CN106426800A - Large hot runner system without interfering system operation after glue leakage - Google Patents

Large hot runner system without interfering system operation after glue leakage Download PDF

Info

Publication number
CN106426800A
CN106426800A CN201610844882.9A CN201610844882A CN106426800A CN 106426800 A CN106426800 A CN 106426800A CN 201610844882 A CN201610844882 A CN 201610844882A CN 106426800 A CN106426800 A CN 106426800A
Authority
CN
China
Prior art keywords
transition
template
flow distribution
distribution plate
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610844882.9A
Other languages
Chinese (zh)
Other versions
CN106426800B (en
Inventor
阮军平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DONGGUAN REHENG INJECTION TECHNOLOGY Co Ltd
Original Assignee
DONGGUAN REHENG INJECTION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DONGGUAN REHENG INJECTION TECHNOLOGY Co Ltd filed Critical DONGGUAN REHENG INJECTION TECHNOLOGY Co Ltd
Priority to CN201610844882.9A priority Critical patent/CN106426800B/en
Publication of CN106426800A publication Critical patent/CN106426800A/en
Application granted granted Critical
Publication of CN106426800B publication Critical patent/CN106426800B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C45/00Injection moulding, i.e. forcing the required volume of moulding material through a nozzle into a closed mould; Apparatus therefor
    • B29C45/17Component parts, details or accessories; Auxiliary operations
    • B29C45/26Moulds
    • B29C45/27Sprue channels ; Runner channels or runner nozzles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C45/00Injection moulding, i.e. forcing the required volume of moulding material through a nozzle into a closed mould; Apparatus therefor
    • B29C45/17Component parts, details or accessories; Auxiliary operations
    • B29C45/72Heating or cooling
    • B29C45/73Heating or cooling of the mould

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Mechanical Engineering (AREA)
  • Moulds For Moulding Plastics Or The Like (AREA)

Abstract

The invention relates to the technical field of hot runners, in particular to a large hot runner system without interfering system operation after glue leakage. The large hot runner system structurally comprises a transition template arranged between a first spreader plate and a second spreader plate; the transition template is provided with a through hole; a transition hot sprue is arranged in the through hole; an inlet end face of the transition hot sprue pushes against the first spreader plate; an outlet end face of the transition hot sprue pushes against the second spreader plate; and a gap between the outer wall of the transition hot sprue and the inner wall of the through hole is bigger than a gap between the periphery part of an opening of the through hole of the transition template and the first spreader plate, and a gap between the periphery part of the opening of the through hole of the transition template and the second spreader plate. In this way, molten glue leaking from the transition hot sprue shall flow into and is collected in the gap between the outer wall of the transition hot sprue and the inner wall of the through hole, and can not leak outwards continuously to flow onto the first spreader plate or the second spreader plate. Therefore, even if the large hot runner system has the glue leakage, normal operation of the overall large hot runner system can be guaranteed, and die wear arising from the glue leakage can be eliminated.

Description

A kind of leak adhesive large-scale TOP-TIP that interference system does not run
Technical field
The present invention relates to Hot runner Technology field, and in particular to a kind of complementary large-scale TOP-TIP that interferes of leak adhesive.
Background technology
Large-scale TOP-TIP is generally provided with multilamellar flow distribution plate, and these flow distribution plates are the central modules of TOP-TIP, Flow distribution plate can not only cause the flow velocity of plastic melts more steady, additionally it is possible to make mould mould filling more uniform, fill Point.In injection moulding process, the plastic melts for flowing out from sprue flow through each sub-runner shunting biography each layer flow distribution plate successively Transport to each hot nozzle, most after flow in the die cavity of mould through hot nozzle.
For current large-scale TOP-TIP, hot flow path leak adhesive is the principal element for causing die wear and disabling, and The multiple area of the leak adhesive of TOP-TIP typically occurs in the joint of two neighboring flow distribution plate, in this place after leak adhesive, plastic melts May proceed to be seeped at two neighboring flow distribution plate, and then so that whole TOP-TIP is all filled up by plastic cement, ultimately result in a whole set of hot-fluid Road system normally cannot be run, and greatly increase the cost that repairs a die.In addition, TOP-TIP leak adhesive is the phenomenon it is difficult to eliminate, people Presently done improvement is all to strengthen sealing to make to reduce at its leak adhesive amount and leak adhesive, but so causes the structure of TOP-TIP more For complexity, cost raising, effect is little.
Outside, existing large-scale TOP-TIP, as the spacing between its two neighboring flow distribution plate is less, two shuntings The heat radiated by plate makes the temperature of mould too high, and then can cause the damage of mould, and as spacing is less, also not It is easy to the setting of cooling system.Also due to the spacing between adjacent flow distribution plate is less, the driving means of valve needle movements are driven Can not possibly be arranged on the spacing internal partition, and the installation site of driving means will also avoid the flow distribution plate that is positioned above, So driving means will be arranged on all flow distribution plates top, this allow for needle length must long enough, not only make material Cost increases, and makes needle be easily bent deformation, affects the mold use life-span.
Content of the invention
Present invention aims to deficiency of the prior art, and provide a kind of the big of leak adhesive not interference system operation Type TOP-TIP, can not only guarantee the normal operation of whole system, and can disappear after the large-scale TOP-TIP leak adhesive Remove the die wear for causing because of leak adhesive.
The purpose of the present invention is achieved through the following technical solutions.
A kind of leak adhesive large-scale TOP-TIP that interference system does not run is provided, including the first template and the second template, institute Stating the first embedded within template has first flow distribution plate affixed with which, and second embedded within template has second flow distribution plate affixed with which, Transition template is provided between first flow distribution plate and second flow distribution plate, transition template offers through hole, in the through hole The hot nozzle of transition is equipped with, the sub-runner of first flow distribution plate is by the transition runner of the hot nozzle of the transition and second flow distribution plate Sub-runner connection, the entrance face of the hot nozzle of the transition supports the first flow distribution plate, and the exit end face of the hot nozzle of the transition is supported Second flow distribution plate, the gap between the hot outer wall of nozzle of the transition and the inwall of the through hole is respectively greater than the stage die Gap between the through hole both ends open periphery of plate and two flow distribution plates.
Wherein, the sealing briquetting of ring-type, institute are provided between the exit end face of the hot nozzle of the transition and second flow distribution plate The gap that states between the outer wall of the hot nozzle of transition and the inwall of the through hole is logical with the transition template more than the sealing briquetting Gap between the both ends open periphery of hole.
Wherein, the edge part of the exit end face of the hot nozzle of the transition offer indent and extend to the hot nozzle of the transition The step of outer wall.
Wherein, the step is ring-shaped step.
Wherein, the arrival end of the hot nozzle of the transition is provided with flange part, and the transition template is provided with the end of the through hole For the limited impression of flange part insertion, the end face of the flange part supports first flow distribution plate, the flange part Other end abuts the bottom surface of the limited impression, and the gap between the hot outer wall of nozzle of the transition and the inwall of the through hole is big Gap between the end face of the flange part and the bottom surface of the limited impression.
Wherein, also include top board, heat-insulated meson between the top board and first flow distribution plate, is provided with, described heat-insulated The axis of the axis of meson and the hot nozzle of the transition is on the same line.
Wherein, the transition template includes the 3rd template between first template and second template.
Wherein, the transition template includes the 3rd template and the part with the first template of the 3rd template proximate, institute State the 3rd template to be located between first template and second template.
Wherein, the 3rd inner formwork has the driving means that valve needle is moved.
Wherein, the 3rd inner formwork has the cooling water channel for lowering the temperature to the driving means.
Beneficial effects of the present invention:
The non-interference large-scale TOP-TIP of the leak adhesive of the present invention, by arranging between the first flow distribution plate and the second flow distribution plate Transition template, and through hole is offered on transition template, the hot nozzle of transition is built in through hole, and the entrance face of the hot nozzle of transition is supported First flow distribution plate, the exit end face of the hot nozzle of transition supports the second flow distribution plate, between the outer wall of the hot nozzle of transition and the inwall of through hole Gap is respectively greater than the gap between the through hole both ends open periphery of transition template and two flow distribution plates, so from the hot nozzle of transition Transition runner oozes out the melten gel for coming by the gap for flowing between inwall of the outer wall of the hot nozzle of transition with through hole, and the gap is formed Transition ring cavity plays pressure release effect, the inflow transition ring cavity that the melten gel for oozing out can continue in this transition ring cavity to the melten gel for oozing out Interior aggregation, outwards oozes out without continuation and flows on the first flow distribution plate or the second flow distribution plate, therefore, even if the present invention's is large-scale TOP-TIP has leak adhesive phenomenon, but is all gathered between inwall of the outer wall of the hot nozzle of transition with through hole due to oozing out the melten gel for coming Gap in, melten gel will not continue to outwards be exuded to flow distribution plate, therefore still be able to guarantee the normal operation of whole system, and energy The die wear that enough eliminations are caused because of leak adhesive.
Description of the drawings
Using accompanying drawing, the invention will be further described, but the embodiment in accompanying drawing does not constitute any limit to the present invention System, for one of ordinary skill in the art, on the premise of not paying creative work, can also obtain according to the following drawings Other accompanying drawings.
Fig. 1 for the present invention a kind of leak adhesive not interference system operation large-scale TOP-TIP structural representation.
Fig. 2 is the mplifying structure schematic diagram at the A in Fig. 1.
Include in Fig. 1 and Fig. 2:
The first template of 1-;
The second template of 2-;
The first flow distribution plate of 3-;
The second flow distribution plate of 4-;
The 3rd template of 5-;
The hot nozzle of 6- transition, 61- flange part;
7- transition ring cavity;
8- sealing briquetting;
9- driving means;
10- top board;
The heat-insulated meson of 11-;
12- melten gel.
Specific embodiment
The invention will be further described with the following Examples, a kind of not interference system operation of leak adhesive of the present invention big Type TOP-TIP, as depicted in figs. 1 and 2, its structure includes the first template 1 and the second template 2, the first template 1 be embedded with Its first affixed flow distribution plate 3, the second template 2 is embedded with second flow distribution plate 4 affixed with which, the first flow distribution plate 3 and second point Transition template is provided between stream plate 4, in the present embodiment, transition template is included the 3rd template 5 and closely pressed with the 3rd template 5 A part for first template 1, the 3rd template 5 is located between the first template 1 and the second template 2, and certain transition template can also be The 3rd independent template 5.
Transition template is provided with through hole, and through hole is built-in with the hot nozzle 6 of transition, and the sub-runner of the first flow distribution plate 3 passes through the hot nozzle 6 of transition Transition runner connect with the sub-runner of the second flow distribution plate 4, multiple for leak adhesive in the contact area of the hot nozzle 6 of two flow distribution plates and transition Area, in prior art, the melten gel 12 that oozes out from there will be flowed on amount flow distribution plate, and then cause the whole TOP-TIP cannot Normal operation.
In the present embodiment, the sealing briquetting 8 of ring-type is provided between the exit end face and the second flow distribution plate 4 of the hot nozzle 6 of transition, Gap between the hot outer wall of nozzle 6 of transition and the inwall of through hole is more than sealing briquetting 8 and stage die positioned at through hole by mouth periphery Gap between plate, the gap between the hot outer wall of nozzle 6 of transition and the inwall of through hole is transition ring cavity 7, even if such present invention There is leak adhesive phenomenon, the melten gel 12 for oozing out from the exit end face of the hot nozzle 6 of transition can be flowed in transition ring cavity 7, and along this transition Ring cavity 7 is flowed up(As shown by the arrows in Figure 2), as the size of transition ring cavity 7 is logical with transition template more than sealing briquetting 8 The size in the gap between the open circumferential portion of hole, the melten gel 12 for oozing out from the exit end face of the hot nozzle 6 of transition will not continue to penetrate into envelope Gap between glue laminated block 8 and transition template(As b primary and secondary tag slot in Fig. 2), enter without being outwards exuded to the second flow distribution plate 4.In addition, hot 6 entrance face of nozzle of transition is provided with flange part 61, transition template is provided with for the insertion of flange part 61 in the end of through hole Limited impression, the first flow distribution plate 3 is supported in the upper surface of flange part 61, and the lower end face of flange part 61 abuts the bottom of limited impression Face, the gap between the hot outer wall of nozzle 6 of transition and the inwall of through hole is more than positioned at the lower surface of flange part 61 and limited impression Gap between bottom surface, the melten gel 12 of such transition ring cavity 7 when flowing up, as the lower surface of flange part 61 is recessed with spacing Gap size between the bottom surface of groove is less(As a primary and secondary tag slot in Fig. 2), melten gel 12 will not also be exuded to the first flow distribution plate 3 On, the melten gel 12 for oozing out from the exit end face of the hot nozzle 6 of transition can only be in aggregation in the transition ring cavity 7, in such transition ring cavity 7 Melten gel 12 has no effect on the operation of whole TOP-TIP, and these leak adhesives do not result in the abrasion of mould yet.Treat that mould makes During with repairing a die after a period of time, the melten gel 12 in this transition ring cavity 7 is removed, and then cause the hot nozzle of transition of the present invention Even if occurring leak adhesive at 6 also miscellaneous part will not be impacted, and then it is able to ensure that the normal operation of whole system, and energy The die wear that enough eliminations are caused because of leak adhesive.
Further, the edge part of the exit end face of the hot nozzle 6 of transition offer indent and extend to the hot nozzle 6 of transition outer The step of wall, the step is connected with transition ring cavity 7, and the step is that ring-shaped step, the so exit end face from the hot nozzle 6 of transition oozes out Melten gel 12 by the ring-shaped step, can more easily flow in transition ring cavity 7, and the presence of the ring-shaped step, cut The melten gel 12 that broken continues the path to the gap flowing between the via openings periphery of sealing briquetting 8 and transition template, and then Play prevention melten gel 12 and be exuded to the second flow distribution plate 4.
Further, closely to press between sealing briquetting 8 and the second flow distribution plate 4(As c primary and secondary tag slot in Fig. 2), prevent Only melten gel 12 oozes out from there.
In the present embodiment, as shown in figure 1, the large-scale TOP-TIP of the present invention also includes top board 10, top board 10 with Be provided with heat-insulated meson 11 between first flow distribution plate 3, the axis of the axis of heat-insulated meson 11 and the hot nozzle 6 of transition on the same line, Pressure so on top board 10 could be applied to the hot nozzle 6 of transition more effectively by heat-insulated meson 11 and the first flow distribution plate 3, enter And so that the first flow distribution plate 3 is closely abutted with the hot nozzle 6 of transition.
In the present embodiment, as shown in figure 1, the 3rd template 5 is built-in with the driving means of valve needle motion, compared to existing In technology, driving means are arranged in top board 10, the installation of inventive drive means without the first flow distribution plate 3 is avoided, also not Interference can be produced with the first flow distribution plate 3, the motility of Design of Dies be increased, and driving means are arranged on the 3rd template 5, Also the length of needle is shortened, and then material cost is reduced, also so that needle is difficult flexural deformation, extends mould and use the longevity Life.In addition, the 3rd template 5 also acts as the effect for intercepting the heat given off by the first flow distribution plate 3 and the second flow distribution plate 4.
Further, the 3rd template 5 is built-in with the cooling water channel for lowering the temperature to driving means.The cooling water channel can have Effect absorbs the heat given off by the first flow distribution plate 3 and the second flow distribution plate 4, and then reduces the mould temperature of whole mould.
Finally it should be noted that above example is only in order to illustrating technical scheme, rather than the present invention is protected The restriction of shield scope, although having made to explain to the present invention with reference to preferred embodiment, one of ordinary skill in the art should Work as understanding, technical scheme can be modified or equivalent, without deviating from the reality of technical solution of the present invention Matter and scope.

Claims (10)

1. the large-scale TOP-TIP of a kind of leak adhesive not interference system operation, including the first template and the second template, described first Embedded within template has first flow distribution plate affixed with which, and second embedded within template has second flow distribution plate affixed with which, its feature It is:Transition template is provided between first flow distribution plate and second flow distribution plate, the transition template is provided with through hole, described Through hole is built-in with the hot nozzle of transition, the transition runner and described second of the sub-runner of first flow distribution plate by the hot nozzle of the transition The sub-runner connection of flow distribution plate, the entrance face of the hot nozzle of the transition supports first flow distribution plate, the going out of the hot nozzle of transition Mouthful end face supports second flow distribution plate, and the gap between the hot outer wall of nozzle of the transition and the inwall of the through hole is respectively greater than Gap between the through hole both ends open peripheral part of the transition template and two flow distribution plates.
2. a kind of leak adhesive according to claim 1 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute State the sealing briquetting that ring-type is provided between the exit end face of the hot nozzle of transition and second flow distribution plate, the outer wall of the hot nozzle of the transition And the gap between the inwall of the through hole more than the sealing briquetting via openings peripheral part and the transition template it Between gap.
3. a kind of leak adhesive according to claim 2 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute The peripheral portion for stating the exit end face of the hot nozzle of transition offers the step of outer wall that is indent and extending to the hot nozzle of the transition.
4. a kind of leak adhesive according to claim 3 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute Step is stated for ring-shaped step.
5. a kind of leak adhesive according to claim 1 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute The arrival end for stating the hot nozzle of transition is provided with flange part, and the transition template is provided with the end of the through hole and inserts for the flange part Limited impression, the end face of the flange part supports first flow distribution plate, and the other end of the flange part abuts described The bottom surface of limited impression, the gap between the hot outer wall of nozzle of the transition and the inwall of the through hole is more than the end of the flange part Gap between the bottom surface of face and the limited impression.
6. the large-scale TOP-TIP of a kind of leak adhesive not interference system operation according to claim 1 or 5, its feature exists In:Also include top board, between the top board and first flow distribution plate, be provided with heat-insulated meson, the axis of the heat-insulated meson With the axis of the hot nozzle of the transition on the same line.
7. a kind of leak adhesive according to claim 1 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute Stating transition template includes the 3rd template between first template and second template.
8. a kind of leak adhesive according to claim 1 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute Stating transition template includes the 3rd template and the part with the first template of the 3rd template proximate, and the 3rd template is located at institute State between the first template and second template.
9. a kind of leak adhesive according to claim 8 not interference system operation large-scale TOP-TIP, it is characterised in that:Institute State the driving means that the 3rd inner formwork has valve needle to move.
10. a kind of leak adhesive according to claim 9 not interference system operation large-scale TOP-TIP, it is characterised in that: 3rd inner formwork has the cooling water channel for lowering the temperature to the driving means.
CN201610844882.9A 2016-09-23 2016-09-23 A kind of leak adhesive large-scale hot runner system that interference system is not run Active CN106426800B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610844882.9A CN106426800B (en) 2016-09-23 2016-09-23 A kind of leak adhesive large-scale hot runner system that interference system is not run

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610844882.9A CN106426800B (en) 2016-09-23 2016-09-23 A kind of leak adhesive large-scale hot runner system that interference system is not run

Publications (2)

Publication Number Publication Date
CN106426800A true CN106426800A (en) 2017-02-22
CN106426800B CN106426800B (en) 2019-05-24

Family

ID=58167128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610844882.9A Active CN106426800B (en) 2016-09-23 2016-09-23 A kind of leak adhesive large-scale hot runner system that interference system is not run

Country Status (1)

Country Link
CN (1) CN106426800B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108405276A (en) * 2018-04-28 2018-08-17 上海华鄂工程技术有限公司 A kind of hot melt melten gel coating production glue spreading apparatus transitional region processing equipment
CN113815195A (en) * 2021-08-27 2021-12-21 台州市黄岩西诺模具有限公司 Anti-leakage structure of split injection molding flow distribution plate

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3829326B2 (en) * 2002-02-27 2006-10-04 三菱マテリアル株式会社 Valve gate type mold equipment
CN2931070Y (en) * 2006-07-28 2007-08-08 先锐模具配件(东莞)有限公司 Valve needle device of heat flow passage die
WO2008040647A1 (en) * 2006-09-29 2008-04-10 Mht Mold & Hotrunner Technology Ag Decompression sprue bush and decompression machine nozzle
CN102672894A (en) * 2012-04-28 2012-09-19 深圳创维精密科技有限公司 Hot nozzle installation structure of hot runner system
CN102909830A (en) * 2012-10-29 2013-02-06 柳道万和(苏州)热流道***有限公司 Tina multi-nozzle tip hot runner system
CN102990873A (en) * 2012-12-20 2013-03-27 成都航天模塑股份有限公司 Mould pouring gate leak proof ring
CN203472069U (en) * 2013-07-31 2014-03-12 优利浦注塑科技(昆山)有限公司 Hot flow channel system for color changing needle valve
CN204687260U (en) * 2015-04-24 2015-10-07 苏州塑道千和热流道科技有限公司 A kind of leakproof injection heat of improvement is chewed
CN205343664U (en) * 2016-01-15 2016-06-29 中山市富晟特热流道科技有限公司 Gluing of sealing of hot runner constructs
CN205467080U (en) * 2016-02-01 2016-08-17 佛山市顺德区弗伦克热流道科技有限公司 Glued structure of leak protection of needle valve formula hot runner
CN206170549U (en) * 2016-09-23 2017-05-17 东莞市热恒注塑科技有限公司 Leak large -scale hot runner system that glues operation of noninterference system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3829326B2 (en) * 2002-02-27 2006-10-04 三菱マテリアル株式会社 Valve gate type mold equipment
CN2931070Y (en) * 2006-07-28 2007-08-08 先锐模具配件(东莞)有限公司 Valve needle device of heat flow passage die
WO2008040647A1 (en) * 2006-09-29 2008-04-10 Mht Mold & Hotrunner Technology Ag Decompression sprue bush and decompression machine nozzle
CN102672894A (en) * 2012-04-28 2012-09-19 深圳创维精密科技有限公司 Hot nozzle installation structure of hot runner system
CN102909830A (en) * 2012-10-29 2013-02-06 柳道万和(苏州)热流道***有限公司 Tina multi-nozzle tip hot runner system
CN102990873A (en) * 2012-12-20 2013-03-27 成都航天模塑股份有限公司 Mould pouring gate leak proof ring
CN203472069U (en) * 2013-07-31 2014-03-12 优利浦注塑科技(昆山)有限公司 Hot flow channel system for color changing needle valve
CN204687260U (en) * 2015-04-24 2015-10-07 苏州塑道千和热流道科技有限公司 A kind of leakproof injection heat of improvement is chewed
CN205343664U (en) * 2016-01-15 2016-06-29 中山市富晟特热流道科技有限公司 Gluing of sealing of hot runner constructs
CN205467080U (en) * 2016-02-01 2016-08-17 佛山市顺德区弗伦克热流道科技有限公司 Glued structure of leak protection of needle valve formula hot runner
CN206170549U (en) * 2016-09-23 2017-05-17 东莞市热恒注塑科技有限公司 Leak large -scale hot runner system that glues operation of noninterference system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108405276A (en) * 2018-04-28 2018-08-17 上海华鄂工程技术有限公司 A kind of hot melt melten gel coating production glue spreading apparatus transitional region processing equipment
CN113815195A (en) * 2021-08-27 2021-12-21 台州市黄岩西诺模具有限公司 Anti-leakage structure of split injection molding flow distribution plate
CN113815195B (en) * 2021-08-27 2023-11-03 台州市黄岩西诺模具有限公司 Split injection molding split flow distribution plate anti-leakage structure

Also Published As

Publication number Publication date
CN106426800B (en) 2019-05-24

Similar Documents

Publication Publication Date Title
CN201677021U (en) Low-pressure casting hub die
CN106426800A (en) Large hot runner system without interfering system operation after glue leakage
CN204658841U (en) A kind of injection mould improved into solation road
CN107901349A (en) Rubber Injection Mold lamps structure
CN206870281U (en) Hot runner system
CN101462154A (en) Water-cooling nozzle structure for plug-in hot core box
CN205202017U (en) Integral cold runner device of rubber injection
CN206170549U (en) Leak large -scale hot runner system that glues operation of noninterference system
CN206446051U (en) An a kind of pipe injection molding channel structure
CN206747574U (en) Cooling body on casting mould
CN206406361U (en) A kind of injection mold with cooling water channel
JP2017100434A (en) Air-cooled sprue bush for injection mold
CN204844713U (en) MSC needle valve formula hot runner system
CN206999522U (en) A kind of more nozzle core side glue mouth TOP-TIPs
CN202781679U (en) Thermoplastic flow channel of notebook die
CN207077697U (en) A kind of high temperature plastics mould for having thermal insulation board
CN204844714U (en) Open hot runner system of MSC
CN202357402U (en) Water transporting sleeve for hot runner system of injection mold
CN201308973Y (en) Water-cooling nozzle structure for plug-in hot core box
CN202480281U (en) Segmented mold pattern block and segmented mold for pore-free tyre
CN113858564A (en) Cooling nozzle precooling structure for injection mold
CN206605748U (en) A kind of blade mold and its cooling system
CN102773418B (en) Rim gating system
CN106914605B (en) Cooling body on casting mould
CN219705877U (en) Chip plastic package die

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant