CN114704085A - Construction method of through pipe reserved hole on cast-in-place concrete floor plate - Google Patents

Construction method of through pipe reserved hole on cast-in-place concrete floor plate Download PDF

Info

Publication number
CN114704085A
CN114704085A CN202210467708.2A CN202210467708A CN114704085A CN 114704085 A CN114704085 A CN 114704085A CN 202210467708 A CN202210467708 A CN 202210467708A CN 114704085 A CN114704085 A CN 114704085A
Authority
CN
China
Prior art keywords
pvc
inner sleeve
sleeve
plate
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210467708.2A
Other languages
Chinese (zh)
Inventor
宁志伟
张菊萍
王魁
白洋
王虹
肖文斌
崔凌升
王慧兵
胡晓洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Sanjian Group Co Ltd
Original Assignee
Shanxi Sanjian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Sanjian Group Co Ltd filed Critical Shanxi Sanjian Group Co Ltd
Priority to CN202210467708.2A priority Critical patent/CN114704085A/en
Publication of CN114704085A publication Critical patent/CN114704085A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/063Re-usable forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a construction method of a through pipe reserved hole on a cast-in-place concrete floor plate, which solves the problem of how to finish forming the through pipe reserved hole on the cast-in-place concrete floor plate with high quality; the sleeved double-layer PVC pipe is used for replacing a traditional steel sleeve, the side wall of each PVC short pipe is cut to obtain a PVC short pipe with an opening, and the two PVC short pipes are sleeved together to achieve the effect that the inside of the sleeve is sealed; fixing the PVC sleeve on a floor slab pouring bottom template through a support frame formed by combining a lead screw and a wood slab; and pouring concrete of the floor plate, after the poured concrete is solidified, removing the screw template support frame in the sleeve, inserting the pointed cone into the elongated opening on the inner sleeve, prying the inner sleeve inwards, taking out the inner sleeve, and taking out the outer sleeve by the same method, thereby obtaining the high-quality formed through-pipe reserved hole.

