In the figure: 1-cushion block, 2-slot, 3-base, 4-mounting seat, 5-backing plate, 6-water tank, 7-injection pipe, 8-water inlet pipe, 9-water pump, 10-water outlet pipe, 11-rotating shaft, 12-mounting frame, 13-bolt, 14-fixing frame, 15-spray head, 16-top frame, 17-horizontal pipe, 18-atomizing frame, 19-baffle, 20-end, 21-thread groove, 22-filtering hole and 23-connecting pipe.
Detailed Description
In order to make the technical problems, technical solutions and advantageous effects to be solved by the present invention more clearly apparent, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Examples
Referring to fig. 1, in an embodiment of the present invention, a green civilization building construction dust settling system includes:
the base 3 is used for supporting the whole green civilized building construction dust settling system;
the mounting frame 12 is movably mounted at the upper end of the base 3 and used for improving the dust falling height;
the top frame 16 is fixedly arranged at the upper end of the mounting frame 12 and used for transversely expanding the dust fall range;
the drain pipe 10 is fixedly arranged on the mounting frame 12 and is used for introducing water flow required by dust fall;
the horizontal pipe 17 is communicated with the top end of the drain pipe 10, is installed and fixed on the top frame 16 and is used for introducing water flow required by dust fall;
the spray head 15 is arranged on the transverse pipe 17 and the drain pipe 10 simultaneously and is used for atomizing the introduced water flow so as to realize the atomizing operation during the building construction operation;
when the green civilized building construction dust suppression system is used, water flow is lifted along the mounting frame 12 through the water discharge pipe 10 until finally reaching the position of the top end transverse pipe 17, and finally the water flow is atomized and sprayed out through the arranged spray head 15 and is used for performing water mist dust suppression on the position of a building site; when the spray head 15 atomizes and sprays the water mist, the rotating shaft 11 can rotate, the direction of the water mist atomized and sprayed by the spray head 15 is adjusted, and the atomization range is expanded;
in an embodiment of the present invention, further comprising: the motor is arranged in the base 3 and used for providing power for rotating the rotating shaft 11 to adjust the direction of the spray head 15; the fixing frame 14 is fixedly arranged on the mounting frame 12 or the top frame 16 through bolts 13 at two sides, and penetrates through the drain pipe 10 or the transverse pipe 17 in the middle for locking and fixing the transverse pipe 17 arranged on the top frame 16 or the drain pipe 10 arranged on the mounting frame 12;
in one embodiment of the invention, a slot 2 is arranged in one side of the base 3, and a cushion block 1 is movably arranged in the slot 2; the cushion block 1 is inserted into the slot 2 formed in one side of the base 3, so that the side edge of the base 3 is supported, the stability of the whole base 3 during placement and atomization dust-settling operation is improved, and the base is not prone to toppling;
in one embodiment of the invention, the other end of the base 3 is fixedly provided with a mounting seat 4, the mounting seat 4 is respectively provided with a backing plate 5 and a water tank 6 from left to right, the backing plate 5 is fixedly provided with a water pump 9, and the upper end of the water tank 6 is provided with a pouring pipe 7 and a water inlet pipe 8; one end of the water inlet pipe 8 extends into the water tank 6, and the other end of the water inlet pipe 8 is communicated with the inlet end of the water pump 9; the discharge end of the water pump 9 is communicated with a drain pipe 10;
starting the water pump 9, wherein the water pump 9 operates to draw the water source in the water tank 6 through the water inlet pipe 8 and convey the water source to the inside of the water outlet pipe 10 for the next atomization operation; when the water pump 9 operates, the backing plate 5 arranged at the lower end of the water pump 9 has certain buffering and damping effects; in addition, after the water source in the water tank 6 is drawn to the bottom, the water source can be introduced into the water tank 6 through the arranged betting pipe 7; similarly, the installed installation seat 4 can also support one side of the base 3;
referring to fig. 2, in an embodiment of the present invention, the nozzle 15 includes an atomizing frame 18 and a connecting pipe 23, a filtering hole 22 is formed on a bottom end surface of the connecting pipe 23, a thread groove 21 is formed on an outer side surface of an upper end of the connecting pipe 23, an end 20 is disposed at a top end of the connecting pipe 23, two sides of the end 20 are welded and fixed to the atomizing frame 18, and a stopper 19 is fixedly installed at a position of the atomizing frame 18 corresponding to an outlet of the end 20;
the spray head 15 is installed with the horizontal pipe 17 or the drain pipe 10 through a thread groove 21 arranged on the surface of a connecting pipe 23, after the spray head 15 is installed inside the horizontal pipe 17 or the drain pipe 10, injected water flows to the position of the horizontal pipe 17 from the position of the drain pipe 10, finally enters the position of an end head 20 through the connecting pipe 23 arranged on the spray head 15 and is sprayed out, high-pressure water flows through the end head 20 and then impacts a baffle 19 fixedly installed on an atomization frame 18, and water mist atomization spraying is generated through secondary impact action and is used for dust fall at the building construction position; the filtering holes 22 formed in the bottom end surface of the connecting pipe 23 can filter water sources entering the connecting pipe 23, so that impurity particles in water are prevented from impacting along with the water sources, the impact on the baffle 19 caused by scraping is accelerated, and the service life of the whole spray head 15 is shortened.
The use method of the green civilized building construction dust suppression system comprises the following steps:
1. starting a water pump 9, sucking a water source in a water tank 6 by the water pump 9 through a water inlet pipe 8 and conveying the water source into a drain pipe 10, wherein the water source reaches the position of a transverse pipe 17 along the inside of the drain pipe 10, and is finally atomized and sprayed out through a spray head 15 arranged on the transverse pipe 17 and the drain pipe 10 to be used for dust fall at the building construction position;
2. at the in-process of shower nozzle 15 to building construction position department atomizing dust fall, can start the motor of 3 internally mounted of base, the motor operation drives the mounting bracket 12 of installation on the pivot 11 and rotates, adjusts the atomizing direction of shower nozzle 15, enlarges the atomizing scope of shower nozzle 15.
In the description of the present invention, unless otherwise expressly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. The utility model provides a green civilization building construction dust fall system which characterized in that, green civilization building construction dust fall system includes:
the base (3) is used for supporting the whole green civilized building construction dust settling system;
the mounting rack (12) is movably mounted at the upper end of the base (3) and used for improving the dust falling height;
the top frame (16) is fixedly arranged at the upper end of the mounting frame (12) and is used for transversely expanding the dust fall range;
the drain pipe (10) is fixedly arranged on the mounting frame (12) and is used for introducing water flow required by dust fall;
the transverse pipe (17) is communicated with the top end of the drain pipe (10), is fixedly arranged on the top frame (16), and is used for introducing water flow required by dust fall; and
and the spray head (15) is arranged on the transverse pipe (17) and the drain pipe (10) and is used for atomizing the introduced water flow so as to realize atomization operation during building construction operation.
2. The green civilization building construction dust fall system of claim 1, characterized in that: further comprising:
the motor is arranged in the base (3) and used for providing power for rotating the rotating shaft (11) to adjust the direction of the spray head (15); and
the two sides of the fixed frame (14) are fixedly arranged on the mounting frame (12) or the top frame (16) through bolts (13); used for locking and fixing the horizontal pipe (17) arranged on the top frame (16) or the drain pipe (10) arranged on the mounting frame (12).
3. The green civilization building construction dust fall system of claim 2, characterized in that: a slot (2) is formed in one side of the base (3), and a cushion block (1) is movably mounted in the slot (2).
4. The green civilization building construction dust fall system of claim 3, characterized in that: the other end of the base (3) is fixedly provided with a mounting seat (4), a backing plate (5) and a water tank (6) are respectively arranged on the mounting seat (4) from left to right, a water pump (9) is fixedly arranged on the backing plate (5), and the upper end of the water tank (6) is provided with a feeding pipe (7) and a water inlet pipe (8); one end of the water inlet pipe (8) extends into the water tank (6), and the other end of the water inlet pipe (8) is communicated with the inlet end of the water pump (9); the discharge end of the water pump (9) is communicated with a drain pipe (10).
5. The green civilization building construction dust fall system of claim 1, characterized in that: shower nozzle (15) are including atomizing frame (18) and connecting pipe (23), filtration pore (22) have been seted up to connecting pipe (23) bottom surface, and connecting pipe (23) upper end outside surface is thread groove (21), and connecting pipe (23) top is equipped with end (20), and end (20) both sides and atomizing frame (18) welded fastening, and atomizing frame (18) correspond the position department installation and are fixed with fender head (19) in the export of end (20).
6. A use method of the green civilized building construction dust suppression system as set forth in any one of claims 1-5, characterized by comprising the steps of:
1. starting a water pump (9), drawing a water source in a water tank (6) by the water pump (9) through a water inlet pipe (8) and conveying the water source to the inside of a drain pipe (10), enabling the water source to reach the position of a transverse pipe (17) along the inside of the drain pipe (10), and finally spraying the water source through atomization of a spray head (15) arranged on the transverse pipe (17) and the drain pipe (10) for dust fall at the building construction position;
2. in the process of atomizing and dedusting the building construction position by the sprayer (15), the motor arranged inside the base (3) can be started, the motor runs to drive the mounting frame (12) arranged on the rotating shaft (11) to rotate, the atomizing direction of the sprayer (15) is adjusted, and the atomizing range of the sprayer (15) is enlarged.
CN202211154750.5A 2022-09-20 2022-09-20 Green civilized building construction dust settling system and application method thereof Withdrawn CN115581986A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211154750.5A CN115581986A (en) 2022-09-20 2022-09-20 Green civilized building construction dust settling system and application method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211154750.5A CN115581986A (en) 2022-09-20 2022-09-20 Green civilized building construction dust settling system and application method thereof

