CN109893802A CN201910191796.6A CN201910191796A CN109893802A CN 109893802 A CN109893802 A CN 109893802A CN 201910191796 A CN201910191796 A CN 201910191796A CN 109893802 A CN109893802 A CN 109893802A
Authority
CN
China
Prior art keywords
energy storage
fire
air
pipeline
shelter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910191796.6A
Other languages
Chinese (zh)
Inventor
姚冰
陈满
王青松
方敏
李勇琦
姜可尚
彭鹏
胡振恺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Branch Of Defense Technology Co Ltd Huan
Peak and Frequency Regulation Power Generation Co of China Southern Power Grid Co Ltd
University of Science and Technology of China USTC
Original Assignee
Anhui Branch Of Defense Technology Co Ltd Huan
Peak and Frequency Regulation Power Generation Co of China Southern Power Grid Co Ltd
University of Science and Technology of China USTC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Branch Of Defense Technology Co Ltd Huan, Peak and Frequency Regulation Power Generation Co of China Southern Power Grid Co Ltd, University of Science and Technology of China USTC filed Critical Anhui Branch Of Defense Technology Co Ltd Huan
Priority to CN201910191796.6A priority Critical patent/CN109893802A/en
Publication of CN109893802A publication Critical patent/CN109893802A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Secondary Cells (AREA)

Abstract

Equipped the invention discloses a kind of for electrochemical energy storage shelter heat management and the system of fire-fighting, solve existing energy storage shelter heat management system or fire-fighting system present in defect.This product includes heat management system, battery module and fire-fighting system, the heat management system includes air-cooled pipeline, refrigeration machine, complete hot heat-exchanger, gas-monitoring module and ventilation solenoid valve, and the fire-fighting system includes that extinguishing chemical discharges pipeline, extinguishing chemical spray release pipeline, extinguishing chemical conveyance conduit, fire-fighting host, flame detector, temperature monitoring module and secondary water fire-fighting connecting pipe by spraying.This product by using the components such as air-cooled pipeline, refrigeration machine, temperature monitoring module, flame detector, fire-fighting host cooperation, shortcomings and deficiencies present in its heat management system for efficiently solving existing energy storage shelter or fire-fighting system, pass through the Top-layer Design Method of integration, it ensure that the safety and reliability of energy storage shelter, reduce the operation risk and maintenance cost of energy storage shelter.

Description

It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting
Technical field
The present invention relates to energy storage shelter field, specifically a kind of system for electrochemical energy storage shelter heat management and fire-fighting Equipment.
Background technique
Energy storage mode is broadly divided into three classes at present: mechanical energy storage, Power Flow, electrochemical energy storage, in all kinds of energy storage types In, electrochemical energy storage project accounting is maximum, is emphasis research direction;In electrochemical energy storage, the item number of lithium ion battery is accounted for More maximum than, installed capacity accounting, increasing degree is also most fast, it has also become electrochemical energy storage technology with fastest developing speed.Energy storage shelter It is to use lithium ion battery as a kind of storage mode of energy-accumulating medium, is one kind of chemical energy storage.
The existing heat management system of energy storage shelter, the deficiencies such as it is uneven that there is thermo parameters methods, and refrigerating efficiency is low;It is existing Fire management system and heat management system between without effective information exchange, cannot be early stage lithium ion battery thermal runaway Pre-warning signal is provided, after thermal runaway occurs for lithium ion battery, the fire extinguishing and cooling of reliable duration, Yi Zao can not be carried out The disaster of forming apparatus or the person.In addition, there is maintenance complexity, O&M costs for existing heat management system and fire-fighting system The disadvantages of high.
Summary of the invention
It is equipped the purpose of the present invention is to provide a kind of for electrochemical energy storage shelter heat management and the system of fire-fighting, with solution Certainly the problems mentioned above in the background art.
To achieve the above object, the invention provides the following technical scheme:
It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting, including heat management system, battery module and disappear Anti- system.The heat management system includes air-cooled pipeline, refrigeration machine, complete hot heat-exchanger, gas-monitoring module and ventilation electricity Magnet valve, the fire-fighting system include that extinguishing chemical discharges pipeline by spraying, extinguishing chemical spray release pipeline, extinguishing chemical conveyance conduit, disappears Anti- host, flame detector, temperature monitoring module and secondary water fire-fighting connecting pipe.Extinguishing chemical discharges pipeline one end by spraying and passes through Pipe electromagnetic valve is connected with extinguishing chemical conveyance conduit, and the other end that extinguishing chemical discharges pipeline by spraying is connected with battery module, opens Water pump is opened pipe electromagnetic valve, can be discharged firing-fighting medium to each battery module in single battery cluster;Close pipeline Solenoid valve, can stop the release of firing-fighting medium, and battery module is provided with shutter, battery module close to the side of energy storage shelter The side of energy storage shelter wall pipeline is provided with the quick interface of air hose and sprays quick interface.
As a further solution of the present invention: air-cooled pipeline includes level-one air hose, second level air hose and three-level air hose, force one wind Pipe is connected with the air intake vent of refrigeration machine, for collecting the hot-air in energy storage shelter;Second level air hose be connected with level-one air hose and Every layer of battery module end is extended to, for transmitting the hot-air in every layer of battery module;Three-level air hose is connected with second level air hose And it is connected to battery module end, for absorbing the hot-air in battery module.
As a further solution of the present invention: gas-monitoring module being installed in level-one air hose, energy storage shelter can be monitored VOC, CO, H of interior battery module2Etc. gas concentrations;And it is mounted with the filtering module and dust filter module of toxic and harmful gas Block safeguards the interior outer space of energy storage shelter for reducing damage of the toxic and harmful gas to patrolman and equipment even is eliminated Compression ring border;Damping sheet is installed in three-level air hose, according to the distance between battery module and refrigeration machine, adjusts each damping sheet Opening and closing degree, to help to realize the pressure balance in air-cooled pipeline.
As a further solution of the present invention: refrigeration machine includes more invariable frequency compressors and 1 high-static pressure fan, according to storage Different refrigeration capacity requirements, is separately turned on wherein several compressors, achievees the effect that quasi- energy-saving and frequency-variable inside energy shelter;The height Static pressure blower provides negative pressure in air-cooled pipeline side, and as the major impetus of the air circulation in air-cooled pipeline, which has Electricity auxiliary heating function will open electricity auxiliary heating function, be conducive to energy storage when energy storage shelter is in high latitude/severe cold areas Starting of the shelter in above-mentioned environment.
The workflow for electrochemical energy storage shelter heat management and the system of fire-fighting equipment, specific steps are such as Under: complete hot heat-exchanger includes 2 complete hot heat exchangers, and it is high to be respectively connected to two lateral extent refrigeration air-conditioning unit of energy storage shelter At the level-one air hose of static pressure blower distal end, by switching ventilation solenoid valve, complete hot heat-exchanger can be made to work respectively In interior circulation pattern and outer circulation mode;
Interior circulation pattern: starting 1 Fans in complete hot heat exchanger, can be remote apart from refrigeration air-conditioning unit high-static pressure fan At the level-one air hose at end, provide positive pressure, thus compensation as pipeline it is too long caused by air loss, guarantee air-cooled pipeline in wind That presses is uniform and stable;Another 1 Fans inside complete hot heat exchanger can also be started when interior circulation pattern, utilize external cold source Hot-air in cooling pipe;
Outer circulation mode: while starting 2 Fans in complete hot heat exchanger, and open external air pipeline, it will be in cabin The high temperature extinguishing chemical steam discharge after the toxic and harmful gas of filtering or thermal runaway occur of aggregation out of my cabin, realizes air Filtering renew or prevent the temperature in shelter from assembling.
As a further solution of the present invention: the acquisition of the temperature sensors such as thermocouple not only can be used in temperature monitoring module The temperature parameter of each battery module in battery cluster, and can by with BMS module (Battery Management System, battery management system) between data communication obtain battery module temperature parameter.
As a further solution of the present invention: the work equipped for electrochemical energy storage shelter heat management and the system of fire-fighting Process further includes the booster fan of the high-static pressure fan and complete hot heat-exchanger by refrigeration air-conditioning unit, is round-the-clockly Gas circulation in cold pipeline and energy storage shelter provides power, and cold air is by battery module close to the blinds of shelter free space side Window is inhaled into battery module, then via the gap between battery module internal cell, is taken away by the modes such as convection current and conduction The waste heat that battery generates when working, then via three-level air hose, light breeze manifold combines in level-one air hose, finally again via Gao Jing The distributed cold wind of pressure fan exports, and returns inside shelter, completes circulation in first cooling by wind pipeline.During circulation, heat Management system selects refrigeration air-conditioning unit or the complete hot heat exchanger of full heat for according to the extraneous different environment temperature of energy storage shelter Group is as cold source: when the environment temperature in the energy storage shelter external world is lower than 10 DEG C, in order to be conducive to the starting of energy storage shelter, starting being made The electricity auxiliary heating function of cold air-conditioner set;It, will in order to save electric energy when the environment temperature in the energy storage shelter external world is lower than 20 DEG C Start complete hot heat-exchanger, close the compressor of refrigeration air-conditioning unit, it is empty to reduce the heat in air-cooled pipeline using external cold source Gas;When the environment temperature in the energy storage shelter external world is higher than 20 DEG C, refrigerating and air-conditioning will be respectively started according to specific refrigeration demand Several compressors of group on the basis of realizing refrigeration purpose, are reduced electric power to the maximum extent and disappeared using quasi- converter technique Consumption will open the complete hot heat-exchanger of full heat when the gas-monitoring module in air-cooled pipeline issues the gas alarms information such as VOC Outer circulation mode, realize that the breathing of air renews in shelter;When thermal runaway occurs for battery, a large amount of extinguishing chemicals of aggregation are high in pipeline When warm steam, the outer circulation mode of the complete hot heat-exchanger of full heat will be also opened, the heat in shelter is moved out out of my cabin, thus more To be effectively reduced temperature in shelter, inhibit thermal runaway diffusion.
As a further solution of the present invention: the work equipped for electrochemical energy storage shelter heat management and the system of fire-fighting Process further includes level-one modes of warning, secondary alarm mode and three-level alarm mode, as VOC, CO, H2Etc. gas concentrations be more than When preset value or when temperature monitoring module displays temperature is more than preset threshold, the level-one modes of warning of energy storage shelter will be triggered;
When flame detector detect electrical equipment initiation fire, will trigger energy storage shelter secondary alarm mode;
As VOC, CO, H2Etc. gas concentrations be more than preset value, and temperature monitoring module displays temperature be more than preset threshold when, The secondary alarm mode of energy storage shelter will be triggered;
Thermal runaway occurs for many places battery core inside energy storage shelter, and after extinguishing chemical release terminates, fire is not still had Effect containment will trigger the three-level alarm mode of energy storage shelter.
As a further solution of the present invention: the work equipped for electrochemical energy storage shelter heat management and the system of fire-fighting Process, by according to different trigger sources, takes different methods: if it is VOC, CO, H when level-one modes of warning is triggered2 Etc. gas concentrations when being more than preset concentration, the outer circulation mode of the complete hot heat-exchanger of the full heat of starting immediately realizes breath Renew with air;It is more than a certain threshold value if it is temperature monitoring module displays temperature, then indoor sound and light signal, communication will be passed through Signal informs administrator, reinforces monitoring, and machine replaces corresponding battery module in due course, eliminates danger;
When system second level on-warning mode is triggered, start the pump working in fire-fighting host immediately, opens simultaneously generation heat and lose The pipe electromagnetic valve of battery cluster bottom, pipeline is discharged by extinguishing chemical in entire battery cluster by spraying where the battery module of control Battery module carries out the atomizing crawl release of firing-fighting medium.It, also will circulation in order to comprehensively inhibit thermal runaway diffusion as far as possible The extinguishing chemical spray release pipeline for being located at cabin top is opened, immersion fire smothering is carried out to energy storage shelter inside, works as fire extinguishing The steam of medium can reach good extinguishing effect when volume fraction is 4%-6% concentration.It recycles crawl for several times, releases every time If putting the firing-fighting medium of dry capacity.By recycling crawl, the long-acting inhibition of temperature in battery module can be realized, prevent re-ignition. The high temperature firing-fighting medium steam generated in battery module, via the outer circulation mode of air-cooled pipeline, discharge is out of my cabin;
When system three-level on-warning mode is triggered, the extinguishing chemical for opening whole firing-fighting mediums discharges pipeline and extinguishing chemical spray by spraying Remaining liq in fire-fighting host liquid reserve tank is all discharged, forms the submergence of firing-fighting medium steam by leaching release pipeline.If fire-fighting master Without residue in machine liquid reserve tank, then the secondary waters fire-fighting such as turn on automatically external secondary water fire-fighting connecting pipe or fire cistern connects Mouthful, pipeline and extinguishing chemical spray release pipeline are discharged by spraying to holding in shelter by the extinguishing chemical of the firing-fighting medium in shelter Continuous fire extinguishing or immersion disposition.
Compared with prior art, the beneficial effects of the present invention are:
This product design is reasonable, by using air-cooled pipeline, refrigeration machine, complete hot heat-exchanger, flame detector, fire-fighting host The cooperation of equal components, efficiently solve existing energy storage shelter heat management system or fire-fighting system present in defect with not Foot ensure that the safety and reliability of energy storage shelter by the Top-layer Design Method of integration, reduce the operation risk of energy storage shelter With maintenance cost.
Detailed description of the invention
Fig. 1 is the explosive view equipped for electrochemical energy storage shelter heat management and the system of fire-fighting.
Fig. 2 is the structural schematic diagram for battery module in electrochemical energy storage shelter heat management and the system of fire-fighting equipment.
Fig. 3 is the explosive view for heat management system in electrochemical energy storage shelter heat management and the system of fire-fighting equipment.
Fig. 4 is the explosive view for fire-fighting system in electrochemical energy storage shelter heat management and the system of fire-fighting equipment.
Wherein: 101- flame detector, 102- extinguishing chemical spray release pipeline, hot heat-exchanger, 104-'s 103- go out entirely Fiery agent discharges pipeline by spraying, and 105- takes a breath solenoid valve, 106- gas-monitoring module, 107- air-cooled pipeline, 108- fire-fighting host, 109- pipe electromagnetic valve, 110- temperature monitoring module, 111- refrigeration machine, 112- extinguishing chemical conveyance conduit, 201- shutter, 202- The quick interface of air hose, 203- spray quick interface, 301- level-one air hose, 302- second level air hose, 303- three-level air hose, 304- damping Plate, 306- filtering module, 401- secondary water fire-fighting connecting pipe.
Specific embodiment
The technical solution of the patent is explained in further detail With reference to embodiment.
Embodiment 1
It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting, including heat management system, battery module and disappear Anti- system, the heat management system include air-cooled pipeline 107, refrigeration machine 111, complete hot heat-exchanger 103, gas-monitoring module 106 and ventilation solenoid valve 105, fire-fighting system include extinguishing chemical discharge by spraying pipeline 104, extinguishing chemical spray release pipeline 102, go out Fiery agent conveyance conduit 112, fire-fighting host 108, flame detector 101, temperature monitoring module 110 and secondary water fire-fighting connecting pipe 401, extinguishing chemical discharges 104 one end of pipeline by spraying and is connected by pipe electromagnetic valve 109 with extinguishing chemical conveyance conduit 112, extinguishing chemical The other end for discharging pipeline 104 by spraying is connected with battery module, and battery module is provided with shutter close to the side of energy storage shelter 201, battery module is provided with the quick interface 202 of air hose close to the side of bulkhead pipeline and sprays quick interface 203.Temperature monitoring The temperature parameter that the temperature sensors such as thermocouple obtain each battery module in battery cluster not only can be used in module 110, but also The temperature parameter of battery module can be obtained by the data communication between BMS module.
Air-cooled pipeline 107 includes level-one air hose 301, second level air hose 302 and three-level air hose 303, level-one air hose 301 and refrigeration The air intake vent of machine 111 is connected, for collecting the hot-air in energy storage shelter;Second level air hose 302 be connected with level-one air hose 301 and Every layer of battery module end is extended to, for transmitting the hot-air in every layer of battery module;Three-level air hose 303 and second level air hose 302 are connected and are connected to battery module end, for absorbing the hot-air in battery module.
Gas-monitoring module 106 is installed in level-one air hose 301, can monitor the VOC of battery module in energy storage shelter, CO、H2Etc. gas concentrations;And it is mounted with the filtering module 306 and dust filtering module of toxic and harmful gas, for reducing very To damage of the toxic and harmful gas to patrolman and equipment is eliminated, the inner air and outer air environment of energy storage shelter is safeguarded;Force 3 wind Damping sheet 304 is installed in pipe 303, according to the distance between battery module and refrigeration machine 111, adjusts each damping sheet 304 Opening and closing degree, to help to realize the pressure balance in air-cooled pipeline 107.
Complete hot heat-exchanger 103 includes 2 complete hot heat exchangers, is respectively connected to two lateral extent refrigeration machine of energy storage shelter At the second level air hose 302 of 111 distal ends, by switching ventilation solenoid valve 105, complete hot heat-exchanger 103 can be made to distinguish work Make in interior circulation pattern and outer circulation mode;In interior circulation pattern, start 1 complete hot heat exchanger, can freeze in distance At the second level air hose 302 of 111 distal end of machine provide positive pressure, thus compensation as second level air hose 302 it is too long caused by air loss, protect It demonstrate,proves the uniform of the wind pressure in air-cooled pipeline and stablizes;In addition, can also start in complete hot heat-exchanger 103 when recycling inside The complete hot heat exchanger of another 1 of portion utilizes the hot-air in the cooling air-cooled pipeline 107 of external cold source;In outer circulation pattern, together Shi Qidong 2 complete hot heat exchangers, and external air pipeline is opened, it will assemble in energy storage shelter by the toxic of filtering Pernicious gas perhaps thermal runaway occur after high temperature extinguishing chemical steam discharge energy storage shelter outside realize the filtering of air renew or Prevent the temperature in energy storage shelter from assembling.
Embodiment 2
It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting, including heat management system, battery module and disappear Anti- system, the heat management system include air-cooled pipeline 107, refrigeration machine 111, complete hot heat-exchanger 103, gas-monitoring module 106 and ventilation solenoid valve 105, fire-fighting system include extinguishing chemical discharge by spraying pipeline 104, extinguishing chemical spray release pipeline 102, go out Fiery agent conveyance conduit 112, fire-fighting host 108, flame detector 101, temperature monitoring module 110 and secondary water fire-fighting connecting pipe 401, extinguishing chemical discharges 104 one end of pipeline by spraying and is connected by pipe electromagnetic valve 109 with extinguishing chemical conveyance conduit 112, extinguishing chemical The other end for discharging pipeline 104 by spraying is connected with battery module, opens water pump, opens pipe electromagnetic valve 109, and fire extinguishing can be situated between Matter discharges inside each battery module to single battery cluster;Pipe electromagnetic valve 109 is closed, releasing for firing-fighting medium can be stopped It puts, battery module is provided with shutter 201 close to the side of energy storage shelter, and battery module is provided with close to the side of bulkhead pipeline The quick interface 202 of air hose and the quick interface 203 of spray.
Refrigeration machine 111 includes more invariable frequency compressors and 1 high-static pressure fan, according to refrigeration different inside energy storage shelter Amount demand is separately turned on wherein several compressors, achievees the effect that quasi- energy-saving and frequency-variable;The high-static pressure fan is in air-cooled pipeline 107 sides provide negative pressure, and as the major impetus of the air circulation in air-cooled pipeline 107, which has electricity auxiliary heating Function will open electricity auxiliary heating function when energy storage shelter is in high latitude/severe cold areas, be conducive to energy storage shelter above-mentioned Starting in environment.
Heat management system selects different refrigeration strategies according to the external temperature of energy storage shelter: when the ring in the energy storage shelter external world When border temperature is lower than 20 DEG C, in order to save electric energy, complete hot heat-exchanger 103 will be started, close the compression of refrigeration air-conditioning unit Machine reduces the hot-air in air-cooled pipeline 107 using external cold source;When the environment temperature in the energy storage shelter external world is higher than 20 DEG C, Several compressors of refrigeration air-conditioning unit will be respectively started according to specific refrigeration demand, using quasi- converter technique, realize On the basis of purpose of freezing, power consumption is reduced to the maximum extent.In particular, the environment temperature when the energy storage shelter external world is lower than 10 DEG C When, in order to be conducive to the starting of energy storage shelter, the electricity auxiliary heating function of refrigeration air-conditioning unit will be started.
The course of work of the heat management system equipped for electrochemical energy storage shelter heat management and the system of fire-fighting is such as Under: inside air-cooled pipeline 107 and energy storage shelter, by the booster fan whole day of refrigeration machine 111 and complete hot heat-exchanger 103 Wait ground and provide power for the gas circulation in air-cooled pipeline 107: cold air is by battery module close to energy storage shelter free space side Shutter 201 be inhaled into battery module, then via the gap between battery module internal cell, pass through convection current and conduction etc. Mode takes away the waste heat generated when internal cell work, then comes together in level-one via three-level air hose 303 and second level air hose 302 Air hose 301 is finally exported via the distributed cold wind of high-static pressure fan again, is returned inside energy storage shelter, and first cooling by wind pipe is completed Circulation in road 107.During circulation, heat management system selects system for according to the extraneous different environment temperature of energy storage shelter Cold 111 or complete hot heat-exchanger 103 are as cold source: when the environment temperature in the energy storage shelter external world is lower than 10 degrees Celsius, In order to be conducive to the starting of energy storage shelter, the electricity auxiliary heating function of refrigeration machine 111 will be started;When the environment temperature in the energy storage shelter external world When degree is lower than 20 degrees Celsius, in order to save electric energy, complete hot heat-exchanger 103 will be started, close the compressor of refrigeration machine 111, The hot-air in air-cooled pipeline 107 is reduced using external cold source;When the environment temperature in the energy storage shelter external world is higher than 20 degrees Celsius, Several compressors of refrigeration machine 111 will be respectively started according to specific refrigeration demand, using quasi- converter technique, be made realizing On the basis of cold purpose, power consumption is reduced to the maximum extent.
When the gas-monitoring module 106 in air-cooled pipeline 107 issues the gas alarms information such as VOC, full heat heat will be opened The outer circulation mode of group of switches 103 realizes that the breathing of air in energy storage shelter renews;
It, also will the complete hot heat exchange of unlatching when assembling a large amount of extinguishing chemical high-temperature steams in air-cooled pipeline 107 when thermal runaway occurs for battery The outer circulation mode of unit 103, the heat in energy storage shelter is moved out out of my cabin, to more effectively reduce temperature in energy storage shelter Degree inhibits thermal runaway diffusion.
The course of work of the fire-fighting system for electrochemical energy storage shelter heat management and the system of fire-fighting equipment is as follows: According to different Disaster Grades, it is divided into level-one early warning, second level warning and three-level warning;
As VOC, CO, H2Etc. gas concentrations be more than a certain concentration when or 110 displays temperature of temperature monitoring module be more than a certain threshold When value, the level-one early warning of energy storage shelter will be triggered;
When flame detector 101 detects the fire that electrical equipment causes, the second level that will trigger energy storage shelter is alerted;
As VOC, CO, H2Etc. gas concentrations be more than a certain concentration, and 110 displays temperature of temperature monitoring module be more than a certain threshold value When, also the second level for triggering energy storage shelter is alerted;
Thermal runaway occurs for many places battery core inside energy storage shelter, and after extinguishing chemical release terminates, fire is not still had Effect containment, the three-level for the system that triggers is alerted;
The level-one early warning of energy storage shelter, second level warning and three-level warning will all be uploaded to the pipe of user and supplier by network Platform.
It can be detected in energy storage shelter by gas-monitoring module 106 in air-cooled pipeline 107 or flame detector 101 Portion whether there is security risk, after determining that fire or battery generation thermal runaway occur for electrical equipment, pass through temperature monitoring mould Block 110 can quickly position the electrical equipment or battery module that the condition of a disaster occurs.
According to different early warning or warning level, implement different fire-fighting Disposal Strategies;
When level-one early warning is triggered, by according to different trigger sources, different methods is taken: if it is VOC, CO, H2Equal gas When bulk concentration is more than a certain concentration, then the outer circulation mode that will start immediately complete hot heat-exchanger 103, realizes breath Renew with air;If it is 110 displays temperature of temperature monitoring module be more than a certain threshold value, then will by indoor sound and light signal, Signal of communication informs administrator, reinforces monitoring, and machine replaces corresponding battery module in due course, eliminates danger;
When the warning of system second level is triggered, starts the pump working in fire-fighting host 108 immediately, open simultaneously generation thermal runaway Battery module where battery cluster bottom pipe electromagnetic valve 109, discharge pipeline 104 by spraying by extinguishing chemical to entire battery cluster In battery module carry out firing-fighting medium atomizing crawl release.In order to comprehensively inhibit thermal runaway diffusion as far as possible, also will It recycles and opens the extinguishing chemical spray release pipeline 102 for being located at cabin top, immersion fire smothering is carried out to energy storage shelter inside, When the steam of firing-fighting medium is in volume fraction 4%-6%, that is, it can reach good extinguishing effect.It recycles crawl for several times, releases every time If putting the firing-fighting medium of dry capacity.By recycling crawl, the long-acting inhibition of temperature in battery module can be realized, prevent re-ignition. The high temperature firing-fighting medium steam generated in battery module, via the outer circulation mode of air-cooled pipeline 107, discharge is out of my cabin;
When the warning of system three-level is triggered, the extinguishing chemical for opening whole firing-fighting mediums discharges pipeline 104 and extinguishing chemical spray by spraying Remaining liq in the liquid reserve tank of fire-fighting host 108 is all discharged, forms the submergence of firing-fighting medium steam by leaching release pipeline 102.Such as Without residue in the liquid reserve tank of fruit fire-fighting host 108, then turn on automatically external secondary water fire-fighting connecting pipe or fire cistern etc. Secondary water fire-fighting connecting pipe 401 discharges pipeline 104 and extinguishing chemical by the extinguishing chemical of the firing-fighting medium in energy storage shelter by spraying Spray release pipeline 102 to carried out in energy storage shelter continue fire extinguishing or immersion dispose.
It should be strongly noted that in the application by air-cooled pipeline 107, refrigeration machine 111, complete hot heat-exchanger 103, Gas-monitoring module 106, extinguishing chemical discharge pipeline 104, extinguishing chemical spray release pipeline 102, extinguishing chemical conveyance conduit by spraying 112, the cooperation of the components such as fire-fighting host 108, flame detector 101, temperature monitoring module 110, realizes the heat of energy storage shelter The whole design of management system and fire-fighting system, fundamentally improves the essential safety of energy storage shelter, and heat management system guarantees The uniform and temperature in temperature field;Fire-fighting system can not only deal with the fire by electrically causing, but also can deal with lithium from Sub- battery is in charge and discharge process due to the fire explosion of various unexpected factors initiation.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.No It should treat any reference in the claims as limiting the claims involved.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (9)

1.一种用于电化学储能方舱热管理和消防的***装备,其特征在于,包括热管理***、电池模块和消防***,所述热管理***包括风冷管道(107)、制冷机(111)、全热热交换机组(103)、气体监测模块(106)和换气电磁阀(105),消防***包括灭火剂喷雾释放管道(104)、灭火剂喷淋释放管道(102)、灭火剂输送管道(112)、消防主机(108)、火焰探测器(101)、温度监测模块(110)和二次水消防连接管道(401),灭火剂喷雾释放管道(104)一端通过管道电磁阀(109)与灭火剂输送管道(112)相连,灭火剂喷雾释放管道(104)的另一端与电池模块相连,电池模块靠近储能方舱的一侧设置有百叶窗(201),电池模块靠近储能方舱壁管道的一侧设置有风管快捷接口(202)和喷淋快捷接口(203)。1. A system equipment for thermal management and fire protection of electrochemical energy storage shelters, characterized in that it comprises a thermal management system, a battery module and a fire fighting system, and the thermal management system comprises an air-cooled pipe (107), a refrigerator (111), a full-heat heat exchange group (103), a gas monitoring module (106) and a ventilation solenoid valve (105), and the fire fighting system includes a fire extinguishing agent spray release pipeline (104), a fire extinguishing agent spray release pipeline (102), The fire extinguishing agent delivery pipeline (112), the fire fighting host (108), the flame detector (101), the temperature monitoring module (110) and the secondary water fire fighting connection pipeline (401), one end of the fire extinguishing agent spray release pipeline (104) is electromagnetically connected through the pipeline The valve (109) is connected to the fire extinguishing agent delivery pipeline (112), and the other end of the fire extinguishing agent spray release pipeline (104) is connected to the battery module, and the side of the battery module close to the energy storage shelter is provided with a shutter (201), and the battery module is close to One side of the energy storage square bulkhead pipeline is provided with an air duct quick interface (202) and a spray quick interface (203). 2.根据权利要求1所述的用于电化学储能方舱热管理和消防的***装备,其特征在于,所述风冷管道(107)包括一级风管(301)、二级风管(302)和三级风管(303),一级风管(301)与制冷机(111)的入风口相连,二级风管(302)与一级风管(301)相连并且延伸至每层电池模块末端,三级风管(303)与二级风管(302)相连并且连接至电池模块末端。2 . The system equipment for thermal management and fire protection of electrochemical energy storage shelters according to claim 1 , wherein the air cooling duct ( 107 ) comprises a primary air duct ( 301 ) and a secondary air duct (302) and a tertiary air duct (303), the primary air duct (301) is connected to the air inlet of the refrigerator (111), and the secondary air duct (302) is connected to the primary air duct (301) and extends to each At the end of the layer battery module, the tertiary air duct (303) is connected with the secondary air duct (302) and connected to the end of the battery module. 3.根据权利要求2所述的用于电化学储能方舱热管理和消防的***装备,其特征在于,所述一级风管(301)内安装有气体监测模块(106)、过滤模块(306)和灰尘过滤模块,三级风管(303)内安装有阻尼板(304)。3. The system equipment for thermal management and fire protection of electrochemical energy storage shelters according to claim 2, wherein a gas monitoring module (106) and a filter module are installed in the primary air duct (301). (306) and the dust filter module, a damping plate (304) is installed in the tertiary air duct (303). 4.根据权利要求1所述的用于电化学储能方舱热管理和消防的***装备,其特征在于,所述制冷机(111)包括多台定频压缩机和1台高静压风机。4. The system equipment for thermal management and fire protection of an electrochemical energy storage shelter according to claim 1, wherein the refrigerator (111) comprises a plurality of fixed-frequency compressors and a high static pressure fan . 5.根据权利要求2所述的用于电化学储能方舱热管理和消防的***装备,其特征在于,所述全热热交换机组(103)包含2台全热热交换机,全热热交换机分别与一级风管(301)相连。5. The system equipment for thermal management and fire protection of electrochemical energy storage shelters according to claim 2, characterized in that, the full-heat heat exchange group (103) comprises 2 full-heat heat exchangers. The switches are respectively connected with the primary air ducts (301). 6.一种如权利要求1-5任一所述的用于电化学储能方舱热管理和消防的***装备的工作流程,具体步骤如下:6. A work flow of the system equipment for electrochemical energy storage shelter thermal management and fire protection as described in any one of claims 1-5, the concrete steps are as follows: 内循环模式:启动全热热交换机内的1台风机,在距离制冷空调机组高静压风机远端的一级风管(301)处提供正压,保证风冷管道(107)内的风压的均匀与稳定;内循环模式时还可以启动全热交换机内部的另1台风机,利用外部冷源冷却一级风管(301)内的热空气;Internal circulation mode: start one fan in the total heat exchanger, and provide positive pressure at the primary air duct (301) at the far end of the high static pressure fan of the refrigeration and air-conditioning unit to ensure the air pressure in the air cooling duct (107). In the internal circulation mode, another fan inside the full heat exchanger can also be started, and the hot air in the primary air duct (301) can be cooled by the external cold source; 外循环模式:同时启动全热热交换机内的2台风机,并且打开对外的空气管道,将舱内聚集的经过过滤的有毒有害气体或者热失控发生后的高温灭火剂蒸汽排出舱外。External circulation mode: start 2 fans in the full heat heat exchanger at the same time, and open the external air duct to discharge the filtered toxic and harmful gases accumulated in the cabin or the high-temperature fire extinguishing agent vapor after thermal runaway occurs. 7.根据权利要求6所述的用于电化学储能方舱热管理和消防的***装备的工作流程,其特征在于,还包括冷空气由电池模块靠近方舱自由空间侧的百叶窗被吸入电池模块,随后经由电池模块内部电池之间的间隙,通过对流和传导的方式带走电池工作时产生的多余热量,再经由三级风管(303)、二级风管(302)汇集于一级风管(301),最后再经由高静压风机的分布式冷风出口返回方舱内部,完成一次风冷管道(107)内循环,在内循环的过程中,热管理***将根据储能方舱外界不同的环境温度,选用制冷空调机组或者全热热交换机组(103)作为冷源:当储能方舱外界的环境温度低于10℃时,将启动制冷空调机组的电辅助加热功能;当储能方舱外界的环境温度低于20℃时,启动全热热交换机组(103),关闭制冷空调机组的压缩机,利用外部冷源降低风冷管道内的热空气;当储能方舱外界的环境温度高于20℃时,根据具体的制冷需求分别启动制冷空调机组的若干台压缩机,当风冷管道(107)内的气体监测模块(106)发出VOC气体预警信息时,将开启全热热交换机组(103)的外循环模式,实现方舱内空气的呼吸换新;当电池发生热失控,管道内聚集大量灭火剂高温蒸汽时,也将开启全热热交换机组(103)的外循环模式,将方舱内的热量搬出方舱外。7. The work flow of the system equipment for electrochemical energy storage shelter thermal management and fire protection according to claim 6, characterized in that it also includes that cold air is drawn into the battery by the shutters on the battery module close to the free space side of the shelter The module then takes away the excess heat generated by the battery through convection and conduction through the gaps between the batteries inside the battery module, and then collects it at the first level through the tertiary air duct (303) and the secondary air duct (302). The air duct (301) is finally returned to the inside of the shelter through the distributed cold air outlet of the high static pressure fan to complete the internal circulation of the air-cooled duct (107). During the internal circulation, the thermal management system will For different ambient temperatures outside, use refrigeration and air-conditioning units or total heat exchange units (103) as the cold source: when the ambient temperature outside the energy storage shelter is lower than 10°C, the electric auxiliary heating function of the refrigeration and air-conditioning units will be activated; When the ambient temperature outside the energy storage shelter is lower than 20°C, start the full heat exchange unit (103), turn off the compressor of the refrigeration and air conditioning unit, and use the external cold source to reduce the hot air in the air-cooled pipe; when the energy storage shelter is When the outside ambient temperature is higher than 20°C, several compressors of the refrigeration and air-conditioning unit are started respectively according to the specific cooling demand. When the gas monitoring module (106) in the air-cooled pipe (107) sends out a VOC gas warning message, it will be turned on. The external circulation mode of the full heat heat exchange group (103) realizes the breathing and renewal of the air in the shelter; when the battery is thermally out of control and a large amount of fire extinguishing agent high-temperature steam accumulates in the pipeline, the full heat heat exchange group (103) will also be turned on. The external circulation mode is adopted, and the heat in the shelter is moved out of the shelter. 8.根据权利要求6所述的用于电化学储能方舱热管理和消防的***装备的工作流程,其特征在于,还包括一级预警模式、二级报警模式和三级报警模式,当VOC、CO、H2气体浓度超过预设值时或者温度监测模块(110)显示温度超过预设阈值时,将触发储能方舱的一级预警模式;8. The work flow of the system equipment for electrochemical energy storage shelter thermal management and fire protection according to claim 6, characterized in that it also includes a first-level warning mode, a second-level alarm mode and a third-level alarm mode, when When the concentration of VOC, CO, and H 2 exceeds the preset value or when the temperature monitoring module (110) shows that the temperature exceeds the preset threshold, the first-level warning mode of the energy storage shelter will be triggered; 当火焰探测器(101)探测到电气设备引发的火灾,将触发储能方舱的二级报警模式;When the flame detector (101) detects a fire caused by electrical equipment, it will trigger the secondary alarm mode of the energy storage shelter; 当VOC、CO、H2气体浓度超过预设值,并且温度监测模块(110)显示温度超过预设阈值时,也将触发储能方舱的二级报警模式;When the VOC, CO, H 2 gas concentration exceeds the preset value, and the temperature monitoring module (110) shows that the temperature exceeds the preset threshold value, the secondary alarm mode of the energy storage shelter will also be triggered; 当储能方舱内部多处电芯发生热失控,在灭火剂释放结束之后,火灾仍然没有得到有效遏制,将触发储能方舱的三级报警模式。When the thermal runaway occurs in many cells inside the energy storage shelter, after the fire extinguishing agent is released, the fire is still not effectively contained, which will trigger the three-level alarm mode of the energy storage shelter. 9.根据权利要求8所述的用于电化学储能方舱热管理和消防的***装备的工作流程,其特征在于,当一级预警模式被触发时,将根据不同的触发源,采取不同的方法:如果是VOC、CO、H2气体浓度超过预设浓度时,立即启动全热热交换机组(103)的外循环模式,实现呼吸过滤和空气换新;如果是温度监测模块(110)显示温度超过预设阈值,通过室内声光信号、通信信号告知管理员,加强监控,并且在适当时机更换相应的电池模块;9 . The work flow of the system equipment for thermal management and fire fighting of electrochemical energy storage shelters according to claim 8 , wherein when the first-level warning mode is triggered, different triggering sources will be adopted. 10 . method: if the concentration of VOC, CO, and H 2 exceeds the preset concentration, immediately start the external circulation mode of the full heat exchange group (103) to realize breathing filtration and air replacement; if it is the temperature monitoring module (110) When the displayed temperature exceeds the preset threshold, the administrator will be notified through indoor sound and light signals and communication signals to strengthen monitoring and replace the corresponding battery module at an appropriate time; 当***二级警告模式被触发时,立即启动消防主机(108)内的水泵工作,同时打开发生热失控的电池模块所在电池簇底部的管道电磁阀(109),通过灭火剂喷雾释放管道(104)对整个电池簇中的电池模块进行灭火介质的喷雾式点动释放,也将循环开启位于舱体顶端的灭火剂喷淋释放管道(102),对储能方舱内部实行浸没式窒息灭火,循环点动数次,每次释放若干容量的灭火介质,电池模块内产生的高温灭火介质蒸汽,经由风冷管道(107)的外循环模式,排出舱外;When the secondary warning mode of the system is triggered, immediately start the water pump in the fire main engine (108), and at the same time open the solenoid valve (109) of the pipeline at the bottom of the battery cluster where the thermal runaway battery module is located, and release the pipeline (104) through the fire extinguishing agent spray. ) to carry out the spray-type jog release of the fire extinguishing medium for the battery modules in the entire battery cluster, and also to open the fire extinguishing agent spray and release pipeline (102) at the top of the cabin in a cyclic manner, and to carry out immersion suffocation fire extinguishing inside the energy storage square. Circulate several times, release a certain capacity of fire extinguishing medium each time, and the high temperature fire extinguishing medium steam generated in the battery module is discharged out of the cabin through the external circulation mode of the air cooling pipe (107); 当***三级警告模式被触发时,打开全部灭火介质的灭火剂喷雾释放管道(104)和灭火剂喷淋释放管道(102),将消防主机(108)储液箱内剩余液体全部释放,形成灭火介质蒸汽浸没,如果消防主机(108)储液箱内无剩余,则自动接通外部二次水消防连接管道(401)或者消防水池的二次水消防接口,借由方舱内的灭火介质的灭火剂喷雾释放管道(104)和灭火剂喷淋释放管道(102)对方舱内进行持续灭火或者浸没式处置。When the system's three-level warning mode is triggered, open the fire extinguishing agent spray release pipeline (104) and the fire extinguishing agent spray release pipeline (102) of all fire extinguishing media, and release all the remaining liquid in the liquid storage tank of the fire fighting host (108), forming a The fire extinguishing medium is immersed in steam. If there is no remaining in the liquid storage tank of the fire fighting main engine (108), the external secondary water fire fighting connection pipeline (401) or the secondary water fire fighting interface of the fire fighting pool will be automatically connected. The fire extinguishing agent spray release pipeline (104) and the fire extinguishing agent spray release pipeline (102) are continuously extinguished or immersed in the other cabin.
CN201910191796.6A 2019-03-14 2019-03-14 It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting Pending CN109893802A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910191796.6A CN109893802A (en) 2019-03-14 2019-03-14 It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910191796.6A CN109893802A (en) 2019-03-14 2019-03-14 It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting

Publications (1)

Publication Number Publication Date
CN109893802A true CN109893802A (en) 2019-06-18

Family

ID=66952203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910191796.6A Pending CN109893802A (en) 2019-03-14 2019-03-14 It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting

Country Status (1)

Country Link
CN (1) CN109893802A (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110496334A (en) * 2019-08-14 2019-11-26 国网江苏省电力有限公司 A battery module structure of lithium iron phosphate energy storage power station protected by fine water mist fire extinguishing technology
CN110613903A (en) * 2019-08-16 2019-12-27 国网江苏省电力有限公司 Control strategy for fire extinguishing system of battery prefabricated cabin of lithium iron phosphate energy storage power station
CN110739424A (en) * 2019-10-28 2020-01-31 广州小鹏汽车科技有限公司 Thermal runaway monitoring method for battery boxes and battery boxes
CN110828935A (en) * 2019-11-14 2020-02-21 中国科学技术大学 A kind of lithium-ion battery electric vehicle safety protection method
CN111641222A (en) * 2020-05-25 2020-09-08 国网浙江省电力有限公司湖州供电公司 Safe mobile energy storage cabin for source network load storage interactive adjustment
CN112023304A (en) * 2020-11-09 2020-12-04 国网江苏省电力有限公司经济技术研究院 Energy storage power station fire-fighting system and control method thereof
CN112038728A (en) * 2020-08-28 2020-12-04 浙江南都电源动力股份有限公司 Cooling and fire-fighting hybrid system for energy storage device and control method thereof
CN112090006A (en) * 2020-11-10 2020-12-18 国网江苏省电力有限公司经济技术研究院 Fire control system and method for prefabricated cabin
CN112332013A (en) * 2019-09-26 2021-02-05 宁德时代新能源科技股份有限公司 Battery pack, vehicle and control method for relieving thermal runaway spread of battery pack
CN113332640A (en) * 2021-06-03 2021-09-03 安徽中科久安新能源有限公司 Fire suppression program-controlled injection strategy for electrochemical energy storage system
CN113386569A (en) * 2021-06-21 2021-09-14 广汽本田汽车有限公司 Thermal runaway protection device for automobile battery
CN113809441A (en) * 2021-09-16 2021-12-17 远景能源有限公司 Battery pack thermal runaway control method and device, energy storage cabinet and storage medium
CN114156587A (en) * 2022-02-10 2022-03-08 瑞诺技术(深圳)有限公司 Lithium battery pack with protection function and household energy storage system thereof
CN114335790A (en) * 2021-11-24 2022-04-12 合肥国轩高科动力能源有限公司 Energy storage battery pack-level immersed fire extinguishing system and battery thermal runaway detection method
CN114392510A (en) * 2022-01-18 2022-04-26 江苏科技大学 System and method for controlling environment of ship container
CN114392512A (en) * 2022-01-19 2022-04-26 阳光新能源开发股份有限公司 Fire-fighting system, control method thereof and energy storage power station
CN114450844A (en) * 2019-11-08 2022-05-06 株式会社Lg新能源 Battery rack and energy storage device including the same
CN114699677A (en) * 2022-03-29 2022-07-05 中国能源建设集团江苏省电力设计院有限公司 Perfluoro hexanone fire extinguishing method suitable for prefabricated cabin of lithium iron phosphate energy storage battery
CN114913660A (en) * 2022-04-27 2022-08-16 应急管理部沈阳消防研究所 Prefabricated cabin electrochemical energy storage system fire monitoring, early warning and positioning device
CN115253127A (en) * 2022-08-12 2022-11-01 龙岩市海德馨汽车有限公司 A mobile energy storage vehicle with intelligent fire protection system and fire control method thereof
EP3993140A4 (en) * 2020-03-05 2022-11-02 LG Energy Solution, Ltd. BATTERY MODULE WITH STRUCTURE WITH RAPID COOLING CAPABILITIES AND EQUIPPED ESS
CN115295917A (en) * 2022-06-29 2022-11-04 常州博瑞电力自动化设备有限公司 Immersion energy storage battery thermal management system and fire control method
CN116345012A (en) * 2023-05-26 2023-06-27 安徽中科中涣智能装备股份有限公司 Thermal safety management system for energy storage battery
CN116966461A (en) * 2023-07-31 2023-10-31 中国长江三峡集团有限公司 Prefabricated cabin energy storage power station fire protection system, prefabricated cabin energy storage power station and control method
CN118526748A (en) * 2024-07-24 2024-08-23 深圳市首航新能源股份有限公司 Energy storage fire extinguishing system and energy storage product

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103977516A (en) * 2014-05-21 2014-08-13 中国科学技术大学 Fire extinguishing system for energy storage units of lithium batteries
WO2016032101A1 (en) * 2014-08-28 2016-03-03 (주)오렌지파워 Energy storage system
CN205790288U (en) * 2016-06-22 2016-12-07 东南(福建)汽车工业有限公司 A kind of battery thermal management system of hybrid vehicle
CN106410298A (en) * 2016-11-01 2017-02-15 广东电网有限责任公司电力科学研究院 Intelligent firefighting system for lithium-ion battery energy storage unit
CN206964922U (en) * 2017-07-20 2018-02-06 烟台创为新能源科技有限公司 A kind of energy-accumulating power station early warning and fire-fighting system
CN109066015A (en) * 2018-09-21 2018-12-21 深圳市欣旺达综合能源服务有限公司 Battery container heat management system
CN109148999A (en) * 2017-12-25 2019-01-04 北京海博思创科技有限公司 Battery thermal management system and energy storage container
CN109432634A (en) * 2018-10-08 2019-03-08 中国科学技术大学 A kind of fire-fighting method of container-type lithium ion battery energy storage system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103977516A (en) * 2014-05-21 2014-08-13 中国科学技术大学 Fire extinguishing system for energy storage units of lithium batteries
WO2016032101A1 (en) * 2014-08-28 2016-03-03 (주)오렌지파워 Energy storage system
CN205790288U (en) * 2016-06-22 2016-12-07 东南(福建)汽车工业有限公司 A kind of battery thermal management system of hybrid vehicle
CN106410298A (en) * 2016-11-01 2017-02-15 广东电网有限责任公司电力科学研究院 Intelligent firefighting system for lithium-ion battery energy storage unit
CN206964922U (en) * 2017-07-20 2018-02-06 烟台创为新能源科技有限公司 A kind of energy-accumulating power station early warning and fire-fighting system
CN109148999A (en) * 2017-12-25 2019-01-04 北京海博思创科技有限公司 Battery thermal management system and energy storage container
CN109066015A (en) * 2018-09-21 2018-12-21 深圳市欣旺达综合能源服务有限公司 Battery container heat management system
CN109432634A (en) * 2018-10-08 2019-03-08 中国科学技术大学 A kind of fire-fighting method of container-type lithium ion battery energy storage system

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110496334B (en) * 2019-08-14 2024-05-17 国网江苏省电力有限公司 Lithium iron phosphate energy storage power station battery module structure protected by water mist fire extinguishing technology
CN110496334A (en) * 2019-08-14 2019-11-26 国网江苏省电力有限公司 A battery module structure of lithium iron phosphate energy storage power station protected by fine water mist fire extinguishing technology
CN110613903A (en) * 2019-08-16 2019-12-27 国网江苏省电力有限公司 Control strategy for fire extinguishing system of battery prefabricated cabin of lithium iron phosphate energy storage power station
CN112332013A (en) * 2019-09-26 2021-02-05 宁德时代新能源科技股份有限公司 Battery pack, vehicle and control method for relieving thermal runaway spread of battery pack
US11342611B2 (en) 2019-09-26 2022-05-24 Contemporary Amperex Technology Co., Limited Battery pack, vehicle and control method for alleviating thermal runaway spreading of battery pack
CN110739424A (en) * 2019-10-28 2020-01-31 广州小鹏汽车科技有限公司 Thermal runaway monitoring method for battery boxes and battery boxes
US12255303B2 (en) 2019-11-08 2025-03-18 Lg Energy Solution, Ltd. Battery rack and power storage device comprising same
CN114450844A (en) * 2019-11-08 2022-05-06 株式会社Lg新能源 Battery rack and energy storage device including the same
CN110828935B (en) * 2019-11-14 2023-04-07 中国科学技术大学 Safety protection method for lithium ion battery electric vehicle
CN110828935A (en) * 2019-11-14 2020-02-21 中国科学技术大学 A kind of lithium-ion battery electric vehicle safety protection method
EP3993140A4 (en) * 2020-03-05 2022-11-02 LG Energy Solution, Ltd. BATTERY MODULE WITH STRUCTURE WITH RAPID COOLING CAPABILITIES AND EQUIPPED ESS
US12211983B2 (en) 2020-03-05 2025-01-28 Lg Energy Solution, Ltd. Battery module having structure capable of rapid cooling, and ESS comprising same
CN111641222A (en) * 2020-05-25 2020-09-08 国网浙江省电力有限公司湖州供电公司 Safe mobile energy storage cabin for source network load storage interactive adjustment
CN112038728A (en) * 2020-08-28 2020-12-04 浙江南都电源动力股份有限公司 Cooling and fire-fighting hybrid system for energy storage device and control method thereof
CN112023304A (en) * 2020-11-09 2020-12-04 国网江苏省电力有限公司经济技术研究院 Energy storage power station fire-fighting system and control method thereof
CN112090006B (en) * 2020-11-10 2021-02-09 国网江苏省电力有限公司经济技术研究院 Fire control system and method for prefabricated cabin
CN112090006A (en) * 2020-11-10 2020-12-18 国网江苏省电力有限公司经济技术研究院 Fire control system and method for prefabricated cabin
CN113332640A (en) * 2021-06-03 2021-09-03 安徽中科久安新能源有限公司 Fire suppression program-controlled injection strategy for electrochemical energy storage system
CN113386569A (en) * 2021-06-21 2021-09-14 广汽本田汽车有限公司 Thermal runaway protection device for automobile battery
CN113809441A (en) * 2021-09-16 2021-12-17 远景能源有限公司 Battery pack thermal runaway control method and device, energy storage cabinet and storage medium
CN114335790A (en) * 2021-11-24 2022-04-12 合肥国轩高科动力能源有限公司 Energy storage battery pack-level immersed fire extinguishing system and battery thermal runaway detection method
CN114392510A (en) * 2022-01-18 2022-04-26 江苏科技大学 System and method for controlling environment of ship container
CN114392512A (en) * 2022-01-19 2022-04-26 阳光新能源开发股份有限公司 Fire-fighting system, control method thereof and energy storage power station
CN114156587B (en) * 2022-02-10 2022-04-26 瑞诺技术(深圳)有限公司 Lithium battery pack with protection function and household energy storage system thereof
CN114156587A (en) * 2022-02-10 2022-03-08 瑞诺技术(深圳)有限公司 Lithium battery pack with protection function and household energy storage system thereof
CN114699677A (en) * 2022-03-29 2022-07-05 中国能源建设集团江苏省电力设计院有限公司 Perfluoro hexanone fire extinguishing method suitable for prefabricated cabin of lithium iron phosphate energy storage battery
CN114913660B (en) * 2022-04-27 2024-03-29 应急管理部沈阳消防研究所 Prefabricated cabin electrochemical energy storage system fire monitoring, early warning and positioning device
CN114913660A (en) * 2022-04-27 2022-08-16 应急管理部沈阳消防研究所 Prefabricated cabin electrochemical energy storage system fire monitoring, early warning and positioning device
CN115295917A (en) * 2022-06-29 2022-11-04 常州博瑞电力自动化设备有限公司 Immersion energy storage battery thermal management system and fire control method
CN115253127A (en) * 2022-08-12 2022-11-01 龙岩市海德馨汽车有限公司 A mobile energy storage vehicle with intelligent fire protection system and fire control method thereof
CN116345012A (en) * 2023-05-26 2023-06-27 安徽中科中涣智能装备股份有限公司 Thermal safety management system for energy storage battery
CN116345012B (en) * 2023-05-26 2023-08-22 安徽中科中涣智能装备股份有限公司 Thermal safety management system for energy storage battery
CN116966461A (en) * 2023-07-31 2023-10-31 中国长江三峡集团有限公司 Prefabricated cabin energy storage power station fire protection system, prefabricated cabin energy storage power station and control method
CN118526748A (en) * 2024-07-24 2024-08-23 深圳市首航新能源股份有限公司 Energy storage fire extinguishing system and energy storage product

Similar Documents

Publication Publication Date Title
CN109893802A (en) It is a kind of to be equipped for electrochemical energy storage shelter heat management and the system of fire-fighting
WO2022016765A1 (en) Fire prevention and control system for lithium ion battery prefabricated container and control method therefor
CN211858718U (en) A perfluorohexanone liquid flow temperature control and fire battery compartment suitable for energy storage power stations
CN209933885U (en) A system equipment for thermal management and fire protection of electrochemical energy storage shelters
CN105703245B (en) A kind of power equipment case
CN110227224A (en) A kind of container-type lithium ion battery energy storage system sprays fire extinguisher coupled structure design
CN114053632A (en) An energy storage device and its control method
CN216820477U (en) Outdoor 5G energy-saving machine room
CN111384341A (en) A kind of lithium battery box with fireproof function and using method thereof
CN209626320U (en) The low dew point return air recirculation system of low NMP concentration
CN116864895A (en) A compact container-type battery energy storage system and fire-fighting method
WO2025055228A1 (en) Dual-protection energy storage cabinet and prevention and control method therefor
CN111132510B (en) A cabinet-type data center operating environment monitoring system and method
CN117543125A (en) Fire early warning exhaust system of energy storage battery compartment and control method
CN113708260A (en) Automatic energy storage preassembled bin formula transformer substation
CN117747999A (en) Cabinet type battery box immersed type heat management fire-fighting system and control method thereof
CN209200034U (en) Battery Packs and Vehicles
CN218414928U (en) A thermal runaway gas treatment device for lithium-ion batteries
CN114300773A (en) Automatic protection system of lithium battery energy storage cabinet
CN214332890U (en) Heat recovery solution dehumidification fresh air purification unit
CN116979581A (en) Energy storage system capable of reducing light rejection and operation method thereof
CN210744522U (en) Substation Current Transformer Secondary Moisture Drive Box
CN217062254U (en) Automatic protection system of lithium battery energy storage cabinet
CN221947220U (en) Cabinet type battery box immersion thermal management fire protection system
CN113193691A (en) Novel generator room and cooling device matched with same for use

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190618

RJ01 Rejection of invention patent application after publication