Description

Construction method of through pipe reserved hole on cast-in-situ concrete floor plate
Technical Field
The invention relates to a cast-in-place concrete floor slab, in particular to a pouring template system with a reserved through hole on the cast-in-place concrete floor slab and a construction method thereof.
Background
In the construction of the main structure of a cast-in-place concrete building, according to the functional requirements of water supply and drainage, heating subsection engineering and ventilation and air conditioning subsection engineering of the building, pipe penetrating holes with small apertures penetrating through a floor slab need to be reserved in a poured concrete floor slab, and vertical pipes such as a water supply and drainage pipe, a heating water pipe and an air conditioning pipe penetrate through the holes; the traditional method for reserving the through pipe holes comprises the following steps: before pouring floor slab concrete, according to the diameter of the stand pipe and the position in the drawing, arranging and fixing a steel sleeve at the corresponding position of the reserved hole on the concrete pouring bottom template of the floor slab, wherein the length of the steel sleeve is about 100 mm longer than the thickness of the poured floor slab; in on-site actual operation, the problem that the embedded steel sleeve is difficult to pull out often exists, and in the pipe pulling operation, the reserved hole is easily damaged locally, and the later repair is needed.
Disclosure of Invention
A construction method of a through pipe reserved hole on a cast-in-place concrete floor slab solves the technical problem of how to finish forming the through pipe reserved hole on the cast-in-place concrete floor slab in a high-quality manner.
The invention solves the technical problems by the following technical scheme:
the general concept of the invention is: the sleeved double-layer PVC pipe replaces a traditional steel sleeve, the side wall of each PVC short pipe is cut along the central axis direction of the short pipe to obtain a PVC short pipe with an opening, the two PVC short pipes are sleeved together, and the long strip-shaped openings cut on the side walls of the two sleeved PVC short pipes are separated by 180 radians to achieve the effect of sealing in the sleeve; fixing the PVC sleeve on a floor slab pouring bottom template through a support frame formed by combining a lead screw and a wood slab; and pouring the concrete of the floor slab, after the poured concrete is solidified, removing the screw template support frame in the sleeve, inserting the pointed cone into the elongated opening on the inner sleeve, prying the inner sleeve inwards, taking out the inner sleeve, and taking out the outer sleeve by the same method, so that a high-quality formed through pipe reserved hole is obtained, and the hole is communicated with the floor slab bottom template after being finally removed.
A cast-in-place concrete floor board is perforated and reserved with a hole and is provided with a bottom template, a PVC outer sleeve and a PVC inner sleeve, wherein the side wall of the PVC outer sleeve is provided with a strip-shaped opening of the outer sleeve along the central axis direction of the pipe; an inner sleeve long-strip-shaped opening is formed in the PVC inner sleeve along the central axis direction of the pipe; the PVC inner sleeve is sleeved in the PVC outer sleeve, and the strip-shaped opening of the outer sleeve and the strip-shaped opening of the inner sleeve are arranged in a staggered manner; on the poling reservation hole position on the bottom die plate top surface is pour to the floor board, the spiro union has circular bed plate, face center department on the top of circular bed plate, the fixed lead screw that is provided with, the interior sheathed tube lower port of PVC outer tube and PVC together, after the circular bed plate of embedding, the apical grafting is on the bottom die plate is pour to the floor board, on the interior sheathed tube last port of PVC outer tube and PVC together, be provided with square apron, center department at square apron is provided with the lead screw and passes the through-hole, the upper end of lead screw is passed the lead screw and is passed behind the through-hole and be in the same place with the screw nut spiro union.
The long-strip-shaped opening of the outer sleeve and the long-strip-shaped opening of the inner sleeve are arranged at intervals of 180 degrees in radian; a round embedded plate is fixedly arranged on the lower bottom surface of the square cover plate and embedded into the upper port of the PVC inner sleeve.
The circular base plate is connected to the floor slab pouring bottom formwork through screws.
A construction method for a through pipe reserved hole on a cast-in-place concrete floor plate comprises the steps of pouring a bottom template, a PVC outer sleeve, a PVC inner sleeve, a circular base plate and a lead screw on the floor plate; the method is characterized by comprising the following steps:
firstly, selecting a PVC pipe with the diameter being the same as that of a reserved hole according to the diameter of the reserved hole on a floor plate, cutting the selected PVC pipe into two short pipes with equal length according to the thickness of the floor plate, namely a PVC outer sleeve and a PVC inner sleeve, wherein the length of the PVC outer sleeve is equal to the thickness of the floor plate plus 100 mm, cutting the PVC outer sleeve on the side wall of the PVC outer sleeve along the central axis direction of the pipe to form a strip-shaped opening of the outer sleeve, and cutting the PVC inner sleeve along the central axis direction of the pipe to form a strip-shaped opening of the inner sleeve; sleeving a PVC outer sleeve and a PVC inner sleeve together, and arranging the long-strip-shaped opening of the outer sleeve and the long-strip-shaped opening of the inner sleeve at an interval of 180-degree radian;
secondly, manufacturing a circular base plate with the diameter equal to the aperture of the PVC inner sleeve, and fixedly connecting a lead screw at the center of the circular base plate along the vertical direction, wherein the length of the lead screw is greater than that of the PVC inner sleeve; manufacturing a square cover plate, wherein the side length of the square cover plate is larger than the diameter of the PVC outer sleeve, and a lead screw penetrating through hole is formed in the center of the square cover plate;
thirdly, fixedly connecting a circular base plate with a lead screw to a position of a reserved hole on the top end face of a floor plate pouring bottom template through a screw, embedding a lower port of the PVC outer sleeve and a lower port of the PVC inner sleeve which are sleeved together into the circular base plate, abutting the circular base plate against the floor plate pouring bottom template, penetrating a square cover plate on the lead screw through a through hole through the lead screw, covering the square cover plate on an upper port of the PVC outer sleeve and the PVC inner sleeve which are sleeved together, screwing a screw nut on the upper end of the lead screw, abutting and fixing the square cover plate on the upper port of the PVC outer sleeve and the PVC inner sleeve which are sleeved together through the screw nut, fixing the PVC outer sleeve and the PVC inner sleeve which are sleeved together on the floor plate pouring bottom template, and sealing the inner cavity of the PVC outer sleeve and the PVC inner sleeve;
fourthly, pouring floor slab concrete;
fifthly, after the concrete of the poured floor plate is solidified, rotating and detaching the screw rod nut, removing the square cover plate, detaching the fixed connecting screw on the circular base plate, and upwards drawing out the screw rod and the circular base plate;
and sixthly, prying the sleeved PVC inner sleeves by using an awl, taking out the sleeved PVC inner sleeves from the holes, prying the PVC outer sleeves bonded with the concrete by using the awl, and taking out the PVC outer sleeves from the holes to obtain the high-quality formed through-pipe reserved holes.
A round embedded plate is fixedly arranged on the lower bottom surface of the square cover plate, the round embedded plate is embedded in an upper port of the PVC inner sleeve, and a lead screw penetrating through hole is arranged at the center of the round embedded plate; and after the floor plate is dismantled and the bottom formwork is poured, the through pipe reserved hole is communicated.
By adopting the construction method, the quality of the through pipe reserved holes on the obtained floor plate is high, the concrete pouring template at the holes is simple and easy to disassemble, and the integrity of the through pipe holes is protected to the maximum extent; the template system of the holes is low in cost, the template fixing system ensures the stability of the template, and the template and the fixed construction can be reused.
Drawings
FIG. 1 is a schematic structural view of a tube-through preformed hole casting formwork system of the present invention;
FIG. 2 is a schematic structural diagram of the sleeved PVC outer sleeve 5 and PVC inner sleeve 7 of the present invention;
fig. 3 is a schematic structural view of the circular base plate 2 and the lead screw 4 of the present invention.
Detailed Description
The invention is described in detail below with reference to the accompanying drawings:
a cast-in-place concrete floor board is worn to manage and is reserved pouring template system of the hole on the floor board, including floor board pour bottom form 1, PVC outer thimble 5 and PVC inner thimble 7, on the sidewall of PVC outer thimble 5, along the central axis direction of the tube, there are rectangular openings 6 of outer thimble; an inner sleeve strip-shaped opening 8 is formed in the PVC inner sleeve 7 along the central axis direction of the pipe; the PVC inner sleeve 7 is sleeved in the PVC outer sleeve 5, and the long-strip-shaped opening 6 of the outer sleeve and the long-strip-shaped opening 8 of the inner sleeve are arranged in a staggered manner; on the poling reservation hole position on the floor board pouring die block board 1 top surface, the spiro union has circular bed plate 2, in the top of circular bed plate 2 face center department, the fixed lead screw 4 that is provided with, the lower port of sleeve pipe 7 in PVC outer tube 5 and the PVC that cup joints together, after embedding circular bed plate 2, the butt connects on floor board pouring die block board 1, on the last port of sleeve pipe 7 in PVC outer tube 5 and the PVC that cup joints together, be provided with square apron 9, it passes the through-hole to be provided with the lead screw in the center department of square apron 9, the upper end of lead screw 4 passes the lead screw and passes behind the through-hole with lead screw nut 11 spiro union together.
The long-strip-shaped opening 6 of the outer sleeve and the long-strip-shaped opening 8 of the inner sleeve are arranged at intervals of 180 degrees in radian; on the lower bottom surface of the square cover plate 9, a circular embedded plate 10 is fixedly arranged, and the circular embedded plate 10 is embedded in the upper port of the PVC inner sleeve 7.
The round base plate 2 is connected to the floor plate pouring bottom formwork 1 through screws 3.
A construction method for a through pipe reserved hole on a cast-in-place concrete floor plate comprises the steps of pouring a bottom template 1 on the floor plate, a PVC outer sleeve 5, a PVC inner sleeve 7, a circular base plate 2 and a screw rod 4; the method is characterized by comprising the following steps:
firstly, selecting a PVC pipe with the diameter same as that of a reserved hole according to the diameter of the reserved hole on a floor plate, cutting the selected PVC pipe into two short pipes with equal length according to the thickness of the floor plate, namely a PVC outer sleeve 5 and a PVC inner sleeve 7, wherein the length of the PVC outer sleeve 5 is equal to the thickness of the floor plate and is 100 mm, cutting the PVC outer sleeve 5 on the side wall of the PVC outer sleeve 5 along the central axis direction of the pipe to form an outer sleeve strip-shaped opening 6, and cutting the PVC inner sleeve 7 along the central axis direction of the pipe to form an inner sleeve strip-shaped opening 8; sleeving a PVC outer sleeve 5 and a PVC inner sleeve 7 together, and arranging the long-strip-shaped opening 6 of the outer sleeve and the long-strip-shaped opening 8 of the inner sleeve at an interval of 180 degrees in radian;
secondly, manufacturing a circular base plate 2 with the diameter equal to the aperture of the PVC inner sleeve 7, fixedly connecting a lead screw 4 at the center of the circular base plate 2 along the vertical direction, wherein the length of the lead screw 4 is greater than that of the PVC inner sleeve 7; manufacturing a square cover plate 9, wherein the side length of the square cover plate 9 is larger than the diameter of the PVC outer sleeve 5, and a lead screw penetrating through hole is formed in the center of the square cover plate 9;
thirdly, fixedly connecting a circular base plate 2 with a screw rod 4 to a position of a reserved hole on the top end surface of a floor plate pouring bottom template 1 through a screw 3, embedding lower ports of a PVC outer sleeve 5 and a PVC inner sleeve 7 which are sleeved together into the circular base plate 2, the top is connected with the floor plate pouring bottom template 1, the square cover plate 9 is connected with the screw rod 4 through the screw rod through the through hole, and the square cover plate 9 is covered and connected on the upper end ports of the PVC outer sleeve 5 and the PVC inner sleeve 7 which are sleeved together, the upper end of the screw rod 4 is screwed with a screw rod nut 11, and the square cover plate 9 is fixedly connected with the upper ports of the PVC outer sleeve 5 and the PVC inner sleeve 7 which are sleeved together in a propping way through the screw rod nut 11, thus fixing the PVC outer sleeve 5 and the PVC inner sleeve 7 which are sleeved together on the floor plate pouring bottom template 1 and sealing the inner cavity of the floor plate pouring bottom template;
fourthly, pouring floor slab concrete;
fifthly, after the concrete for pouring the floor plate is solidified, rotating and disassembling the screw nut 11, removing the square cover plate 9, disassembling the fixed connecting screw 3 on the circular base plate, and drawing out the screw rod 4 and the circular base plate 2 upwards, wherein the floor plate is only about 100 mm thick, so that an operator can easily stretch a screwdriver into a hole to disassemble the screw 3;
sixthly, prying the sleeved PVC inner sleeve 7 by using an awl, taking the sleeved PVC inner sleeve 7 out of the hole, prying the PVC outer sleeve 5 bonded with concrete by using the awl, taking the PVC outer sleeve out of the hole, and obtaining a high-quality formed through-pipe reserved hole, wherein the PVC inner sleeve 7 is easily and easily dismantled as the PVC inner sleeve 7 is provided with the inner sleeve strip-shaped opening 8, and the PVC inner sleeve 7 can be easily taken out of the hole as long as the side wall of the inner sleeve strip-shaped opening 8 on the PVC inner sleeve 7 is pried into the hole; likewise, the PVC outer sleeve 5 is also removed.
A round embedded plate 10 is fixedly arranged on the lower bottom surface of the square cover plate 9, the round embedded plate 10 is embedded in the upper port of the PVC inner sleeve 7, and a lead screw penetrating through hole is arranged at the center of the round embedded plate 10; at the moment, the circular base plate 2, the lead screw 4, the circular embedded plate 10, the square cover plate 9 and the lead screw nut 11 form a stable supporting system for the PVC outer sleeve 5 and the PVC inner sleeve 7 which are sleeved together, so that the reserved hole position can not drift when the floor concrete is poured; after the floor slab pouring bottom formwork 1 is dismantled, the through pipe reserved holes are communicated, the through pipe holes are formed in the front according to the requirements of the construction process, and the floor slab pouring bottom formwork 1 is dismantled in the back.

Claims (2)

1. A construction method for a through pipe reserved hole on a cast-in-place concrete floor plate comprises the steps of pouring a bottom template (1) on the floor plate, a PVC outer sleeve (5), a PVC inner sleeve (7), a circular base plate (2) and a lead screw (4); the method is characterized by comprising the following steps:
firstly, selecting a PVC pipe with the diameter the same as that of a reserved hole according to the diameter of the reserved hole on a floor plate, cutting the selected PVC pipe into two short pipes with equal length according to the thickness of the floor plate, namely a PVC outer sleeve (5) and a PVC inner sleeve (7), wherein the length of the PVC outer sleeve (5) is equal to the thickness of the floor plate plus 100 mm, cutting the PVC outer sleeve (5) along the central axis direction of the pipe on the side wall of the PVC outer sleeve (5) to form an outer sleeve strip-shaped opening (6), and cutting the PVC inner sleeve (7) along the central axis direction of the pipe to form an inner sleeve strip-shaped opening (8); sleeving a PVC outer sleeve (5) and a PVC inner sleeve (7) together, and arranging the long-strip-shaped opening (6) of the outer sleeve and the long-strip-shaped opening (8) of the inner sleeve at intervals of 180-degree radians;
secondly, a circular base plate (2) with the diameter equal to the aperture of the PVC inner sleeve (7) is manufactured, a lead screw (4) is fixedly connected to the center of the circular base plate (2) along the vertical direction, and the length of the lead screw (4) is greater than that of the PVC inner sleeve (7); manufacturing a square cover plate (9), wherein the side length of the square cover plate (9) is larger than the diameter of the PVC outer sleeve (5), and a lead screw penetrating through hole is formed in the center of the square cover plate (9);
thirdly, fixedly connecting a circular base plate (2) with a lead screw (4) at a reserved hole position on the top end face of a floor plate pouring bottom template (1) through a screw (3), embedding lower ports of a PVC outer sleeve (5) and a PVC inner sleeve (7) which are sleeved together on the circular base plate (2), butting against the floor plate pouring bottom template (1), penetrating a square cover plate (9) through a through hole through the lead screw to the lead screw (4), covering the square cover plate (9) on upper ports of the PVC outer sleeve (5) and the PVC inner sleeve (7) which are sleeved together, screwing an upper screw nut (11) at the upper end of the lead screw (4), butting and fixing the square cover plate (9) on upper ports of the PVC outer sleeve (5) and the PVC inner sleeve (7) which are sleeved together through the screw nut (11), and fixing the PVC inner sleeve (5) and the PVC inner sleeve (7) which are sleeved together on the floor plate pouring bottom template (1) And sealing the inner cavity of the upper cover;
fourthly, pouring floor slab concrete;
fifthly, after the concrete of the floor slab to be poured is solidified, rotating and detaching the screw rod nut (11), removing the square cover plate (9), detaching the fixed connecting screw (3) on the circular base plate, and drawing out the screw rod (4) and the circular base plate (2) upwards;
and sixthly, prying the sleeved PVC inner sleeve (7) by using an awl, taking out the sleeved PVC inner sleeve from the hole, prying the PVC outer sleeve (5) adhered with the concrete by using the awl, and taking out the PVC outer sleeve from the hole to obtain the high-quality formed perforated pipe reserved hole.
2. The construction method of the preformed hole of the pipe penetrating on the cast-in-place concrete floor plate according to the claim 1, characterized in that a round embedded plate (10) is fixedly arranged on the lower bottom surface of a square cover plate (9), the round embedded plate (10) is embedded in the upper port of a PVC inner sleeve (7), and a screw rod penetrating through hole is arranged at the center of the round embedded plate (10); after the floor plate is removed and the bottom template (1) is poured, the through pipe reserved hole is communicated.
CN202210467708.2A 2022-04-29 2022-04-29 Construction method of through pipe reserved hole on cast-in-place concrete floor plate Pending CN114704085A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210467708.2A CN114704085A (en) 2022-04-29 2022-04-29 Construction method of through pipe reserved hole on cast-in-place concrete floor plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210467708.2A CN114704085A (en) 2022-04-29 2022-04-29 Construction method of through pipe reserved hole on cast-in-place concrete floor plate

Publications (1)

Publication Number Publication Date
CN114704085A true CN114704085A (en) 2022-07-05

Family

ID=82177255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210467708.2A Pending CN114704085A (en) 2022-04-29 2022-04-29 Construction method of through pipe reserved hole on cast-in-place concrete floor plate

Country Status (1)

Country Link
CN (1) CN114704085A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264883A (en) * 2014-09-02 2015-01-07 中国建筑第八工程局有限公司 Concrete slab reserved hole structure and construction method thereof
CN105781104A (en) * 2016-05-04 2016-07-20 北京住总第三开发建设有限公司 Top plate reserved hole construction form and construction method thereof
CN205669314U (en) * 2016-05-04 2016-11-02 北京住总第三开发建设有限公司 A kind of top board preformed hole construction mould
CN106677529A (en) * 2016-12-20 2017-05-17 北京首钢建设集团有限公司 Structure and construction method of reserved hole PVC sleeve mould
CN109680940A (en) * 2019-02-01 2019-04-26 山西三建集团有限公司 Preserved pipeline passes through the pre-embedded device and built-in process in hole in floor concrete casting
CN209924437U (en) * 2019-02-26 2020-01-10 中国二冶集团有限公司 Novel detachable die for reserving holes
CN212224626U (en) * 2020-05-07 2020-12-25 四川省第六建筑有限公司 Mould for reserving hole on concrete member
CN112576031A (en) * 2020-11-30 2021-03-30 中国核工业第二二建设有限公司 Reusable reserved hole reservation device and construction method
CN213868925U (en) * 2020-11-10 2021-08-03 中国十九冶集团有限公司 A design mould that is used for cast-in-place floor pipeline to reserve entrance to a cave

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264883A (en) * 2014-09-02 2015-01-07 中国建筑第八工程局有限公司 Concrete slab reserved hole structure and construction method thereof
CN105781104A (en) * 2016-05-04 2016-07-20 北京住总第三开发建设有限公司 Top plate reserved hole construction form and construction method thereof
CN205669314U (en) * 2016-05-04 2016-11-02 北京住总第三开发建设有限公司 A kind of top board preformed hole construction mould
CN106677529A (en) * 2016-12-20 2017-05-17 北京首钢建设集团有限公司 Structure and construction method of reserved hole PVC sleeve mould
CN109680940A (en) * 2019-02-01 2019-04-26 山西三建集团有限公司 Preserved pipeline passes through the pre-embedded device and built-in process in hole in floor concrete casting
CN209924437U (en) * 2019-02-26 2020-01-10 中国二冶集团有限公司 Novel detachable die for reserving holes
CN212224626U (en) * 2020-05-07 2020-12-25 四川省第六建筑有限公司 Mould for reserving hole on concrete member
CN213868925U (en) * 2020-11-10 2021-08-03 中国十九冶集团有限公司 A design mould that is used for cast-in-place floor pipeline to reserve entrance to a cave
CN112576031A (en) * 2020-11-30 2021-03-30 中国核工业第二二建设有限公司 Reusable reserved hole reservation device and construction method

Similar Documents

Publication Publication Date Title
CN103821366B (en) Clear water concrete metope grooved stereo wood pattern decoration construction method
CN109208790B (en) Single-side formwork erecting construction method for arc shear wall
CN101225909B (en) Locating preburied sleeve for electrical installation project
CN102691415A (en) Bridge embedded part and method for mounting bridge using bridge embedded part
CN104594641B (en) The reinforcing bar localization method that a kind of precast wall body is installed
CN108755972B (en) Foot pad for prefabricated part and using method thereof
CN105952148A (en) Easy-to-demount inner aluminum form support system for narrow deformation joint and construction method
CN107762139A (en) Cast-in-place concrete haunch wall aluminium alloy chamfering formwork supporting adn fixing device and method
CN106760502A (en) Shear wall end cylinder construction method
CN204645727U (en) A kind of prefabricated toilet
CN209874483U (en) Detachable fixing die for reserved air conditioner hole of shear wall
CN107639723A (en) A kind of the production template and production method of concrete prefabricated wallboard with holes
CN114704085A (en) Construction method of through pipe reserved hole on cast-in-place concrete floor plate
CN110130646A (en) The Constructional Col-umn Construction method of device is poured based on tool-type intelligence compressional structure column
CN204983661U (en) Light steel is framed greatly, integrative -in -place mould support system is decorated in protection that keeps warm
CN113090025B (en) Aluminum mold matching overhanging outer frame construction method of full concrete outer wall structure
CN110905202A (en) Wall formwork perpendicularity adjusting assembly and construction method thereof
CN218952805U (en) Pouring template system for perforating pipe reserved holes on cast-in-place concrete floor slab
CN107882243B (en) A kind of cassette ceiling and construction method of concrete-filled rectangular steel tube waffle beam structure
CN109208799B (en) Construction method for early formwork removal in structure hole of waffle slab
CN202596173U (en) Embedded part for cable bridge
CN103161311B (en) Large diameter reinforced concrete pipe road crosses the construction method of abutment
CN207344800U (en) A kind of production template of concrete prefabricated wallboard with holes
CN110965766A (en) Template for construction of deformation joint of shear wall structure, construction structure and construction method
CN103726648B (en) Cast-in-situ lightweight aggregate concrete filler wall slip-form construction template system and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220705