Publications (1)

Publication Number Publication Date
CN115581986A true CN115581986A (en) 2023-01-10

Family

ID=84773147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211154750.5A Withdrawn CN115581986A (en) 2022-09-20 2022-09-20 Green civilized building construction dust settling system and application method thereof

Country Status (1)

Country Link
CN (1) CN115581986A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117322799A (en) * 2023-11-07 2024-01-02 山东航天电子技术研究所 Environment-friendly decoration dust fall device based on visual transmission

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117322799A (en) * 2023-11-07 2024-01-02 山东航天电子技术研究所 Environment-friendly decoration dust fall device based on visual transmission
CN117322799B (en) * 2023-11-07 2024-04-09 山东航天电子技术研究所 Environment-friendly decoration dust fall device based on visual transmission

Similar Documents

Publication Publication Date Title
CN115581986A (en) Green civilized building construction dust settling system and application method thereof
CN110585836B (en) Sanding and dust removing integrated machine
CN220003446U (en) Dust removal and noise reduction device for building construction
CN219253018U (en) Water mist purifying spray booth
CN110812992A (en) Green is water spray dust collecting equipment for construction
CN211275114U (en) Panel paint spraying apparatus is used to building engineering fitment
CN114151083B (en) Air-compressing and low-pressure water-spraying air-water curtain dust settling device of coal mining machine
CN211725130U (en) Spraying dust-settling device
CN212762619U (en) Ceramic tile edging chamfer apparatus for producing
CN206844034U (en) A kind of civil engineering depositing dust spray system
CN209885485U (en) Novel tower crane sprays device
CN210753391U (en) Paint gas recovery and purification device for paint spray booth
CN214416739U (en) High-flow water mist injection device for tracked vehicle
CN213377391U (en) Environment-friendly spraying device is used in bamboo furniture processing
CN213468277U (en) Gas-liquid mixing negative pressure aeration nozzle
CN215916822U (en) Dustproof sprinkler that uses of construction
CN220499584U (en) Dustproof structure of marble cutter
CN216878464U (en) Fountain environmental protection dust remover
CN220197370U (en) Rotary micro-nano abrasive jetting device
CN220633561U (en) Water spraying device for building engineering
CN214437523U (en) Dust removal spray set for construction safety engineering
CN221359153U (en) Green dust collector
CN218653693U (en) Dust falling device for stirring building
CN212492109U (en) Dust fall flow tube for building construction
CN214403515U (en) Well cementation cement truck and dust collector thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20230110