CN103741568A - High-fill settling subgrade grouting process - Google Patents

High-fill settling subgrade grouting process Download PDF

Info

Publication number
CN103741568A
CN103741568A CN201310725755.3A CN201310725755A CN103741568A CN 103741568 A CN103741568 A CN 103741568A CN 201310725755 A CN201310725755 A CN 201310725755A CN 103741568 A CN103741568 A CN 103741568A
Authority
CN
China
Prior art keywords
grouting
hole
fill
subgrade
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310725755.3A
Other languages
Chinese (zh)
Inventor
王家全
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University of Science and Technology
Original Assignee
Guangxi University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University of Science and Technology filed Critical Guangxi University of Science and Technology
Priority to CN201310725755.3A priority Critical patent/CN103741568A/en
Publication of CN103741568A publication Critical patent/CN103741568A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a high-fill settling subgrade grouting process, which comprises the steps of uniformly distributing grouting holes in a working face, wherein part of the grouting holes are taken as pilot holes; performing a drilling hole-forming process on each pilot hole; performing a grouting process on the drilled hole of each pilot hole; and according to acquired high-fill settling subgrade form data, performing the summarization of the drilling process and the grouting process on each pilot hole. According to the high-fill settling subgrade grouting process disclosed by the invention, subgrade form data is acquired in the process of drilling, then a grouting scheme for the grouting holes is determined, the drilling and grouting of subsequent grouting holes are guided by using geological conditions summarized by the pilot holes and a construction process, and the construction of plenty of normal holes can be performed then, so that the large-area construction implementation is facilitated. In such a way, the physical and mechanical properties of a whole subgrade are improved, so that the subgrade is not settled under the action of traffic loads and dead-weights, and buildings subjected to non-uniform settlement are restored to normal positions, thereby increasing the strength and stiffness of the subgrade, and preventing or weakening the re-settling of the subgrade.

Description

High settlement of fill grouting of road bed technique
Technical field
The present invention relates to grouting process technical field, relate in particular to a kind of high settlement of fill grouting of road bed technique.
Background technology
The large-scale expressway construction in west area, inevitably to run into roadbed high fill out deep-cut, the engineering problem such as old road reorganization and expansion, it is one of study hotspot of engineering field that high fills embankment Defects Treatment becomes.High fills embankment generally all has long construction period, and hydrogeology is complicated, and narrow field requires strictly construction quality, and embankment protection grade is high, high cost feature.These features have determined that high fills embankment is different from general common embankment, have possessed disease compared with the condition of high rate.As time goes on and the repeated action of vehicular load after high embankment Practical Completion,, high embankment is faced with the danger of whole sinking, local subsidence and slope failure.
More serious when local subgrade settlement, area is larger, changes in the situation that the method for banketing cannot meet the demands, need to adopt grouting to process local roadbed.Grouting process is to utilize hydraulic pressure, air pressure or electrochemical principle, sinking part embankment filled soil is holed, guarantee that hole depth penetrates weak floor, slurries are evenly injected to crack and the hole of various media via grouting pipe, control after certain hour, make slurries and original grogs or crack be cemented to an integral body, form " calculus body " that a physical property and chemical property all can be more stable, improve the physico-mechanical properties of whole ground, make roadbed under traffic load and Gravitative Loads, no longer produce sedimentation, make the building that differential settlement occurs return to original position, thereby improve the strength and stiffness of roadbed, prevent or weaken sinking again of roadbed.
Summary of the invention
The object of the present invention is to provide a kind of high settlement of fill grouting of road bed technique, to improve the physico-mechanical properties of whole ground, make roadbed under traffic load and Gravitative Loads, no longer produce sedimentation, make the building that differential settlement occurs return to original position, thereby improve the strength and stiffness of roadbed, prevent or weaken sinking again of roadbed.
For achieving the above object, the present invention has adopted following technical scheme:
High settlement of fill grouting of road bed technique, the step of this technique is:
S1, at high settlement of fill roadbed work plane, carry out the even cloth hole of injected hole, and using the described injected hole of some as pilot hole;
S2, pilot hole described in each is implemented to Completion of Drilling Hole technique: first install orifice sleeve and carry out solid pipe, whole hole after drilling to completion then, and adopt mud circulation to carry out hole clearly to the boring of pilot hole described in each;
In boring procedure, gather at a certain distance compactness, intensity, initial pressure, drilling depth, the grouting position state data of this layer of roadbed;
S3, the boring of pilot hole described in each is implemented to grouting process: adopt slurry floral tube down at the bottom of hole, then the method for Piecemeal erection packer is carried out slip casting, and institute's injection slurry is single liquid slurries from bottom to top;
S4, according to the high settlement of fill roadbed morphological data gathering, determine geology and geomorphology, then each pilot hole is implemented the summary of bore process and grouting process.
As the improvement to technique scheme, the quantity of described pilot hole is 25%~35% of described injected hole quantity.
As the improvement to technique scheme, described high settlement of fill roadbed comprises gravelly soil, gravel soil filler roadbed and cohesive soil filler roadbed.
As the improvement to technique scheme, the grouting pressure of described slip casting is 0.5 MPa~4.0 MPa.
As the improvement to technique scheme, the boring aperture of described injected hole is 91~130mm.
Compared with prior art, the invention has the beneficial effects as follows:
The injected hole that high settlement of fill grouting of road bed technique of the present invention is chosen some is as pilot hole, and in boring procedure, obtain roadbed morphological data, determine the grouting program of injected hole, the boring, the slip casting that utilize geological condition that pilot hole sums up and construction technology to instruct follow-up injected hole, can follow up in a large number in normal hole, be conducive to large area and launch construction.Improve the physico-mechanical properties of whole ground, make roadbed under traffic load and Gravitative Loads, no longer produce sedimentation, make the building that differential settlement occurs return to original position, thereby improve the strength and stiffness of roadbed, prevent or weaken sinking again of roadbed.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the process chart of high settlement of fill grouting of road bed technique of the present invention.
The specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills are not making the every other embodiment obtaining under creative work prerequisite, any modification of doing, are equal to replacement, improvement etc., within all should being included in protection scope of the present invention.
As shown in Figure 1, high settlement of fill grouting of road bed technique of the present invention, the step of this technique is:
S1, at high settlement of fill roadbed work plane, carry out the even cloth hole of injected hole, and using the described injected hole of some as pilot hole;
S2, pilot hole described in each is implemented to Completion of Drilling Hole technique: first install orifice sleeve and carry out solid pipe, whole hole after drilling to completion then, and adopt mud circulation to carry out hole clearly to the boring of pilot hole described in each;
In boring procedure, gather at a certain distance compactness, intensity, initial pressure, drilling depth, the grouting position state data of this layer of roadbed;
S3, the boring of pilot hole described in each is implemented to grouting process: adopt slurry floral tube down at the bottom of hole, then the method for Piecemeal erection packer is carried out slip casting, and institute's injection slurry is single liquid slurries from bottom to top;
S4, according to the high settlement of fill roadbed morphological data gathering, determine geology and geomorphology, then each pilot hole is implemented the summary of bore process and grouting process.
The quantity of described pilot hole is 25%~35% of described injected hole quantity.
Described high settlement of fill roadbed comprises gravelly soil, gravel soil filler roadbed and cohesive soil filler roadbed.
The grouting pressure of described slip casting is 0.5 MPa~4.0 MPa.
The boring aperture of described injected hole is 91~130mm.

Claims (5)

1. a high settlement of fill grouting of road bed technique, is characterized in that: the step of this technique is:
S1, at high settlement of fill roadbed work plane, carry out the even cloth hole of injected hole, and using the described injected hole of some as pilot hole;
S2, pilot hole described in each is implemented to Completion of Drilling Hole technique: first install orifice sleeve and carry out solid pipe, whole hole after drilling to completion then, and adopt mud circulation to carry out hole clearly to the boring of pilot hole described in each;
In boring procedure, gather at a certain distance compactness, intensity, initial pressure, drilling depth, the grouting position state data of this layer of roadbed;
S3, the boring of pilot hole described in each is implemented to grouting process: adopt slurry floral tube down at the bottom of hole, then the method for Piecemeal erection packer is carried out slip casting, and institute's injection slurry is single liquid slurries from bottom to top;
S4, according to the high settlement of fill roadbed morphological data gathering, determine geology and geomorphology, then each pilot hole is implemented the summary of bore process and grouting process.
2. high settlement of fill grouting of road bed technique according to claim 1, is characterized in that: the quantity of described pilot hole is 25%~35% of described injected hole quantity.
3. high settlement of fill grouting of road bed technique according to claim 1 and 2, is characterized in that: described high settlement of fill roadbed comprises gravelly soil, gravel soil filler roadbed and cohesive soil filler roadbed.
4. high settlement of fill grouting of road bed technique according to claim 3, is characterized in that: the grouting pressure of described slip casting is 0.5 MPa~4.0 MPa.
5. high settlement of fill grouting of road bed technique according to claim 3, is characterized in that: the boring aperture of described injected hole is 91~130mm.
CN201310725755.3A 2013-12-25 2013-12-25 High-fill settling subgrade grouting process Pending CN103741568A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310725755.3A CN103741568A (en) 2013-12-25 2013-12-25 High-fill settling subgrade grouting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310725755.3A CN103741568A (en) 2013-12-25 2013-12-25 High-fill settling subgrade grouting process

Publications (1)

Publication Number Publication Date
CN103741568A true CN103741568A (en) 2014-04-23

Family

ID=50498627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310725755.3A Pending CN103741568A (en) 2013-12-25 2013-12-25 High-fill settling subgrade grouting process

Country Status (1)

Country Link
CN (1) CN103741568A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389254A (en) * 2014-11-20 2015-03-04 江苏省交通科学研究院股份有限公司 Rockfill embankment sinking disease treatment construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011014975A1 (en) * 2009-08-05 2011-02-10 Proes S.A. Flexible paving structure for streets and roads, comprised of a stabilized inferior base and an upper laying pavement of reduced thickness
CN102392402A (en) * 2011-11-11 2012-03-28 中铁六局集团有限公司 Road and bridge transition section grouting construction method used during jacking construction
CN102561139A (en) * 2012-01-13 2012-07-11 鞍钢集团矿业公司 High-strength steel fiber concrete pavement structure for high-tonnage automobile and construction method
CN102864712A (en) * 2012-10-16 2013-01-09 中铁第四勘察设计院集团有限公司 Method and structure for micro-disturbance renovating of existing high speed railway subgrade deformation disease
CN102888795A (en) * 2012-10-25 2013-01-23 中铁十九局集团有限公司 Karst roadbed grouting process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011014975A1 (en) * 2009-08-05 2011-02-10 Proes S.A. Flexible paving structure for streets and roads, comprised of a stabilized inferior base and an upper laying pavement of reduced thickness
CN102392402A (en) * 2011-11-11 2012-03-28 中铁六局集团有限公司 Road and bridge transition section grouting construction method used during jacking construction
CN102561139A (en) * 2012-01-13 2012-07-11 鞍钢集团矿业公司 High-strength steel fiber concrete pavement structure for high-tonnage automobile and construction method
CN102864712A (en) * 2012-10-16 2013-01-09 中铁第四勘察设计院集团有限公司 Method and structure for micro-disturbance renovating of existing high speed railway subgrade deformation disease
CN102888795A (en) * 2012-10-25 2013-01-23 中铁十九局集团有限公司 Karst roadbed grouting process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389254A (en) * 2014-11-20 2015-03-04 江苏省交通科学研究院股份有限公司 Rockfill embankment sinking disease treatment construction method

Similar Documents

Publication Publication Date Title
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN105178326B (en) Upper soft lower hard water rich strata base pit engineering building enclosure water-stopping method
CN103993594B (en) A kind of micro-nano bubble process can liquefied foundation device and working method
CN102888795A (en) Karst roadbed grouting process
CN101967794A (en) New technology for treating vehicle bump at bridge ends
CN107151956A (en) It is a kind of to there is pressure to return the grouting method that slurry reinforces covered karst embankment
CN104386409A (en) Water conservancy method using grounding drilling and water source guidance and storage in goaf for coal mine areas
CN103498697A (en) Filling and construction method for goaf below tunnel
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN111764960B (en) Coal mining separation layer water damage prevention and control method
CN105220590A (en) Many karst collapses roadbed injecting treatment method
CN107268365A (en) A kind of Construction of Soft Soil Subgrade technique
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN109440757A (en) A kind of foundation reinforcement method for karst region
CN110410001A (en) A kind of construction method of superhard rock stratum pile foundation pore-forming
CN104894935A (en) Existing expressway (railway) embankment lightening settlement control method
CN103741568A (en) High-fill settling subgrade grouting process
Holter et al. Modern pre‐injection in underground construction with rapid‐setting microcements and colloidal silica–applications in conventional and TBM‐tunnelling
CN108951308A (en) A kind of restorative procedure of high-speed railway subgrade arch deformation
CN101985881A (en) Method for preventing vertical shaft wellhole from being damaged
CN105484791A (en) Comprehensive tunnel drainage, precipitation and pressure reduction construction method
CN107905219A (en) The construction method of ultra-deep hand excavation stake holes under a kind of complex geological condition
CN114991774A (en) Ground subsection descending type grouting method for crushed andesite basalt stratum
CN106761849A (en) Supporting construction is served as a contrast at the beginning of a kind of high density formation tunnel based on lock foot pad plate
CN103556552A (en) Reinforcing method of slightly soft type soft-foundation service road

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140423