CN103114597B - Environment protection explosion squeezing silting embanking method - Google Patents

Environment protection explosion squeezing silting embanking method Download PDF

Info

Publication number
CN103114597B
CN103114597B CN2013100522308A CN201310052230A CN103114597B CN 103114597 B CN103114597 B CN 103114597B CN 2013100522308 A CN2013100522308 A CN 2013100522308A CN 201310052230 A CN201310052230 A CN 201310052230A CN 103114597 B CN103114597 B CN 103114597B
Authority
CN
China
Prior art keywords
explosive
unit
mean
explosion
depth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2013100522308A
Other languages
Chinese (zh)
Other versions
CN103114597A (en
Inventor
俞元洪
余朝伟
许松节
谢士猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO HIGH-TECH ZONE SEA-CLOSURE ENGINEERING TECHNOLOGY DEVELOPMENT Co Ltd
Original Assignee
NINGBO HIGH-TECH ZONE SEA-CLOSURE ENGINEERING TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO HIGH-TECH ZONE SEA-CLOSURE ENGINEERING TECHNOLOGY DEVELOPMENT Co Ltd filed Critical NINGBO HIGH-TECH ZONE SEA-CLOSURE ENGINEERING TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN2013100522308A priority Critical patent/CN103114597B/en
Publication of CN103114597A publication Critical patent/CN103114597A/en
Application granted granted Critical
Publication of CN103114597B publication Critical patent/CN103114597B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses an environment protection explosion squeezing silting embanking method. Explosives inside each hole of explosive bags are divided into a plurality of evenly separated explosives in the order from top to bottom. An air cushion layer is fixedly arranged at the bottom of a section of explosives at the bottom layer, and the mode of blowing up the explosive bags sequentially in sections is adopted in a combination mode. The environment protection explosion squeezing embanking method has the advantages of being capable of buffering and wakening intense earthquake waves, high-pressure impact waves and high-decibel noises generated by the explosion in a short distances, being wider in application range, and capable of being used in areas with higher environment protection requirements like an cultivation area, an area near neighborhood and the like.

Description

Silt fill method is squeezed in the environment-friendly type explosion
Technical field
The present invention relates to a kind of explosion and squeeze silt fill method, especially relate to a kind of environment-friendly type explosion and squeeze silt fill method.
Background technology
China's Coastal Areas has thicker marine mud matter clay layer more, and when based process, if the conventional methods such as employing excavation are removed mud, not only cost is high, and technical difficulty is large.
It is one of ten new technologies of builing industry of Ministry of Construction's popularization that deposit technique is squeezed in explosion.Explosion is squeezed deposit technique and is reduced silt structure intensity by Blast Shock, utilize simultaneously the deadweight of stone riprap itself make quick-fried before stone riprap in equilibrium state to slippage in the mud at strength decreased place, reach the purpose of mud, stone displacement, there are the characteristics such as the low and settling amount of short, cost of duration is little, technical economic benefit is extremely remarkable, has been widely used in the harbour mole and the engineering such as reclaim fields from the sea.
At present, ocean engineering borehole blasting removing silt for replacement mud maximum ga(u)ge has surpassed 20m, and deeper and deeper trend is arranged.Along with the increase of the displacement mud degree of depth, squeeze the silt effect for obtaining good explosion, increase the single hop explosive quantity inevitable with total dose.But, the increase of dose produces sharp pounding, high-pressure shocking wave and high-decibel noise in the time of can causing explosion on the one hand, marine organisms living environment, peripheral resident living and offshore building are formed to tremendous influence, and the policy intractability of blast working is large on the other hand, easily causes claim for eot.Therefore, the crowded silt fill method of conventional blasting method should not be for ,Jin residential block, culture zone and other zone higher to environmental requirement at present.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of crowded silt fill method of environment-friendly type explosion that seismic wave consumingly, high-pressure shocking wave and high-decibel noise that explosion can be produced cushions rapidly decay in short distance, and the method can be for ,Jin residential block, culture zone and other zone higher to environmental requirement.
The present invention solves the problems of the technologies described above adopted technical scheme: silt fill method is squeezed in a kind of environment-friendly type explosion, comprises the following steps:
1. at first according to geology prospecting report, soil mechanics calculation principle and levee body design height, determine levee body throwing height, then according to levee body throwing height and levee body design section, calculate levee body throwing width, again according to the geological condition of Practical Project, repeat the throwing situation on Construction Condition and slope, determine throwing drilling depth length;
2. at first according to Underwater Soft Foundation Treatment by Blasting empirical formula q ' l=q 0l hh mwwith
Figure BDA00002838134100021
calculate quick-fried unit length dose, the wherein q ' of filling out of dike head lmean line cloth dose; q 0mean the amount of consumption of drugs of compacting mud by explosion unit volume mud, its span is 0.2~0.3; L hmean once to push away the throwing drilling depth length of filling out, H mwmean to count the conversion silt depth that covers the depth of water; H mmean the displacement silt depth that comprises mud bag bump height; r mmean water severe; r wmean mud severe; H wmean to cover the depth of water, i.e. the above depth of water of mud face; Then determine total dose of onepull according to the dike head width, last according to the definite corresponding hole count of the blasting charge and the explosive payload of the single hole blasting charge laid of total dose;
3. the explosive in the blasting charge of every hole is divided in accordance with the order from top to bottom to evenly isolated a plurality of explosives unit, in the bottom of an explosive unit of the bottom, is fixedly installed air cushion layer;
4. according to total dose of every separate explosion, take explosion minimum influence scope as basis, determine the Influence of The Blasting Vibration zone; And the maximum explosive charge of single hop of determining explosion with this, wherein the maximum explosive charge of single hop is according to formula
Figure BDA00002838134100026
calculate, Q is the maximum explosive charge of single hop; V is that safety allows shake speed; R is Influence of The Blasting Vibration Region control ultimate range; K,
Figure BDA00002838134100027
be the relevant attenuation parameter of geology, orographic condition in Yu Bao district, the span of K is 50~350,
Figure BDA00002838134100028
span be 1.3~2;
5. according to ripple Crow Paderewski formula
Figure BDA00002838134100022
calculate the elementary errors time Δ t of non-electric millisecond time-delay detonator, wherein a means pitch of holes; c pmean the compression stress wave spread speed; t 1mean the deep hole implode pressure-acting time, its empirical value is
Figure BDA00002838134100023
q means the explosive payload of the single hole blasting charge;
Figure BDA00002838134100024
above formula result of calculation is that integer is got its value, if non-integer is got its whole value according to advancing a method;
7. throwing building stones;
8. along jackstone and on every side near the mudstone boundary line of mud the designated depth place lay the blasting charge, and explosion;
9. on the basis of sedimentation jackstone repeating step 7.~8., until guaranteeing that whole jackstones are fully bottomed.
Described step 4. in each explosive unit be spherical cartridge bag.
Described step 4. in spacing between adjacent two explosive unit be 8cm~15cm, the coefficient of coup of each explosive unit is 0.4~0.9, detonating fuse runs through each explosive unit, and air cushion layer is perpendicular to each explosive unit, and each explosive unit and air cushion layer are contained in the cylinder type hollow explosive loader.
Explosive is emulsion, and air cushion layer is nylon bladder.
Compared with prior art, the invention has the advantages that by the explosive by the blasting charge of every hole and be divided in accordance with the order from top to bottom evenly isolated a plurality of explosives unit, bottom in an explosive unit of the bottom is fixedly installed air cushion layer, and in conjunction with adopting the segmentation mode of rendrock bag successively, seismic wave consumingly, high-pressure shocking wave and high-decibel noise that explosion is produced cushion rapidly decay in short distance, the scope of application is more extensive, and method of the present invention can be for ,Jin residential block, culture zone and other zone higher to environmental requirement;
When each explosive unit is spherical cartridge bag in the blasting charge, explosion can be shaken to prompt drop low 40%~60%;
Spacing between adjacent two explosive unit is 8cm~15cm, the coefficient of coup of each explosive unit is 0.4~0.9, detonating fuse runs through each explosive unit, air cushion layer is perpendicular to each explosive unit, when each explosive unit and air cushion layer are contained in the cylinder type hollow explosive loader, can reduce shake speed, extend the propagation time of seismic wave, suppress the propagation distance of concussion of blasting.
The accompanying drawing explanation
The schematic diagram that Fig. 1 is the blasting charge of the present invention;
The floor map that Fig. 2 is blasting construction method;
The schematic cross-sectional view that Fig. 3 is blasting construction method.
The specific embodiment
Below in conjunction with accompanying drawing, embodiment is described in further detail the present invention.
Embodiment mono-: silt fill method is squeezed in a kind of environment-friendly type explosion, comprises the following steps:
1. at first according to geology prospecting report, soil mechanics calculation principle and levee body design height, determine levee body throwing height, then according to levee body throwing height and levee body design section, calculate levee body throwing width, again according to the geological condition of Practical Project, repeat the throwing situation on Construction Condition and slope, determine throwing drilling depth length;
2. at first according to Underwater Soft Foundation Treatment by Blasting empirical formula q ' l=q 0l hh mwwith
Figure BDA00002838134100031
calculate quick-fried unit length dose, the wherein q ' of filling out of dike head lmean line cloth dose, unit is Kg/m; q 0mean the amount of consumption of drugs of compacting mud by explosion unit volume mud, its span is 0.2~0.3, and unit is Kg/m 3; L hmean once to push away the throwing drilling depth length of filling out, unit is m, H mwmean to count the conversion silt depth that covers the depth of water, unit is m; H mmean the displacement silt depth that comprises mud bag bump height, unit is m; r mmean water severe, unit is Kg/m 3; r wmean mud severe, unit is Kg/m 3; H wmean to cover the depth of water, i.e. the above depth of water of mud face, unit is m; Then determine total dose of onepull according to the dike head width, last according to the definite corresponding hole count of the blasting charge 5 and the explosive payload of the single hole blasting charge 5 laid of total dose;
8. the explosive in the blasting charge of every hole is divided in accordance with the order from top to bottom to even isolated multistage explosive, in the bottom of the explosive unit of the bottom, is fixedly installed air cushion layer;
4. according to total dose of every separate explosion, take explosion minimum influence scope as basis, determine the Influence of The Blasting Vibration zone; And the maximum explosive charge of single hop of determining explosion with this, wherein the maximum explosive charge of single hop is according to formula
Figure BDA00002838134100041
calculate, Q is the maximum explosive charge (kg) of single hop; V is that safety allows shake speed (cm/s); R is Influence of The Blasting Vibration Region control ultimate range (m); K,
Figure BDA00002838134100042
be the relevant attenuation parameter of geology, orographic condition in Yu Bao district, the span of K is 50~350,
Figure BDA00002838134100043
span be 1.3~2; Each explosive unit is spherical cartridge bag, spacing between adjacent two explosive unit is 15cm, and the coefficient of coup of each explosive unit is 0.9, and detonating fuse 2 runs through each explosive unit, air cushion layer 3 is perpendicular to each explosive unit, and each explosive unit and air cushion layer 3 are contained in the cylinder type hollow explosive loader; Explosive is emulsion, and air cushion layer 3 is nylon bladder; The K of quick-fried district different lithology,
Figure BDA00002838134100044
be worth as shown in table 1;
Table 1
5. according to ripple Crow Paderewski formula calculate the elementary errors time △ t of non-electric millisecond time-delay detonator, wherein a means pitch of holes, and unit is m.c pmean the compression stress wave spread speed, unit is m/s; t 1mean the deep hole implode pressure-acting time, its empirical value is
Figure BDA00002838134100047
unit is s; Q means the explosive payload of the single hole blasting charge 5, and unit is kg;
Figure BDA00002838134100051
Figure BDA00002838134100052
above formula result of calculation is that integer is got its value, if non-integer is got its whole value according to advancing a method;
7. throwing building stones;
8. along jackstone and on every side near the mudstone boundary line of mud the designated depth place lay the blasting charge 5, and press initiator 4 and carry out explosion;
9. on the basis of sedimentation jackstone repeating step 7.~8., until guaranteeing that whole jackstones are fully bottomed.
Embodiment bis-: silt fill method is squeezed in a kind of environment-friendly type explosion, comprises the following steps:
1. at first according to geology prospecting report, soil mechanics calculation principle and levee body design height, determine levee body throwing height, then according to levee body throwing height and levee body design section, calculate levee body throwing width, again according to the geological condition of Practical Project, repeat the throwing situation on Construction Condition and slope, determine throwing drilling depth length;
2. at first according to Underwater Soft Foundation Treatment by Blasting empirical formula q ' l=q 0l hh mwwith
Figure BDA00002838134100053
calculate quick-fried unit length dose, the wherein q ' of filling out of dike head lmean line cloth dose, unit is Kg/m; q 0mean the amount of consumption of drugs of compacting mud by explosion unit volume mud, its span is 0.2~0.3, and unit is Kg/m 3; L hmean once to push away the throwing drilling depth length of filling out, unit is m, H mwmean to count the conversion silt depth that covers the depth of water, unit is m; H mmean the displacement silt depth that comprises mud bag bump height, unit is m; r mmean water severe, unit is Kg/m 3; r wmean mud severe, unit is Kg/m 3; H wmean to cover the depth of water, i.e. the above depth of water of mud face, unit is m; Then determine total dose of onepull according to the dike head width, last according to the definite corresponding hole count of the blasting charge 5 and the explosive payload of the single hole blasting charge 5 laid of total dose;
3. the explosive in the blasting charge of every hole is divided in accordance with the order from top to bottom to even isolated multistage explosive, in the bottom of the explosive unit of the bottom, is fixedly installed air cushion layer;
4. according to total dose of every separate explosion, take explosion minimum influence scope as basis, determine the Influence of The Blasting Vibration zone; And the maximum explosive charge of single hop of determining explosion with this, wherein the maximum explosive charge of single hop is according to formula
Figure BDA00002838134100054
calculate, Q is the maximum explosive charge (kg) of single hop; V is that safety allows shake speed (cm/s); R is Influence of The Blasting Vibration Region control ultimate range (m); K,
Figure BDA00002838134100055
be the relevant attenuation parameter of geology, orographic condition in Yu Bao district, the span of K is 50~350, span be 1.3~2; Each explosive unit is spherical cartridge bag, spacing between adjacent two explosive unit is 8cm, and the coefficient of coup of each explosive unit is 0.4, and detonating fuse 2 runs through each explosive unit, air cushion layer 3 is perpendicular to each explosive unit, and each explosive unit and air cushion layer 3 are contained in the cylinder type hollow explosive loader; Explosive is emulsion, and air cushion layer 3 is nylon bladder; The K of quick-fried district different lithology, be worth as shown in table 2;
Table 2
Figure BDA00002838134100062
5. according to ripple Crow Paderewski formula
Figure BDA00002838134100063
calculate the elementary errors time △ t of non-electric millisecond time-delay detonator, wherein a means pitch of holes, and unit is m; c pmean the compression stress wave spread speed, unit is m/s; t 1mean the deep hole implode pressure-acting time, its empirical value is
Figure BDA00002838134100064
unit is s; G means the explosive payload of the single hole blasting charge 5, and unit is kg;
Figure BDA00002838134100065
l
Figure BDA00002838134100066
above formula result of calculation is that integer is got its value, if non-integer is got its whole value according to advancing a method;
7. throwing building stones;
8. along jackstone and on every side near the mudstone boundary line of mud the designated depth place lay the blasting charge, and press initiator 4 and carry out explosion;
9. on the basis of sedimentation jackstone repeating step 7.~8., until guaranteeing that whole jackstones are fully bottomed.
In above-mentioned all embodiment, all doses that the total dose of explosion is once detonation, the dose that dynamite quantity per hole is each hole of dike head, the maximum explosive charge of single hop is for determining periphery is not damaged according to the security implication scope, utilize every section explosive quantity in a sound higher limit after the millisecond detonator segmentation, the total dose of its borehole blasting=dynamite quantity per hole * hole count, the maximum explosive charge * of the total dose of explosion=single hop segments, the maximum explosive charge of single hop is controlled several dynamite quantity per holes: the maximum explosive charge * of dynamite quantity per hole * hole count=single hop segments.

Claims (2)

1. silt fill method is squeezed in an environment-friendly type explosion, it is characterized in that comprising the following steps:
1. at first according to geology prospecting report, soil mechanics calculation principle and levee body design height, determine levee body throwing height, then according to levee body throwing height and levee body design section, calculate levee body throwing width, again according to the geological condition of Practical Project, repeat the throwing situation on Construction Condition and slope, determine throwing drilling depth length;
2. at first according to Underwater Soft Foundation Treatment by Blasting empirical formula q l'=q 0l hh mwwith
Figure FDA0000397905910000012
calculate quick-fried unit length dose, the wherein q of filling out of dike head l' expression line cloth dose; q 0mean the amount of consumption of drugs of compacting mud by explosion unit volume mud, its span is 0.2~0.3; L hmean once to push away the throwing drilling depth length of filling out, H mwmean to count the conversion silt depth that covers the depth of water; H mmean the displacement silt depth that comprises mud bag bump height; r mmean water severe; r wmean mud severe; H wmean to cover the depth of water, i.e. the above depth of water of mud face; Then determine total dose of onepull according to the dike head width, last according to the definite corresponding hole count of the blasting charge and the explosive payload of the single hole blasting charge laid of total dose;
3. the explosive in the blasting charge of every hole is divided in accordance with the order from top to bottom to evenly isolated a plurality of explosives unit, in the bottom of an explosive unit of the bottom, is fixedly installed air cushion layer;
4. according to total dose of every separate explosion, take explosion minimum influence scope as basis, determine the Influence of The Blasting Vibration zone; And the maximum explosive charge of single hop of determining explosion with this, wherein the maximum explosive charge of single hop is according to formula
Figure FDA0000397905910000017
calculate, Q is the maximum explosive charge of single hop; V is that safety allows shake speed; R is Influence of The Blasting Vibration Region control ultimate range; K,
Figure FDA0000397905910000018
be the relevant attenuation parameter of geology, orographic condition in Yu Bao district, the span of K is 50~350, span be 1.3~2;
5. according to ripple Crow Paderewski formula calculate the elementary errors time Δ t of non-electric millisecond time-delay detonator, wherein a means pitch of holes; c pmean the compression stress wave spread speed; t 1mean the deep hole implode pressure-acting time, its empirical value is
Figure FDA0000397905910000015
q means the explosive payload of the single hole blasting charge;
6. according to formula
Figure FDA0000397905910000016
calculate non-electric millisecond delay detonator hop count, above formula result of calculation is that integer is got its value, if non-integer is got its whole value according to advancing a method;
7. throwing building stones;
8. along jackstone and on every side near the mudstone boundary line of mud the designated depth place lay the blasting charge, and explosion;
9. on the basis of sedimentation jackstone repeating step 7.~8., until guaranteeing that whole jackstones are fully bottomed;
Described step 4. in each explosive unit be spherical cartridge bag; Described step 4. in spacing between adjacent two explosive unit be 8cm~15cm, the coefficient of coup of each explosive unit is 0.4~0.9, detonating fuse runs through each explosive unit, and air cushion layer is perpendicular to each explosive unit, and each explosive unit and air cushion layer are contained in the cylinder type hollow explosive loader.
2. silt fill method is squeezed in environment-friendly type explosion according to claim 1, it is characterized in that explosive is emulsion, and air cushion layer is nylon bladder.
CN2013100522308A 2013-02-18 2013-02-18 Environment protection explosion squeezing silting embanking method Active CN103114597B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100522308A CN103114597B (en) 2013-02-18 2013-02-18 Environment protection explosion squeezing silting embanking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100522308A CN103114597B (en) 2013-02-18 2013-02-18 Environment protection explosion squeezing silting embanking method

Publications (2)

Publication Number Publication Date
CN103114597A CN103114597A (en) 2013-05-22
CN103114597B true CN103114597B (en) 2013-12-25

Family

ID=48413024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100522308A Active CN103114597B (en) 2013-02-18 2013-02-18 Environment protection explosion squeezing silting embanking method

Country Status (1)

Country Link
CN (1) CN103114597B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104406471B (en) * 2014-10-23 2016-04-13 沈雪松 The diversion blasting construction method of intertidal zone explosive replacement fill
CN106643359B (en) * 2016-08-17 2018-04-17 中交一航局第三工程有限公司 A kind of method of explosive replacement processing slope shoulder position residual sludge
CN107228607A (en) * 2017-06-16 2017-10-03 长江三峡设备物资有限公司 A kind of dam foundation ditch base surface constant volume air cushion blasting method
CN108360499B (en) * 2018-02-11 2020-10-02 北京中科力***技术工程有限公司 Large-area blasting compaction treatment method for runway foundation
CN108842717A (en) * 2018-07-13 2018-11-20 陈婷 A kind of riverway sludge method for cleaning
CN109975523B (en) * 2019-04-29 2021-06-29 华侨大学 Method for predicting engineering property of explosive silt-squeezing mixed layer

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2802716B2 (en) * 1993-12-21 1998-09-24 鉱研工業株式会社 Earthquake prevention method
CN101319497A (en) * 2007-06-06 2008-12-10 北京中科力***技术工程有限公司 Method for consolidating mud soft base by explosion and piling prepressing united drainage
CN102061696A (en) * 2011-01-27 2011-05-18 宁波高新区围海工程技术开发有限公司 Environment-friendly blasting compaction method for treating soft foundation
CN102116006A (en) * 2011-03-23 2011-07-06 大连市市政设计研究院有限责任公司 Method for building sea filling embankment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2802716B2 (en) * 1993-12-21 1998-09-24 鉱研工業株式会社 Earthquake prevention method
CN101319497A (en) * 2007-06-06 2008-12-10 北京中科力***技术工程有限公司 Method for consolidating mud soft base by explosion and piling prepressing united drainage
CN102061696A (en) * 2011-01-27 2011-05-18 宁波高新区围海工程技术开发有限公司 Environment-friendly blasting compaction method for treating soft foundation
CN102116006A (en) * 2011-03-23 2011-07-06 大连市市政设计研究院有限责任公司 Method for building sea filling embankment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
***排淤填石法在水利水电工程中的应用研究;邹文明;《人民长江》;20050620(第06期) *
邹文明.***排淤填石法在水利水电工程中的应用研究.《人民长江》.2005,(第06期),

Also Published As

Publication number Publication date
CN103114597A (en) 2013-05-22

Similar Documents

Publication Publication Date Title
CN103114597B (en) Environment protection explosion squeezing silting embanking method
CN103267455B (en) Dam foundation one-step forming drilling blasting method by combining energy dissipation and energy collection of blast hole bottom
CN102061696A (en) Environment-friendly blasting compaction method for treating soft foundation
CN103148748B (en) Pressure-adjustable expansion plastic pipe deep hole blasting control method
CN1474930A (en) Drillhole blasting
KR101040787B1 (en) Blasting method in horizontal direction using deck charge
CN108662958B (en) Pre-splitting blasting system for foundation pit excavation
CN108360499B (en) Large-area blasting compaction treatment method for runway foundation
EP2582907B1 (en) Method employing pressure transients in hydrocarbon recovery operations
CN114877769A (en) Offshore bank underwater slope bedrock blasting excavation construction method and blasting charge structure
CN109405687B (en) Underwater kerf explosive charge blasting device based on uncoupled explosive charge and construction method thereof
CN1253633C (en) Control-loaded explosive sludge-extruding displacement method
CN109610462B (en) The grouting equipment for washing away the slip casting means of defence of disaster for submarine pipeline and its using
CN111721173A (en) Bridge group pile foundation shallow hole blasting air bag vibration reduction structure and construction method
CN100374655C (en) Synchronous blast-enlarging treatment method for liquified soil foundation of highway
RU2635421C1 (en) Method of transforming construction properties of low-bound watered grounds by explosion of explosive charges
CN105160144B (en) A kind of monitoring method suitable for soft-medium explosion bulge and blast chamber motion
RU2531410C1 (en) Method of forming waterproof screen in cracked watercut mountain arrays using bridging
RU2494341C1 (en) Method to arrange deep profiled grooves by means of excavating explosions
CN105258582B (en) A kind of explosive column and excavation technology smooth for foundation plane Blasting Excavation
Kaushik et al. Comprehensive review on principles and practices of underwater drilling and blasting, its environmental impacts, and mitigation techniques
RU2280237C1 (en) Method for drilling of blasting operations
Kato et al. Ground vibration from blast-induced liquefaction testing in Christchurch, New Zealand
CN220206522U (en) Explosive loading structure for blasting in extremely hard rock under urban complex environment
CN113107498B (en) Construction method for shield tunnel to penetrate through local invasive rock stratum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant