CN101349059A CNA2008101968122A CN200810196812A CN101349059A CN 101349059 A CN101349059 A CN 101349059A CN A2008101968122 A CNA2008101968122 A CN A2008101968122A CN 200810196812 A CN200810196812 A CN 200810196812A CN 101349059 A CN101349059 A CN 101349059A
Authority
CN
China
Prior art keywords
concrete
pile
driller
hole
depth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008101968122A
Other languages
Chinese (zh)
Inventor
张国银
万凯军
吴跃钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co
Original Assignee
CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co filed Critical CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co
Priority to CNA2008101968122A priority Critical patent/CN101349059A/en
Publication of CN101349059A publication Critical patent/CN101349059A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention relates to a new technology for pressing and filling reinforced concrete by a long spiral driller, which comprises the following steps: a pile setting position is measured and placed; the driller is automatically leveled in position and stops to drill a hole tills reaching the designed depth; a pylome of the middle part of a blade of the long spiral driller always passes through the bottom of a driller head; a valve is used to control the on-off; a marker for controlling the pile forming depth is made on a frame of a driller tower; the top of the blade of a long spiral drill stem adopts a hose with corresponding specification, which is connected with a concrete conveying pipe; a concrete conveying pump in the middle of the blade of the drill stem is used to convey concrete to the bottom of the drilled hole; the concrete is conveyed and the drill stem is upwards lifted to reach the designed height;, and then the concrete is stopped to convey; a crane lifts a reinforced steel cage; an oscillator and a steel pipe connecting device are adopted to transport the reinforced steel cage to the designed depth for pile forming; therefore, the operation is circulated. The new technology has the advantages that through a plurality of practices, when a fourth system soil layer and a loose pebble layer are drilled, the pile is filled by holes; with the method, the method can improve the effect by 120 percent, reduce cost for pile forming, well ensure the quality of pile forming, has remarkable effect, avoids the accident of safety and further meet the requirement of environmental protection.

Description

New technique of long screw driller for press pouring reinforced concrete
Technical field
The present invention relates to the exploration engineering field, a kind of specifically new technique of long screw driller for press pouring reinforced concrete.
Background technology
Building trade foundation construction castinplace pile all is to adopt rotary drilling (or percussion drilling) pile hole at present, with residue at the bottom of mud cleaning hole wall and the hole, after satisfied precipitation requires, transfers reinforcing cage with crane more then; One save downcomer and then to bottom, stake hole, the concrete that top adopts the funnel perfusion to stir.
This operation procedure long construction period, difficulty of construction is bigger, and each step control time is long, all needs crane lifting, the cost height, the pile effect is low, is easy to generate pile quality segregation and fracture accident, security incident takes place simultaneously easily, and the environmental protection degree is lower, and the assurance of construction quality is had certain influence.
Summary of the invention
The objective of the invention is to develop a kind of quality, efficient height, cost is low, the new technique of long screw driller for press pouring reinforced concrete of safety, environmental protection.
New technique of long screw driller for press pouring reinforced concrete of the present invention, its step is as follows:
(1) measuring stake position;
(2) rig autofitting leveling;
(3) hole and stop boring to projected depth: long-spiral drilling machine blade middle part through hole one use the valve gauge tap through to the drill bit bottom, makes marks on the rig pylon and controls the pile degree of depth;
(4) the long screw drill rod vane tip adopts the flexible pipe of corresponding specification to be connected with the concrete carrier pipe, carries concrete at drilling rod blade middle part toward foot of hole with concrete transfer pump, and conveying concrete limit, limit up promotes drilling rod and reaches design height, stops to carry concrete;
(5) crane install reinforcing cage adopts vibrator and steel pipe linkage conveying steel cage to the projected depth pile;
(6) pile is laid in the rig displacement, so cycle operation.
Concrete transfer pump is to adopting steel pipe to connect between the rig.
The advantage of new technique of long screw driller for press pouring reinforced concrete of the present invention is: long screw auger advances because crawler attachment is arranged, and own translational speed is fast, simultaneously the fast effect height of pile-forming speed; The pouring concrete be utilize concrete transfer pump to be transported to the hole by certain pressure at the bottom of, faster than traditional funnel pouring concrete speed, quality is good; The present invention is without the mud hole flushing, also just do not need mud pit, compliance with environmental protection requirements more, and labour intensity reduces, and cost reduces; Employing is transferred reinforcing cage after pouring concrete, can play the closely knit effect of vibrating to the concrete of pile from top to bottom, guarantees pile quality better; Because long-spiral drilling machine oneself moves, pour concrete adopts pumping, has reduced the crane operation degree, reduces labor intensity, and reduces operating cost, has also reduced the generation of security incident.Through facts have proved that repeatedly pore-creating filling pile in creeping into Quaternary system soil layer and loose boulder bed adopts the present invention, can improve effect 120%, the pile cost reduces, and pile quality also obtains fine assurance, effect is remarkable, has avoided security incident, more satisfies environmental protection requirement.
Description of drawings
Fig. 1 is the process chart of new technique of long screw driller for press pouring reinforced concrete.
The specific embodiment
According to shown in Figure 1, new technique of long screw driller for press pouring reinforced concrete, its step is as follows:
(1) measuring stake position;
(2) rig autofitting leveling;
(3) hole and stop boring to projected depth: long-spiral drilling machine blade middle part through hole one use the valve gauge tap through to the drill bit bottom, makes marks on the rig pylon and controls the pile degree of depth;
(4) the long screw drill rod vane tip adopts the flexible pipe of corresponding specification to be connected with the concrete carrier pipe, carries concrete at drilling rod blade middle part toward foot of hole with concrete transfer pump, and conveying concrete limit, limit up promotes drilling rod and reaches design height, stops to carry concrete;
(5) crane install reinforcing cage adopts vibrator and steel pipe linkage conveying steel cage to the projected depth pile;
(6) pile is laid in the rig displacement, so cycle operation.

Claims (1)

1, a kind of new technique of long screw driller for press pouring reinforced concrete is characterized in that: its step is as follows:
(1) measuring stake position;
(2) rig autofitting leveling;
(3) hole and stop boring to projected depth: long-spiral drilling machine blade middle part through hole one use the valve gauge tap through to the drill bit bottom, makes marks on the rig pylon and controls the pile degree of depth;
(4) the long screw drill rod vane tip adopts the flexible pipe of corresponding specification to be connected with the concrete carrier pipe, carries concrete at drilling rod blade middle part toward foot of hole with concrete transfer pump, and conveying concrete limit, limit up promotes drilling rod and reaches design height, stops to carry concrete;
(5) crane install reinforcing cage adopts vibrator and steel pipe linkage conveying steel cage to the projected depth pile;
(6) pile is laid in the rig displacement, so cycle operation.
CNA2008101968122A 2008-08-29 2008-08-29 New technique of long screw driller for press pouring reinforced concrete Pending CN101349059A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008101968122A CN101349059A (en) 2008-08-29 2008-08-29 New technique of long screw driller for press pouring reinforced concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008101968122A CN101349059A (en) 2008-08-29 2008-08-29 New technique of long screw driller for press pouring reinforced concrete

Publications (1)

Publication Number Publication Date
CN101349059A true CN101349059A (en) 2009-01-21

Family

ID=40268010

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008101968122A Pending CN101349059A (en) 2008-08-29 2008-08-29 New technique of long screw driller for press pouring reinforced concrete

Country Status (1)

Country Link
CN (1) CN101349059A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892663A (en) * 2010-07-13 2010-11-24 新疆电力设计院 Pile foundation manufacturing method
CN102535445A (en) * 2012-02-07 2012-07-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile
CN104631438A (en) * 2015-01-27 2015-05-20 安徽同济建设集团有限责任公司 Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN114575338A (en) * 2022-04-07 2022-06-03 江西省地质工程(集团)公司 Method for processing hollow hole section of long spiral cast-in-place pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892663A (en) * 2010-07-13 2010-11-24 新疆电力设计院 Pile foundation manufacturing method
CN102535445A (en) * 2012-02-07 2012-07-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile
CN102535445B (en) * 2012-02-07 2013-09-04 陕西桩鑫建设工程有限公司 Molding device and molding method for long spiral extruding rock-entering cast-in-place pile
CN104631438A (en) * 2015-01-27 2015-05-20 安徽同济建设集团有限责任公司 Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN104631438B (en) * 2015-01-27 2016-08-24 安徽同济建设集团有限责任公司 Long auger guncreting uplift pile construction method
CN114575338A (en) * 2022-04-07 2022-06-03 江西省地质工程(集团)公司 Method for processing hollow hole section of long spiral cast-in-place pile

Similar Documents

Publication Publication Date Title
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN104563148B (en) building pile foundation construction method
CN103510510B (en) A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method
CN109056706A (en) A kind of Karst Geological Landscape poured pile base construction method
CN105714834B (en) A kind of construction technology of hardpan preexisting hole grouting behind shaft or drift lining H profile steel stake
CN108570983A (en) The pile base construction method and its casing of non-filler large size solution cavity
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN111594041A (en) Rapid hole forming construction method for large-diameter deep hole pile foundation under karst geology
CN113323584B (en) Drilling method of large-scale vibration long spiral drilling machine
CN109518677A (en) Punching Borehole Cast-in-place Concrete Pile karst cave treatment method
CN109183790A (en) A kind of Screw Pile and its construction tool and construction method
CN110344414A (en) A kind of pilot hole plant stake piling all-in-one machine
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN101349059A (en) New technique of long screw driller for press pouring reinforced concrete
CN103556551A (en) Dumbbell-shaped bored pile composite foundation structure used for reinforcing soft foundations of embankment and construction method thereof
CN106284311B (en) A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig
CN110273413A (en) A kind of efficient construction method of prefabricated pile
CN218148483U (en) Tower crane foundation structure
CN206971210U (en) A kind of long casing in pile foundation construction
CN106759296A (en) Drainable irregular-section bamboo joint pipe pile and root planting type construction method thereof
CN101245597A (en) Breast wall type cast-in-situ bored pile construction method and pile machine
CN102817349A (en) Method for consolidating soft soil foundations through fine dynamic compaction replacement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090121