CN104695895A - Plugging method integrating channel blocking and leakage plugging - Google Patents

Plugging method integrating channel blocking and leakage plugging Download PDF

Info

Publication number
CN104695895A
CN104695895A CN201410818172.XA CN201410818172A CN104695895A CN 104695895 A CN104695895 A CN 104695895A CN 201410818172 A CN201410818172 A CN 201410818172A CN 104695895 A CN104695895 A CN 104695895A
Authority
CN
China
Prior art keywords
well section
sleeve pipe
plugging
leakage loss
pipe leakage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410818172.XA
Other languages
Chinese (zh)
Inventor
王萍萍
赵永凯
邹吉有
路学宽
贾海舰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410818172.XA priority Critical patent/CN104695895A/en
Publication of CN104695895A publication Critical patent/CN104695895A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Sealing Material Composition (AREA)

Abstract

The invention belongs to a method for plugging a casing leakage well section and external casing channeling in an oil well, and particularly relates to a plugging method integrating channel blocking and leakage plugging. According to the plugging method integrating channel blocking and leakage plugging, a chemical composite plugging agent RB/H-I, high-temperature resistant composite resin and G-level oil well cement are adopted and combined to plug the casing leakage well section and the external casing channeling. The plugging method has the benefits as follows: the plugging method is simple, the construction is convenient, the plugging effect is good, an oil layer does not leak water during production, the plugging success rate for each time is up to 98%, and the production benefits of the oil well is increased.

Description

Sealing skill integration method for blocking
Technical field
The invention belongs to a kind of sleeve pipe leakage loss well section in oil well and pipe are altered outward and carry out method for blocking, particularly a kind of sealing skill integration method for blocking.
Background technology
At present, because of factors such as geology in oilfield development process, cause the sleeve pipe leakage loss in oil well, steam injection exploitation one is taken turns and the Behavior of Hardened Cement Paste outside sleeve pipe will be caused to damage, cause altering outside pipe, because sleeve pipe leakage loss and outer the altering of pipe cause top to alter the end under water waterbornely to alter, make oil well High water cut, have a strong impact on oil well production, traditional is utilize squeeze method method for blocking to altering method for blocking outside sleeve pipe leakage loss well section and pipe, because cement density large fluidity is good, penetration is strong, clamp-on how much cement, capital is lost in a large number along loose area, near wellbore zone storage is little, even if formation some strength, under 10MPa pressure promotes, also move after causing cement, cause new crack, thus repeatedly construct and be also difficult to reach construction effect, one time shutoff success rate can only reach 40%.
Summary of the invention
In order to overcome the problems referred to above, the invention provides a kind of sealing skill integration method for blocking, leak stopping is exactly that sleeve pipe leakage loss well section in shutoff oil well and perforation envelope alter well section, it is exactly that the damage of shutoff sleeve pipe external cause Behavior of Hardened Cement Paste causes pipe to alter outward that envelope is altered, envelope is altered general employing and to be altered the end on top under water and waterbornely alter passage shale layer position perforation, carry out envelope to alter, sealing skill integration method for blocking adopts chemically composited blocking agent RB/H-I, high temperature resistant compound resin and G level oil well cement combine and carry out shutoff to sleeve pipe leakage loss well section and outer the altering of pipe, chemically composited blocking agent RB/H-I, shutoff carrys out aquaporin, thermal production well formation depletion is seriously played stifled temporarily simultaneously, fill up formation depletion and carry out aquaporin, owing to there being good mobility, shutoff distance, easily enter high-permeability reservoir, water-swellable, the barrier of strength of stability can be formed in water layer, stop the diffusion of water, meet oil to dissolve simultaneously, do not block duct, space, ensure oil reservoir not water outlet in production, high temperature resistant compound resin, to stop that high temperature steam injection damages hard blocking agent, G level oil well cement, strengthen near wellbore zone plugging strength, shutoff space and duct, sealing skill integration method for blocking is adopted to prove altering the construction carrying out shutoff outside sleeve pipe leakage loss well section and pipe by more than 300 mouthful, Liaohe Oil Field oil well, one time shutoff success rate reaches more than 98%.
The present invention solves the technical scheme that its technical problem takes: a kind of sealing skill integration method for blocking, this sealing skill integration method for blocking adopts chemically composited blocking agent RB/H-I, high temperature resistant compound resin and G level oil well cement combine and carry out shutoff to sleeve pipe leakage loss well section and outer the altering of pipe, its special character is: method for blocking alters upper 100 meters of of well section by under plugging tubing string to sleeve pipe leakage loss well section and perforation envelope, close wellhead assembly, alter well section by plugging tubing string to sleeve pipe leakage loss well section and perforation envelope with pump truck and clamp-on chemically composited blocking agent RB/H-I, 150-180 ton, blocking radius will reach more than 3 meters, pressure reaches 8-10MPa, alter well section to sleeve pipe leakage loss well section and perforation envelope and clamp-on high temperature resistant compound resin 2-3 ton, altering well section to sleeve pipe leakage loss well section and perforation envelope again, to clamp-on density be 18.5g/cm 3g level oil well cement 12-15 ton after, clear water alters the G level oil well cement top of finally clamp-oning more than well section 10 meters of cement surface to sleeve pipe leakage loss well section and perforation envelope is squeezed in sleeve pipe, Hou Ning is after 24 hours, trip out plugging tubing string, again drilling out tubing string is lowered into sleeve pipe leakage loss well section and perforation envelope alters the cement surface at upper 100 meters of of well section, cement trepan in sleeve pipe is fallen to take ground to, finally alter well section with pump truck to sleeve pipe leakage loss well section and perforation envelope and suppress 15MPa, termination of pumping car is after 30 minutes, and Pressure Drop 14.5-15MPa is that shutoff is qualified.
The invention has the beneficial effects as follows: method for blocking is simple, easy construction, and plugging effect is good, ensure oil reservoir not water outlet in production, one time shutoff success rate reaches 98/%, improves oil well production benefit.
Detailed description of the invention
Method for blocking: be alter upper 100 meters of of well section by under plugging tubing string to sleeve pipe leakage loss well section and perforation envelope, close wellhead assembly, alter well section by plugging tubing string to sleeve pipe leakage loss well section and perforation envelope with pump truck and clamp-on chemically composited blocking agent RB/H-I, 150-180 ton, blocking radius will reach more than 3 meters, pressure reaches 8-10MPa, alters well section clamp-on high temperature resistant compound resin 2-3 ton to sleeve pipe leakage loss well section and perforation envelope, then altering well section to sleeve pipe leakage loss well section and perforation envelope, to clamp-on density be 18.5g/cm 3g level oil well cement 12-15 ton after, clear water alters the G level oil well cement top of finally clamp-oning more than well section 10 meters of G level oil well cement face to sleeve pipe leakage loss well section and perforation envelope is squeezed in sleeve pipe, Hou Ning is after 24 hours, trip out plugging tubing string, again drilling out tubing string is lowered into sleeve pipe leakage loss well section and perforation envelope alters the cement surface at upper 100 meters of of well section, cement trepan in sleeve pipe is fallen to take ground to, finally alter well section place with pump truck to sleeve pipe leakage loss well section and perforation envelope and suppress 15MPa, termination of pumping car is after 30 minutes, and Pressure Drop 14.5-15MPa is that shutoff is qualified.

Claims (1)

1. a sealing skill integration method for blocking, this sealing skill integration method for blocking adopts chemically composited blocking agent RB/H-I, high temperature resistant compound resin and G level oil well cement combine and carry out shutoff to sleeve pipe leakage loss well section and outer the altering of pipe, it is characterized in that: method for blocking alters upper 100 meters of of well section by under plugging tubing string to sleeve pipe leakage loss well section and perforation envelope, close wellhead assembly, alter well section by plugging tubing string to sleeve pipe leakage loss well section and perforation envelope with pump truck and clamp-on chemically composited blocking agent RB/H-I, 150-180 ton, blocking radius will reach more than 3 meters, pressure reaches 8-10MPa, alter well section to sleeve pipe leakage loss well section and perforation envelope and clamp-on high temperature resistant compound resin 2-3 ton, altering well section to sleeve pipe leakage loss well section and perforation envelope again, to clamp-on density be 18.5g/cm 3g level oil well cement 12-15 ton after, clear water alters the G level oil well cement top of finally clamp-oning more than well section 10 meters of cement surface to sleeve pipe leakage loss well section and perforation envelope is squeezed in sleeve pipe, Hou Ning is after 24 hours, trip out plugging tubing string, again drilling out tubing string is lowered into sleeve pipe leakage loss well section and perforation envelope alters the cement surface at upper 100 meters of of well section, cement trepan in sleeve pipe is fallen to take ground to, finally alter well section with pump truck to sleeve pipe leakage loss well section and perforation envelope and suppress 15MPa, termination of pumping car is after 30 minutes, and Pressure Drop 14.5-15MPa is that shutoff is qualified.
CN201410818172.XA 2014-12-14 2014-12-14 Plugging method integrating channel blocking and leakage plugging Pending CN104695895A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410818172.XA CN104695895A (en) 2014-12-14 2014-12-14 Plugging method integrating channel blocking and leakage plugging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410818172.XA CN104695895A (en) 2014-12-14 2014-12-14 Plugging method integrating channel blocking and leakage plugging

Publications (1)

Publication Number Publication Date
CN104695895A true CN104695895A (en) 2015-06-10

Family

ID=53343398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410818172.XA Pending CN104695895A (en) 2014-12-14 2014-12-14 Plugging method integrating channel blocking and leakage plugging

Country Status (1)

Country Link
CN (1) CN104695895A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257241A (en) * 2015-09-24 2016-01-20 中国石油天然气股份有限公司 Method for cementing plug of horizontal well
CN105443071A (en) * 2015-12-07 2016-03-30 中国石油天然气股份有限公司 Process for blocking underwater channeling of roof
CN107701143A (en) * 2016-08-09 2018-02-16 中国石油化工股份有限公司 A kind of multi-section multi-layer sealing skill devices and methods therefor based on one-trip string
CN108756806A (en) * 2018-04-26 2018-11-06 四川光亚聚合物化工有限公司 Pipe leakage administering method is altered outside a kind of production of hydrocarbons well casing
CN109403936A (en) * 2018-11-15 2019-03-01 中国石油天然气股份有限公司 Process method and device for sealing high-temperature and high-pressure leakage well
CN110725663A (en) * 2019-11-06 2020-01-24 中国石油天然气股份有限公司 Chemical plugging process for well without damage of fixed pipe column sleeve of bridge plug
CN111075393A (en) * 2019-12-18 2020-04-28 中国石油天然气股份有限公司 Oil-gas field casing damage well long well section plugging resin repair process

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5957205A (en) * 1997-08-18 1999-09-28 Alberta Oil Sands Technology And Research Authority Sand exclusion liner and method of using the same
CN1400376A (en) * 2002-09-12 2003-03-05 大庆油田有限责任公司 Cement band pressure curing channelling-blocking method
CN101769138A (en) * 2010-01-07 2010-07-07 东莞天佳塑胶五金制品有限公司 Leak-proof method of circulating fluid of oil well

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5957205A (en) * 1997-08-18 1999-09-28 Alberta Oil Sands Technology And Research Authority Sand exclusion liner and method of using the same
CN1400376A (en) * 2002-09-12 2003-03-05 大庆油田有限责任公司 Cement band pressure curing channelling-blocking method
CN101769138A (en) * 2010-01-07 2010-07-07 东莞天佳塑胶五金制品有限公司 Leak-proof method of circulating fluid of oil well

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王龙: "中121井化学固结+交联成膜技术承压堵漏技术浅析", 《西部探矿工程》 *
闫新华等: "HZ-D化学堵剂封堵技术研究", 《消费导刊》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257241A (en) * 2015-09-24 2016-01-20 中国石油天然气股份有限公司 Method for cementing plug of horizontal well
CN105257241B (en) * 2015-09-24 2018-03-09 中国石油天然气股份有限公司 Method for cementing plug of horizontal well
CN105443071A (en) * 2015-12-07 2016-03-30 中国石油天然气股份有限公司 Process for blocking underwater channeling of roof
CN107701143A (en) * 2016-08-09 2018-02-16 中国石油化工股份有限公司 A kind of multi-section multi-layer sealing skill devices and methods therefor based on one-trip string
CN107701143B (en) * 2016-08-09 2019-08-30 中国石油化工股份有限公司 A kind of multi-section multi-layer sealing skill devices and methods therefor based on one-trip string
CN108756806A (en) * 2018-04-26 2018-11-06 四川光亚聚合物化工有限公司 Pipe leakage administering method is altered outside a kind of production of hydrocarbons well casing
CN109403936A (en) * 2018-11-15 2019-03-01 中国石油天然气股份有限公司 Process method and device for sealing high-temperature and high-pressure leakage well
CN109403936B (en) * 2018-11-15 2021-01-01 中国石油天然气股份有限公司 Process method and device for sealing high-temperature and high-pressure leakage well
CN110725663A (en) * 2019-11-06 2020-01-24 中国石油天然气股份有限公司 Chemical plugging process for well without damage of fixed pipe column sleeve of bridge plug
CN110725663B (en) * 2019-11-06 2022-02-01 中国石油天然气股份有限公司 Chemical plugging process for well without damage of fixed pipe column sleeve of bridge plug
CN111075393A (en) * 2019-12-18 2020-04-28 中国石油天然气股份有限公司 Oil-gas field casing damage well long well section plugging resin repair process
CN111075393B (en) * 2019-12-18 2021-11-30 中国石油天然气股份有限公司 Oil-gas field casing damage well long well section plugging resin repair process

Similar Documents

Publication Publication Date Title
CN104695895A (en) Plugging method integrating channel blocking and leakage plugging
CN102926770B (en) Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN104265354B (en) A kind of low air permeability coal seam waterpower phase transformation fracturing strengthening gas pumping method
CN106014330B (en) Method for improving chemical plugging success rate of leakage casing damage well
WO2016082188A1 (en) Hot dry rock multi-cycle heating system and production method therefor
CN105756650B (en) Method for realizing staged fracturing of horizontal well by adopting mixed temporary plugging agent to block tubular channeling
CN104879108A (en) Heat-injection enhanced extracting and mining method of coal bed gas U-type well
CN207048739U (en) A kind of low gaseous mine gas ground extraction technology drilled well bore structure
CN104695927A (en) Coiled tubing and production tubing combined string fracturing and well completion integrated method
CN204252967U (en) Hot dry rock multi cycle heating system
CN104564001A (en) Horizontal well multi-cluster fracturing method and multi-cluster perforating and fracturing pipe column for implementing method
CN102146782A (en) Steam and nitrogen composite swallowing-spitting oil extraction method
CN102562012A (en) Method for improving recovery ratio of water-flooding developed common heavy oil reservoir
CN204703876U (en) Bridge type concentric separate injection pipe column
CN104594870A (en) Fracturing production increasing method
CN104533354A (en) Plug type sand control method for slim hole sidetracked well
CN104265254A (en) Oil production technological method for multi-stage plug injection of oil-soluble viscosity reducer and liquid CO2 in deep super-heavy oil
CN110886594B (en) Method for exploiting coal bed gas
CN105443098A (en) Coal mine underground borehole segmented fixed hydraulic fracturing fixation hole device and method
CN105178910A (en) Horizontal well water plugging process pipe column and method
CN104121000B (en) Water plugging method for low-permeability fractured reservoir casing completion horizontal well
CN202228038U (en) Pipe string for plugging shallow-layer sleeve leakage water injection well
CN108625841A (en) Horizontal well annulus sealing and ball-throwing sliding sleeve combined repeated fracturing method
CN107654207A (en) Section method for fixed-point preset sand plug of coiled tubing horizontal well
CN103470241B (en) Two bunches of jetting tubing strings and two bunches of jetting annular fracturing methods

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 124010, room 1, unit 9, building 501, Lake New Town, Xinglongtai, Liaoning, Panjin

Applicant after: Wang Pingping

Address before: 124010, room 1, unit 9, Chang Lake New District, Xinglongtai, Liaoning, Panjin 501, China

Applicant before: Wang Pingping

COR Change of bibliographic data
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150610