CN107761717A - The construction method of sand content in mud is controlled in filling pile construction - Google Patents

The construction method of sand content in mud is controlled in filling pile construction Download PDF

Info

Publication number
CN107761717A
CN107761717A CN201610664554.0A CN201610664554A CN107761717A CN 107761717 A CN107761717 A CN 107761717A CN 201610664554 A CN201610664554 A CN 201610664554A CN 107761717 A CN107761717 A CN 107761717A
Authority
CN
China
Prior art keywords
mud
construction
borehole cleaning
sand
filling pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610664554.0A
Other languages
Chinese (zh)
Inventor
崔松明
朱松
张智博
唐春乐
方吉
耿帆
丁明鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610664554.0A priority Critical patent/CN107761717A/en
Publication of CN107761717A publication Critical patent/CN107761717A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses the construction method that sand content in mud is controlled in a kind of filling pile construction, this method carries out measure of pile position unwrapping wire first, interim casing is installed, drill perforate, pore-forming, judge that drill bit enters rock scar, whole hole, then for the first time using mud separator and slush pump borehole cleaning after 5~7 hours, 2~3 hours of slush pump direct circulation borehole cleaning are used again and detect mud index, screwing steel bars cage, transfer steel reinforcement cage, slush pump borehole cleaning is used for the second time 1~2 hour and detect mud index, using tremie placing concrete, ultrasound examination is carried out after 7 days, complete filling pile construction.Sand content in mud meets construction requirement when this method ensure that bored concrete pile borehole cleaning, shortens the bored concrete pile borehole cleaning time, accelerates filling pile construction speed, improves filling pile construction quality, reduces construction cost.

Description

The construction method of sand content in mud is controlled in filling pile construction
Technical field
The present invention relates to the construction method that sand content in mud is controlled in a kind of filling pile construction.
Background technology
With the development of infrastructure, bored pile construction is widely used, wherein influenceing cast-in-situ bored pile matter The mud property index request more and more higher of amount.Sand content in mud refers to that the sand grains in mud more than 74um accounts for mud cumulative volume Percentage composition, the main function of mud is retaining wall, takes slag and cooling and lubricating effect, when under the high speed conditions of drilling rod, mud contains sand It is serious to slush pump, drilling rod and bit wear when rate is high, therefore provide that sand content in mud can not be more than 4%, and in drilling process Desanding purification work need to be carried out.For complicated geological soil layer, during as carried out cast-in-situ bored pile construction in peat soil layer, mud Proportion, viscosity and sand factor control it is difficult, cause the filling pile construction time greatly to extend, complete one within average 10 days or so The construction of stake, efficiency of construction is seriously reduced, improve construction cost.
For filling pile construction, traditional construction technology be measure of pile position unwrapping wire, the interim casing of installation, drilling rod perforate, into Hole, judge that drill bit enters rock scar, whole hole, then first time slush pump reacting cycle borehole cleaning 24~48 hours and detect mud index, Screwing steel bars cage is simultaneously transferred in hole, and second slush pump borehole cleaning 5~6 hours simultaneously detects mud index, is adopted after casting concrete With ultrasound examination, filling pile construction is completed.By traditional construction technique, filling pile construction pore-creating is smooth, but mud contains behind whole hole Sand coarse aggregate ratio difficulty up to standard, first time borehole cleaning overlong time is caused to reach 48 hours or so so that the single filling pile construction duration Long, filling pile construction speed is slow, has a strong impact on filling pile construction progress.According to bored concrete pile circular bit mud endless form Difference, circular bit is divided into direct circulation drilling and reverse circulation drilling.Direct circulation is that flushing liquor is sent by slush pump by drilling rod Enter bottom hole, then by bottom hole out of hole on return to ground;Reverse circulating flushing liquor is just opposite with the route of direct circulation.Bored concrete pile rushes Hit pore-forming drill and mud borehole cleaning is mainly carried out using direct circulation, the direct circulation impact holing technological operation is simple, is adapted to various soil Layer filling pile construction, enters rock and cuts that rock speed of application is fast, and filling pile construction quality is good, and construction input cost is low;Reverse circulation drilling is only Suitable for circular bit, circular bit construction input cost is very high, and the very slow rock sample sometimes of rock drilling layer can not take out, no It is adapted to construct at layer of sand, is only suitable for argillic horizon and friction-type filling pile construction.
The content of the invention
The technical problems to be solved by the invention are to provide the construction party that sand content in mud is controlled in a kind of filling pile construction Method, sand content in mud meets construction requirement when this method ensure that bored concrete pile borehole cleaning, shortens the bored concrete pile borehole cleaning time, accelerates perfusion Pile driving construction speed, filling pile construction quality is improved, reduce construction cost.
In order to solve the above technical problems, the construction method of sand content in mud is controlled in filling pile construction of the present invention including as follows Step:
Step 1: being irrigated a measure of pile position unwrapping wire according to design drawing, interim casing is installed, its position is checked simultaneously Increase fender pile;
Step 2: stake machine starts to construct, percussion drilling pore-forming technique is taken to be constructed, mud off;
Step 3: carrying out drive sampling according to speed of fulfiling hole, with reference to geological prospecting borehole data, judge to creep into soil layer type, sentence Determine drill bit and enter rock scar, it is determined that entering rock depth, whole hole is crept into according to rock depth is entered;
Step 4: carrying out first time borehole cleaning using direct circulation using mud separator and slush pump behind whole hole, while process steel Muscle cage, and sand content in mud, viscosity and proportion index are detected, 5~7 hour sand factors of borehole cleaning reach 3%, use mud again afterwards Stock pump direct circulation borehole cleaning 2~3 hours to mud balance reaches 1.15~1.2g/ml, 30~40s of viscosity, sand factor 2%, completes the Borehole cleaning;
Step 5: installing steel reinforcement cage using loop wheel machine merogenesis, steel reinforcement cage is carried out clear for the second time using slush pump direct circulation after installing Hole 1~2 hour, detection mud balance reach 1.10~1.15g/ml, 30~40s of viscosity, sand factor 2%, complete clear for the second time Hole;
Step 6: using tremie placing concrete, ultrasonic wave integrity test detection, the qualified completion of testing inspection are carried out after 7 days Filling pile construction.
Further, the direct circulation borehole cleaning irrigates mud into drilling using slush pump, by the midge of mud separator Mud in mouth suction drilling, sand grains flows out from sand export after separation, and slurries flow to sedimentation basin from overfall mouth, and slurries are after precipitation Into mud pit.
Due to controlling the construction method of sand content in mud to employ above-mentioned technical proposal, i.e. this method in filling pile construction of the present invention Measure of pile position unwrapping wire is carried out first, interim casing is installed, and drill perforate, pore-forming, judges that drill bit enters rock scar, whole hole, Ran Hou First use mud separator and slush pump borehole cleaning be after 5~7 hours, then using 2~3 hours of slush pump direct circulation borehole cleaning simultaneously Detect mud index, screwing steel bars cage transfers steel reinforcement cage, and second using slush pump borehole cleaning 1~2 hour and detects mud and refer to Mark, using tremie placing concrete, ultrasound examination is carried out after 7 days, completes filling pile construction.This method ensure that bored concrete pile is clear Sand content in mud meets construction requirement during hole, shortens the bored concrete pile borehole cleaning time, accelerates filling pile construction speed, improves bored concrete pile and applies Working medium amount, reduce construction cost.
Brief description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is borehole cleaning schematic diagram in the construction method for controlled in filling pile construction of the present invention sand content in mud.
Embodiment
Embodiment includes following step as shown in figure 1, controlling the construction method of sand content in mud in filling pile construction of the present invention Suddenly:
Step 1: being irrigated the measure of pile position unwrapping wire of stake 3 according to design drawing, interim casing is installed, its position is checked And increase fender pile;
Step 2: stake machine starts to construct, percussion drilling pore-forming technique is taken to be constructed, mud off;
Step 3: carrying out drive sampling according to speed of fulfiling hole, with reference to geological prospecting borehole data, judge to creep into soil layer type, sentence Determine drill bit and enter rock scar, it is determined that entering rock depth, whole hole is crept into according to rock depth is entered;
Step 4: carrying out first time borehole cleaning using direct circulation using mud separator 1 and slush pump 2 behind whole hole, process simultaneously Steel reinforcement cage, and sand content in mud, viscosity and proportion index are detected, 5~7 hour sand factors of borehole cleaning reach 3%, use again afterwards 2 direct circulation borehole cleaning of slush pump 2~3 hours to mud balance reaches 1.15~1.2g/ml, 30~40s of viscosity, sand factor 2%, complete Into first time borehole cleaning;
Step 5: installing steel reinforcement cage using loop wheel machine merogenesis, steel reinforcement cage is carried out clear for the second time using the direct circulation of slush pump 2 after installing Hole 1~2 hour, detection mud balance reach 1.10~1.15g/ml, 30~40s of viscosity, sand factor 2%, complete clear for the second time Hole;
Step 6: using tremie placing concrete, ultrasonic wave integrity test detection, the qualified completion of testing inspection are carried out after 7 days Bored concrete pile 3 is constructed.
Preferably, the direct circulation borehole cleaning irrigates mud into drilling using slush pump 2, by the suction of mud separator 1 Mud in mouth suction drilling is starched, sand grains flows out from sand export after separation, and slurries flow to sedimentation basin 4, slurries warp from overfall mouth 13 Enter mud pit 5 after precipitation.
This method summarizes filling pile construction experience by live research and analysis, and traditional construction technique is changed Enter, increase mud separator carries out borehole cleaning, so as to greatly shorten the reaching standard time of sand content in mud, improves borehole cleaning efficiency, adds Fast filling pile construction speed, and improve pile quality;Reclaimed simultaneously by mud purification, reduce construction cost, reduce environment Pollution;This method construction is simple is easy, and cost is relatively low, convenient and practical.

Claims (2)

1. the construction method of sand content in mud is controlled in a kind of filling pile construction, it is characterised in that this method comprises the following steps:
Step 1: being irrigated a measure of pile position unwrapping wire according to design drawing, interim casing is installed, its position is checked simultaneously Increase fender pile;
Step 2: stake machine starts to construct, percussion drilling pore-forming technique is taken to be constructed, mud off;
Step 3: carrying out drive sampling according to speed of fulfiling hole, with reference to geological prospecting borehole data, judge to creep into soil layer type, sentence Determine drill bit and enter rock scar, it is determined that entering rock depth, whole hole is crept into according to rock depth is entered;
Step 4: carrying out first time borehole cleaning using direct circulation using mud separator and slush pump behind whole hole, while process steel Muscle cage, and sand content in mud, viscosity and proportion index are detected, 5~7 hour sand factors of borehole cleaning reach 3%, use mud again afterwards Stock pump direct circulation borehole cleaning 2~3 hours to mud balance reaches 1.15~1.2g/ml, 30~40s of viscosity, sand factor 2%, completes the Borehole cleaning;
Step 5: installing steel reinforcement cage using loop wheel machine merogenesis, steel reinforcement cage is carried out clear for the second time using slush pump direct circulation after installing Hole 1~2 hour, detection mud balance reach 1.10~1.15g/ml, 30~40s of viscosity, sand factor 2%, complete clear for the second time Hole;
Step 6: using tremie placing concrete, ultrasonic wave integrity test detection, the qualified completion of testing inspection are carried out after 7 days Filling pile construction.
2. the construction method of sand content in mud is controlled in filling pile construction according to claim 1, it is characterised in that:It is described Direct circulation borehole cleaning irrigates mud into drilling using slush pump, by mud in the pulp absorbing hole suction drilling of mud separator, warp Sand grains flows out from sand export after separation, and slurries flow to sedimentation basin from overfall mouth, and slurries enter mud pit after precipitation.
CN201610664554.0A 2016-08-15 2016-08-15 The construction method of sand content in mud is controlled in filling pile construction Pending CN107761717A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610664554.0A CN107761717A (en) 2016-08-15 2016-08-15 The construction method of sand content in mud is controlled in filling pile construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610664554.0A CN107761717A (en) 2016-08-15 2016-08-15 The construction method of sand content in mud is controlled in filling pile construction

Publications (1)

Publication Number Publication Date
CN107761717A true CN107761717A (en) 2018-03-06

Family

ID=61259714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610664554.0A Pending CN107761717A (en) 2016-08-15 2016-08-15 The construction method of sand content in mud is controlled in filling pile construction

Country Status (1)

Country Link
CN (1) CN107761717A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110004992A (en) * 2019-04-19 2019-07-12 贵州省交通规划勘察设计研究院股份有限公司 It is a kind of can real-time monitoring bored pile construction device and its application method
CN110552379A (en) * 2018-05-31 2019-12-10 江苏腾达工程检测有限公司 method for measuring slurry index of cast-in-situ bored pile
CN112554173A (en) * 2020-11-16 2021-03-26 上海建工集团股份有限公司 Construction method of cast-in-place pile
CN117145410A (en) * 2023-11-01 2023-12-01 湖南路桥建设集团有限责任公司 Reverse circulation bored pile construction device and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001200537A (en) * 2000-01-21 2001-07-27 Sumitomo Osaka Cement Co Ltd Soil improving method and support pile for soil improvement
CN102704873A (en) * 2012-06-07 2012-10-03 徐守田 Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device
CN202645477U (en) * 2012-06-12 2013-01-02 甘肃路桥建设集团有限公司 Bored pile vibrating screen slag eliminating device
CN203655190U (en) * 2013-09-29 2014-06-18 深圳市工勘岩土工程有限公司 Hole cleaning equipment for cast-in-place bored pile
CN105804059A (en) * 2014-12-31 2016-07-27 上海市机械施工集团有限公司 Cast-in-situ bored pile hole-forming device and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001200537A (en) * 2000-01-21 2001-07-27 Sumitomo Osaka Cement Co Ltd Soil improving method and support pile for soil improvement
CN102704873A (en) * 2012-06-07 2012-10-03 徐守田 Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device
CN202645477U (en) * 2012-06-12 2013-01-02 甘肃路桥建设集团有限公司 Bored pile vibrating screen slag eliminating device
CN203655190U (en) * 2013-09-29 2014-06-18 深圳市工勘岩土工程有限公司 Hole cleaning equipment for cast-in-place bored pile
CN105804059A (en) * 2014-12-31 2016-07-27 上海市机械施工集团有限公司 Cast-in-situ bored pile hole-forming device and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郗宁,成水武,韩宝国: ""超长钻孔灌注桩的施工方法及质量控制"", 《公路交通科技》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110552379A (en) * 2018-05-31 2019-12-10 江苏腾达工程检测有限公司 method for measuring slurry index of cast-in-situ bored pile
CN110004992A (en) * 2019-04-19 2019-07-12 贵州省交通规划勘察设计研究院股份有限公司 It is a kind of can real-time monitoring bored pile construction device and its application method
CN112554173A (en) * 2020-11-16 2021-03-26 上海建工集团股份有限公司 Construction method of cast-in-place pile
CN117145410A (en) * 2023-11-01 2023-12-01 湖南路桥建设集团有限责任公司 Reverse circulation bored pile construction device and construction method
CN117145410B (en) * 2023-11-01 2024-02-09 湖南路桥建设集团有限责任公司 Reverse circulation bored pile construction device

Similar Documents

Publication Publication Date Title
CN100412314C (en) Process for gas collection by a well with one mouth and multiple branches drilled along coal layer
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
RU2693069C1 (en) Steel installation for core drilling and new environmentally friendly construction method, capable of replacing trench and well survey
CN107761717A (en) The construction method of sand content in mud is controlled in filling pile construction
CN102808427B (en) Composite grouting reinforcement anti-seepage treatment technology
CN106149679A (en) The construction technology of diaphram wall built by slotter
CN109630045A (en) The multi-functional full well section dynamic circulation experimental system for simulating of drilling well
CN107246007B (en) A kind of CFG of construction method
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN105443072A (en) Horizontal well oil-string casing well cementation method
CN112814737B (en) Collapse column advanced treatment method and system based on laminated multi-branch horizontal well
CN112252332A (en) Grooving construction method for underground diaphragm wall of ultra-deep shaft
CN203066913U (en) Hole drilling construction equipment of reverse circulation drill
CN204940391U (en) Construction of diaphragm wall groove milling system
CN101057059A (en) Method for installing horizon catheter used for aborsbing sea water
CN104141300A (en) Foundation pile hole drilling construction process
CN107964940A (en) A kind of construction method of continuous wall trench underground
CN208506279U (en) A kind of auger underground water level detecting device
CN203891785U (en) Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well
CN111005379A (en) Construction method for removing pile body of reinforced concrete cast-in-place pile
Rodríguez-Estrella et al. Methodologies for abstraction from coastal aquifers for supplying desalination plants in the south-east of Spain
CN103334443A (en) Mud cement pebble layer composite geological impacting hole forming dewatering well construction method
CN101353894B (en) Filling pile construction pore-creating method of pervious ultra-deep loose backfill two-piece stone zone
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment
CN204530680U (en) A kind of Churn drill sieve sand punched hole construction device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180306